CN109128725A - A kind of welding for steel structure method - Google Patents

A kind of welding for steel structure method Download PDF

Info

Publication number
CN109128725A
CN109128725A CN201811334205.8A CN201811334205A CN109128725A CN 109128725 A CN109128725 A CN 109128725A CN 201811334205 A CN201811334205 A CN 201811334205A CN 109128725 A CN109128725 A CN 109128725A
Authority
CN
China
Prior art keywords
welding
steel construction
steel
steel structure
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811334205.8A
Other languages
Chinese (zh)
Inventor
蒋博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811334205.8A priority Critical patent/CN109128725A/en
Publication of CN109128725A publication Critical patent/CN109128725A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass

Abstract

The invention discloses a kind of welding for steel structure methods, by needing the end welded to be immersed in the cleaning liquid and acetic acid mixing liquid that ratio is 100:1 in steel construction, worker impregnates the spot after relaxation and rust stain polishing cleaning to steel structure surface by sand paper, it is rinsed and is air-dried by clear water after cleaning, drilling between steel construction is welded and fixed with screw connection by welding gun by operator, the output end of protective gas container is opened while to welding between steel construction, it is cut by cutting machine the position that screw protrudes from steel structure surface, and it is polished by grinding apparatus welding for steel structure position, keep the surface of steel construction for after smooth shape, one layer of chlorinated rubber paint is coated at welding for steel structure, after being dried to chlorinated rubber paint, the surface layer of steel construction sprays F-C paint again, the surface of F-C paint is coated again anti- Rust oil effectively improves the rust resistance and corrosion resistance effect when use of steel construction later period, improves the fastness of welding for steel structure.

Description

A kind of welding for steel structure method
Technical field
The present invention relates to welding for steel structure field, specially a kind of welding for steel structure method.
Background technique
The structure that steel construction is made of steel material is one of main building construction types.Structure is mainly by fashioned iron With the components composition such as joist steel, steel column, steel truss made of steel plate etc., and using silanization, pure manganese phosphatization, washing drying, zinc-plated Equal derusting rust-proofings technique.Weld seam, bolt or rivet interlacement are generallyd use between each component or component.Because its self weight is lighter, and apply Work is easy, is widely used in the fields such as large-sized workshop, venue, Super High.
It there are three types of the connection type of steel construction is general, is welded to connect, is bolted and rivet interlacement.It is welded to connect because having Any orientation, angle and the shape of steel can be directly connected to, member section, saving steel, simple structure, system are not weakened It makes conveniently, the rigidity of connection is big, good seal performance, preferably uses automated job, is widely used the advantages that high production efficiency. Welded connecting is that the heat generated by electric arc makes welding rod and weldment local melting, weld seam is condensed into through cooling, thus by weldment It links into an integrated entity.In high-temperature soldering cooling procedure, the steel near weld seam are because of high temperature action formation heat affected area, due to not Uniform high temperature and cooling make structure generate residual stress and residual deformation and become fragile, and to the bearing capacity of steel construction, rigidity and make There is certain influence with performance.
Since steel construction is in moist and corrosive media environment, it is easy corrosion, especially weld between steel construction To object load-bearing capacity after being corroded, strong influence is caused to the fastness connected between steel construction.
Summary of the invention
The purpose of the present invention is to provide a kind of welding for steel structure methods, to solve mentioned above in the background art ask Topic.
To achieve the above object, the invention provides the following technical scheme: a kind of welding for steel structure method, specifically includes following Step:
S1, removing surface: the welding for steel structure end for needing to be welded and fixed is immersed in inside cleaning liquid, the steel construction weldering after immersion It connects end and is polished by grinding apparatus welding position, is dried after clearing up the spot of polishing position;
S2, drilling are fixed: the drilling that steel construction needs welding position to drill through suitable inner diameter by drilling machine, and welded in needs Two groups of steel constructions are worn the drilling opened up by screw and fixed;
S3, weld preparation: welding rod will be packed into inside welding gun, and to welding rod warm-up operation, the input terminal of welding gun is connected protection Gas container;
S4, welding for steel structure are fixed: drilling between steel construction is welded and fixed with screw connection after heating to welding rod for welding gun, right After fixed angle is reinforced between steel construction, the weld seam between steel construction is welded, and same to what is welded between steel construction When open protective gas container output end, by protective gas container output protection gas to the welding position between steel construction Protection;
S5, weld protective treatment: coating one layer of chlorinated rubber paint at welding for steel structure, is dried to chlorinated rubber paint Afterwards, the surface layer of steel construction sprays F-C paint again, coats antirust oil again to the surface of F-C paint.
Preferably, it is blended into acetic acid in S1 inside cleaning solution, the ratio of cleaning solution and acetic acid is 100:1, is welded to steel construction It connects end and impregnates 15-40min inside cleaning solution.
Preferably, S1 generates the steel construction after immersion by the polishing derusting of sand paper manual operation, and to polishing steel construction Rust by spray cleaning, and drying is air-dried to cleaning positions.
Preferably, carbon-dioxide protecting gas, and the output of gas shield container are filled in S3 inside gas shield container It holds corresponding with welding rod.
Preferably, perpendicular when being welded and fixed between S4 steel construction, the inclined drilling to starting between steel construction of screw Wear fixation, when level is welded and fixed between steel construction, using U-shaped structure screw respectively with need fixed steel construction end face The drilling opened up is fixed.
Preferably, screw uses mild steel structure setting, and screw passes through steel construction and extends the position of steel construction out by setting Standby cutting, keeps steel construction end face in same plane.
Preferably, coating chlorinated rubber paint in welding for steel structure position is before beaten welding position by sander in S5 Mill, keeps the finish of steel structure surface.
Preferably, for steel construction when spraying F-C paint, keeping steel construction peripheral temperature is 25 DEG C, humidity 80% in S5.
Compared with prior art, the beneficial effects of the present invention are: the present invention is soaked by the end for needing to weld by steel construction The 30min in the cleaning liquid and acetic acid mixing liquid that ratio is 100:1 is steeped, the rust stain spot of welding for steel structure position is passed through Acetate structure impregnate relaxation after, to steel construction take out, worker by sand paper to steel structure surface impregnate relaxation after spot and Stain of becoming rusty, which is polished, clears up, and is rinsed and is air-dried by clear water after cleaning, while impregnating cleaning to steel construction, welding rod is mounted on welding gun On welding rod is preheated, drill to the position that needs to weld between steel construction, and bore position is fixed by screw, operation Drilling between steel construction is welded and fixed with screw connection by welding gun by person, right after reinforcing to fixed angle between steel construction Weld seam between steel construction is welded, and the output end of protective gas container is opened while to welding between steel construction, The welding position between steel construction is protected by protective gas container output protection gas, screw protrudes from steel structure surface Position cuts it by cutting machine, and is polished by grinding apparatus welding for steel structure position, keeps the surface of steel construction to be After smooth shape, one layer of chlorinated rubber paint is coated at welding for steel structure, after being dried to chlorinated rubber paint, the surface layer of steel construction F-C paint is sprayed again, antirust oil is coated again to the surface of F-C paint, and antirust when effectively improving the use of steel construction later period is anti- Corrosive effect improves the fastness of welding for steel structure.
Specific embodiment
Below in conjunction with illustrating in the embodiment of the present invention, technical solution in the embodiment of the present invention carries out clear Chu is fully described by, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments. Based on the embodiments of the present invention, obtained by those of ordinary skill in the art without making creative efforts all Other embodiments shall fall within the protection scope of the present invention.
Embodiment 1
The present invention provides a kind of welding for steel structure methods, specifically includes the following steps:
S1, removing surface: acetic acid is blended into the ratio of installation 100:1 inside steel construction derusting cleaning liquid body, needs to be welded and fixed Welding for steel structure end be immersed in inside cleaning liquid 15 minutes, the welding for steel structure end after immersion is manually right by sand paper Welding position polishing, the spot for generation of polishing is sprayed by clear water cleans, and air-dries steel construction location of moisture to drying;
S2, drilling are fixed: according to fixed angle is needed between steel construction, selecting the screw or U-shaped screw of T-shaped, steel knot Structure needs welding position to drill through the drilling of suitable inner diameter by drilling machine, and perpendicular when being welded and fixed between steel construction, screw is in Inclination wears fixation to the drilling started between steel construction, when level is welded and fixed between steel construction, using the screw of U-shaped structure It is fixed respectively with the drilling for needing fixed steel construction end face to open up;
S3, weld preparation: welding rod will be packed into inside welding gun, and to welding rod warm-up operation, the input terminal of welding gun is connected protection Gas container, is filled with carbon-dioxide protecting gas inside gas shield container, and the output end of gas shield container corresponds to welding gun Corresponding with welding rod installation place, when welding rod between steel construction to welding, carbon dioxide gas protects welding position, avoids sky Oxygen in gas enters the position welded between steel construction, and weld is led to problems such as slight crack, bubble occur;
S4, welding for steel structure are fixed: drilling between steel construction is welded and fixed with screw connection after heating to welding rod for welding gun, right After fixed angle is reinforced between steel construction, the weld seam between steel construction is welded, and same to what is welded between steel construction When open protective gas container output end, by protective gas container output protection gas to the welding position between steel construction Protection;
S5, weld protective treatment: after welding between steel construction, the position that screw protrudes from steel structure surface passes through cutting machine It is cut, and by grinding apparatus to welding for steel structure position polish, keep steel construction surface be smooth shape after, in steel knot Structure weld coats one layer of chlorinated rubber paint, and after dry to chlorinated rubber paint, keeping the temperature on steel construction periphery is 25 DEG C, humidity It is 80%, the surface layer of steel construction sprays F-C paint again, coats antirust oil again to the surface of F-C paint.
In summary it is said: steel structure surface being immersed in the cleaning liquid and acetic acid mixing liquid that ratio is 100:1 15min, it is too short to steel construction soaking time, cause spot and rust stain of steel structure surface etc. not to be impregnated completely, needs worker Either manually or by sand paper to the spot of steel structure surface and rust stain cleaning, welding for steel structure position can not be cleaned out, be caused When to welding for steel structure, welding position easily occurs being mingled with impurity, influences the fastness welded between steel construction, to influence steel knot The overall stability of structure.
Embodiment 2
The present invention provides a kind of welding for steel structure methods, specifically includes the following steps:
S1, removing surface: acetic acid is blended into the ratio of installation 100:1 inside steel construction derusting cleaning liquid body, needs to be welded and fixed Welding for steel structure end be immersed in inside cleaning liquid 40 minutes, the welding for steel structure end after immersion is manually right by sand paper Welding position polishing, the spot for generation of polishing is sprayed by clear water cleans, and air-dries steel construction location of moisture to drying;
S2, drilling are fixed: according to fixed angle is needed between steel construction, selecting the screw or U-shaped screw of T-shaped, steel knot Structure needs welding position to drill through the drilling of suitable inner diameter by drilling machine, and perpendicular when being welded and fixed between steel construction, screw is in Inclination wears fixation to the drilling started between steel construction, when level is welded and fixed between steel construction, using the screw of U-shaped structure It is fixed respectively with the drilling for needing fixed steel construction end face to open up;
S3, weld preparation: welding rod will be packed into inside welding gun, and to welding rod warm-up operation, the input terminal of welding gun is connected protection Gas container, is filled with carbon-dioxide protecting gas inside gas shield container, and the output end of gas shield container corresponds to welding gun Corresponding with welding rod installation place, when welding rod between steel construction to welding, carbon dioxide gas protects welding position, avoids sky Oxygen in gas enters the position welded between steel construction, and weld is led to problems such as slight crack, bubble occur;
S4, welding for steel structure are fixed: drilling between steel construction is welded and fixed with screw connection after heating to welding rod for welding gun, right After fixed angle is reinforced between steel construction, the weld seam between steel construction is welded, and same to what is welded between steel construction When open protective gas container output end, by protective gas container output protection gas to the welding position between steel construction Protection;
S5, weld protective treatment: after welding between steel construction, the position that screw protrudes from steel structure surface passes through cutting machine It is cut, and by grinding apparatus to welding for steel structure position polish, keep steel construction surface be smooth shape after, in steel knot Structure weld coats one layer of chlorinated rubber paint, and after being dried to chlorinated rubber paint, keeping the temperature on steel construction periphery is 25 DEG C, Humidity is 80%, and the surface layer of steel construction sprays F-C paint again, coats antirust oil again to the surface of F-C paint.
In summary described: steel structure surface to be immersed in the cleaning liquid and acetic acid mixing liquid that ratio is 100:1 40min causes to cause inside cleaning liquid when impregnating steel construction due to having the acetic acid of certain content in cleaning liquid Acetic acid affects to welding for steel structure position sour corrosion to the steel construction density being immersed in inside cleaning liquid, When worker impregnates position sanding operation to steel construction by sand paper, easily because worker is excessive to immersion position polishing dynamics or polishing Overlong time and cause the surface of steel construction to be worn seriously, influence to the welding between steel construction, after reducing welding for steel structure Service life.
Embodiment 3
A kind of welding for steel structure method, specifically includes the following steps:
S1, removing surface: acetic acid is blended into the ratio of installation 100:1 inside steel construction derusting cleaning liquid body, needs to be welded and fixed Welding for steel structure end be immersed in inside cleaning liquid 30 minutes, the welding for steel structure end after immersion is manually right by sand paper Welding position polishing, the spot for generation of polishing is sprayed by clear water cleans, and air-dries steel construction location of moisture to drying;
S2, drilling are fixed: according to fixed angle is needed between steel construction, selecting the screw or U-shaped screw of T-shaped, steel knot Structure needs welding position to drill through the drilling of suitable inner diameter by drilling machine, and perpendicular when being welded and fixed between steel construction, screw is in Inclination wears fixation to the drilling started between steel construction, when level is welded and fixed between steel construction, using the screw of U-shaped structure It is fixed respectively with the drilling for needing fixed steel construction end face to open up;
S3, weld preparation: welding rod will be packed into inside welding gun, and to welding rod warm-up operation, the input terminal of welding gun is connected protection Gas container, is filled with carbon-dioxide protecting gas inside gas shield container, and the output end of gas shield container corresponds to welding gun Corresponding with welding rod installation place, when welding rod between steel construction to welding, carbon dioxide gas protects welding position, avoids sky Oxygen in gas enters the position welded between steel construction, and weld is led to problems such as slight crack, bubble occur;
S4, welding for steel structure are fixed: drilling between steel construction is welded and fixed with screw connection after heating to welding rod for welding gun, right After fixed angle is reinforced between steel construction, the weld seam between steel construction is welded, and same to what is welded between steel construction When open protective gas container output end, by protective gas container output protection gas to the welding position between steel construction Protection;
S5, weld protective treatment: after welding between steel construction, the position that screw protrudes from steel structure surface passes through cutting machine It is cut, and by grinding apparatus to welding for steel structure position polish, keep steel construction surface be smooth shape after, in steel knot Structure weld coats one layer of chlorinated rubber paint, and after being dried to chlorinated rubber paint, the surface layer of steel construction sprays F-C paint again, Antirust oil is coated again to the surface of F-C paint.
In summary described: to need the end welded to be immersed in the cleaning liquid and acetic acid that ratio is 100:1 in steel construction 30min in mixing liquid takes steel construction after the rust stain spot of welding for steel structure position is impregnated relaxation by acetate structure Out, worker impregnates the spot after relaxation and rust stain polishing cleaning to steel structure surface by sand paper, is rushed after cleaning by clear water Wash it is air-dried, to steel construction impregnate clear up while, welding rod is mounted on welding gun, welding rod is preheated, between steel construction The position drilling for needing to weld, and fixes bore position by screw, operator by welding gun to drilling between steel construction and Screw connection is welded and fixed, and after reinforcing to fixed angle between steel construction, welds to the weld seam between steel construction, and To the output end for opening protective gas container while welding between steel construction, pass through protective gas container output protection gas pair Welding position protection between steel construction, it is cut by cutting machine in the position that screw protrudes from steel structure surface, and passes through Grinding apparatus polishes to welding for steel structure position, and keeping the surface of steel construction is the coating one at welding for steel structure after smooth shape Layer chlorinated rubber paint, after being dried to chlorinated rubber paint, the surface layer of steel construction sprays F-C paint again, to the surface of F-C paint Antirust oil is coated again, is effectively improved the rust resistance and corrosion resistance effect when use of steel construction later period, is improved the secured of welding for steel structure Property.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (8)

1. a kind of welding for steel structure method, it is characterised in that: specifically includes the following steps:
S1, removing surface: the welding for steel structure end for needing to be welded and fixed is immersed in inside cleaning liquid, the steel construction weldering after immersion It connects end and is polished by grinding apparatus welding position, is dried after clearing up the spot of polishing position;
S2, drilling are fixed: the drilling that steel construction needs welding position to drill through suitable inner diameter by drilling machine, and welded in needs Two groups of steel constructions are worn the drilling opened up by screw and fixed;
S3, weld preparation: welding rod will be packed into inside welding gun, and to welding rod warm-up operation, the input terminal of welding gun is connected protection Gas container;
S4, welding for steel structure are fixed: drilling between steel construction is welded and fixed with screw connection after heating to welding rod for welding gun, right After fixed angle is reinforced between steel construction, the weld seam between steel construction is welded, and same to what is welded between steel construction When open protective gas container output end, by protective gas container output protection gas to the welding position between steel construction Protection;
S5, weld protective treatment: coating one layer of chlorinated rubber paint at welding for steel structure, is dried to chlorinated rubber paint Afterwards, the surface layer of steel construction sprays F-C paint again, coats antirust oil again to the surface of F-C paint.
2. a kind of welding for steel structure method according to claim 1, it is characterised in that: be blended into vinegar in S1 inside cleaning solution The ratio of acid, cleaning solution and acetic acid is 100:1, and 15-40min is impregnated inside cleaning solution to welding for steel structure end.
3. a kind of welding for steel structure method according to claim 1, it is characterised in that: S1 passes through the steel construction after immersion The polishing derusting of sand paper manual operation, and the rust generated to polishing steel construction passes through spray cleaning, and air-dries drying to cleaning positions.
4. a kind of welding for steel structure method according to claim 1, it is characterised in that: filled inside gas shield container in S3 Enter carbon-dioxide protecting gas, and the output end of gas shield container is corresponding with welding rod.
5. a kind of welding for steel structure method according to claim 1, it is characterised in that: perpendicular welding between S4 steel construction When fixed, screw is inclined to wear fixation to the drilling started between steel construction, when level is welded and fixed between steel construction, uses The screw of U-shaped structure is fixed with the drilling for needing fixed steel construction end face to open up respectively.
6. a kind of welding for steel structure method according to claim 5, it is characterised in that: screw is set using low-carbon steel construction It sets, screw is cut across the position that steel construction extends steel construction out by equipment, keeps steel construction end face in same plane.
7. a kind of welding for steel structure method according to claim 1, it is characterised in that: applied in S5 to welding for steel structure position It is polished by sander before covering chlorinated rubber paint welding position, keeps the finish of steel structure surface.
8. a kind of welding for steel structure method according to claim 1, it is characterised in that: steel construction is in spraying F-C paint in S5 When, keeping steel construction peripheral temperature is 25 DEG C, humidity 80%.
CN201811334205.8A 2018-11-09 2018-11-09 A kind of welding for steel structure method Pending CN109128725A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811334205.8A CN109128725A (en) 2018-11-09 2018-11-09 A kind of welding for steel structure method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811334205.8A CN109128725A (en) 2018-11-09 2018-11-09 A kind of welding for steel structure method

Publications (1)

Publication Number Publication Date
CN109128725A true CN109128725A (en) 2019-01-04

Family

ID=64808065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811334205.8A Pending CN109128725A (en) 2018-11-09 2018-11-09 A kind of welding for steel structure method

Country Status (1)

Country Link
CN (1) CN109128725A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109746584A (en) * 2019-03-21 2019-05-14 风范绿色建筑(常熟)有限公司 A kind of welding for steel structure anti-corrosive technology
CN111408857A (en) * 2019-12-25 2020-07-14 丽水市正阳电力设计院有限公司 Treatment method for weather-resistant steel welding seam
CN115847100A (en) * 2023-02-28 2023-03-28 江门市润宇传感器科技有限公司 Welding equipment and welding method for anti-corrosion shell

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291883A (en) * 1999-04-09 2000-10-20 Toda Constr Co Ltd Method and device for curing welding of steel member
CN108436212A (en) * 2018-06-04 2018-08-24 哈尔滨沃丁科技开发有限公司 The welding method of aluminium alloy panel
CN108723559A (en) * 2018-06-29 2018-11-02 张维秀 A kind of steel-structure thick plate welding construction method under low-temperature environment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291883A (en) * 1999-04-09 2000-10-20 Toda Constr Co Ltd Method and device for curing welding of steel member
CN108436212A (en) * 2018-06-04 2018-08-24 哈尔滨沃丁科技开发有限公司 The welding method of aluminium alloy panel
CN108723559A (en) * 2018-06-29 2018-11-02 张维秀 A kind of steel-structure thick plate welding construction method under low-temperature environment

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
中华人民共和国第一机械工业部统编: "《电镀工工艺学》", 30 September 1982, 科学普及出版社 *
住房和建设部工程质量安全监管司等: "《全国民用建筑工程设计技术措施》", 31 December 2009, 中国计划出版社 *
余厚极: "《简明结构吊装手册》", 31 May 1995, 中国建筑工业出版社 *
韩庆华等: "《大跨建筑结构》", 31 January 2014, 天津大学出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109746584A (en) * 2019-03-21 2019-05-14 风范绿色建筑(常熟)有限公司 A kind of welding for steel structure anti-corrosive technology
CN111408857A (en) * 2019-12-25 2020-07-14 丽水市正阳电力设计院有限公司 Treatment method for weather-resistant steel welding seam
CN115847100A (en) * 2023-02-28 2023-03-28 江门市润宇传感器科技有限公司 Welding equipment and welding method for anti-corrosion shell

Similar Documents

Publication Publication Date Title
CN109128725A (en) A kind of welding for steel structure method
CN110640600A (en) Novel corrosion prevention process for offshore wind power tower
CN112403866A (en) Surface treatment method for anti-corrosion steel beam component and anti-corrosion steel beam component
CN101554677A (en) Explosive welding method for titanium-steel-stainless steel double-sided composite steel plate
CN110238014A (en) A kind of construction method of ship fresh-water tank coating
CN106811716A (en) The construction technology of anticorrosive composite coating of steel structure
CN104786001B (en) A kind of waste and old insulated tubing performance recovery technique
CN107419208A (en) A kind of surface zinc-plated processing technique of cast steel workpiece
CN106826124A (en) The processing method of rod member for grid
CN103586187A (en) Coating process for exported oil truck
CN101554679A (en) Explosive welding method for 2205 double-phase steel composite steel plate for large-scale hydraulic engineering
CN108251782A (en) A kind of sugar mill shaft element electric arc spraying repair novel construction skill
CN108723559A (en) A kind of steel-structure thick plate welding construction method under low-temperature environment
CN111451723B (en) Manufacturing process of baffle plate groove guide plate
CN101554674A (en) Explosive welding method for martensitic stainless steel 00Cr13Ni5Mo composite steel plate
CN101554675A (en) Explosive welding method for 410S stainless steel and CrMo steel composite steel plate
CN112958417A (en) Surface coating process of high-strength tensile alloy steel pipe
CN112091471B (en) Processing method of steel beam component structure and steel beam component structure
CN112458274A (en) Preparation method of fretting wear resistant coating on surface of titanium alloy workpiece
CN2923742Y (en) Sueprsonic-ceramic anti-corrosion coating for repairing reinforced welding part
CN109836027A (en) The restorative procedure of sludge drying device
CN113696103B (en) Long-service-life steel rail treatment method
CN111238286A (en) Anticorrosion treatment method for shell of shell-and-tube heat exchanger
CN112251596B (en) Method for improving fatigue performance of steel plate and butt-welded joint
CN101559518A (en) Explosive welding method of NO6625 alloy and 16MnR low alloy steel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104