CN109193540A - A kind of Railway Tunnel leaky cable holding clamp - Google Patents

A kind of Railway Tunnel leaky cable holding clamp Download PDF

Info

Publication number
CN109193540A
CN109193540A CN201810952884.9A CN201810952884A CN109193540A CN 109193540 A CN109193540 A CN 109193540A CN 201810952884 A CN201810952884 A CN 201810952884A CN 109193540 A CN109193540 A CN 109193540A
Authority
CN
China
Prior art keywords
fixture
fastener
leaky cable
cover board
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810952884.9A
Other languages
Chinese (zh)
Inventor
曹从咏
周梦笛
李志刚
夏熙童
秦予铮
盛楚倩
胡芳芳
束俊杰
谈俊希
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing University of Science and Technology
Original Assignee
Nanjing University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing University of Science and Technology filed Critical Nanjing University of Science and Technology
Priority to CN201810952884.9A priority Critical patent/CN109193540A/en
Publication of CN109193540A publication Critical patent/CN109193540A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/08Installations of electric cables or lines in or on the ground or water in tunnels

Abstract

The present invention, which provides, a kind of can be used to the parts such as novel clamping apparatus, including pedestal, shaft, cover board and fastener of leaky cable in fixed Railway Tunnel.Fixture is fixed on tunnel wall surface by bolt and hexagonal internal screw thread stud when use, by leaky cable as rear cover closing lid plate in fixture pedestal, fastener insurance is opened, completes the fixation of leaky cable.The present invention is by designing a new leakage cable fixture, it can bear the shock loading for the Piston Action Wind that the train of higher overall trip speed generates in tunnel, unique fastener structure can prevent cable in use process from falling off, anchoring engaging structure can solve the problems, such as the whole transfer in use of existing fixture, have higher safety and reliability.

Description

A kind of Railway Tunnel leaky cable holding clamp
Technical field
The invention belongs to mechanical engineering fields, and in particular to a kind of for fixing leaky cable in Railway Tunnel Fixture.
Background technique
Leaky cable is the important equipment of high speed rail system, is the best mode that high-speed railway communicates in tunnel, and Holding clamp is the unique scheme being fixed on leaky cable in high-speed rail tunnel.But with the continuous improvement of train operation speed, Also more acutely, existing fixture structure will be no longer applicable in the impact of generated Piston Action Wind train when running in tunnel.At present The leaky cable holding clamp of domestic each deposit is only used for 350 kilometers and runs speed per hour below, has no relevant to speed-raising Matched fixture technical solution, therefore this kind of technical solution need to be laid in advance.And in practical projects, there is cables for existing fixture Handling are inconvenient, anchor the problems such as transfer, high temperature embrittlement.Therefore, study that a kind of applicable speed is fast, intensity is high, height easy to use Fast railway tunnel leakage cable fixture can also be improved railway auxiliary facility state to China railways speed-raising important in inhibiting is supported Productionization degree.
Summary of the invention
It is an object of the invention to overcome the problems, such as the prior art be applicable in speed it is low, using difficulty, provide a kind of novel Railway Tunnel leakage cable fixture is able to bear the Piston Action Wind shock loading generated when higher speed per hour train operation, more square Just worker installs and unloads cable.
Above-mentioned purpose of the invention realizes that dependent claims are to select else or have by the technical characteristic of independent claims The mode of benefit develops the technical characteristic of independent claims.
To reach above-mentioned purpose, the technical solution adopted in the present invention is as follows:
A kind of Railway Tunnel leaky cable holding clamp, which is characterized in that including pedestal, shaft, cover board and fastener. Fixture is fixed on tunnel wall surface by bolt and hexagonal internal screw thread stud, leaky cable is closed as rear cover in fixture pedestal Cover board opens fastener insurance, completes the fixation of leaky cable.By designing a new leakage cable fixture, can bear higher The shock loading for the Piston Action Wind that the train of overall trip speed generates in tunnel, unique fastener structure can prevent electric in use process Cable falls off, and anchoring engaging structure can solve the problems, such as the whole transfer in use of existing fixture, has higher safety and can By property, in which: pedestal includes stiffener plate, cable card slot and positioning screw hole.Positioning screw hole is used for positioning stud, prevents fixture whole Body transfer;Card slot is for placing cable;Stiffener plate is used to improve the reliability and security of fixture.
Cover board includes buffer substrate tablet and outer hook.Buffer substrate tablet prevents cable because of generation when train passes through for fixing cable position Piston Action Wind and shake, and play cushioning effect;Outer hook is used for and fastener cooperation carries out the fixed cable of locking.
Buckle includes safety device and buckling device, and buckling device is used to cooperate fixed cable, insurance with the fastener of cover board Device is used to prevent fixture to be opened accidentally because of non-artificial factor after fastener fastening.
Shaft is used for chain connects cover plate and pedestal, opens and closes convenient for fixture.
In further embodiment, a kind of Railway Tunnel leaky cable holding clamp has positioning spiral shell simultaneously Hole can cooperate with the hexagonal internal screw thread stud of standard and be fixed.
In further embodiment, a kind of Railway Tunnel leaky cable holding clamp setting buffer substrate tablet, one Aspect can fix cable, and buffer function on the other hand can be played when train is shaken by cable.
In further embodiment, there is a kind of Railway Tunnel leaky cable holding clamp insurance to tie simultaneously Structure can prevent it from causing cable surprisingly to fall off because of non-artificial factor at work;
In further embodiment, a kind of Railway Tunnel leaky cable holding clamp is equipped with stiffener plate, Fixture overall structural strength is improved, prevents from being broken in engineering because of the impact of Piston Action Wind.
The invention has the benefit that the present invention can bear higher operation by designing a new leakage cable fixture The shock loading for the Piston Action Wind that the train of speed generates in tunnel, unique fastener structure can prevent cable in use process de- It falls, anchoring engaging structure can solve the problems, such as the whole transfer in use of existing fixture, have higher safety and reliability
Detailed description of the invention
Fig. 1 is external form schematic diagram of the invention.
Fig. 2 is main view of the invention.
Fig. 3 is side view of the invention.
Fig. 4 is bottom view of the invention.
Fig. 5 is fastener internal structure chart one of the present invention.
Fig. 6 is fastener internal structure chart two of the present invention.
Specific embodiment
In order to better understand the technical content of the present invention, special to lift specific example and illustrate appended by cooperating as follows.
As shown above, Railway Tunnel leaky cable holding clamp is by pedestal 1, cover board 2, shaft 4 and 10 groups of fastener At.Cover board and pedestal are attached by shaft 1, shaft 2 52, setting retaining spring 7 and shaft 6 in fastener, on buckle 8 Safety device 9 is set.
Wherein, pedestal 1 is for placing leaky cable;Buckle 8 passes through and cover board 1, the cooperation of cover board 2 32 carry out cable It is fixed;Retaining spring 7 make buckle 8 keep buckling state, safety device by on pedestal locating piece cooperate, prevent fixture because Non-artificial factor is opened accidentally.
Using above-mentioned high-speed railway leaky cable holding clamp, the working efficiency of leaky cable handling is improved, supports China The further speed-raising of high-speed railway improves me and crosses the degree domestic of high-speed railway auxiliary facility.
As alternative embodiment, as shown in figure 4, having positioning device on bottom plate, can cooperate with hexagonal internal screw thread stud, when When fixture is fixed on tunnel wall surface, whole transfer phenomenon will not occur.
As alternative embodiment, as shown in Figure 1, buffer substrate tablet is used to fix cable position, when preventing cable from passing through because of train The Piston Action Wind of generation and shake, and play cushioning effect.
As alternative embodiment, as shown in figure 5, have safety structure simultaneously, can prevent its at work because it is non-artificial because Element and cause cable surprisingly to fall off.
As alternative embodiment, as shown in figure 4, being equipped with stiffener plate, fixture overall structural strength is improved, is prevented in engineering It is middle to be broken because of the impact of Piston Action Wind.

Claims (6)

1. a kind of Railway Tunnel leaky cable holding clamp, which is characterized in that the fixture passes through spiral shell in bolt and hexagonal Line stud is fixed on tunnel wall surface, and the fixture pedestal (1) and rear cover closing lid plate (2) are equipped with leaky cable, the leakage Cable is insured by fastener (10) to be fixed: the fixture includes pedestal (1), cover board (2), shaft (4) and fastener (10), the lid Plate (2) is divided into cover board one (31) and cover board two (32), and the shaft (4) is divided into shaft one (51) and shaft two (52), the hook Button (10) is divided into fastener one (111) and fastener two (112);The cover board one (31) and cover board two (32) one end pass through shaft respectively The other end of one (51) and shaft two (52) and pedestal (1) connection, the cover board one (31) and cover board two (32) passes through hook respectively Detain one (111) and fastener two (112) and pedestal (1) connection.
2. a kind of Railway Tunnel leaky cable holding clamp according to claim 1, which is characterized in that the fastener It (10) further include shaft (6), retaining spring (7), buckle (8) and safety device (9), the safety device (9) is set to the button On plate (8).
3. a kind of Railway Tunnel leaky cable holding clamp according to claim 1, which is characterized in that the pedestal It (1) further include stiffener plate, cable card slot and positioning screw hole.
4. a kind of Railway Tunnel leaky cable holding clamp according to claim 1, which is characterized in that the cover board (2) buffer substrate tablet and outer hook are additionally provided on, the outer hook and fastener (10) are used cooperatively.
5. a kind of Railway Tunnel leaky cable holding clamp according to claim 1, which is characterized in that the fixture It is additionally provided with the positioning screw hole being used cooperatively with hexagonal internal screw thread stud.
6. a kind of Railway Tunnel leaky cable holding clamp according to claim 1, which is characterized in that the fixture It is additionally provided with stiffener plate.
CN201810952884.9A 2018-08-21 2018-08-21 A kind of Railway Tunnel leaky cable holding clamp Pending CN109193540A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810952884.9A CN109193540A (en) 2018-08-21 2018-08-21 A kind of Railway Tunnel leaky cable holding clamp

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810952884.9A CN109193540A (en) 2018-08-21 2018-08-21 A kind of Railway Tunnel leaky cable holding clamp

Publications (1)

Publication Number Publication Date
CN109193540A true CN109193540A (en) 2019-01-11

Family

ID=64919145

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810952884.9A Pending CN109193540A (en) 2018-08-21 2018-08-21 A kind of Railway Tunnel leaky cable holding clamp

Country Status (1)

Country Link
CN (1) CN109193540A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103075577A (en) * 2013-01-28 2013-05-01 中天日立射频电缆有限公司 Novel leakage cable fixing device for high-speed railway
CN204254050U (en) * 2014-11-03 2015-04-08 中国航空工业集团公司西安飞机设计研究所 A kind of nonmetal clamping stirrup
CN104577922A (en) * 2015-01-23 2015-04-29 中国电力工程顾问集团中南电力设计院有限公司 Infinite-rotating-angle anti-galloping spacer wire clamp with locking device and installation and detachment method
CN204333760U (en) * 2014-11-18 2015-05-13 中国南方电网有限责任公司超高压输电公司贵阳局 Can the insulator replacement fixture of self-locking
CN106356780A (en) * 2016-11-18 2017-01-25 安徽江淮汽车股份有限公司 Automotive wire clamp

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103075577A (en) * 2013-01-28 2013-05-01 中天日立射频电缆有限公司 Novel leakage cable fixing device for high-speed railway
CN204254050U (en) * 2014-11-03 2015-04-08 中国航空工业集团公司西安飞机设计研究所 A kind of nonmetal clamping stirrup
CN204333760U (en) * 2014-11-18 2015-05-13 中国南方电网有限责任公司超高压输电公司贵阳局 Can the insulator replacement fixture of self-locking
CN104577922A (en) * 2015-01-23 2015-04-29 中国电力工程顾问集团中南电力设计院有限公司 Infinite-rotating-angle anti-galloping spacer wire clamp with locking device and installation and detachment method
CN106356780A (en) * 2016-11-18 2017-01-25 安徽江淮汽车股份有限公司 Automotive wire clamp

Similar Documents

Publication Publication Date Title
Aad et al. Search for the decay Bs0→ μ+ μ− with the ATLAS detector
MY168799A (en) Railway rail fastening apparatus
MY125396A (en) Railway baseplate assembly
CN109193540A (en) A kind of Railway Tunnel leaky cable holding clamp
CN206397308U (en) A kind of keeper locking device
CN103544894B (en) LED display casing mounting structure
CN106300157B (en) A kind of cable core arrangement arrangement auxiliary tool
CN205992897U (en) Split type Kato for electronic equipment
CN207221144U (en) A kind of safety belt backup protection rope fixing device for cement pole operation
NZ615631A (en) Tamper evident device
CN208413673U (en) A kind of maglev vehicle hanging equipment falling proof device
CN209561944U (en) A kind of distribution box insulated leg
CN208970942U (en) A kind of power equipment rain cover
CN106088416B (en) The cladding connector of back bolt type self-locking
Burkhardt et al. Plans for high beta optics in the LHC
CN203393526U (en) Steel rail holder
CN104913122A (en) Wire fixing clamp
CN207194367U (en) A kind of mosaic fixing device
CN204794879U (en) Prevent solar control ware wiring fastener that terminal pine takes off
CN206878398U (en) A kind of cable testing bridge fixing device
CN205745675U (en) A kind of Cable hanger
CN206053498U (en) A kind of connecting elements in electric power pylon
BR9815505A (en) Resilient clamp for attaching rail tracks to a foundation
CN203537711U (en) Cable fixing protector, combination and cabinet
CN109930822A (en) A kind of house side template ruggedized construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190111

RJ01 Rejection of invention patent application after publication