CN109066738A - A kind of interconnection consumption method for measuring and calculating and its system based on dynamic load balancing - Google Patents

A kind of interconnection consumption method for measuring and calculating and its system based on dynamic load balancing Download PDF

Info

Publication number
CN109066738A
CN109066738A CN201811141651.7A CN201811141651A CN109066738A CN 109066738 A CN109066738 A CN 109066738A CN 201811141651 A CN201811141651 A CN 201811141651A CN 109066738 A CN109066738 A CN 109066738A
Authority
CN
China
Prior art keywords
value
extra
high voltage
voltage direct
moment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811141651.7A
Other languages
Chinese (zh)
Other versions
CN109066738B (en
Inventor
向萌
左剑
胡臻
柳永妍
呙虎
张可人
沈阳武
崔挺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd, State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811141651.7A priority Critical patent/CN109066738B/en
Publication of CN109066738A publication Critical patent/CN109066738A/en
Application granted granted Critical
Publication of CN109066738B publication Critical patent/CN109066738B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/26Arrangements for eliminating or reducing asymmetry in polyphase networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/50Arrangements for eliminating or reducing asymmetry in polyphase networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The interconnection consumption method for measuring and calculating and its system, this method that the invention discloses a kind of based on dynamic load balancing include S1: based on network load balance building short-term dynamic balancing the load model;S2: the plan start-up mode of short-term dynamic balancing the load model and power grid local unit based on building calculates the upper limit value and lower limit value of extra-high voltage direct-current interconnection consumption planned value at each moment to be studied;S3: segmented mode based on the extra-high voltage direct-current tie line plan curve prestored the and upper limit value of extra-high voltage direct-current interconnection consumption planned value and lower limit value obtain the sectional curve of extra-high voltage direct-current interconnection consumption planned value at each moment to be studied.The method of the invention has measured extra-high voltage direct-current interconnection consumption planned value, so that the subsequent sectional curve by extra-high voltage direct-current interconnection consumption planned value is applied to scheduling institution, improves clean energy resource and dissolves ratio.

Description

A kind of interconnection consumption method for measuring and calculating and its system based on dynamic load balancing
Technical field
The invention belongs to dispatching of power netwoks fields, and in particular to a kind of interconnection consumption measurement calculation based on dynamic load balancing Method and its system.
Background technique
With the unique advantage of interconnecting ties plan, electricity transaction realizes energy resources optimization in China and matches It sets, the situation for efficiently solving disadvantage and den and depositing, and power grid increasingly closely contacts between major area and province and interconnection is defeated It is promoted to electric energy power hardware, so that optimization of energy resources have more solid foundation.However, current grid structure and extreme misery Electric resources status constrains the extensive consumption of clean energy resource, how to give full play to all kinds of regulating measures of power grid, sufficiently consumption with It is equal to reduce power purchase for reducing power grid thermoelectricity ratio, Optimization of Energy Structure for extra-high voltage direct-current electric power based on clean energy resource power generation Valence realizes energy-saving and emission-reduction, is of great significance and current urgent problem to be solved.Therefore, it obtains with clean energy resource power generation and is The consumption amount of main extra-high voltage direct-current electric power is planned a few days ago to instruct scheduling institution to specify, excellent when carrying out Real-time Balancing calculating First consider that extra-high voltage direct-current interconnection is the vital link that solves the above problems.However, having lacked one kind in the prior art Reliably, in a manner of the consumption amount of extra-high voltage direct-current interconnection of the fast acquiring based on clean energy resource generates electricity.
Summary of the invention
The interconnection consumption method for measuring and calculating that the object of the present invention is to provide a kind of based on short-term dynamic balancing the load and its System, realize it is reliable, fast acquiring with clean energy resource generate electricity based on extra-high voltage direct-current interconnection consumption amount, be scheduling institution Scheduling data are provided, so that system maximum capacity consumption under the conditions of meeting safe and stable operation is extra-high based on clean energy resource Press DC link.
On the one hand, the present invention provides a kind of interconnection consumption method for measuring and calculating based on short-term dynamic balancing the load, including Following steps:
S1: based on network load balance building short-term dynamic balancing the load model;
Dt=GL,t+Gr,t+Lh,t+Lother,t
In formula, DtIndicate load value of the power grid in t moment, GL,tIndicate power generating value of the power grid local unit in t moment, Gr,t Indicate power generating value of the power grid clean energy resource in t moment, Lh,tIndicate extra-high voltage direct-current interconnection t moment tie line plan value, Lother,tSummation of other interconnections of expression in addition to extra-high voltage direct-current interconnection in the tie line plan value of t moment;
S2: the plan start-up mode of short-term dynamic balancing the load model and power grid local unit based on building calculates The upper limit value and lower limit value of extra-high voltage direct-current interconnection consumption planned value at each moment to be studied;
S3: the segmented mode based on the extra-high voltage direct-current tie line plan curve prestored and spy at each moment to be studied The upper limit value and lower limit value of high voltage direct current interconnection consumption planned value obtain the segmentation of extra-high voltage direct-current interconnection consumption planned value Curve;
Wherein, the piecewise interval on the sectional curve of extra-high voltage direct-current interconnection consumption planned value and extra-high voltage direct-current are got in touch with The piecewise interval of line Plan Curve corresponds, and extra-high voltage direct-current interconnection dissolves each segment identifier in the sectional curve of planned value There are one group of consumption planned value maximum value and minimum value, calculation formula are as follows for interior correspondence:
In formula,WithL(Ti) it is illustrated respectively in period TiThe maximum of interior extra-high voltage direct-current interconnection consumption planned value Value and minimum value,WithThe upper limit value for dissolving planned value at t moment on extra-high voltage direct-current interconnection is illustrated respectively in under Limit value, Ti、TnI-th of piecewise interval in extra-high voltage direct-current tie line plan curve is respectively indicated, n-th of piecewise interval is corresponding Period, n are the piecewise interval number of extra-high voltage direct-current tie line plan curve.
It should be appreciated that extra-high voltage direct-current interconnection in this field is mainly based on clean energy resource.The method of the invention exists When considering the digestion capability of extra-high voltage direct-current interconnection, comprehensive analysis load, local system water transfer fire generated output, clean energy resource with And other interconnections and then short-term dynamic balancing the load model is constructed, not only allow for province's inner equilibrium, it is also contemplated that transprovincially Power balance carries out the calculating of the consumption amount of extra-high voltage direct-current interconnection under based on short-term dynamic balancing the load model, so that System maximum capacity under the conditions of meeting safe and stable operation dissolves the extra-high voltage interconnection based on clean energy resource.Therefore, originally The sectional curve for inventing obtained extra-high voltage direct-current interconnection consumption planned value can be applied to can be used as scheduling institution formulation day Preceding plan makes it pay the utmost attention to extra-high voltage direct-current interconnection when carrying out Real-time Balancing calculating.
The formula from above-mentioned S3 is it is found that in period TiThe maximum value of interior extra-high voltage direct-current interconnection consumption planned value For in period TiMinimum value in the interior planned value maximum value of place's consumption constantly that requires study;In period TiInterior extra-high straightening Flow the minimum value of interconnection consumption planned valueL(Ti) it is in period TiThe interior planned value minimum value of place's consumption constantly that requires study In maximum value.
Preferably, extra-high voltage direct-current interconnection dissolves the upper limit value of planned value under at each moment to be studied in step S2 The calculation formula of limit value is as follows:
In formula,WithIt is illustrated respectively in the upper limit value and lower limit of the sum of had interconnection consumption planned value at t moment Value, wherein the upper limit value of the sum of had interconnection consumption planned value at t momentAnd lower limit valueCalculation formula such as Under:
In formula, DtThe predicted load of ' expression t moment, Gr,tIndicate the prediction power generating value of t moment clean energy resource,Power grid local unit is respectively indicated in the power output upper limit of t moment and power output lower limit.
Preferably, the power output upper limit of the power grid local unit in t momentIt is the 100% of booting capacity, power grid local Power output lower limit of the group in t momentIt is the 50% of booting capacity.
Preferably, the moment to be studied chosen in S2 is using 15min as gap periods at the time of point.
The moment to be studied is essentially 96 points, i.e., it is daily in 15 minutes for a time point.
On the other hand, the present invention also provides a kind of calculating systems based on the above method, including balance model to construct module And processing module;
Wherein, balance model constructs module, for based on network load balance building short-term dynamic balancing the load model;
Processing module, for calculate the consumption planned value of extra-high voltage direct-current interconnection at each moment to be studied upper limit value and Lower limit value;
Processing module, for calculating the maximum value and minimum of each piecewise interval extra-high voltage direct-current interconnection consumption planned value Value, and then obtain the sectional curve of extra-high voltage direct-current interconnection consumption planned value.
Beneficial effect
1, the present invention provides a kind of measuring method of completely new consumption amount for obtaining extra-high voltage direct-current interconnection, which is logical Building short-term dynamic balancing the load model is crossed to calculate extra-high voltage direct-current interconnection consumption planned value at each moment to be studied Upper limit value and lower limit value, then the conventional stage mode of foundation extra-high voltage direct-current tie line plan curve obtain extra-high voltage direct-current contact Line dissolves the sectional curve of planned value, calculates simply, acquisition modes are convenient.
2, the method for the invention is when considering the digestion capability of extra-high voltage direct-current interconnection, comprehensive analysis load, local System water transfer fire generated output, clean energy resource and other interconnections construct short-term dynamic balancing the load model in turn, not only Consider province's inner equilibrium, it is also contemplated that power balance transprovincially carries out extra-high straightening under based on short-term dynamic balancing the load model Flow the consumption amount of interconnection be calculated reliable consumption amount of plan as a result, system is made to meet safe and stable operation item Maximum capacity dissolves the extra-high voltage interconnection based on clean energy resource under part, and the sectional curve of obtained consumption planned value is by local Scheduling executes, to help to improve safe operation of electric network stability.
Detailed description of the invention
Fig. 1 is a kind of flow chart of the measuring method of completely new consumption amount for obtaining extra-high voltage direct-current interconnection of the invention.
Specific embodiment
Below in conjunction with embodiment, the present invention is described further.
As shown in Figure 1, a kind of interconnection based on short-term dynamic balancing the load provided by the invention dissolves method for measuring and calculating, Include the following steps:
S1: based on network load balance building short-term dynamic balancing the load model.Wherein, using network load balance as base Plinth, short-term dynamic balancing the load model need to meet such as following formula:
Dt=GL,t+Gr,t+Lh,t+Lother,t
In formula, DtIndicate load value of the power grid in t moment, GL,tIndicate power generating value of the power grid local unit in t moment, Gr,t Indicate power generating value of the power grid clean energy resource in t moment, Lh,tIndicate extra-high voltage direct-current interconnection t moment tie line plan value, Lother,tSummation of other interconnections of expression in addition to extra-high voltage direct-current interconnection in the tie line plan value of t moment.
S2: the plan start-up mode of short-term dynamic balancing the load model and power grid local unit based on building calculates The upper limit value and lower limit value of planned value are dissolved on extra-high voltage direct-current interconnection at each 96 point.
Firstly, obtaining power output lower limit of the local unit at 96 points according to the unit start-up mode plan of power grid localWith The power output upper limitIn the present embodiment, set that other tie line plans are constant and local startup-shutdown mode is constant therefore each The power output lower limit at momentIt is the 50% of booting capacity, the upper limit of contributingIt is the 100% of booting capacity.
According to the short-term dynamic balancing the load model in step S1, the consumption planned value of all interconnections of t moment is obtained The sum of calculation formula it is as follows:
Lall,t=Dt′-(GL,t+Gr,t)
In formula, Lall,tIndicate the sum of had interconnection consumption planned value, D at t momenttThe load prediction of ' expression t moment Value, Gr,tIndicate the prediction power generating value of t moment clean energy resource.Therefore by the power output lower limit at 96 pointsWith the power output upper limit The upper limit value and lower limit value of the sum of the consumption planned value of all interconnections at 96 points can be calculated by substituting into the formula, as follows It is shown:
In formula,WithIt is illustrated respectively in the upper limit value and lower limit of the sum of had interconnection consumption planned value at t moment Value.So the upper limit value and the lower limit value that dissolve planned value on extra-high voltage direct-current interconnection at each 96 point are as follows:
In formula,WithIt is illustrated respectively at t moment and dissolves plan (at each 96 point) on extra-high voltage direct-current interconnection The upper limit value and lower limit value of value.By dissolving planned value upper limit value at available 96 point of extra-high voltage direct-current interconnection of above-mentioned calculating The maximum curve of composition, lower limit valueThe minimum curve of composition.
S3: the segmented mode based on the extra-high voltage direct-current tie line plan curve prestored and spy at each moment to be studied The upper limit value and lower limit value of high voltage direct current interconnection consumption planned value obtain the segmentation of extra-high voltage direct-current interconnection consumption planned value Curve.
The curve type of extra-high voltage direct-current tie line plan curve is usually step type, therefore special within one section of period High voltage direct current interconnection dissolves the curve of planned value by a plurality of rectilinear(-al).By being carried out to 96 points of consumption planned values of each period Processing, it is assumed that extra-high voltage direct-current tie line plan value curve is made of n ladder, therefore curve can be divided into n sections, Ti∈ {T1,T2,…Tn}.Within each period, the sectional curve of extra-high voltage direct-current interconnection consumption planned value is expressed as follows:
In formula,WithL(Ti) it is illustrated respectively in period TiThe maximum of interior extra-high voltage direct-current interconnection consumption planned value Value and minimum value.From above-mentioned formula it is found that in period TiThe maximum value of interior extra-high voltage direct-current interconnection consumption planned value For in period TiMinimum value in interior all 96 points of consumptions planned value maximum values;In period TiInterior extra-high voltage direct-current interconnection Dissolve the minimum value of planned valueL(Ti) it is in period TiMaximum value in interior all 96 points of consumptions planned value minimum values.
On the other hand, the present invention also provides the calculating system based on the method, including balance model building module and Processing module;
Wherein, balance model constructs module, for based on network load balance building short-term dynamic balancing the load model;
Processing module, for calculate the consumption planned value of extra-high voltage direct-current interconnection at each moment to be studied upper limit value and Lower limit value;
Processing module, for calculating the maximum value and minimum of each piecewise interval extra-high voltage direct-current interconnection consumption planned value Value, and then obtain the sectional curve of extra-high voltage direct-current interconnection consumption planned value.
Wherein, above-mentioned module is divided into division of functionality, and in some embodiments, part of module can merge or tear open Solution, the present invention is to this without specifically limiting.
The method of the invention is when considering the digestion capability of extra-high voltage direct-current interconnection, comprehensive analysis load, local system Water transfer fire generated output, clean energy resource and other interconnections construct short-term dynamic balancing the load model in turn, not only examine Province's inner equilibrium is considered, it is also contemplated that power balance transprovincially carries out extra-high voltage direct-current under based on short-term dynamic balancing the load model The calculating of the consumption amount of interconnection, so that system maximum capacity under the conditions of meeting safe and stable operation dissolves with clean energy resource and is Main extra-high voltage interconnection.
It is emphasized that example of the present invention be it is illustrative, without being restrictive, thus the present invention it is unlimited Example described in specific embodiment, other all obtained according to the technique and scheme of the present invention by those skilled in the art Embodiment does not depart from present inventive concept and range, and whether modification or replacement, also belong to protection model of the invention It encloses.

Claims (5)

1. a kind of interconnection based on dynamic load balancing dissolves method for measuring and calculating, it is characterised in that;Include the following steps:
S1: based on network load balance building short-term dynamic balancing the load model;
Dt=GL,t+Gr,t+Lh,t+Lother,t
In formula, DtIndicate load value of the power grid in t moment, GL,tIndicate power generating value of the power grid local unit in t moment, Gr,tIt indicates Power generating value of the power grid clean energy resource in t moment, Lh,tIndicate extra-high voltage direct-current interconnection t moment tie line plan value, Lother,tSummation of other interconnections of expression in addition to extra-high voltage direct-current interconnection in the tie line plan value of t moment;
S2: the plan start-up mode of short-term dynamic balancing the load model and power grid local unit based on building calculates each The upper limit value and lower limit value of extra-high voltage direct-current interconnection consumption planned value at moment to be studied;
S3: the segmented mode based on the extra-high voltage direct-current tie line plan curve prestored and extra-high voltage at each moment to be studied The upper limit value and lower limit value of DC link consumption planned value obtain the sectional curve of extra-high voltage direct-current interconnection consumption planned value;
Wherein, the piecewise interval and extra-high voltage direct-current interconnection meter on the sectional curve of extra-high voltage direct-current interconnection consumption planned value The piecewise interval of tracing corresponds, and extra-high voltage direct-current interconnection dissolves in the sectional curve of planned value in each piecewise interval It is corresponding that there are one group of consumption planned value maximum value and minimum value, calculation formula are as follows:
In formula,WithL(Ti) it is illustrated respectively in period TiThe maximum value of interior extra-high voltage direct-current interconnection consumption planned value with most Small value,WithIt is illustrated respectively in the upper limit value and lower limit value for dissolving planned value at t moment on extra-high voltage direct-current interconnection, Ti、TnRespectively indicate i-th of piecewise interval in extra-high voltage direct-current tie line plan curve, n-th of piecewise interval corresponding time Section, n are the piecewise interval number of extra-high voltage direct-current tie line plan curve.
2. according to the method described in claim 1, it is characterized by: extra-high voltage direct-current joins at each moment to be studied in step S2 The upper limit value of winding thread consumption planned value and the calculation formula of lower limit value are as follows:
In formula,WithIt is illustrated respectively in the upper limit value and lower limit value of the sum of had interconnection consumption planned value at t moment, Wherein, at t moment the sum of had interconnection consumption planned value upper limit valueAnd lower limit valueCalculation formula it is as follows:
In formula, D 'tIndicate the predicted load of t moment, G 'r,tIndicate the prediction power generating value of t moment clean energy resource, Power grid local unit is respectively indicated in the power output upper limit of t moment and power output lower limit.
3. according to the method described in claim 2, it is characterized by: power grid local unit t moment the power output upper limitTo open The 100% of machine capacity, power output lower limit of the power grid local unit in t momentIt is the 50% of booting capacity.
4. according to the method described in claim 1, it is characterized by: the moment to be studied chosen in S2 is using 15min as interval Point at the time of period.
5. a kind of calculating system based on any one of claim 1-4 the method, it is characterised in that: constructed including balance model Module and processing module;
Wherein, balance model constructs module, for based on network load balance building short-term dynamic balancing the load model;
Processing module, for calculating the upper limit value and lower limit of extra-high voltage direct-current interconnection consumption planned value at each moment to be studied Value;
Processing module, for calculating the maxima and minima of each piecewise interval extra-high voltage direct-current interconnection consumption planned value, And then obtain the sectional curve of extra-high voltage direct-current interconnection consumption planned value.
CN201811141651.7A 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system Active CN109066738B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811141651.7A CN109066738B (en) 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811141651.7A CN109066738B (en) 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system

Publications (2)

Publication Number Publication Date
CN109066738A true CN109066738A (en) 2018-12-21
CN109066738B CN109066738B (en) 2021-04-23

Family

ID=64766474

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811141651.7A Active CN109066738B (en) 2018-09-28 2018-09-28 Dynamic load balance-based tie line absorption amount calculation method and system

Country Status (1)

Country Link
CN (1) CN109066738B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102075014A (en) * 2011-01-06 2011-05-25 清华大学 Large grid real-time scheduling method for accepting access of wind power
CN104578183A (en) * 2015-01-28 2015-04-29 国家电网公司 Tie-line power transmission plan optimization method for improving low-carbon level of electric system
CN105470956A (en) * 2015-12-29 2016-04-06 中国电力科学研究院 Optimal dispatching method for inter-provincial interconnecting line for production analogue simulation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102075014A (en) * 2011-01-06 2011-05-25 清华大学 Large grid real-time scheduling method for accepting access of wind power
CN104578183A (en) * 2015-01-28 2015-04-29 国家电网公司 Tie-line power transmission plan optimization method for improving low-carbon level of electric system
CN105470956A (en) * 2015-12-29 2016-04-06 中国电力科学研究院 Optimal dispatching method for inter-provincial interconnecting line for production analogue simulation

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
HAIBO ZHANG,SEN ZHANG: "A New Strategy of HVDC Operation for Maximizing Renewable Energy Accommodation", 《2017 IEEE POWER & ENERGY SOCIETY GENERAL MEETING》 *
舒印彪等: "新能源消纳关键因素分析及解决措施研究", 《中国电机工程学报》 *

Also Published As

Publication number Publication date
CN109066738B (en) 2021-04-23

Similar Documents

Publication Publication Date Title
KR20190073340A (en) Intelligent grid operation system for managing distributed energy resources in the grid
WO2009109591A1 (en) Method and system for efficient commodity distribution and production
CN106684915A (en) Wind-hydrogen coupling power generation system optimization method and device thereof
CN102244677A (en) Green energy Cloud computing method and system
Amicarelli et al. Multi-agent system for day-ahead energy management of microgrid
Liska et al. Research on smart home energy management system
CN108695893A (en) A kind of provincial power network new energy abandons electricity influence factor decomposition method
CN109066738A (en) A kind of interconnection consumption method for measuring and calculating and its system based on dynamic load balancing
Kassim et al. Mobile application for electric power monitoring on energy consumptions at a campus university
Chinthavali et al. Solid state power substations (SSPS): A multi-hierarchical architecture from substation to grid edge
CN106203704A (en) Introduce the generating set CO2 emissions measuring method of water-storage device
CN106786568B (en) A kind of distribution power automation terminal is layouted planning and configuration method
Tajwar et al. Solar Photovoltaic-Based Smart Metering System
CN116468302A (en) Building park energy structure evaluation method, system, electronic equipment and storage medium
Tang et al. Benefits allocation method for demand response in smart distribution network with high PV penetration
CN109995094B (en) Planning method and system for AC/DC hybrid micro-grid
CN109871983B (en) Electric power energy management system
Miljan et al. Optimal bidding for a large battery-electrolyzer facility in the day-ahead market
Klaić et al. Load management scheme using air conditioning electric power consumption and photovoltaic power system generation
Mancasi et al. Evolution of smart buildings. A Romanian case
Awad et al. Co-simulation-based evaluation of volt-var control
Li et al. Economic assessment of voltage sags based on quality engineering theory
Yu et al. Analysis of DC distribution efficiency based on metered data in a typical Hong Kong office building
Liu et al. Cascade Hydro-Photovoltaic Storage Complementary Power Station Planning Software
CN115619102B (en) Electrical calculation checking method based on new energy power abandonment rate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant