CN109138541A - Biomass and domestic garbage burning electricity generation integration plant area arragement construction - Google Patents
Biomass and domestic garbage burning electricity generation integration plant area arragement construction Download PDFInfo
- Publication number
- CN109138541A CN109138541A CN201810759343.4A CN201810759343A CN109138541A CN 109138541 A CN109138541 A CN 109138541A CN 201810759343 A CN201810759343 A CN 201810759343A CN 109138541 A CN109138541 A CN 109138541A
- Authority
- CN
- China
- Prior art keywords
- area
- biomass
- power generation
- plant area
- steam turbine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H5/00—Buildings or groups of buildings for industrial or agricultural purposes
- E04H5/02—Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Engine Equipment That Uses Special Cycles (AREA)
Abstract
The invention discloses a kind of biomass and domestic garbage burning electricity generation integration plant area arragement constructions, including the administration quarter for life office, against the circulation drainage facility area and main building area of administration quarter, against the fuel infrastructures area in circulation drainage facility area and main building area, the circulation drainage facility area includes comprehensive pump house and cooling stack, the main building area includes air compressor house and warehouse, biomass power generation plant area and garbage incinerating power plant area, the biomass power generation plant area and garbage incinerating power plant area share entrance hall and control room, steam turbine building and chimney, outdoor stock ground is disposed in the fuel infrastructures area, siccative canopy, penetrating fluid treatment region, oil-firing pump house, truck scale and control room.The present invention can either solve zonal garbage problem, and can rationally utilize biomass energy, have energy conservation and environmental protection, build the advantages such as low with operation cost.
Description
Technical field
The present invention relates to technical field of power generation, and in particular to a kind of biomass and domestic garbage burning electricity generation integration plant area
Arragement construction.
Background technique
Country's waste incineration and generating electricity has had certain scale in medium-sized or above city at present, has the scale of sole investment
Benefit.But in samll cities and towns and rural area, since population is limited, the small scale of independent waste incineration and generating electricity, benefit is restricted,
Do not have the scale and benefit of sole investment, therefore builds slow.Simultaneously as the garbage disposal that town & country does not perfect
Mode, a large amount of rubbish cannot be handled, be posed a big pressure to environment.In addition, due to having preferably in samll cities and towns and rural area
Biomass resource, country encourage biomass power generation project, to reduce environmental pollution caused by due to villager's crop straw burning.But by
It layouts in current state's endogenous substance power generation by waste combustion project more, stalk resource is also subject to certain restrictions, and individual biomass is burnt
Burning power generation project, which is often subject to stalk resource amount deficiency, causes operation and income to be affected, and the construction and operation of biomass all go out
The stagnation of existing biggish puzzlement.There is an urgent need to new modes for current status to solve the problems, such as this.
Summary of the invention
The purpose of the invention is to overcome the shortcomings of above-mentioned background technique, a kind of biomass and consumer waste incineration are provided
Generating integrated plant area's arragement construction.
In order to achieve the goal above, a kind of biomass provided by the invention and domestic garbage burning electricity generation integration plant area cloth
Structure is set, including the administration quarter for life office, the circulation drainage facility area against administration quarter and main building area, abuts recirculated water
The fuel infrastructures area in facility area and main building area, the circulation drainage facility area include comprehensive pump house and cooling stack,
The main building area includes air compressor house and warehouse, biomass power generation plant area and garbage incinerating power plant area, the biomass fermentation
Area of power plant includes between entrance hall and control room, steam turbine building, biomass boiler room, slag, desulfurizer, deduster, biomass air-introduced machine
And chimney, the garbage incinerating power plant area include entrance hall and control room, steam turbine building, discharging hall, dump pit, waste incineration pot
Between furnace and waste heat boiler, garbage flue gas Clean room, rubbish air-introduced machine and chimney, the biomass power generation plant area and waste incineration hair
Area of power plant shares entrance hall and control room, steam turbine building and chimney, and outdoor stock ground is disposed in the fuel infrastructures area, siccative canopy, is seeped
Transparent liquid treatment region, oil-firing pump house, truck scale and control room.
It is equipped with deaerator bay in above scheme, in the steam turbine building, biomass power generation unit, waste incineration and generating electricity unit, rises
Heavy-duty machine and space for maintenance, the biomass power generation unit and waste incineration and generating electricity unit are coaxially arranged, and the space for maintenance is located at
Biomass power generation unit end corresponds to biomass power generation unit in the deaerator bay and waste incineration and generating electricity unit is respectively equipped with one
Press membrane deaerator, the high pressure rotary film oxygen eliminator and middle pressure membrane deaerator by removing in platform high pressure rotary film oxygen eliminator and one
Oxygen heating steam main pipe, which is drawn, to be connect.
In above scheme, the biomass power generation unit is 1 × 30MW high temperature, high pressure, condensing steam turbine generator group, institute
Stating waste incineration and generating electricity unit is 1 × 9MW medium temperature, middle pressure, condensing steam turbine generator group, the biomass power generation unit and rubbish
The operating layer absolute altitude of rubbish power generation by waste combustion unit is 8m, and the operating pressure of the high pressure rotary film oxygen eliminator is 0.588MPa, described
The operating pressure of middle pressure membrane deaerator is 0.27MPa, and the crane is the electrical bibeam bridge crane of 32/10t, described
Except oxygen layer absolute altitude is 15.0m in deaerator bay.
Technical solution provided by the invention has the benefit that
The present invention by by garbage incinerating power plant area and biomass power generation plant area science, rationally, effectively combine together,
Comp comprehensive layout considers as a whole, compared to exploitation two independent projects of operation, reduces whole development, construction and operation cost, increases
The whole investment repayment of project, the ability to ward off risks is stronger, not only sufficiently solves zonal garbage problem, but also reasonable employment biology
Mass-energy source, energy conservation and environmental protection is great to social effect, has preferable development prospect.
Detailed description of the invention
Fig. 1 is arragement construction schematic diagram of the invention;
Fig. 2 is Tu1Zhong main building area arragement construction schematic diagram;
Fig. 3 is steam turbine building overlooking structure diagram in Fig. 2;
Fig. 4 is steam turbine building section structure diagram in Fig. 2.
In figure: administration quarter 1 recycles drainage facility area 2, comprehensive pump house 2a, cooling stack 2b, main building area 3, sky
Press room and warehouse 3a, biomass power generation plant area 3b, biomass boiler room 3b1,3b2 between slag, desulfurizer 3b3, deduster
3b4, biomass air-introduced machine 3b5, garbage incinerating power plant area 3c, discharging hall 3c1, dump pit 3c2, garbage burning boiler and remaining
3c3 between heat boiler, garbage flue gas Clean room 3c4, rubbish air-introduced machine 3c5, entrance hall and control room 3d, steam turbine building 3e, deaerator bay
3e1, biomass power generation unit 3e2, waste incineration and generating electricity unit 3e3, crane 3e4, space for maintenance 3e5, high pressure revolve film deoxygenation
Steam main pipe 3e8 is heated in device 3e6, middle pressure membrane deaerator 3e7, deoxygenation, chimney 3f, fuel infrastructures area 4, and outdoor stock ground 4a is done
Material shed 4b, penetrating fluid treatment region 4c, oil-firing pump house 4d, truck scale and control room 4e.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and embodiments.
Biomass and domestic garbage burning electricity generation integration plant area arragement construction as shown in Figure 1, including done for living
Public administration quarter 1, against the circulation drainage facility area 2 of administration quarter and main building area 3, against circulation drainage facility area 2 and main building area 3
Fuel infrastructures area 4, the circulation drainage facility area 2 includes comprehensive pump house 2a and cooling stack 2b, the main building
Area 3 includes air compressor house and warehouse 3a, biomass power generation plant area 3b and garbage incinerating power plant area 3c, the biomass power plant
Area 3b includes 3b2, desulfurizer 3b3, deduster between entrance hall and control room 3d, steam turbine building 3e, biomass boiler room 3b1, slag
3b4, biomass air-introduced machine 3b5 and chimney 3f, the garbage incinerating power plant area 3c include entrance hall and control room 3d, steam turbine building
3c3, garbage flue gas Clean room 3c4, rubbish draw between 3e, discharging hall 3c1, dump pit 3c2, garbage burning boiler and waste heat boiler
Blower 3c5 and chimney 3f, the biomass power generation plant area 3b and garbage incinerating power plant area 3c share entrance hall and control room 3d, vapour
Computer room 3e and chimney 3f is disposed with outdoor stock ground 4a, siccative canopy 4b, penetrating fluid treatment region 4c, fuel oil in the fuel infrastructures area 4
Pump house 4d and truck scale and control room 4e.
It is equipped with deaerator bay 3e1 in above-mentioned steam turbine building 3e, biomass power generation unit 3e2, waste incineration and generating electricity unit 3e3, rises
Heavy-duty machine 3e4 and space for maintenance 3e5, the biomass power generation unit 3e2 and waste incineration and generating electricity unit 3e3 are coaxially arranged, described
Space for maintenance 3e5 is located at the end biomass power generation unit 3e2, corresponds to biomass power generation unit 3e2 and rubbish in the deaerator bay 3e1
Rubbish power generation by waste combustion unit 3e3 is respectively equipped with pressure membrane deaerator 3e7, the height in a high pressure rotary film oxygen eliminator 3e6 and one
Pressure membrane deaerator 3e6 and middle pressure membrane deaerator 3e7 is drawn by deoxygenation heating steam main pipe 3e8 to be connect.
Above-mentioned biomass power generation unit 3e2 is 1 × 30MW high temperature, high pressure, condensing steam turbine generator group, and the rubbish is burnt
Burning generating set 3e3 is 1 × 9MW medium temperature, middle pressure, condensing steam turbine generator group, the biomass power generation unit 3e2 and rubbish
The operating layer absolute altitude of power generation by waste combustion unit 3e3 is 8m, and the operating pressure of the high pressure rotary film oxygen eliminator 3e6 is 0.588MPa,
The operating pressure of medium pressure membrane deaerator 3e7 is 0.27MPa, and the crane 3e4 is the electrical bibeam bridge of 32/10t
Crane, the deaerator bay 3e1 are interior except oxygen layer absolute altitude is 15.0m.
Other unspecified parts belong to the prior art.
Claims (3)
1. biomass and domestic garbage burning electricity generation integration plant area arragement construction, it is characterised in that: including being used for life office
Administration quarter (1), the circulation drainage facility area (2) against administration quarter and main building area (3), against circulation drainage facility area (2) and main
The fuel infrastructures area (4) in workshop area (3), the circulation drainage facility area (2) include that comprehensive pump house (2a) and gravity-flow ventilation are cooling
Tower (2b), the main building area (3) include air compressor house and warehouse (3a), biomass power generation plant area (3b) and waste incineration and generating electricity
Plant area (3c), the biomass power generation plant area (3b) include entrance hall and control room (3d), steam turbine building (3e), biomass boiler room
(3b2), desulfurizer (3b3), deduster (3b4), biomass air-introduced machine (3b5) and chimney (3f), the rubbish between (3b1), slag
Rubbish power generation by waste combustion plant area (3c) include entrance hall and control room (3d), steam turbine building (3e), discharging hall (3c1), dump pit (3c2),
(3c3), garbage flue gas Clean room (3c4), rubbish air-introduced machine (3c5) and chimney (3f) between garbage burning boiler and waste heat boiler,
The biomass power generation plant area (3b) and garbage incinerating power plant area (3c) share entrance hall and control room (3d), steam turbine building (3e) and
Chimney (3f), the fuel infrastructures area (4) is interior to be disposed with outdoor stock ground (4a), siccative canopy (4b), penetrating fluid treatment region (4c), combustion
Oil pump room (4d) and truck scale and control room (4e).
2. biomass as described in claim 1 and domestic garbage burning electricity generation integration plant area arragement construction, it is characterised in that:
It is equipped with deaerator bay (3e1) in the steam turbine building (3e), biomass power generation unit (3e2), waste incineration and generating electricity unit (3e3), rises
Heavy-duty machine (3e4) and space for maintenance (3e5), the biomass power generation unit (3e2) and waste incineration and generating electricity unit (3e3) coaxial cloth
It sets, the space for maintenance (3e5) is located at the end biomass power generation unit (3e2), corresponds to biomass fermentation in the deaerator bay (3e1)
Motor group (3e2) and waste incineration and generating electricity unit (3e3), which are respectively equipped in a high pressure rotary film oxygen eliminator (3e6) and one, presses rotation
Film oxygen-eliminating device (3e7), the high pressure rotary film oxygen eliminator (3e6) and middle pressure membrane deaerator (3e7) heat steam mother by deoxygenation
Pipe (3e8), which draws, to be connect.
3. biomass as claimed in claim 2 and domestic garbage burning electricity generation integration plant area arragement construction, it is characterised in that:
The biomass power generation unit (3e2) is 1 × 30MW high temperature, high pressure, condensing steam turbine generator group, the waste incineration and generating electricity
Unit (3e3) is 1 × 9MW medium temperature, middle pressure, condensing steam turbine generator group, and the biomass power generation unit (3e2) and rubbish are burnt
The operating layer absolute altitude for burning generating set (3e3) is 8m, and the operating pressure of the high pressure rotary film oxygen eliminator (3e6) is
0.588MPa, the operating pressure of medium pressure membrane deaerator (3e7) are 0.27MPa, and the crane (3e4) is 32/10t's
Electrical bibeam bridge crane, the deaerator bay (3e1) are interior except oxygen layer absolute altitude is 15.0m.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810759343.4A CN109138541B (en) | 2018-07-11 | 2018-07-11 | Biomass and domestic garbage incineration power generation integrated plant area arrangement structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810759343.4A CN109138541B (en) | 2018-07-11 | 2018-07-11 | Biomass and domestic garbage incineration power generation integrated plant area arrangement structure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109138541A true CN109138541A (en) | 2019-01-04 |
CN109138541B CN109138541B (en) | 2020-10-02 |
Family
ID=64800169
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810759343.4A Active CN109138541B (en) | 2018-07-11 | 2018-07-11 | Biomass and domestic garbage incineration power generation integrated plant area arrangement structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109138541B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110130685A (en) * | 2019-05-09 | 2019-08-16 | 山西省工业设备安装集团有限公司 | A kind of domestic garbage burning electricity generation construction techniques |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102588020A (en) * | 2011-01-07 | 2012-07-18 | 中国电力工程顾问集团公司 | Solar power generation and thermal power generation combined turbine-generator unit and realizing method |
CN205420297U (en) * | 2016-04-01 | 2016-08-03 | 中冶华天工程技术有限公司 | Distributed energy system based on domestic waste and living beings |
CN106287642A (en) * | 2016-09-05 | 2017-01-04 | 重庆科技学院 | Combustion gas based on refuse gasification and the coaxial combined generating system of steam turbine |
JP2017155739A (en) * | 2016-03-04 | 2017-09-07 | 三菱日立パワーシステムズ株式会社 | Power generating system |
-
2018
- 2018-07-11 CN CN201810759343.4A patent/CN109138541B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102588020A (en) * | 2011-01-07 | 2012-07-18 | 中国电力工程顾问集团公司 | Solar power generation and thermal power generation combined turbine-generator unit and realizing method |
JP2017155739A (en) * | 2016-03-04 | 2017-09-07 | 三菱日立パワーシステムズ株式会社 | Power generating system |
CN205420297U (en) * | 2016-04-01 | 2016-08-03 | 中冶华天工程技术有限公司 | Distributed energy system based on domestic waste and living beings |
CN106287642A (en) * | 2016-09-05 | 2017-01-04 | 重庆科技学院 | Combustion gas based on refuse gasification and the coaxial combined generating system of steam turbine |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110130685A (en) * | 2019-05-09 | 2019-08-16 | 山西省工业设备安装集团有限公司 | A kind of domestic garbage burning electricity generation construction techniques |
Also Published As
Publication number | Publication date |
---|---|
CN109138541B (en) | 2020-10-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206429276U (en) | A kind of thermal power plant's clean energy resource utilizes system | |
CN205065727U (en) | City solid waste burns power generation system in coordination | |
CN110465534A (en) | A kind of comprehensive energy for farm utilizes system | |
CN111156529A (en) | Method and system for preparing fuel incineration hazardous waste from domestic sludge | |
CN109138541A (en) | Biomass and domestic garbage burning electricity generation integration plant area arragement construction | |
CN208282120U (en) | Coal cooperates with combustion power generation system with rubbish | |
CN100584473C (en) | Distributed energy system for energy and resource integrated circulating utilization | |
CN202188770U (en) | Smoke and waste heat comprehensive utilization device of annular kiln | |
CN202647784U (en) | Household refuse incineration waste heat power generation system for compensating heat by virtue of solar energy | |
CN106940017A (en) | The system and method for coal-burning power plant's cooperated with consumer waste gasification | |
CN106171060A (en) | A kind of based on straw burning self-driving type rotary tillage system | |
CN108894546A (en) | Biomass and domestic garbage burning electricity generation integration main building arrangement structure | |
JPH08218652A (en) | House having energy converting system | |
CN109340774A (en) | A kind of power generator based on waste incineration | |
CN103574577A (en) | Biomass high-effect combined heat and power generation system | |
CN208652567U (en) | A kind of refuse burning system and combustion turbine combined complementary power supply device | |
CN208534620U (en) | A kind of environmental protection generating equipment | |
CN104129898B (en) | Solar energy mud constant temperature mummification harmless treatment device and method | |
CN203744215U (en) | Biomass high-effect combined heat and power generation system | |
CN202470074U (en) | System for winter garbage wet steam fermentation of household garbage incineration power plant | |
CN108518254A (en) | A kind of biomass fermentation electric equipment and its application method being applied to ground utility grid distribution | |
CN205481020U (en) | High -efficient small -size waste incinerator of multilayer formula | |
CN206447840U (en) | Combustion engine Combined Cycle Unit and biomass gasifying furnace integral type energy utilization system | |
CN219867899U (en) | Movable small-size domestic waste burns device | |
CN214949073U (en) | Energy comprehensive utilization system of kitchen waste treatment plant |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |