CN109117570A - A kind of power distribution network optimized maintenance method based on distributed photovoltaic - Google Patents

A kind of power distribution network optimized maintenance method based on distributed photovoltaic Download PDF

Info

Publication number
CN109117570A
CN109117570A CN201810975803.7A CN201810975803A CN109117570A CN 109117570 A CN109117570 A CN 109117570A CN 201810975803 A CN201810975803 A CN 201810975803A CN 109117570 A CN109117570 A CN 109117570A
Authority
CN
China
Prior art keywords
maintenance
load
formula
individual
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810975803.7A
Other languages
Chinese (zh)
Inventor
徐孟霞
张二龙
钟成元
陈祥平
朱代发
甘新华
王富根
赵吴鹏
莫平生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Anqing Power Supply Co of State Grid Anhui Electric Power Co Ltd
Yuexi Power Supply Co of State Grid Anhui Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Anqing Power Supply Co of State Grid Anhui Electric Power Co Ltd
Yuexi Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Anqing Power Supply Co of State Grid Anhui Electric Power Co Ltd, Yuexi Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201810975803.7A priority Critical patent/CN109117570A/en
Publication of CN109117570A publication Critical patent/CN109117570A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/04Constraint-based CAD
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Health & Medical Sciences (AREA)
  • Operations Research (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Primary Health Care (AREA)
  • Quality & Reliability (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The power distribution network optimized maintenance method based on distributed photovoltaic that the invention discloses a kind of, comprising: the building of S1, repair time Optimized model;The building of S2, load transfer path Optimized model;The solution of S3, model.The present invention establishes the overhaul of the equipments time for considering a variety of constraint conditions and load transfer path combined optimization model, takes Revised genetic algorithum to be solved with load transfer path optimization problem for overhaul of the equipments is time-optimized, in the hope of global optimum.The overhaul of the equipments time is optimized first, then turns to be powered by other feeder lines by suitable path by the load influenced by maintenance by the optimization of load transfer path, to obtain optimal maintenance solution.Under the premise of guaranteeing system safety operation, the power supply reliability of system is improved to greatest extent, avoids repeating to have a power failure, reduces the loss of outage of user and power supply enterprise.

Description

A kind of power distribution network optimized maintenance method based on distributed photovoltaic
Technical field
The present invention relates to grid maintenance technical field, in particular a kind of power distribution network optimized maintenance based on distributed photovoltaic Method.
Background technique
In recent years, as policies at different levels are intensively put into effect, distributed photovoltaic power is developed rapidly.It is a large amount of distributed Power grid makes power distribution network become the multiterminal network interconnected throughout power supply and user by the single-terminal network of conventional radiation formula, The direction of energy no longer uniaxially flows to each load from substation bus bar, is possible to exist in the region of scheduled outage maintenance The distributed generation resource of isolated operation causes anti-power transmission, becomes the new risk for threatening service personnel's safety.In addition, a large amount of distributed Plant-grid connection low-voltage network, to power distribution network short circuit current level, power quality, relay protection, automation equipment movement and System stabilization etc. can all generate certain influence.
Traditional power distribution network maintenance solution formulate power loss load caused by thinking mainly passes through interconnection switch and will overhaul with Non- power loss route is connected, and gets around maintenance part and is powered, to reduce scope of power outage.Due to the limitation of line transmission capacity And the requirement that node voltage is stable, part this may by the load that interconnection switch is powered in traditional maintenance solution not yet It obtains and does not cut off, to ensure maintenance and power supply safety.
Summary of the invention
Technical problem to be solved by the present invention lies in provide a kind of power distribution network optimized maintenance side based on distributed photovoltaic Method has reached repair time optimization and the optimization of load transfer path by genetic algorithm.
In order to solve the above-mentioned technical problem, technical scheme is as follows:
A kind of power distribution network optimized maintenance method based on distributed photovoltaic, this method comprises:
The building of S1, repair time Optimized model: repair time optimization aim is to reduce the sale of electricity loss of power supply enterprise, It is as follows to establish repair time optimized mathematical model:
Objective function:
In formula: F is sale of electricity failure costs;P is electricity price;N is repair apparatus sum;T is maintenance period sum;pitFor t Power failure load caused by i-th of overhaul of the equipments of period;UitFor the situation of i-th of repair apparatus of t period, when taking 0, indicate Equipment operates normally, and when taking 1, indicates that equipment is stopped transport and overhauls;
Its constraint condition are as follows:
1) Line Flow constrains:
|Sl|≤Slmax
In formula: SlFor the trend of route l, SlmaxFor route l allow by trend limit value;
3) mutual exclusion maintenance constraint:
In order to avoid load point has a power failure in maintenance, some equipment cannot overhaul simultaneously, therefore formulate in maintenance plan It cannot be arranged in the identical period in journey;
xj>xi+Di+1
In formula: xiAnd xjThe respectively beginning repair time of ith and jth equipment;DiIt is lasting for i-th of overhaul of the equipments Duration (is uniformly converted to number of days);
3) resource constraint is overhauled:
Since resource is limited, the limitation that maintenance plan is also contemplated that service ability, including service personnel's quantity and skill are formulated Art ability, capacity of equipment etc.:
In formula: M is the equipment number that can be overhauled simultaneously, uitSituation is set for i-th of t period maintenance, when taking 0, is indicated Equipment operates normally, and when taking 1, indicates that equipment is stopped transport and overhauls;
4) time adjustment constraint: | xi-xi0|≤Λi
In formula: x0iIt is declared for i-th of equipment and starts the repair time;ΛiFor the i equipment adjustment time limit value;
5) constraint is overhauled simultaneously:
In a system, primary the problem of can solve that have a power failure wants comprehensively solve, does not allow to occur because inconsiderate It repeats to have a power failure and solves the problems, such as same system.Therefore, some equipment must overhaul simultaneously.In of that month all maintenance, it is all make it is same The maintenance of route, same node point power loss, is regarded as repeating interruption maintenance weighing when carrying out maintenance plan time sequential routine Multiple interruption maintenance was arranged in the identical period, i.e., only allows to have a power failure in this maintenance plan implementation procedure primary.
xi=xj
xiAnd xjThe respectively beginning repair time of ith and jth equipment;
Since power supply system covers biggish geographic area, it is contemplated that service work personnel and the quantity limit for overhauling fund System will fully consider that service personnel overhauls the reasonability of route when formulating maintenance plan, former nearby according to geographical location as far as possible Then reasonable arrangement maintenance sequence, the overhaul managements expense such as not only reduced labor intensity but also can reduce travel charge in this way is to improve Economic benefit.
xj=xi+Di+1;
8) the maintenance constraint that can not be changed: the maintenance that the time cannot be changed includes: the maintenance that 1. higher level traffic department formulates Plan;2. extending to the maintenance of this month last month;3. trouble hunting etc..The initial time of this kind of maintenance is regarded as determining, no Participate in the layout of maintenance plan time.
xi=Bi
In formula: BiI-th of the equipment assigned for higher level's scheduling starts the repair time;
9) overhauls window constrains:
Scheduled overhaul is to carry out in the project for the unified regulation defined in the whole nation issued by authorities, period
Maintenance.Therefore the date of survey of equipment has regular hour limitation.
In formula: XiAllow to start repair time set for i-th of equipment
The building of S2, load transfer path Optimized model: load transfer path optimization aim is to reduce sale of electricity loss, is subtracted Few switch operation, makes full use of distributed photovoltaic power to turn on-load, improves power supply reliability, establish optimized mathematical model such as Under:
Objective function:
1) sale of electricity loss is reduced:
2) switch operating cost is reduced:
F2=min { β nops}
β is that switch operates primary expense;Nops is the switch number of operations for carrying out load transfer;
3) the transfer path power supply reliability of meter and distributed photovoltaic, which improves, saves failure costs:
In formula: Q is the repair apparatus set for needing transfer load;PiFor the load that has a power failure caused by i-th of overhaul of the equipments;DiFor The lasting duration of i-th of overhaul of the equipments (being uniformly converted to number of days), βiSystem reliability when for i-th of overhaul of the equipments reduces damage It loses, a turns on-load with the presence or absence of photo-voltaic power supply for load transfer path, is to take 1, otherwise takes 0;
Its constraint condition are as follows:
1) effective power flow constrains:
|Sls|≤Slmax s
In formula: lSFor the effective power flow of route l, lmax s be route l allow by effective power flow limit value;
2) voltage out-of-limit constrains:
VK.min≤VK’≤VK.max
In formula: VK', VK, min, VK, max are respectively the voltage and voltage bound of each node after transfer load;
3) network topology constrains: the network after carrying out load transfer must still maintain radial operation.
g∈G
In formula: g is the network topology structure after transfer load;G is radial networks topological structure.
The solution of S3, model: divided by globally optimal solution or suboptimal solution of the genetic algorithm to above-mentioned objective function Analysis, expression is defined as: SGA=(C, F (x), P0, M,Γ, ψ, T);
In formula: the coding method of C-individual;
F (x)-individual fitness evaluation function;
P0-initial population selection;
M-population size;
- selection operator;
Γ-crossover operator;
ψ-mutation operator;
T-genetic operation termination condition;
For seeking the optimization problem of objective function minimum value, theoretically only need to simply increase it negative sign can It is translated into the optimization problem for seeking objective function maximum value, it may be assumed that
Min f (x)=max (- f (x))
When optimization aim is to find a function maximum value, and when objective function always takes positive value, can directly set the suitable of individual Response F (X) is equal to corresponding target function value f (x), it may be assumed that
.F (X)=f (x)
As one of preferred embodiment of the invention, in the solution of the model: to meet wanting for the negated negative value of fitness It asks, basic genetic algorithmic generally uses one of following two method that target function value f (x) is transformed to individual fitness F (X), for asking the optimization problem of objective function maximum value, transform method are as follows:
C in formulaminIt is one of following three kinds for a suitably relatively small number:
A: a preassigned lesser number;
B: it evolves to currently on behalf of minimum target functional value only;
C: the minimum target functional value in former generation or nearest several generations group;
For asking the optimization problem of objective function minimum value, transform method are as follows:
Cmax is the biggish number that suitably compares in formula, is one of following three kinds:
A: a preassigned biggish number;
B: it evolves to currently on behalf of maximum target functional value only;
C: the maximum target functional value in former generation or nearest several generations group.
As one of preferred embodiment of the invention, in the solution of the model, selection operator is ratio selection operator, Its specific implementation procedure is:
1) summation of the fitness of all individuals in group is first calculated;
2) size of the relative adaptability degrees of each individual is secondly calculated, individual is genetic to general in next-generation group Rate;
3) it finally reuses simulation disk operation (random number between i.e. 0 to 1) and determines selected time of each individual Number.
As one of preferred embodiment of the invention, in the solution of the model, crossover operator is single point crossing operator, Its specific implementation procedure is:
1) random pair two-by-two is carried out to the individual in group, if group size is M, shared [M/2] is to being mutually paired Group of individuals.Wherein [x] indicates the maximum integer for being not more than x;
2) individual being mutually paired to every a pair, being randomly provided the position after a certain locus is crosspoint.Tinction The length of body is n, then shares (n-1) a possible cross-point locations;
3) individual being mutually paired to every a pair is exchanged with each other two in its intersection according to the crossover probability A of setting The chromosome dyad of body, to produce two new individuals.
As one of preferred embodiment of the invention, in the solution of the model, mutation operator is basic bit mutation calculation Son, specific implementation procedure is:
1) to each locus of individual, specify it for change point according to mutation probability Pm;
2) change point specified to each negates operation to its genic value or is replaced with other allele values, To produce a new individual.
As one of preferred embodiment of the invention, the operation process of the genetic algorithm are as follows:
(1) it initializes: input initial parameter;
(2) coding production initial population, genetic algebra Gen=1;
(3) stochastic simulation is carried out under constraint condition;
(4) fitness function value is calculated;
(5) convergence judgement is carried out, YES exports decoding result;It returns to selection when NO to intersect, make a variation, Gen=Gen+1, then It is secondary to return to initialization input parameter.
Beneficial effect
The present invention establishes the overhaul of the equipments time for considering a variety of constraint conditions and load transfer path combined optimization model, Revised genetic algorithum is taken to be solved with load transfer path optimization problem for overhaul of the equipments is time-optimized, to demand perfection Office is optimal.The overhaul of the equipments time is optimized first, then passes through the load that the optimization of load transfer path will be influenced by maintenance Turn to be powered by other feeder lines by suitable path, so that optimal maintenance solution is obtained, it is final to obtain power supply enterprise's sale of electricity damage The smallest maintenance plan and power failure load are lost, number of operations and the smallest load transfer path scheme of system losses are switched.? Under the premise of guaranteeing system safety operation, the power supply reliability of system is improved to greatest extent, avoids repeating to have a power failure, and reduces user With the loss of outage of power supply enterprise, to achieve the effect that system and social two-win.
Detailed description of the invention
Fig. 1 is the operational flowchart of the genetic algorithm of the present embodiment 1;
Fig. 2 is the schematic diagram of the single point crossing operation of the present embodiment 1;
Fig. 3 is the schematic diagram of the basic bit mutation operation of the present embodiment 1;
Fig. 4 is the disk schematic diagram of the present embodiment 1.
Specific embodiment
The effect of to make to structure feature of the invention and being reached, has a better understanding and awareness, to preferable Examples and drawings cooperate detailed description, be described as follows:
Mentality of designing and principle of the invention: the establishment of power distribution network maintenance plan actually belongs to a with constraint conditions Optimization problem.When the maintenance plan acquired meets all constraint conditions, it is feasible for claiming this plan.Many feasible In scheme, the scheme with optimization objective function value is required optimal solution.According to this guiding theory, can establish The Optimized model of maintenance plan, the model of foundation generally require to solve by complicated mathematical algorithm implementation model, the knot of solution Fruit is theoretic optimal distribution maintenance plan.
The present invention is started with from operable practical method, the establishment of the maintenance plan in routine work is studied, when examining Under conditions of the external constraint of worry is relatively fewer, according to the plan simple possible that the method is worked out, there is practicability, still In the more situation of external constraint condition, then this method is limited to, i.e. the cost concept part covering of maintenance benefit and load The factors such as the optimization benefit embodiment of transfer path cannot be embodied in a model, containing a large amount of especially in Modern power distribution net Distributed photovoltaic power in the case where, the establishment of maintenance plan seems more complicated, it is therefore desirable to it is excellent to construct a set of multiple target Change model, realizes the optimization for adapting to the distribution maintenance plan of new energy access.
Compared with traditional power distribution network maintenance plan establishment, the low and medium voltage distribution network containing distributed photovoltaic power overhauls meter Formulations drawn increases inspection operation step when cutting off photo-voltaic power supply in maintenance and power failure electrical verification workload and is examining The actions such as Inform when done photovoltaic power generation enterprise restores electricity are repaired, the increased content of institute was all referred to repair time and inspection Load transfer path while the key of optimization when repairing.
Therefore, (the distribution multiple target optimized maintenance model based on PV, PV are defined as point for the present invention constructs object module Cloth photovoltaic) tentatively consider reliability objectives function and economic cost objective function synthesis.Specific optimum ideals are as follows:
The overhaul of the equipments time for considering a variety of constraint conditions and load transfer path combined optimization model are established, for setting Standby repair time optimization and load transfer path optimization problem take Revised genetic algorithum to be solved, in the hope of global optimum. The overhaul of the equipments time is optimized first, then the load influenced by maintenance is passed through by conjunction by the optimization of load transfer path Suitable path turns to be powered by other feeder lines, so that optimal maintenance solution is obtained, it is final to obtain power supply enterprise's sale of electricity loss reduction Maintenance plan and power failure load, switch number of operations and the smallest load transfer path scheme of system losses.Guaranteeing system Under the premise of system safe operation, the power supply reliability of system is improved to greatest extent, avoids repeating to have a power failure, and reduces user and power supply The loss of outage of enterprise, to achieve the effect that system and social two-win.
Based on the above mentality of designing and principle: referring to Fig. 1-3, a kind of distribution based on distributed photovoltaic of the present embodiment Net optimized maintenance method, this method comprises:
The building of S1, repair time Optimized model: examining time-optimized target is in the premise for guaranteeing power distribution network safe operation Under, sale of electricity caused by improving power grid power supply reliability to greatest extent and reducing power grid due to maintenance is lost.And power grid power supply is reliable Property can be reflected by load frequency of power cut and power failure load.When being overhauled, when can be by the superior and the subordinate's overhaul of the equipments Between cooperation, reduce repeat have a power failure and it is unnecessary power failure to reduce frequency of power cut.Since different periods load level is different, Sale of electricity loss brought by overhauling in different periods has very big difference, therefore can pass through the repair time of optimization equipment To reduce sale of electricity loss.
By analyzing above, repair time optimization aim is to reduce the sale of electricity loss of power supply enterprise, and it is excellent to establish the repair time It is as follows to change mathematical model:
Objective function:
In formula: F is sale of electricity failure costs;P is electricity price;N is repair apparatus sum;T is maintenance period sum;pitFor t Power failure load caused by i-th of overhaul of the equipments of period;UitFor the situation of i-th of repair apparatus of t period, when taking 0, indicate Equipment operates normally, and when taking 1, indicates that equipment is stopped transport and overhauls;
Its constraint condition are as follows:
1) Line Flow constrains:
|Sl|≤Slmax
In formula: SlFor the trend of route l, SlmaxFor route l allow by trend limit value;
2) mutual exclusion maintenance constraint:
In order to avoid load point has a power failure in maintenance, some equipment cannot overhaul simultaneously, therefore formulate in maintenance plan It cannot be arranged in the identical period in journey;
xj>xi+Di+1
In formula: xiAnd xjThe respectively beginning repair time of ith and jth equipment;DiIt is lasting for i-th of overhaul of the equipments Duration (is uniformly converted to number of days);
3) resource constraint is overhauled:
Since resource is limited, the limitation that maintenance plan is also contemplated that service ability, including service personnel's quantity and skill are formulated Art ability, capacity of equipment etc.:
In formula: M is the equipment number that can be overhauled simultaneously, uitSituation is set for i-th of t period maintenance, when taking 0, is indicated Equipment operates normally, and when taking 1, indicates that equipment is stopped transport and overhauls;
4) time adjustment constraint: | xi-xi0|≤Λi
In formula: x0iIt is declared for i-th of equipment and starts the repair time;ΛiFor the i equipment adjustment time limit value;
5) constraint is overhauled simultaneously:
In a system, primary the problem of can solve that have a power failure wants comprehensively solve, does not allow to occur because inconsiderate It repeats to have a power failure and solves the problems, such as same system.Therefore, some equipment must overhaul simultaneously.In of that month all maintenance, it is all make it is same The maintenance of route, same node point power loss, is regarded as repeating interruption maintenance weighing when carrying out maintenance plan time sequential routine Multiple interruption maintenance was arranged in the identical period, i.e., only allows to have a power failure in this maintenance plan implementation procedure primary.
xi=xj
xiAnd xjThe respectively beginning repair time of ith and jth equipment;
Since power supply system covers biggish geographic area, it is contemplated that service work personnel and the quantity limit for overhauling fund System will fully consider that service personnel overhauls the reasonability of route when formulating maintenance plan, former nearby according to geographical location as far as possible Then reasonable arrangement maintenance sequence, the overhaul managements expense such as not only reduced labor intensity but also can reduce travel charge in this way is to improve Economic benefit.
xj=xi+Di+1;
6) the maintenance constraint that can not be changed: the maintenance that the time cannot be changed includes: the maintenance that 1. higher level traffic department formulates Plan;2. extending to the maintenance of this month last month;3. trouble hunting etc..The initial time of this kind of maintenance is regarded as determining, no Participate in the layout of maintenance plan time.
xi=Bi
In formula: BiI-th of the equipment assigned for higher level's scheduling starts the repair time;
7) overhauls window constrains:
Scheduled overhaul is to carry out in the project for the unified regulation defined in the whole nation issued by authorities, period
Maintenance.Therefore the date of survey of equipment has regular hour limitation.
In formula: XiAllow to start repair time set for i-th of equipment;
Processing to constraint condition
First, the processing to inequality constraints:
Inequality constraints is handled using the method for penalty function.
Second, the processing of peer-to-peer constraint: form optimized variable collection
The building of S2, load transfer path Optimized model: when equipment is overhauled, to guarantee that load does not have a power failure as far as possible, Overhaul special work formulation maintenance plan simultaneously, corresponding load transfer path need to be provided.Since power distribution network wiring is complicated, inspection It is more to repair task, certain transfer path can only often be selected according to self-operating experience by overhauling special work in actual operation.It is such Transfer path is likely to only feasible path, and optimal selection is all not necessarily from safety and economy.Therefore it needs It will be according to the actual conditions of service work, it is established that load transfer path Optimized model simultaneously proposes to be suitble to solve the optimization problem Algorithm.Especially in the power distribution network of a large amount of distributed photovoltaic powers access, it can select to underestimate the load period as far as possible It overhauls and load is transferred to the distributed photovoltaic for having power supply nargin except service area and power.
Load transfer path optimization aim is to improve power grid to greatest extent under the premise of guaranteeing power distribution network safe operation Power supply reliability and grid switching operation that can be as few as possible transfers a load on All other routes, combines non-service area The distribution and power output of photovoltaic power generation power supply, to avoid load point to have a power failure to the maximum extent and reduce system caused by load transfer Network loss.
In terms of power grid power supply reliability: can be by selecting suitable load transfer path transfer load to the maximum extent And the equipment having a power failure will be caused to be arranged in the maintenance of load valley period, have a power failure load caused by can reducing because of inspection and repair shop, thus It is final to improve power supply reliability.Sale of electricity loss aspect: since overhaul of the equipments may cut off the company of certain load points and power supply point Connect, load will be caused to have a power failure when this sub-load does not have backup path or backup path off-capacity, thus should as far as possible by Corresponding maintenance task is arranged in the load valley period to reduce sale of electricity loss.
Sale of electricity loss aspect: since overhaul of the equipments may cut off the connection of certain load points and power supply point, when this part Load does not have load will be caused to have a power failure when backup path or backup path off-capacity, so will should overhaul accordingly as far as possible Task is arranged in the load valley period to reduce sale of electricity loss.
Switch number of operations: when load point is there are when a plurality of backup path, should selection operation on-off times as far as possible it is few Transfer scheme, to reduce switch operating cost as far as possible.
Distributed photovoltaic turns band capability analysis: when load point is there are when a plurality of backup path, preferential selection is in non-maintenance area There are the route or platform area transfer load of photovoltaic power generation plant-grid connection in domain, to guarantee power supply capacity and power supply reliability.Transfer is negative Network loss caused by lotus: theoretically, causing load point to have a power failure when to avoid certain overhauls of the equipments, need to carry out corresponding load transfer, Additional network loss is caused to power grid, therefore selects the path of less network loss as far as possible, but due in real process due to selection Network loss variation is relatively small caused by path is different, ignores simplified processing herein.
By analyzing above, load transfer path optimization aim is to reduce sale of electricity loss, reduces switch operation, sufficiently benefit Turn on-load with distributed photovoltaic power, improve power supply reliability, it is as follows to establish optimized mathematical model:
Objective function:
1) sale of electricity loss is reduced:
2) switch operating cost is reduced:
F2=min { β nops}
β is that switch operates primary expense;Nops is the switch number of operations for carrying out load transfer;
3) the transfer path power supply reliability of meter and distributed photovoltaic, which improves, saves failure costs:
In formula: Q is the repair apparatus set for needing transfer load;PiFor caused by i-th of overhaul of the equipments
Power failure load;DiFor the lasting duration of i-th of overhaul of the equipments (being uniformly converted to number of days), βiFor i-th of overhaul of the equipments When system reliability reduce loss, it is to take 1, otherwise that a, which is that load transfer path turns on-load with the presence or absence of photo-voltaic power supply, Take 0;
Its constraint condition are as follows:
1) effective power flow constrains:
|Sls|≤Slmax s
In formula: lSFor the effective power flow of route l, lmax s be route l allow by effective power flow limit value;
2) voltage out-of-limit constrains:
VK.min≤VK’≤VK.max
In formula: VK', VK, min, VK, max are respectively the voltage and voltage bound of each node after transfer load;
3) network topology constrains: the network after carrying out load transfer must still maintain radial operation.
g∈G
In formula: g is the network topology structure after transfer load;G is radial networks topological structure.
The solution of S3, model: above-mentioned optimization problem is decoupled into and solves the sub- optimization problem of following two by solution throughway: inspection Load path optimization problem when repairing time optimal problem and maintenance.Repair time optimizes input condition: load prediction information, inspection Repair the maintenance resource information of company, the coordination maintenance the constraint relationship of corresponding maintenance procedure and equipment room.Pass through asking for the problem The maintenance plan of available repair apparatus is solved, and using this as the input condition of maintenance load path transfer optimization problem.Inspection Repair load transfer path optimization input condition: initial network structure, equipment static parameter (impedance, allow by most spring tide Restriction value etc.), distributed photovoltaic power access point position, distributed photovoltaic power curve, load prediction information etc..
The repair time is optimized using genetic algorithm based on initial maintenance plan, the maintenance meter optimized It draws, and carries out the optimization of load transfer path, available a variety of transfers for this as the input condition of load transfer path optimization Scheme, according to power failure load daily load prediction curve, the potential loss avoided with sale of electricity loss, power supply reliability raising is opened Closing operational losses is that objective function uses genetic algorithm optimization again, corrects the repair time, finally obtains sale of electricity loss reduction Maintenance plan and power loss load, switch number of operations and the highest load transfer path of power supply reliability.
Genetic algorithm (GAS-genetic algorithms) is a kind of based on nature natural selection and naturally hereditary machine 1 kind of randomized optimization process of system, genetic algorithm (Genetic Algorithms, abbreviation GA) are a kind of former based on natural selection Search (optimizing) algorithm of reason and natural genetic mechanism, it is the life concern mechanism simulated in nature, in manual system Realize the optimization of specific objective.It is as a kind of global optimization search, with its simple general-purpose, strong robustness and it is implicit simultaneously Row processing the advantages that and be used widely.
The algorithm requires the property of objective function, or even is all not necessarily intended to explicitly write out objective function, Feature possessed by genetic algorithm is one group of record, it can recorde multiple solutions.Genetic algorithm becomes in the decision to problem After amount coding, calculating process is fairly simple, and can comparatively fast obtain a satisfactory solution.Due to the above-mentioned model category of this section In multiple-objection optimization, and need to seek the Model Group of globally optimal solution or suboptimal solution, therefore genetic algorithm is selected to ask as model It is proper that solution method makees this solution.
By analyzing above, analyzed by globally optimal solution or suboptimal solution of the genetic algorithm to above-mentioned objective function, Its expression is defined as: SGA=(C, F (x), P0, M,Γ, ψ, T);
In formula: the coding method of C-individual;
F (x)-individual fitness evaluation function;
P0-initial population selection;
M-population size;
- selection operator;
Γ-crossover operator;
ψ-mutation operator;
T-genetic operation termination condition;
In genetic algorithm, determine that it is general in next-generation group that the individual is genetic to the size of individual adaptation degree Rate.The fitness of individual is bigger, and it is also bigger which is genetic to follow-on probability;Conversely, the fitness of individual is smaller, It is also smaller that the individual is genetic to follow-on probability.Basic genetic algorithmic use ratio selection operator is each in group to determine Individual is genetic to the quantity in next-generation group.For the genetic probability for being computed correctly each individual under different situations, it is desirable that institute There is the fitness of individual to be necessary for positive number or zero, cannot be negative.
It, theoretically only need to be simply to it by analyzing the optimization problem it is found that for seeking objective function minimum value above The optimization problem for seeking objective function maximum value can be translated by increasing a negative sign, it may be assumed that
Min f (x)=max (- f (x))
When optimization aim is to find a function maximum value, and when objective function always takes positive value, can directly set the suitable of individual Response F (X) is equal to corresponding target function value f (x), it may be assumed that
.F (X)=f (x)
But the target function value in actual optimization problem has just and also has negative, and optimization aim finds a function maximum value, also asks Function minimum, it is clear that it is this requirement of nonnegative number that two formulas, which can not guarantee fitness individual under all situations all, above.So It must seek a kind of general and effectively by target function value to the transformational relation individual adaptation degree, be guaranteed by it The total negated negative value of individual adaptation degree.Therefore, as one of preferred embodiment of the invention, in the solution of the model: to meet The requirement of the negated negative value of fitness, basic genetic algorithmic generally use one of following two method to become target function value f (x) It is changed to the fitness F (X) of individual, for asking the optimization problem of objective function maximum value, transform method are as follows:
C in formulaminIt is one of following three kinds for a suitably relatively small number:
A: a preassigned lesser number;
B: it evolves to currently on behalf of minimum target functional value only;
C: the minimum target functional value in former generation or nearest several generations group;
For asking the optimization problem of objective function minimum value, transform method are as follows:
Cmax is the biggish number that suitably compares in formula, is one of following three kinds:
A: a preassigned biggish number;
B: it evolves to currently on behalf of maximum target functional value only;
C: the maximum target functional value in former generation or nearest several generations group.
Selection operator or the effect for replicating operator be select some more excellent individuals from the former generation group, and It is copied into next-generation group.The most frequently used mutually most basic selection operator is ratio selection operator.So-called ratio selection is calculated Son, refers to that individual is selected and the probability being genetic in next-generation group is directly proportional to the fitness size of the individual.Ratio choosing It selects actually one kind and returns random selection.It is illustrated in figure 4 disk schematic diagram.Entire disk is divided into of different sizes Some covering of the fans respectively correspond and are worth different some election contest articles.When the disk being rotating stops naturally, Article on pointer meaning covering of the fan just returns victor all.Although the pointer of disk specifically stop at which covering of the fan be can not be pre- It surveys, but it is that can estimate that pointer, which is directed toward the probability of each covering of the fan, it is directly proportional to the central angle size of each covering of the fan: A possibility that fenestra angle is bigger, is parked in the covering of the fan is also bigger;A possibility that central angle is smaller, is parked in the covering of the fan is also smaller.With This is similar, and in genetic algorithm, entire group is divided by each individual, and the fitness of each individual is in the suitable of all individuals Proportion is also not of uniform size in the sum of response, this ratio value has carved up entire disk surface, they also determine it is each each and every one The probability that body is genetic in next-generation group.Therefore, as one of preferred embodiment of the invention, in the solution of the model In, selection operator is ratio selection operator, and specific implementation procedure is:
1) summation of the fitness of all individuals in group is first calculated;
2) size of the relative adaptability degrees of each individual is secondly calculated, individual is genetic to general in next-generation group Rate;
3) it finally reuses simulation disk operation (random number between i.e. 0 to 1) and determines selected time of each individual Number.
As one of preferred embodiment of the invention, in the solution of the model, crossover operator is single point crossing operator, It is illustrated in figure 2 the schematic diagram (by taking binary coding as an example) of single point crossing operation, specific implementation procedure is:
1) random pair two-by-two is carried out to the individual in group, if group size is M, shared [M/2] is to being mutually paired Group of individuals.Wherein [x] indicates the maximum integer for being not more than x;
2) individual being mutually paired to every a pair, being randomly provided the position after a certain locus is crosspoint.Tinction The length of body is n, then shares (n-1) a possible cross-point locations;
3) individual being mutually paired to every a pair is exchanged with each other two in its intersection according to the crossover probability A of setting The chromosome dyad of body, to produce two new individuals.
As one of preferred embodiment of the invention, in the solution of the model, mutation operator is basic bit mutation calculation Son is illustrated in figure 3 the schematic diagram of basic bit mutation operation, and specific implementation procedure is:
1) to each locus of individual, specify it for change point according to mutation probability Pm;
2) change point specified to each negates operation to its genic value or replaces with other allele values To produce a new individual.
As one of preferred embodiment of the invention, the operation process of the genetic algorithm are as follows:
(1) it initializes: input initial parameter;
(2) coding production initial population, genetic algebra Gen=1;
(3) stochastic simulation is carried out under constraint condition;
(4) fitness function value is calculated;
(5) convergence judgement is carried out, YES exports decoding result;It returns to selection when NO to intersect, make a variation, Gen=Gen+1, then It is secondary to return to initialization input parameter:
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and what is described in the above embodiment and the description is only the present invention Principle, various changes and improvements may be made to the invention without departing from the spirit and scope of the present invention, these variation and Improvement is both fallen in the range of claimed invention.The present invention claims protection scope by appended claims and Its equivalent defines.

Claims (6)

1. a kind of power distribution network optimized maintenance method based on distributed photovoltaic, which is characterized in that this method comprises:
The building of S1, repair time Optimized model: repair time optimization aim is to reduce the sale of electricity loss of power supply enterprise, establishes inspection It is as follows to repair time-optimized mathematical model:
Objective function:
In formula: F is sale of electricityFailure costs;P is electricity price;N is repair apparatus sum;T For maintenance period sum;pitFor power failure load caused by i-th of the overhaul of the equipments of t period;UitIt is overhauled for i-th of the t period The situation of equipment when taking 0, indicates that equipment operates normally, and when taking 1, indicates that equipment is stopped transport and overhauls;
Its constraint condition are as follows:
1) Line Flow constrains:
|Sl|≤SlmaxIn formula: SlFor the trend of route l, SlmaxFor route l allow by trend limit value;
2) mutual exclusion maintenance constraint:
In order to avoid load point has a power failure in maintenance, some equipment cannot overhaul simultaneously, therefore in maintenance plan formulation process It cannot be arranged in the identical period;
xj>xi+Di+1
In formula: xiAnd xjThe respectively beginning repair time of ith and jth equipment;DiFor the lasting duration of i-th of overhaul of the equipments (being uniformly converted to number of days);
3) resource constraint is overhauled:
Since resource is limited, the limitation that maintenance plan is also contemplated that service ability is formulated:
In formula: M is the equipment number that can be overhauled simultaneously, uitSituation is set for i-th of t period maintenance, when taking 0, indicates equipment It operates normally, when taking 1, indicates that equipment is stopped transport and overhaul;
4) time adjustment constraint: | xi-xi0|≤Λi
In formula: x0iIt is declared for i-th of equipment and starts the repair time;ΛiFor the i equipment adjustment time limit value;
5) constraint is overhauled simultaneously:
In a system, primary the problem of can solve that have a power failure wants comprehensively solve, does not allow to repeat because inconsiderate Power failure solves the problems, such as same system, therefore:
xi=xj
xiAnd xjThe respectively beginning repair time of ith and jth equipment;
Since power supply system covers biggish geographic area, it is contemplated that service work personnel and the quantity limitation for overhauling fund, To fully consider that service personnel overhauls the reasonability of route when formulating maintenance plan, it is reasonable according to geographical location nearby principle as far as possible Maintenance sequence is arranged, thus:
xj=xi+Di+1;
6) the maintenance constraint that can not be changed:
xi=Bi
In formula: BiI-th of the equipment assigned for higher level's scheduling starts the repair time;
7) overhauls window constrains:
In formula: XiAllow to start repair time set for i-th of equipment
The building of S2, load transfer path Optimized model: it is as follows to establish optimized mathematical model:
Objective function:
1) sale of electricity loss is reduced:
2) switch operating cost is reduced:
F2=min { β nops}
β is that switch operates primary expense;Nops is the switch number of operations for carrying out load transfer;
3) the transfer path power supply reliability of meter and distributed photovoltaic, which improves, saves failure costs:
In formula: Q is the repair apparatus set for needing transfer load;PiFor the load that has a power failure caused by i-th of overhaul of the equipments;DiIt is i-th The lasting duration of overhaul of the equipments, βiSystem reliability when for i-th of overhaul of the equipments reduces loss, and a is that load transfer path is No there are photo-voltaic power supplies to turn on-load, is, takes 1, otherwise takes 0;
Its constraint condition are as follows:
1) effective power flow constrains:
|Sls|≤Slmax s
In formula: lSFor the effective power flow of route l, lmax s be route l allow by effective power flow limit value;
2) voltage out-of-limit constrains:
VK.min≤VK’≤VK.max
In formula: VK', VK, min, VK, max are respectively the voltage and voltage bound of each node after transfer load;
3) network topology constrains: the network after carrying out load transfer must still maintain radial operation.
g∈G
In formula: g is the network topology structure after transfer load;G is radial networks topological structure.
The solution of S3, model: it is analyzed by globally optimal solution or suboptimal solution of the genetic algorithm to above-mentioned objective function, table Show formula is defined as:
In formula: the coding method of C-individual;
F (x)-individual fitness evaluation function;
P0-initial population selection;
M-population size;
- selection operator;
Γ-crossover operator;
ψ-mutation operator;
T-genetic operation termination condition;
For seeking the optimization problem of objective function minimum value, theoretically only need to simply increase it negative sign can be by its turn Turn to the optimization problem for seeking objective function maximum value, it may be assumed that
Min f (x)=max (- f (x))
When optimization aim is to find a function maximum value, and when objective function always takes positive value, can directly set the fitness F of individual (X) it is equal to corresponding target function value f (x), it may be assumed that
F (X)=f (x).
2. the power distribution network optimized maintenance method according to claim 1 based on distributed photovoltaic, which is characterized in that in the model Solution in: for the requirement for meeting the negated negative value of fitness, for asking the optimization problem of objective function maximum value, transform method Are as follows:
C in formulaminIt is one of following three kinds for a suitably relatively small number:
A: a preassigned lesser number;
B: it evolves to currently on behalf of minimum target functional value only;
C: the minimum target functional value in former generation or nearest several generations group;
For asking the optimization problem of objective function minimum value, transform method are as follows:
Cmax is the biggish number that suitably compares in formula, is one of following three kinds:
A: a preassigned biggish number;
B: it evolves to currently on behalf of maximum target functional value only;
C: the maximum target functional value in former generation or nearest several generations group.
3. the power distribution network optimized maintenance method according to claim 1 based on distributed photovoltaic, which is characterized in that in the model Solution in, selection operator be ratio selection operator, specific implementation procedure is:
1) summation of the fitness of all individuals in group is first calculated;
2) size of the relative adaptability degrees of each individual, the probability that individual is genetic in next-generation group are secondly calculated;
3) it finally reuses simulation disk operation and determines the selected number of each individual.
4. the power distribution network optimized maintenance method according to claim 1 based on distributed photovoltaic, which is characterized in that in the model Solution in, crossover operator be single point crossing operator, specific implementation procedure is:
1) random pair two-by-two is carried out to the individual in group, if group size is M, shared [M/2] is to being mutually paired Body group.Wherein [x] indicates the maximum integer for being not more than x;
2) individual being mutually paired to every a pair, being randomly provided the position after a certain locus is crosspoint.Tinction body Length is n, then shares (n-1) a possible cross-point locations;
3) individual that every a pair is mutually paired, according to setting crossover probability A its intersection be exchanged with each other two it is individual Chromosome dyad, to produce two new individuals.
5. the power distribution network optimized maintenance method according to claim 1 based on distributed photovoltaic, which is characterized in that in the model Solution in, mutation operator be basic bit mutation operator, specific implementation procedure is:
1) to each locus of individual, specify it for change point according to mutation probability Pm;
2) change point specified to each negates operation to its genic value or is replaced with other allele values, thus Produce a new individual.
6. the power distribution network optimized maintenance method according to claim 1 based on distributed photovoltaic, which is characterized in that the heredity is calculated The operation process of method are as follows:
(1) it initializes: input initial parameter;
(2) coding production initial population, genetic algebra Gen=1;
(3) stochastic simulation is carried out under constraint condition;
(4) fitness function value is calculated;
(5) convergence judgement is carried out, YES exports decoding result;It returns to selection when NO to intersect, make a variation, Gen=Gen+1 is turned again to Initialization input parameter.
CN201810975803.7A 2018-08-24 2018-08-24 A kind of power distribution network optimized maintenance method based on distributed photovoltaic Pending CN109117570A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810975803.7A CN109117570A (en) 2018-08-24 2018-08-24 A kind of power distribution network optimized maintenance method based on distributed photovoltaic

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810975803.7A CN109117570A (en) 2018-08-24 2018-08-24 A kind of power distribution network optimized maintenance method based on distributed photovoltaic

Publications (1)

Publication Number Publication Date
CN109117570A true CN109117570A (en) 2019-01-01

Family

ID=64860828

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810975803.7A Pending CN109117570A (en) 2018-08-24 2018-08-24 A kind of power distribution network optimized maintenance method based on distributed photovoltaic

Country Status (1)

Country Link
CN (1) CN109117570A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110263992A (en) * 2019-06-12 2019-09-20 苏州智睿新能信息科技有限公司 It is a kind of based on client to the optimal plan power failure method of electric service susceptibility
CN111950786A (en) * 2020-08-06 2020-11-17 上海交通大学 Two-stage maintenance scheduling method for steel enterprise equipment under complex constraint
CN112149842A (en) * 2020-09-04 2020-12-29 深圳供电局有限公司 Power grid maintenance management method and device
CN112418499A (en) * 2020-11-16 2021-02-26 广东电网有限责任公司 Power grid maintenance planning optimization method and device and computer readable storage medium
CN112488379A (en) * 2020-11-26 2021-03-12 北京交通大学 Method and system for optimizing maintenance plan of high-speed railway motor train unit
CN112488354A (en) * 2020-10-28 2021-03-12 国网宁夏电力有限公司经济技术研究院 Low-cost configuration method for operation and maintenance of power distribution network after clean energy access
CN113191575A (en) * 2021-06-16 2021-07-30 广东电网有限责任公司 Power distribution network maintenance power failure mode optimization method and device, terminal and storage medium
CN113505915A (en) * 2021-06-18 2021-10-15 国网吉林省电力有限公司吉林供电公司 Method for optimizing maintenance plan of power distribution network containing distributed power supply
CN113988390A (en) * 2021-10-18 2022-01-28 浙江大学 Unit maintenance optimization method based on support vector machine
CN116404646A (en) * 2023-06-08 2023-07-07 国网江西省电力有限公司电力科学研究院 Power system scheduling method and system considering standby risk
CN116486969A (en) * 2023-06-25 2023-07-25 广东工业大学 Genetic algorithm-based material optimal correlation relation acquisition method and application

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279578A (en) * 2015-10-27 2016-01-27 天津大学 Power supply optimization configuration bilevel programming method in active distribution network region
CN105552896A (en) * 2015-12-31 2016-05-04 国家电网公司 Distributed photovoltaic power generation based power distribution network peak load control method
CN105574611A (en) * 2015-12-14 2016-05-11 国家电网公司 Overhaul plan optimization method containing distributed power distribution network

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279578A (en) * 2015-10-27 2016-01-27 天津大学 Power supply optimization configuration bilevel programming method in active distribution network region
CN105574611A (en) * 2015-12-14 2016-05-11 国家电网公司 Overhaul plan optimization method containing distributed power distribution network
CN105552896A (en) * 2015-12-31 2016-05-04 国家电网公司 Distributed photovoltaic power generation based power distribution network peak load control method

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
M. A. FOTOUHI 等: "Strategic maintenance scheduling of distributed generations in oligopolistic electricity markets", 《2009 IEEE ELECTRICAL POWER & ENERGY CONFERENCE (EPEC)》 *
刘剑平 等: "《普通高等教育十二五规划教材 深基坑支护理论与应用》", 30 June 2013, 冶金工业出版社 *
张姿姿 等: "考虑天气及电价的配网计划检修双层优化模型", 《电力科学与工程》 *
朱新菊 等: "配电网检修计划优化问题的研究", 《陕西电力》 *
编委会 著: "《高等学校应用型本科创新人才培养计划指定教材 智能制造信息系统开发》", 31 August 2017, 西安电子科技大学出版社 *
颜磊: "计及分布式电源接入的配电网检修计划优化方法", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110263992A (en) * 2019-06-12 2019-09-20 苏州智睿新能信息科技有限公司 It is a kind of based on client to the optimal plan power failure method of electric service susceptibility
CN110263992B (en) * 2019-06-12 2023-07-04 苏州智睿新能信息科技有限公司 Optimal planned power outage method based on customer sensitivity to power supply service
CN111950786A (en) * 2020-08-06 2020-11-17 上海交通大学 Two-stage maintenance scheduling method for steel enterprise equipment under complex constraint
CN112149842A (en) * 2020-09-04 2020-12-29 深圳供电局有限公司 Power grid maintenance management method and device
CN112488354A (en) * 2020-10-28 2021-03-12 国网宁夏电力有限公司经济技术研究院 Low-cost configuration method for operation and maintenance of power distribution network after clean energy access
CN112488354B (en) * 2020-10-28 2022-05-13 国网宁夏电力有限公司经济技术研究院 Low-cost configuration method for operation and maintenance of power distribution network after clean energy access
CN112418499A (en) * 2020-11-16 2021-02-26 广东电网有限责任公司 Power grid maintenance planning optimization method and device and computer readable storage medium
CN112488379A (en) * 2020-11-26 2021-03-12 北京交通大学 Method and system for optimizing maintenance plan of high-speed railway motor train unit
CN112488379B (en) * 2020-11-26 2024-03-19 北京交通大学 Maintenance plan optimization method and system for high-speed railway motor train unit
CN113191575B (en) * 2021-06-16 2024-01-23 广东电网有限责任公司 Optimization method, device, terminal and storage medium for power distribution network maintenance power failure mode
CN113191575A (en) * 2021-06-16 2021-07-30 广东电网有限责任公司 Power distribution network maintenance power failure mode optimization method and device, terminal and storage medium
CN113505915A (en) * 2021-06-18 2021-10-15 国网吉林省电力有限公司吉林供电公司 Method for optimizing maintenance plan of power distribution network containing distributed power supply
CN113988390A (en) * 2021-10-18 2022-01-28 浙江大学 Unit maintenance optimization method based on support vector machine
CN116404646B (en) * 2023-06-08 2023-10-20 国网江西省电力有限公司电力科学研究院 Power system scheduling method and system considering standby risk
CN116404646A (en) * 2023-06-08 2023-07-07 国网江西省电力有限公司电力科学研究院 Power system scheduling method and system considering standby risk
CN116486969B (en) * 2023-06-25 2023-09-26 广东工业大学 Genetic algorithm-based material optimal correlation relation acquisition method and application
CN116486969A (en) * 2023-06-25 2023-07-25 广东工业大学 Genetic algorithm-based material optimal correlation relation acquisition method and application

Similar Documents

Publication Publication Date Title
CN109117570A (en) A kind of power distribution network optimized maintenance method based on distributed photovoltaic
Mishra et al. A comprehensive review on power distribution network reconfiguration
Martins et al. Active distribution network integrated planning incorporating distributed generation and load response uncertainties
Zhao et al. Service restoration for a renewable-powered microgrid in unscheduled island mode
Begovic et al. Impact of renewable distributed generation on power systems
Syahputra Fuzzy multi-objective approach for the improvement of distribution network efficiency by considering DG
Rastgou et al. Improved harmony search algorithm for electrical distribution network expansion planning in the presence of distributed generators
Shukla et al. Allocation of optimal distributed generation using GA for minimum system losses in radial distribution networks
Poudel et al. A generalized framework for service restoration in a resilient power distribution system
CN108122068A (en) A kind of power distribution network risk-averse retailer method and system
Dabbaghjamanesh et al. Networked microgrid security and privacy enhancement by the blockchain-enabled Internet of Things approach
Dehghani et al. Multi-stage resilience management of smart power distribution systems: A stochastic robust optimization model
Abubakar et al. Optimal reconfiguration of radial distribution networks using improved genetic algorithm
CN109829560B (en) Renewable energy power generation cluster access planning method for power distribution network
Ramaswamy et al. Relevance of voltage control, grid reconfiguration and adaptive protection in smart grids and genetic algorithm as an optimization tool in achieving their control objectives
Igder et al. Service restoration through microgrid formation in distribution networks: A review
Ashoornezhad et al. A two‐stage multi‐period distribution network expansion planning considering the integration of private investors
Farzin et al. A hierarchical scheme for outage management in multi‐microgrids
Gilani et al. Probabilistic method for optimal placement of wind-based distributed generation with considering reliability improvement and power loss reduction
Wang et al. Using multiple DGs for distribution system service restoration after extreme events
Ma et al. Decentralized robust optimal dispatch of user-level integrated electricity-gas-heat systems considering two-level integrated demand response
Ilic et al. A framework for evaluating electric power grid improvements in puerto rico
Hamid-Oudjana et al. Optimum dynamic network reconfiguration in smart grid considering photovoltaic source
Hu et al. A load switching group based feeder-level microgrid energy management algorithm for service restoration in power distribution system
Esmaeili et al. Optimal operational scheduling of smart microgrids considering hourly reconfiguration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190101