CN109189006A - Concrete prefabricated element makes production line monitoring method and system - Google Patents
Concrete prefabricated element makes production line monitoring method and system Download PDFInfo
- Publication number
- CN109189006A CN109189006A CN201810764596.0A CN201810764596A CN109189006A CN 109189006 A CN109189006 A CN 109189006A CN 201810764596 A CN201810764596 A CN 201810764596A CN 109189006 A CN109189006 A CN 109189006A
- Authority
- CN
- China
- Prior art keywords
- data
- production line
- concrete prefabricated
- prefabricated element
- line capacity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/418—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
- G05B19/4185—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by the network communication
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06K—GRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
- G06K17/00—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
- G06K17/0022—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/30—Nc systems
- G05B2219/31—From computer integrated manufacturing till monitoring
- G05B2219/31088—Network communication between supervisor and cell, machine group
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P80/00—Climate change mitigation technologies for sector-wide applications
- Y02P80/40—Minimising material used in manufacturing processes
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Abstract
The present invention provides a kind of concrete prefabricated element production production line monitoring method and systems, field demand data, inventory data and production line capacity data including passing through data terminal timing acquiring concrete prefabricated element;After server receives field demand data, inventory data and production line capacity data, field demand data are compared with the sum of inventory data and production line capacity data, judge whether the sum of inventory data and production line capacity data meet field demand data;If being unsatisfactory for, analysis and regulation is carried out to production line capacity data, until meeting the requirement of field demand data, realize that prefabricated components produce the intelligent control of multi-process by the feedback of live actual demand, optimize the production procedure of prefabricated components, the reconstruct for realizing prefabricated components production procedure realizes that the dynamic control of the raw material supply of concrete prefabricated element, raw material are processed on demand, component produces on demand, minimize storage.
Description
Technical field
The present invention relates to a kind of concrete prefabricated element production production line monitoring method and systems.
Background technique
The fast development of the buildings and municipal works such as the prefabrication and assembly construction house in China, prefabrication and assembly construction bridge, results in coagulation
The quick production of native prefabricated components becomes a big demand.But prefabricated member model is more, quantity is big, along with entry is same
When the construction requirement that produces, from production plan, mold plan, library programming, material planning, scheduling of production, quality management, logistics
Very high management requirement is proposed with each links such as goods, supply and demand communications.
Summary of the invention
The purpose of the present invention is to provide a kind of concrete prefabricated element production production line monitoring method and system, Neng Gouman
The high Collaborative Control requirement of each link of sufficient concrete prefabricated element production production.
To solve the above problems, the present invention provides a kind of concrete prefabricated element production production line monitoring method, comprising:
Field demand data, inventory data and the production line production capacity number of data terminal timing acquiring concrete prefabricated element
According to, and it is sent to server;
After server receives the field demand data, inventory data and production line capacity data, by the field demand
Data are compared with the sum of inventory data and production line capacity data, judge that the sum of inventory data and production line capacity data are
It is no to meet the field demand data;
If satisfied, then keeping existing production line capacity data;
If not satisfied, then according to the difference of the sum of the field demand data and inventory data and production line capacity data,
Analysis and regulation is carried out to production line capacity data, until meeting the requirement of the field demand data.
Further, in the above-mentioned methods, the inventory data of data terminal timing acquiring concrete prefabricated element, comprising:
Reservoir area is divided according to the different type of concrete prefabricated element, and is divided in each reservoir area according to engineering, position
Warehouse compartment binds a RFID card for each warehouse compartment, to the digitlization identity ID of each RFID card write-in warehouse compartment, in each warehouse compartment
Concrete prefabricated element on paste two dimensional code, pass through the reading of the RFID and the scanning of two dimensional code, data terminal timing acquiring
The inventory data of concrete prefabricated element.
Further, in the above-mentioned methods, the production line capacity data of data terminal timing acquiring concrete prefabricated element,
Include:
Maintenance pedestal for each production concrete prefabricated element binds a RFID card, to the maintenance pedestal
The digitlization identity ID of the maintenance pedestal is written in RFID card;
The production line production capacity of concrete prefabricated element corresponding to the digitlization identity ID of pedestal is conserved described in real-time update
Data;
The production line capacity data of the updated concrete prefabricated element of data terminal timing acquiring.
Further, in the above-mentioned methods, further includes:
Template for each production concrete prefabricated element binds a RFID card, is written to the RFID card of the template
Digitize identity ID;
The corresponding use state of digitlization identity ID of each template of real-time update.
Further, in the above-mentioned methods, further includes:
The storage machine data bank for establishing the production raw material of concrete prefabricated element analyzes the storage processing number in real time
According to demand of stocking up, storage quantity, the dynamic relationship of processing progress of the production raw material in library;
According to the difference of the sum of the field demand data and inventory data and production line capacity data, to production line production capacity
Data carry out analysis and regulation, comprising:
The digitlization identity ID of the corresponding use state of digitlization identity ID, the maintenance pedestal based on each template
The demand of stocking up of the production line capacity data of corresponding concrete prefabricated element and the production raw material, adds storage quantity
The dynamic relationship of work progress, using shop-floor management technology to it is described maintenance pedestal, template and produce raw material processing, stock up
Combination adjustment is optimized, so that the field demand data are equal with the sum of inventory data and production line capacity data.
Another side according to the present invention provides a kind of concrete prefabricated element production production line monitoring system, comprising:
Data terminal is produced for the field demand data of timing acquiring concrete prefabricated element, inventory data and production line
Energy data, and it is sent to server;
Server, after receiving the field demand data, inventory data and production line capacity data, by the scene
Demand data is compared with the sum of inventory data and production line capacity data, judge inventory data and production line capacity data it
Whether the field demand data are met;If satisfied, then keeping existing production line capacity data;If not satisfied, then basis
The difference of the sum of the field demand data and inventory data and production line capacity data, analyzes production line capacity data
Adjustment, until meeting the requirement of the field demand data.
Further, in above system, further includes:
Division module divides reservoir area for the different type according to concrete prefabricated element, and divides according to engineering, position
Warehouse compartment in each reservoir area binds a RFID card for each warehouse compartment, the digitlization identity ID of warehouse compartment is written to each RFID card,
Two dimensional code is pasted on the concrete prefabricated element in each warehouse compartment;
The data terminal, for the scanning of reading and two dimensional code by the RFID, timing acquiring is concrete prefabricated
The inventory data of component.
Further, in above system, further includes:
Binding module, for binding a RFID card for the maintenance pedestal of each production concrete prefabricated element, to institute
The digitlization identity ID of the maintenance pedestal is written in the RFID card for stating maintenance pedestal;The digital incarnation of pedestal is conserved described in real-time update
The production line capacity data of concrete prefabricated element corresponding to part ID;
The data terminal, the production line capacity data for the updated concrete prefabricated element of timing acquiring.
Further, in above system, the binding module is also used to as each production concrete prefabricated element
Template binds a RFID card, and digitlization identity ID is written to the RFID card of the template;The number of each template of real-time update
The corresponding use state of word incarnation part ID.
Further, in above system, the server is also used to establish the production raw material of concrete prefabricated element
Storage machine data bank, analyze in real time the demand of stocking up of production raw material in the storage machine data bank, storage quantity,
The dynamic relationship of processing progress;The corresponding use state of digitlization identity ID, the maintenance pedestal based on each template
The demand of stocking up of the production line capacity data of concrete prefabricated element corresponding to digitlization identity ID and the production raw material,
Storage quantity, the dynamic relationship of processing progress, using shop-floor management technology to the maintenance pedestal, template and production raw material
Processing, stocking up optimizes combination adjustment so that the field demand data and inventory data and production line capacity data it
With it is equal.
Compared with prior art, the present invention passes through the field demand number of data terminal timing acquiring concrete prefabricated element
According to, inventory data and production line capacity data, and it is sent to server;Server receives the field demand data, inventory
According to after production line capacity data, the field demand data are compared with the sum of inventory data and production line capacity data
It is right, judge whether the sum of inventory data and production line capacity data meet the field demand data;If satisfied, then keeping existing
Production line capacity data;If not satisfied, then according to the field demand data and inventory data and production line capacity data it
The difference of sum carries out analysis and regulation to production line capacity data, until meeting the requirement of field demand data.The present invention can solve
The multi-process Collaborative Control problem of certainly current concrete prefabricated element production, realizes prefabricated structure by the feedback of live actual demand
Part produces the intelligent control of multi-process, optimizes the production procedure of prefabricated components, realizes the reconstruct of prefabricated components production procedure,
Realize that the dynamic control of the raw material supply of concrete prefabricated element, raw material are processed on demand, component produces on demand, minimizes storehouse
Storage.
Detailed description of the invention
Fig. 1 is the concrete prefabricated element production production line monitoring method flow chart of one embodiment of the invention.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real
Applying mode, the present invention is described in further detail.
As shown in Figure 1, the present invention provides a kind of concrete prefabricated element production production line monitoring method, comprising:
Step S1, field demand data, inventory data and the production line of data terminal timing acquiring concrete prefabricated element
Capacity data, and it is sent to server;
Step S2 will be described existing after server receives the field demand data, inventory data and production line capacity data
Field demand data is compared with the sum of inventory data and production line capacity data, judges inventory data and production line capacity data
The sum of whether meet the field demand data;
Step S3, if satisfied, then keeping existing production line capacity data;
Step S4, if not satisfied, then according to the field demand data and the sum of inventory data and production line capacity data
Difference, analysis and regulation is carried out to production line capacity data, until meeting the requirements of field demand data.
Here, above-mentioned steps S1~step S4 can be repeated constantly, the present invention can solve current concrete prefabricated element
The multi-process Collaborative Control problem of production realizes that prefabricated components produce the intelligence control of multi-process by the feedback of live actual demand
System, optimizes the production procedure of prefabricated components, realizes the reconstruct of prefabricated components production procedure, realize concrete prefabricated element
The dynamic control of raw material supply, raw material are processed on demand, component produces on demand, minimize storage.
In concrete prefabricated element production one embodiment of production line monitoring method of the invention, in step S1, data terminal
The inventory data of timing acquiring concrete prefabricated element, comprising:
Reservoir area is divided according to the different type of concrete prefabricated element, and is divided in each reservoir area according to engineering, position
Warehouse compartment binds a RFID card for each warehouse compartment, to the digitlization identity ID of each RFID card write-in warehouse compartment, in each warehouse compartment
Concrete prefabricated element on paste two dimensional code, pass through the reading of the RFID and the scanning of two dimensional code, data terminal timing acquiring
The inventory data of concrete prefabricated element.
Here, binding a RFID card, the digitlization identity as warehouse compartment to realize inventory figures for each warehouse compartment
ID.Coding uses subregion segmented volumetric space encoding principle, i.e., reservoir area is divided according to the different type of component, according to engineering, portion
Position divides warehouse compartment, is precisely gone out by RFID or two-dimensional code scanning component, is put in storage, and realizes that inventory implements to update.
In concrete prefabricated element production one embodiment of production line monitoring method of the invention, in step S1, data terminal
The production line capacity data of timing acquiring concrete prefabricated element, comprising:
Maintenance pedestal for each production concrete prefabricated element binds a RFID card, to the maintenance pedestal
The digitlization identity ID of the maintenance pedestal is written in RFID card;
The production line production capacity of concrete prefabricated element corresponding to the digitlization identity ID of pedestal is conserved described in real-time update
Data;
The production line capacity data of the updated concrete prefabricated element of data terminal timing acquiring.
Here, for the production figures for realizing concrete prefabricated element, for supporting for each production concrete prefabricated element
It protects pedestal and binds a RFID card, the digitlization identity ID as maintenance pedestal.Realize the precision of each pedestal production component,
Real-time update conserves pedestal production status, the real-time output of statistics disparity items, different parts component.
In concrete prefabricated element production one embodiment of production line monitoring method of the invention, further includes:
Template for each production concrete prefabricated element binds a RFID card, is written to the RFID card of the template
Digitize identity ID;
The corresponding use state of digitlization identity ID of each template of real-time update.
Here, the digitlization of the template to realize production concrete prefabricated element, is that a template binds a RFID card,
Digitlization identity ID as template.The use state of real-time update template realizes the optimization turnover of each piece of template.
In concrete prefabricated element production one embodiment of production line monitoring method of the invention, further includes:
The storage machine data bank for establishing the production raw material of concrete prefabricated element analyzes the storage processing number in real time
According to demand of stocking up, storage quantity, the dynamic relationship of processing progress of the production raw material in library;
Step S4, according to the difference of the sum of the field demand data and inventory data and production line capacity data, to life
Producing line capacity data carries out analysis and regulation, comprising:
The digitlization identity ID of the corresponding use state of digitlization identity ID, the maintenance pedestal based on each template
The demand of stocking up of the production line capacity data of corresponding concrete prefabricated element and the production raw material, adds storage quantity
The dynamic relationship of work progress, using shop-floor management technology to it is described maintenance pedestal, template and produce raw material processing, stock up
Optimal combination adjustment is carried out, so that the field demand data are equal with the sum of inventory data and production line capacity data.
Here, breakeven analysis is based on, using shop-floor management technology to the maintenance pedestal, template and production former material
The processing of material, stocking up carries out optimal combination adjustment, to realize the field demand data and inventory data and production line production capacity
The sum of data are equal.
The present invention also provides another concrete prefabricated elements to make production line monitoring system, comprising:
Data terminal is produced for the field demand data of timing acquiring concrete prefabricated element, inventory data and production line
Energy data, and it is sent to server;
Server, after receiving the field demand data, inventory data and production line capacity data, by the scene
Demand data is compared with the sum of inventory data and production line capacity data, judge inventory data and production line capacity data it
Whether the field demand data are met;If satisfied, then keeping existing production line capacity data;If not satisfied, then basis
The difference of the sum of the field demand data and inventory data and production line capacity data, analyzes production line capacity data
Adjustment, until meeting the requirement of the field demand data.
Further, in above system, further includes:
Division module divides reservoir area for the different type according to concrete prefabricated element, and divides according to engineering, position
Warehouse compartment in each reservoir area binds a RFID card for each warehouse compartment, the digitlization identity ID of warehouse compartment is written to each RFID card,
Two dimensional code is pasted on the concrete prefabricated element in each warehouse compartment;
The data terminal, for the scanning of reading and two dimensional code by the RFID, timing acquiring is concrete prefabricated
The inventory data of component.
Further, in above system, further includes:
Binding module, for binding a RFID card for the maintenance pedestal of each production concrete prefabricated element, to institute
The digitlization identity ID of the maintenance pedestal is written in the RFID card for stating maintenance pedestal;The digital incarnation of pedestal is conserved described in real-time update
The production line capacity data of concrete prefabricated element corresponding to part ID;
The data terminal, the production line capacity data for the updated concrete prefabricated element of timing acquiring.
Further, in above system, the binding module is also used to as each production concrete prefabricated element
Template binds a RFID card, and digitlization identity ID is written to the RFID card of the template;The number of each template of real-time update
The corresponding use state of word incarnation part ID.
Further, in above system, the server is also used to establish the production raw material of concrete prefabricated element
Storage machine data bank, analyze in real time the demand of stocking up of production raw material in the storage machine data bank, storage quantity,
The dynamic relationship of processing progress;The corresponding use state of digitlization identity ID, the maintenance pedestal based on each template
The demand of stocking up of the production line capacity data of concrete prefabricated element corresponding to digitlization identity ID and the production raw material,
Storage quantity, the dynamic relationship of processing progress, using shop-floor management technology to the maintenance pedestal, template and production raw material
Processing, stocking up optimizes combination adjustment so that the field demand data and inventory data and production line capacity data it
With it is equal.
For details, reference can be made to the corresponding parts of each method embodiment for the detailed content of each system embodiment of the present invention, here, not
It repeats again.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other
The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
Professional further appreciates that, unit described in conjunction with the examples disclosed in the embodiments of the present disclosure
And algorithm steps, can be realized with electronic hardware, computer software, or a combination of the two, in order to clearly demonstrate hardware and
The interchangeability of software generally describes each exemplary composition and step according to function in the above description.These
Function is implemented in hardware or software actually, the specific application and design constraint depending on technical solution.Profession
Technical staff can use different methods to achieve the described function each specific application, but this realization is not answered
Think beyond the scope of this invention.
Obviously, those skilled in the art can carry out various modification and variations without departing from spirit of the invention to invention
And range.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies range it
Interior, then the invention is also intended to include including these modification and variations.
Claims (10)
1. a kind of concrete prefabricated element makes production line monitoring method characterized by comprising
Field demand data, inventory data and the production line capacity data of data terminal timing acquiring concrete prefabricated element, and
It is sent to server;
After server receives the field demand data, inventory data and production line capacity data, by the field demand data
It is compared with the sum of inventory data and production line capacity data, judges whether the sum of inventory data and production line capacity data are full
The foot field demand data;
If satisfied, then keeping existing production line capacity data;
If not satisfied, then according to the difference of the sum of the field demand data and inventory data and production line capacity data, to life
Producing line capacity data carries out analysis and regulation, until meeting the requirement of the field demand data.
2. concrete prefabricated element as described in claim 1 makes production line monitoring method, which is characterized in that data terminal is fixed
When acquire concrete prefabricated element inventory data, comprising:
Reservoir area is divided according to the different type of concrete prefabricated element, and divides the warehouse compartment in each reservoir area according to engineering, position,
A RFID card is bound for each warehouse compartment, it is mixed in each warehouse compartment to the digitlization identity ID of each RFID card write-in warehouse compartment
Two dimensional code is pasted on solidifying soil prefabricated components, passes through the reading of the RFID and the scanning of two dimensional code, data terminal timing acquiring coagulation
The inventory data of native prefabricated components.
3. concrete prefabricated element as claimed in claim 2 makes production line monitoring method, which is characterized in that data terminal is fixed
When acquire concrete prefabricated element production line capacity data, comprising:
Maintenance pedestal for each production concrete prefabricated element binds a RFID card, to the RFID card of the maintenance pedestal
The digitlization identity ID of the maintenance pedestal is written;
The production line capacity data of concrete prefabricated element corresponding to the digitlization identity ID of pedestal is conserved described in real-time update;
The production line capacity data of the updated concrete prefabricated element of data terminal timing acquiring.
4. concrete prefabricated element as claimed in claim 3 makes production line monitoring method, which is characterized in that further include:
Template for each production concrete prefabricated element binds a RFID card, and number is written to the RFID card of the template
Incarnation part ID;
The corresponding use state of digitlization identity ID of each template of real-time update.
5. concrete prefabricated element as claimed in claim 4 makes production line monitoring method, which is characterized in that further include:
The storage machine data bank for establishing the production raw material of concrete prefabricated element, analyzes the storage machine data bank in real time
In production raw material demand of stocking up, storage quantity, the dynamic relationship of processing progress;
According to the difference of the sum of the field demand data and inventory data and production line capacity data, to production line capacity data
Carry out analysis and regulation, comprising:
The digitlization identity ID institute of the corresponding use state of digitlization identity ID, the maintenance pedestal based on each template is right
The production line capacity data for the concrete prefabricated element answered and the production demand of stocking up of raw material, storage quantity, process into
The dynamic relationship of degree to the maintenance pedestal, template and produces the processing of raw material, progress of stocking up using shop-floor management technology
Optimum organization adjustment, so that the field demand data are equal with the sum of inventory data and production line capacity data.
6. a kind of concrete prefabricated element makes production line monitoring system characterized by comprising
Data terminal, for the field demand data of timing acquiring concrete prefabricated element, inventory data and production line production capacity number
According to, and it is sent to server;
Server, after receiving the field demand data, inventory data and production line capacity data, by the field demand
Data are compared with the sum of inventory data and production line capacity data, judge that the sum of inventory data and production line capacity data are
It is no to meet the field demand data;If satisfied, then keeping existing production line capacity data;If not satisfied, then according to
The difference of the sum of field demand data and inventory data and production line capacity data, carries out analysis tune to production line capacity data
It is whole, until meeting the requirement of the field demand data.
7. concrete prefabricated element as claimed in claim 6 makes production line monitoring system, which is characterized in that further include:
Division module divides reservoir area for the different type according to concrete prefabricated element, and each according to engineering, position division
Warehouse compartment in reservoir area binds a RFID card for each warehouse compartment, to the digitlization identity ID of each RFID card write-in warehouse compartment, every
Two dimensional code is pasted on concrete prefabricated element in a warehouse compartment;
The data terminal, for the scanning of reading and two dimensional code by the RFID, timing acquiring concrete prefabricated element
Inventory data.
8. concrete prefabricated element as claimed in claim 7 makes production line monitoring system, which is characterized in that further include:
Binding module is supported for binding a RFID card for the maintenance pedestal of each production concrete prefabricated element to described
The digitlization identity ID of the maintenance pedestal is written in the RFID card of shield pedestal;The digitlization identity ID of pedestal is conserved described in real-time update
The production line capacity data of corresponding concrete prefabricated element;
The data terminal, the production line capacity data for the updated concrete prefabricated element of timing acquiring.
9. concrete prefabricated element as claimed in claim 8 makes production line monitoring system, which is characterized in that the binding mould
Block is also used to bind a RFID card for the template of each production concrete prefabricated element, write to the RFID card of the template
Enter to digitize identity ID;The corresponding use state of digitlization identity ID of each template of real-time update.
10. concrete prefabricated element as claimed in claim 9 makes production line monitoring system, which is characterized in that the service
Device is also used to establish the storage machine data bank of the production raw material of concrete prefabricated element, analyzes the storage processing in real time
Demand of stocking up, storage quantity, the dynamic relationship of processing progress of production raw material in database;Number based on each template
The life of concrete prefabricated element corresponding to the corresponding use state of word incarnation part ID, the digitlization identity ID for conserving pedestal
Demand of stocking up, storage quantity, the dynamic relationship of processing progress of producing line capacity data and the production raw material, using production line
Emulation technology to it is described maintenance pedestal, template and produce raw material processing, stock up optimize combination adjustment so that described existing
Field demand data is equal with the sum of inventory data and production line capacity data.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810764596.0A CN109189006A (en) | 2018-07-12 | 2018-07-12 | Concrete prefabricated element makes production line monitoring method and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810764596.0A CN109189006A (en) | 2018-07-12 | 2018-07-12 | Concrete prefabricated element makes production line monitoring method and system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109189006A true CN109189006A (en) | 2019-01-11 |
Family
ID=64935993
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810764596.0A Pending CN109189006A (en) | 2018-07-12 | 2018-07-12 | Concrete prefabricated element makes production line monitoring method and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109189006A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030018546A1 (en) * | 2001-07-20 | 2003-01-23 | International Business Machines Corporation | Network-based supply chain management method |
CN1508731A (en) * | 2002-12-14 | 2004-06-30 | 鸿富锦精密工业(深圳)有限公司 | Main production arrangement management system and method |
CN1556486A (en) * | 2003-12-31 | 2004-12-22 | 冶金自动化研究设计院 | Integrated iron and steel enterprise production process on line planning and controlling system and method |
CN103310310A (en) * | 2013-06-25 | 2013-09-18 | 浙江大学 | Multi-type steel batch rolling dynamic production planning system |
CN105045236A (en) * | 2015-07-21 | 2015-11-11 | 江苏云道信息技术有限公司 | Assembly line production scheduling method and system |
CN107341596A (en) * | 2017-06-20 | 2017-11-10 | 上海交通大学 | Task optimization method based on level Task Network and critical path method |
-
2018
- 2018-07-12 CN CN201810764596.0A patent/CN109189006A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20030018546A1 (en) * | 2001-07-20 | 2003-01-23 | International Business Machines Corporation | Network-based supply chain management method |
CN1508731A (en) * | 2002-12-14 | 2004-06-30 | 鸿富锦精密工业(深圳)有限公司 | Main production arrangement management system and method |
CN1556486A (en) * | 2003-12-31 | 2004-12-22 | 冶金自动化研究设计院 | Integrated iron and steel enterprise production process on line planning and controlling system and method |
CN103310310A (en) * | 2013-06-25 | 2013-09-18 | 浙江大学 | Multi-type steel batch rolling dynamic production planning system |
CN105045236A (en) * | 2015-07-21 | 2015-11-11 | 江苏云道信息技术有限公司 | Assembly line production scheduling method and system |
CN107341596A (en) * | 2017-06-20 | 2017-11-10 | 上海交通大学 | Task optimization method based on level Task Network and critical path method |
Non-Patent Citations (3)
Title |
---|
于宝琴: "《现代物流技术与应用》", 31 January 2017, 重庆大学出版社 * |
宋文官,易艳红: "《卓越•连锁经营管理系列 连锁企业信息管理》", 31 July 2016, 复旦大学出版社 * |
彭力: "《无线射频识别(RFID)技术基础 第2版》", 31 August 2016, 北京航空航天大学出版社 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104866599B (en) | The production method and system of Visual Report Forms | |
Cordeiro et al. | Theoretical proposal of steps for the implementation of the Industry 4.0 concept | |
CN103955754A (en) | Mold workshop scheduling method based on real-time production data collection | |
CN103729735A (en) | Engineering progress condition management method based on BS frame | |
CN104423960A (en) | Continuous project integration method and continuous project integration system | |
CN106648716A (en) | Increment updating method, server and intelligent card | |
CN102567593A (en) | Parameterization designing system for non-standard parts of hydraulic cylinders and method thereof | |
CN103745406A (en) | Visual ore dressing production full-flow technic index optimized decision system and method thereof | |
CN108989358A (en) | One kind being based on ICP/IP protocol frame operation data acquisition methods | |
CN103646303A (en) | A flexible management information system used for customizing processes and forms in a ship enterprise | |
CN106709612A (en) | System and method for carrying out data interaction between ERP and MES | |
US10019467B2 (en) | Method, system and computer readable medium for managing design updates in a manufacturing execution system | |
CN109522527A (en) | A method of site construction technology establishment is carried out using software systems | |
Delfino et al. | Industrial internet of things: Digital twins | |
Han et al. | A novel IoT-Cloud-BIM based intelligent information management system in building industrialization | |
Herčko et al. | Industry 4.0 as a factor of productivity increase | |
CN103729742A (en) | Data resource management system based on SOA framework and model drive framework | |
CN109977128B (en) | Power grid planning data fusion method based on temporal dimension | |
CN115239173A (en) | Scheduling plan generation method and device, electronic equipment and storage medium | |
CN109189006A (en) | Concrete prefabricated element makes production line monitoring method and system | |
CN111815235A (en) | Engineering material management and control method and device based on BIM, storage medium and computer equipment | |
De Carolis et al. | Cyber-physical systems in manufacturing: future trends and research priorities | |
CN111027803A (en) | Construction management method and construction management system | |
CN115719189A (en) | Material management method, platform, medium and system | |
CN102479348A (en) | Code reuse-oriented MES (manufacturing execution system) business modeling system and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190111 |
|