CN109098319A - A kind of review light lath wall construction method - Google Patents
A kind of review light lath wall construction method Download PDFInfo
- Publication number
- CN109098319A CN109098319A CN201810876970.6A CN201810876970A CN109098319A CN 109098319 A CN109098319 A CN 109098319A CN 201810876970 A CN201810876970 A CN 201810876970A CN 109098319 A CN109098319 A CN 109098319A
- Authority
- CN
- China
- Prior art keywords
- wallboard
- mortar
- light lath
- construction method
- wall construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
- E04B2/86—Walls made by casting, pouring, or tamping in situ made in permanent forms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
Abstract
The invention discloses a kind of review light lath wall construction methods, and checking light lath wall includes multiple wallboards, and this approach includes the following steps, first the edge applying mortar on wallboard;Then the multiple wallboards for having smeared mortar are moved to assembled position and carry out assembly;Again with crowbar tilt wallboard until panel tops squeeze out mortar, timber wedge is then clogged between wallboard and ground;Steel nail is hammered between two neighboring wallboard, steel nail is hammered into direction obliquely;And wallboard and beam are fixed by connecting reinforcing bar, fix wallboard and column also by connection reinforcing bar, and the edge joint position between wallboard and beam fills mortar, the edge joint position between wallboard and column fills mortar;After mortar strength reaches requirement, timber wedge is taken out, the gap between wallboard and ground is then filled up with mortar;Plate stitch is smoothed out with the plate stitch between each wallboard of Cracking-proof belt sealing label, then with mortar.Present invention process is simple, can effectively improve construction quality and efficiency.
Description
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of review light lath wall construction method.
Background technique
Prefabricated grout wall, also known as review sandwich energy-saving wall board are fixed using single-layer double-side cement fibrolite plate through sizing grinding tool,
Interior filling EPS polystyrene foam particles concrete, vibrated, conserve it is prefabricated form, then the wall formed by assembled fixation,
Review light lath wall be prefabricated grout wall one kind, because its from heavy and light and keep the temperature, cut off the water supply, prevent fires and airtight aspect have it is bright
Aobvious advantage and be widely applied, but existing review light lath wall complicated construction technique, construction quality and efficiency are lower.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of review light lath wall construction methods, and simple process can
Effectively improve construction efficiency and quality.
In order to solve the above technical problem, the present invention provides technical solution it is as follows:
A kind of review light lath wall construction method, the review light lath wall includes multiple wallboards, which includes
Following steps:
1) the edge applying mortar on the wallboard;
2) the multiple wallboards for having smeared mortar are moved to assembled position and carry out assembly;
3) and with crowbar tilt wallboard until panel tops squeeze out mortar, then between wallboard and ground clog timber wedge and incite somebody to action
Wallboard is fixed temporarily;
4) steel nail is hammered between two neighboring wallboard, the steel nail hammers between two neighboring wallboard in direction obliquely;
And wallboard and beam are fixed by connecting reinforcing bar, fix wallboard and column also by connection reinforcing bar, and between wallboard and beam
Edge joint position fill mortar, edge joint position between wallboard and column fills mortar;
5) after mortar strength reaches design requirement, timber wedge is taken out, the gap between wallboard and ground is then filled up with mortar;
6) plate stitch between each wallboard of Cracking-proof belt sealing label is used, then is smoothed out plate stitch with mortar.
In the step 4), the tilt angle of steel nail is 40~50 °.
In the step 5), the method for filling up gap between wallboard and ground with mortar are as follows: stitched between wallboard and ground
The two sides of gap dry patching mortar simultaneously, until mortar tamps the gap between wallboard and ground.
In the step 6), the width of the Cracking-proof belt is not less than 9cm.
In the step 6), Cracking-proof belt uses glass fabric.
In the step 3), wallboard is tilted with crowbar until panel tops also utilize crowbar to wallboard before squeezing out mortar
Position is corrected.
Wall decoration is also carried out after the step 6).
The method of the wall decoration are as follows: paving plasterboard or calcium silicate board with microporous on the metope of wallboard.
The invention has the following advantages: review light lath wall construction method of the invention, simple process, wall are steady
Qualitative good, wallboard contact position is less prone to crack, and construction quality is good, construction efficiency is high.
Specific embodiment
The present invention is further explained in the light of specific embodiments, so that those skilled in the art can be preferably
Understand the present invention and can be practiced, but illustrated embodiment is not as a limitation of the invention.
Present embodiment discloses a kind of review light lath wall construction methods, and checking light lath wall includes multiple wallboards,
Structured base layer cleaning is first carried out when construction, then carries out line setting, is then followed the steps below:
1) the edge applying mortar on wallboard;For example, the edge connecting with other wallboards, beam or column can be needed to apply on wallboard
Smear mortar;
2) the multiple wallboards for having smeared mortar are moved to assembled position and carry out assembly;The joint gap of adjacent wall board is 10mm;
3) position of wallboards is corrected using crowbar, and with crowbar tilt wallboard until panel tops squeeze out mortar, namely
So that mortar from seam crossing squeeze out, with guarantee between wallboard and wallboard or wallboard and other beams, column between can effectively connect
It closes, then clogs timber wedge between wallboard and ground and level wallboard and play the role of being fixed temporarily wallboard;
4) steel nail is hammered between two neighboring wallboard, to realize the connection of two neighboring wallboard, also i.e. by steel nail from a wall
Plate hammers into, and the extension end of steel nail penetrates its adjacent wallboard;Steel nail is hammered into direction obliquely in two neighboring wallboard when hammering into
Between;And wallboard and beam are fixed by connecting reinforcing bar, fix wallboard and column also by connection reinforcing bar, it is strong with enhancing connection
Degree, and the edge joint position between wallboard and beam fills mortar, the edge joint position between wallboard and column fills mortar;
Wherein, steel nail hammers between two neighboring wallboard in direction obliquely, is conducive to the connective stability for enhancing two wallboards
And bonding strength;
It connects reinforcing bar and uses L-type steel muscle, bonding strength is high.
In a wherein embodiment, when hammering into, the tilt angle of steel nail is 40~50 °, to guarantee between two wallboards more
Good connection effect.
Preferably, the tilt angle of steel nail is 45 °, and steel nail length is 400mm.
5) after mortar strength reaches 5MPa, timber wedge is taken out, the gap between wallboard and ground is then filled up with mortar;
The method for filling up gap between wallboard and ground with mortar are as follows: sand is clogged in the two sides in gap simultaneously between wallboard and ground
Slurry, until mortar tamps the gap between wallboard and ground, which is conducive to keep the stabilization of wallboard in the filling process
Property;
Further, the side merging connected on wallboard with ground has reinforcing bar, to enhance the connective stability on ground and wallboard.
6) plate stitch between each wallboard of Cracking-proof belt sealing label is used, then is smoothed out plate stitch with mortar, to effectively prevent opening at plate stitch
It splits, then in every face wall body, inspection in time is equalled its whole degree and verticality and adjusted after the installation is completed.
Further, the width of Cracking-proof belt is not less than 9cm.
Further, Cracking-proof belt uses glass fabric.
Further, wall decoration is also carried out after step 6).
The method of wall decoration are as follows: paving plasterboard or calcium silicate board with microporous on the metope of wallboard, it can also be in the metope of wallboard
Upper berth wallpaper.
Wherein, when wallboard is connected with steel construction pillar, U-shaped card can be set in each wallboard and pillar seam crossing, and
Seam crossing fills out sealant and sealant;
When wallboard is connect with floor, beam, in the bar planting of wallboard top, bar planting elbow is squeezed into wallboard, and between wallboard and floor
Seam, the seam crossing perfusion mortar between wallboard and beam, gluing filling;U-shaped card is welded on girder steel by girder steel, gap
Sealant is broken at place.
The review light lath wall construction method of the present embodiment, simple process, wall stability is good, and wallboard contact position is not easy
There is crack, construction quality is good, construction efficiency is high.
Embodiment described above is only to absolutely prove preferred embodiment that is of the invention and being lifted, protection model of the invention
It encloses without being limited thereto.Those skilled in the art's made equivalent substitute or transformation on the basis of the present invention, in the present invention
Protection scope within.Protection scope of the present invention is subject to claims.
Claims (8)
1. a kind of review light lath wall construction method, the review light lath wall includes multiple wallboards, characterized in that this is applied
Work method the following steps are included:
1) the edge applying mortar on the wallboard;
2) the multiple wallboards for having smeared mortar are moved to assembled position and carry out assembly;
3) and with crowbar tilt wallboard until panel tops squeeze out mortar, then between wallboard and ground clog timber wedge and incite somebody to action
Wallboard is fixed temporarily;
4) steel nail is hammered between two neighboring wallboard, the steel nail hammers between two neighboring wallboard in direction obliquely;
And wallboard and beam are fixed by connecting reinforcing bar, fix wallboard and column also by connection reinforcing bar, and between wallboard and beam
Edge joint position fill mortar, edge joint position between wallboard and column fills mortar;
5) after mortar strength reaches design requirement, timber wedge is taken out, the gap between wallboard and ground is then filled up with mortar;
6) plate stitch between each wallboard of Cracking-proof belt sealing label is used, then is smoothed out plate stitch with mortar.
2. review light lath wall construction method as described in claim 1, characterized in that in the step 4), steel nail inclines
Rake angle is 40~50 °.
3. review light lath wall construction method as described in claim 1, characterized in that in the step 5), filled out with mortar
The method in gap between full wallboard and ground are as follows: the two sides in gap while dry patching mortar between wallboard and ground, until mortar
Tamp the gap between wallboard and ground.
4. review light lath wall construction method as described in claim 1, characterized in that in the step 6), the anticracking
The width of band is not less than 9cm.
5. review light lath wall construction method as described in claim 1, characterized in that in the step 6), Cracking-proof belt is adopted
Use glass fabric.
6. review light lath wall construction method as described in claim 1, characterized in that in the step 3), stuck up with crowbar
Wallboard is played until panel tops are also corrected position of wallboards using crowbar before squeezing out mortar.
7. review light lath wall construction method as described in claim 1, characterized in that also carry out wall after the step 6)
Face decoration.
8. review light lath wall construction method as claimed in claim 7, characterized in that the method for the wall decoration are as follows:
Paving plasterboard or calcium silicate board with microporous on the metope of wallboard.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810876970.6A CN109098319A (en) | 2018-08-03 | 2018-08-03 | A kind of review light lath wall construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810876970.6A CN109098319A (en) | 2018-08-03 | 2018-08-03 | A kind of review light lath wall construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109098319A true CN109098319A (en) | 2018-12-28 |
Family
ID=64848409
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810876970.6A Pending CN109098319A (en) | 2018-08-03 | 2018-08-03 | A kind of review light lath wall construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109098319A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114775897A (en) * | 2022-04-26 | 2022-07-22 | 中建八局第四建设有限公司 | Wall concealed pipeline slotting-free construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3995402A (en) * | 1975-06-04 | 1976-12-07 | Gerard Parenteau | Panelling assembly for partitions, walls or the like |
CN102777045A (en) * | 2012-08-09 | 2012-11-14 | 龙信建设集团有限公司 | Construction method for assembling light energy-saving composite wallboards on separation wall |
CN102777041A (en) * | 2012-07-27 | 2012-11-14 | 中山建华墙体材料有限公司 | Installation technology of inner separation wall body |
CN103074949A (en) * | 2013-02-05 | 2013-05-01 | 南通联泷建筑材料有限公司 | Construction method for environment-friendly light energy-saving wallboard |
-
2018
- 2018-08-03 CN CN201810876970.6A patent/CN109098319A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3995402A (en) * | 1975-06-04 | 1976-12-07 | Gerard Parenteau | Panelling assembly for partitions, walls or the like |
CN102777041A (en) * | 2012-07-27 | 2012-11-14 | 中山建华墙体材料有限公司 | Installation technology of inner separation wall body |
CN102777045A (en) * | 2012-08-09 | 2012-11-14 | 龙信建设集团有限公司 | Construction method for assembling light energy-saving composite wallboards on separation wall |
CN103074949A (en) * | 2013-02-05 | 2013-05-01 | 南通联泷建筑材料有限公司 | Construction method for environment-friendly light energy-saving wallboard |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114775897A (en) * | 2022-04-26 | 2022-07-22 | 中建八局第四建设有限公司 | Wall concealed pipeline slotting-free construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104790595B (en) | Pitched roof adjustable tile system construction method | |
CN106801517B (en) | External reinforcing and reinforcing method for school shed with prefabricated porous plate brick mixed structure | |
CN108797847A (en) | A kind of assembled steel frame wall filled with masonry structural system and its construction method | |
CN105484391A (en) | Construction method for manufacturing heat-preservation waterproof wall through light heat-preservation GRC disassembling-free formworks | |
CN104234271B (en) | A kind of self-insulating light wallboard system and installation method | |
CN110080530B (en) | Anchoring construction method for glazed tile slope roof in severe cold region | |
CN111502247A (en) | Wall formwork bottom plugging device, formwork support system and formwork supporting construction method | |
CN101761155A (en) | Construction method for ceramsite concrete light-weight wall boards | |
CN208934190U (en) | A kind of assembled steel frame wall filled with masonry structural system | |
CN105464399A (en) | Prefabricated checkered plate steel truss strengthening reinforced concrete frame beam structure and strengthening method | |
CN207484711U (en) | A kind of antiseep construction of horizontal structure deformation joint | |
CN109098319A (en) | A kind of review light lath wall construction method | |
CN212866852U (en) | Wall form bottom plugging device and form support system | |
CN109930856A (en) | A kind of the old and new's wall concatenation construction method | |
CN102031876A (en) | Method for newly adding upright column for building | |
CN108385456A (en) | A kind of board-like ballastless track bed board integral replacing method of cast-in-place railway roadbed | |
CN209723369U (en) | Light sandwich concrete masonry is used for the structure and wall body structure of cold district | |
CN208718153U (en) | The band embedded ALC wallboard shock-resistant node structure in frame top | |
CN106284999A (en) | Assembled architecture haydite concrete batten of internal partition mounting process | |
CN110284725A (en) | A kind of reinforced concrete frame node negative moment of girder assembly steel construction and its reinforcement means | |
CN105780975B (en) | The control technique of partition wall plank split | |
CN104863273A (en) | Method and structure of using cement-based grouting materials to seal wall splicing seam | |
CN105525700A (en) | Method for building indoor wall body by high-precision building blocks and wall body structure | |
CN204626735U (en) | Pitched roof adjustable tile system | |
CN209670134U (en) | Assembled wall right angle connecting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181228 |