CN109061473A - A kind of Wind turbines master control system grid adaptability filed detection system and method - Google Patents

A kind of Wind turbines master control system grid adaptability filed detection system and method Download PDF

Info

Publication number
CN109061473A
CN109061473A CN201811123751.7A CN201811123751A CN109061473A CN 109061473 A CN109061473 A CN 109061473A CN 201811123751 A CN201811123751 A CN 201811123751A CN 109061473 A CN109061473 A CN 109061473A
Authority
CN
China
Prior art keywords
switch
wind turbines
value
adaptability
voltage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811123751.7A
Other languages
Chinese (zh)
Other versions
CN109061473B (en
Inventor
何廷
何廷一
李胜男
马红升
杨蕾
孟贤
和鹏
郭晓宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Yunnan Power System Ltd
Original Assignee
Electric Power Research Institute of Yunnan Power System Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Yunnan Power System Ltd filed Critical Electric Power Research Institute of Yunnan Power System Ltd
Priority to CN201811123751.7A priority Critical patent/CN109061473B/en
Publication of CN109061473A publication Critical patent/CN109061473A/en
Application granted granted Critical
Publication of CN109061473B publication Critical patent/CN109061473B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/34Testing dynamo-electric machines
    • G01R31/343Testing dynamo-electric machines in operation

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Control Of Eletrric Generators (AREA)
  • Testing Relating To Insulation (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

This application discloses a kind of Wind turbines master control system grid adaptability filed detection system and method, the detection system includes: the first bus, bypass, major loop, the second bus and three impedance bleeder circuits.In the application, detection system is low-voltage device, is moved easily and transports, and can carry out the test of more Wind turbines grid adaptabilities in a short time, suitable for inspecting the recruitment evaluation after blower after wind field fan improvement by random samples.

Description

A kind of Wind turbines master control system grid adaptability filed detection system and method
Technical field
This application involves Wind turbines technical field, in particular to a kind of Wind turbines master control system grid adaptability is existing Field detecting system and method.
Background technique
35kV movable type grid adaptability detection platform has been developed at present, which carries out repeatedly scene examination It tests.Fig. 1 is the usage scenario of detection platform 9 in the prior art.Following problems are found in test at the scene: one, the wind inspected by random samples Motor group tests the requirement for not being able to satisfy the grid-connected aptitude tests standard of Wind turbines for the first time, requires producer and carries out multiple component Replacement and software change could complete test.Two, grid adaptability detection platform is by two containers (each container about 35 Ton), test requires to can be only done sampling observation to the hoisting transportation of container and the dilatory of 35kV cable and installation, short time every time The test of one Wind turbines of wind power plant, remaining Wind turbines can only by producer's later period according to scene find the problem of into Row rectification, but due to lacking field demonstration, the effect of rectification is difficult to assess;Three, current transformer 690V generally pacifies point of incoming cables Equipped with filter circuit, when carrying out grid adaptability test, filter circuit will affect the output quantity of detection platform, and then influence test As a result.
Summary of the invention
The application's is designed to provide a kind of Wind turbines master control system grid adaptability filed detection system and side Method, to solve the problems, such as that detection platform inconvenience in the prior art is mobile and transports.
In a first aspect, a kind of Wind turbines master control system grid adaptability on-site test system provided by the embodiments of the present application System, the detection system includes: the first bus, bypass, major loop, the second bus and three impedance bleeder circuits;
First bus is connect with Wind turbines distribution transformer;
First bus and the bypass connect, and are provided with first switch in the bypass;
First bus is also connect with the major loop, second switch is disposed on the major loop, IGBT is changed Flow device and third switch;
The first switch and third switch are connect with second bus respectively;
Second bus is connect with three impedance bleeder circuits;
The impedance bleeder circuit includes first resistor and second resistance, the input terminal of the first resistor and described second The input terminal of resistance is connect with the output end of second bus respectively, and main control PLC is connect by secondary line with current transformer, described The output end of first resistor and the output end of second resistance are connect with the secondary line.
Second aspect, embodiments herein provide a kind of Wind turbines master control system grid adaptability on-site test Method the described method comprises the following steps:
It determines impedance bleeder circuit parameter, according to impedance bleeder circuit parameter, first resistor value and second resistance value is set, The parameter is R1/R2, and R1 is first resistor value, and R2 is second resistance value;
It will test between the access main control PLC of system and current transformer;
First switch is closed, second switch and third switch is disconnected, obtains the voltage for bypassing added voltage value and main control PLC Sampled value judges whether bypass added voltage value and the voltage sample value of main control PLC meets the first preset ratio;
If meeting the first preset ratio, first switch is disconnected, closes second switch and third switch, modification impedance partial pressure Circuit parameter resets first resistor value and second resistance value according to modified impedance bleeder circuit parameter;
Second switch and third switch are closed, first switch is disconnected, starts detection system, judges voltage value added by major loop Whether meet the second preset ratio with the voltage sample value of main control PLC;
If meeting the second preset ratio, by the way that IGBT inverter parameter simulation test condition is arranged, Wind turbines are detected Grid adaptability.
Further, it is described detection Wind turbines grid adaptability include frequency adaptability, three-phase imbalance adaptability, Flickering adaptability and harmonic wave adaptability.
Further, the method also includes:
If meeting the second preset ratio, the voltage and current signals acquired using data collecting instrument calculate Wind turbines The active power and reactive power of outlet transformer.
Further, the step of determining impedance bleeder circuit parameter, comprising:
According to Ui/ (R1+R2)=Uo/R2, computing impedance bleeder circuit parameter, wherein Ui 380V, Uo are current transformer Voltage value.
Further, if described meet the first preset ratio, first switch is disconnected, second switch is closed and third is opened It closes, modifies impedance bleeder circuit parameter according to modified impedance bleeder circuit parameter and reset first resistor value and second The step of resistance value includes:
If meeting the first preset ratio, first switch is disconnected, closes second switch and third switch;
Measure the voltage difference U io of the input terminal of first resistor and the input terminal of second resistance, the voltage at second resistance both ends Poor Uoo;
According to (Uio-U)/(R1+R2)=Uoo/R2, the pressure drop U of IGBT inverter is calculated;
According to pressure drop U, modifies impedance bleeder circuit parameter and reset according to modified impedance bleeder circuit parameter First resistor value and second resistance value.
From the above technical scheme, this application provides a kind of inspections of Wind turbines master control system grid adaptability scene Examining system and method, the detection system include: the first bus, bypass, major loop, the second bus and three impedance partial pressure electricity Road.In the application, detection system is low-voltage device, is moved easily and transports, and can carry out more Wind turbines electricity in a short time Net compatibility test, suitable for inspecting the recruitment evaluation after blower after wind field fan improvement by random samples.
Detailed description of the invention
In order to illustrate the technical solutions in the embodiments of the present application or in the prior art more clearly, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the application Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is the usage scenario of detection platform in the prior art
Fig. 2 is a kind of Wind turbines master control system grid adaptability filed detection system provided by the embodiments of the present application Structural schematic diagram;
Fig. 3 is wiring schematic diagram when detection system provided by the embodiments of the present application uses.
It illustrates:
Wherein, 1- Wind turbines distribution transformer, the first bus of 2-, 3- bypass, 31- first switch, 4- major loop, 41- Second switch, 42-IGBT inverter, 43- third switch, the second bus of 5-, 6- impedance bleeder circuit, 61- first resistor, 62- Second resistance, 7- main control PLC, 8- current transformer, 9- detection platform, 10- detection system, 11- Wind turbines outlet transformer, 12- Data collecting instrument.
Specific embodiment
In a first aspect, being illustrated referring to Fig. 2 to presently filed embodiment, a kind of Wind turbines master control system power grid Adaptability filed detection system includes: the first bus 2, bypass 3, major loop 4, the second bus 5 and three impedance bleeder circuits 6;
Grid adaptability filed detection system in the application uses indirect AC convertor, controls device entirely based on power electronics Part, output voltage curve are programmable.Output voltage uses closed-loop control, and voltage adjusting dynamic characteristic is good, and control precision is high, output Voltage phase sequence, phase, amplitude and frequency Independent adjustable, voltage change and recovery curve are smooth, meet domestic Wind turbines The test requirements document of grid adaptability.
First bus 2 is connect with Wind turbines distribution transformer 1;
First bus 2 is connect with the bypass 3, is provided with first switch 31 in the bypass 3;
First bus 2 is also connect with the major loop 4, be disposed on the major loop 4 second switch 41, IGBT inverter 42 and third switch 43;
The first switch 31 and third switch 43 are connect with second bus 5 respectively;
Second bus 5 is connect with three impedance bleeder circuits 6;
The impedance bleeder circuit 6 include first resistor 61 and second resistance 62, the input terminal of the first resistor 61 and The input terminal of the second resistance 62 is connect with the output end of second bus 5 respectively, and main control PLC 7 is by secondary line and becomes It flows device 8 to connect, the output end of the first resistor 61 and the output end of second resistance 62 are connect with the secondary line.
The first bus 2 and the second bus 5 are three-phase p-wire in the application.
The 380V voltage that the application is exported using Wind turbines distribution transformer 1 is as input voltage;Input voltage passes through The AV-DC-AC low voltage electric network adaptive testing device commutation inversion that IGBT is constituted obtains the three-phase tested for grid adaptability Voltage;Three-phase test voltage, which is transformed to current transformer 8 by impedance bleeder circuit 6, can input the three-phase voltage signal of main control PLC 7, Main control PLC 7 is according to secondary singal to making a response;Wind turbines are judged according to the requirement of the response condition of main control PLC 7 and standard The grid adaptability ability of master control.
The application adds " secondary singal " in secondary side to detect the detection system of Wind turbines master control power grid adaptability.Two It is double measurement amount that secondary side, which adds the basic principle of the detection method of " secondary singal " to be the input quantity of Wind turbines main control PLC 7, That is the control of Wind turbines is the survey secondary for signals such as wind speed, propeller pitch angle, revolving speed, network voltage, electric currents of main control PLC 7 The response of amount amount can make master control by the different voltages disturbing signal that grid adaptability standard requirements are added in secondary side PLC7 thinks that power grid characteristic changes, and then main control PLC 7 makes corresponding response according to control logic, is responded by these, For example, blower whether the data that off-grid and data collecting instrument are collected, so that it may judge that Wind turbines grid adaptability ability is The no requirement for meeting standard.
The application detection system is based on voltage source tandem principle, and back-to-back Semiconductor Converting Technology is pressed in, can run generation generation The power trains such as Network Voltage Deviation, frequency departure, imbalance of three-phase voltage, flickering and harmonic wave required by the grid-connected directive/guide in various countries of boundary System operational limit operating condition.Detection system working voltage 6KV/10kV, 35kV is optional, rated capacity 4MVA, detection system deviation tune Adjusting range 0%Un-130%Un, frequency departure adjustable range 45Hz-66Hz, non-equilibrium among three phase voltages adjustable range 0.5%- 10%, total voltage percent harmonic distortion adjustable range 0.5%-10%, can be by adjusting voltage amplitude and the flexible simulating grid of phase Variation.
In the prior art, detection device high pressure once concatenates, and using container form, volume is big, transporting and hoisting is at high cost, In addition Wind turbines quantity is big, and the short time is difficult to carry out the recruitment evaluation after extensive field test and blower rectification;The application The system of proposition using distribution transforming 380UV as input, using IGBT inverter 42 by voltage transformation be grid adaptability test It uses the decompression of impedance bleeder circuit 6 for main control PLC 7 can be inputted from secondary side after waveform, and then carries out the adaptation of Wind turbines power grid Property detection method, it is simple and effective;Detection system is low-voltage device, is moved easily and transports, and can carry out more in a short time Wind turbines grid adaptability test, suitable for inspecting the recruitment evaluation after blower after wind field fan improvement by random samples.
Test is completed in primary equipment access in the prior art, and the capacity of testing equipment has to be larger than Wind turbines single machine appearance Amount, capacity limit make on-site test test remain white space.The method that secondary dosage is used in the application, avoids tradition When changing primary side 690V primary voltage test Wind turbines in test, influence of the point of incoming cables filter circuit to testing experiment;And And secondary side test does not need to require the capacity of test platform to be greater than tested Wind turbines capacity, is equally applicable to 8-10MW Wind turbines.
Second aspect, a kind of Wind turbines master control system grid adaptability in-situ check and test method, comprising the following steps:
Before using detection system detection grid adaptability, need to confirm to whether IGBT inverter 42 makes moist. If following steps can be continued by not making moist.
It determines impedance bleeder circuit parameter, according to impedance bleeder circuit parameter, impedance is set in the detection system and divides electricity Road parameter setting first resistor value and second resistance value, the parameter are R1/R2, and R1 is first resistor value, and R2 is second resistance Value;
According to wiring schematic diagram shown in Fig. 3, will test between the access current transformer 8 of system 10 and main control PLC 7;
Specifically, stopping testing blower, stop the Wind turbines distribution transformer 1 for testing blower, disconnects Wind turbines distribution and become The high-pressure side on-load switch of depressor 1 disconnects the secondary line between current transformer 8 and main control PLC 7, will test system 10 and accesses unsteady flow On device 8 and the secondary line of main control PLC 7, data collecting instrument 12 is accessed.
First switch 31 is closed, second switch 41 and third switch 43 are disconnected, obtains voltage value and master control added by bypass 3 The voltage sample value of PLC7, judges whether the voltage sample value of voltage value added by bypass 3 and main control PLC 7 meets the first default ratio Example;
The specific debugging software and data collecting instrument 12 for passing through producer, while recording added voltage value and master in bypass 3 The actual voltage sample value of PLC7 to be controlled, judges whether to meet the first preset ratio, first preset ratio is (R1+R2)/R2, Voltage value added by the bypass 3 is the voltage difference U i i of the input terminal of first resistor and the input terminal of second resistance.
If meeting the first preset ratio, first switch is disconnected, closes second switch and third switch, modification impedance partial pressure Circuit parameter resets first resistor value and second resistance value according to modified impedance bleeder circuit parameter.
Specifically, illustrating that there is no problem for device in bypass 3 if meeting the first preset ratio, can carrying out repairing in next step Positive impedance bleeder circuit parameter.
Second switch and third switch are closed, first switch is disconnected, starts detection system, judges voltage value added by major loop Whether meet the second preset ratio with the voltage sample value of main control PLC;
Second preset ratio is (R1+R2)/R2, wherein voltage value added by major loop is Wind turbines distribution transformer electricity Pressure subtracts the voltage value that the voltage drop value of IGBT inverter obtains.
Specifically, starting detection device, output meet the test waveform of grid adaptability regulation detection, pass through the tune of producer Software and data collecting instrument are tried, while recording added voltage value and the actual voltage sample value of main control PLC 7 on major loop 4.
If meeting the second preset ratio, by the way that IGBT inverter parameter simulation test condition is arranged, Wind turbines are detected Grid adaptability.
IGBT inverter on major loop 4 is surveyed referring to professional standard NB/T 31054_2014 Wind turbines grid adaptability Try parameter setting and triggering control that regulation carries out inverter.
Specifically, limited load 100kw first starts blower, it is suitable by the parameter simulation network voltage of IGBT converter Control Ying Xing, frequency adaptability, three-phase imbalance adaptability, flickering adaptability and harmonic wave adaptability carry out test item by item, and test passes through Load limitation is opened gradually to be tested, until load limitation is all open, after the completion of test, according to blower whether off-grid and The data analysis result of data collecting instrument, judges whether blower meets grid adaptability requirement.
The test of Wind turbines grid adaptability is to generate electricity in Wind turbines step-up transformer high-pressure side using test device The grid disturbances such as net voltage deviation, frequency departure, imbalance of three-phase voltage, voltage flicker and harmonic wave, so that it is tested to verify examination The service ability of Wind turbines and a wind-electricity integration testing inspection behavior of relaying configuration.
Further, it is described detection Wind turbines grid adaptability include frequency adaptability, three-phase imbalance adaptability, Flickering adaptability and harmonic wave adaptability.
Further, the method also includes:
If meeting the second preset ratio, the voltage and current signals acquired using data collecting instrument calculate Wind turbines The active power and reactive power of outlet transformer 10.
Further, the step of determining impedance bleeder circuit parameter, comprising:
According to Ui/ (R1+R2)=Uo/R2, computing impedance bleeder circuit parameter, wherein Ui 380V, Uo provide for producer Current transformer voltage value.
Further, if described meet the first preset ratio, first switch is disconnected, closes second switch and third Switch modifies impedance bleeder circuit parameter, according to modified impedance bleeder circuit parameter, resets first resistor value and the The step of two resistance values includes:
If meeting the first preset ratio, first switch is disconnected, closes second switch and third switch;
Measure the voltage difference U io of the input terminal of first resistor and the input terminal of second resistance, the voltage at second resistance both ends Poor Uoo;
According to (Uio-U)/(R1+R2)=Uoo/R2, the pressure drop U of IGBT inverter is calculated.
According to pressure drop U, modifies impedance bleeder circuit parameter and reset according to modified impedance bleeder circuit parameter First resistor value and second resistance value.
Present application contemplates the influences of 42 pressure drop of IGBT inverter, and the impedance bleeder circuit of needs is first tested using bypass 3 Parameter R1/R2 is avoided in the method for testing modified R 1/R2 using major loop 4 because 42 pressure drop of IGBT inverter influence is secondary Input value, so as to cause fan test failure.
From the above technical scheme, this application provides a kind of inspections of Wind turbines master control system grid adaptability scene Examining system and method, the detection system include: the first bus 2, bypass 3, major loop 4, the second bus 5 and three impedance partial pressures Circuit 6.In the application, detection system is low-voltage device, is moved easily and transports, and can carry out more Wind turbines in a short time Grid adaptability test, suitable for inspecting the recruitment evaluation after blower after wind field fan improvement by random samples.
Those skilled in the art will readily occur to its of the application after considering specification and practicing application disclosed herein Its embodiment.This application is intended to cover any variations, uses, or adaptations of the application, these modifications, purposes or Person's adaptive change follows the general principle of the application and including the undocumented common knowledge in the art of the application Or conventional techniques.The description and examples are only to be considered as illustrative, and the true scope and spirit of the application are by following Claim is pointed out.
It should be understood that the application is not limited to the precise structure that has been described above and shown in the drawings, and And various modifications and changes may be made without departing from the scope thereof.Scope of the present application is only limited by the accompanying claims.

Claims (6)

1. a kind of Wind turbines master control system grid adaptability filed detection system, which is characterized in that the detection system packet It includes: the first bus (2), bypass (3), major loop (4), the second bus (5) and three impedance bleeder circuits (6);
First bus (2) connect with Wind turbines distribution transformer (1);
First bus (2) connect with the bypass (3), is provided with first switch (31) on the bypass (3);
First bus (2) also connect with the major loop (4), is disposed with second switch on the major loop (4) (41), IGBT inverter (42) and third switch (43);
The first switch (31) and third switch (43) are connect with second bus (5) respectively;
Second bus (5) connect with three impedance bleeder circuits (6);
The impedance bleeder circuit (6) includes first resistor (61) and second resistance (62), the input of the first resistor (61) The input terminal of end and the second resistance (62) is connect with the output end of second bus (5) respectively, and main control PLC (7) passes through Secondary line is connect with current transformer (8), the output end of the first resistor (61) and the output end and described two of second resistance (62) Secondary line connection.
2. a kind of Wind turbines master control system grid adaptability in-situ check and test method, which is characterized in that the method includes with Lower step:
It determines impedance bleeder circuit parameter, according to impedance bleeder circuit parameter, first resistor value and second resistance value is set, it is described Parameter is R1/R2, and R1 is first resistor value, and R2 is second resistance value;
It will test between the access main control PLC of system and current transformer;
First switch is closed, second switch and third switch is disconnected, obtains the voltage sample for bypassing added voltage value and main control PLC Value judges whether bypass added voltage value and the voltage sample value of main control PLC meets the first preset ratio;
If meeting the first preset ratio, first switch is disconnected, second switch and third switch is closed, modifies impedance bleeder circuit Parameter resets first resistor value and second resistance value according to modified impedance bleeder circuit parameter;
Second switch and third switch are closed, first switch is disconnected, starts detection system, judges voltage value and master added by major loop Whether the voltage sample value of control PLC meets the second preset ratio;
If meeting the second preset ratio, by the way that IGBT inverter parameter simulation test condition is arranged, the electricity of Wind turbines is detected Net adaptability.
3. a kind of Wind turbines master control system grid adaptability in-situ check and test method according to claim 2, feature Be, it is described detection Wind turbines grid adaptability include frequency adaptability, three-phase imbalance adaptability, flickering adaptability and Harmonic wave adaptability.
4. a kind of Wind turbines master control system grid adaptability in-situ check and test method according to claim 2, feature It is, the method also includes:
If meeting the second preset ratio, the voltage and current signals acquired using data collecting instrument calculate Wind turbines outlet The active power and reactive power of transformer.
5. a kind of Wind turbines master control system grid adaptability in-situ check and test method according to claim 2, feature It is, the step of the determining impedance bleeder circuit parameter, comprising:
According to Ui/ (R1+R2)=Uo/R2, computing impedance bleeder circuit parameter, wherein Ui 380V, Uo are the voltage of current transformer Value.
6. a kind of Wind turbines master control system grid adaptability in-situ check and test method according to claim 2, feature It is, if described meet the first preset ratio, disconnects first switch, closes second switch and third switch, modification impedance point Volt circuit parameter, according to modified impedance bleeder circuit parameter, the step of resetting first resistor value and second resistance value Include:
If meeting the first preset ratio, first switch is disconnected, closes second switch and third switch;
Measure the voltage difference U io of the input terminal of first resistor and the input terminal of second resistance, the voltage difference at second resistance both ends Uoo;
According to (Uio-U)/(R1+R2)=Uoo/R2, the pressure drop U of IGBT inverter is calculated;
According to pressure drop U, impedance bleeder circuit parameter is modified according to modified impedance bleeder circuit parameter and resets first Resistance value and second resistance value.
CN201811123751.7A 2018-09-26 2018-09-26 Wind turbine main control system power grid adaptability field detection system and method Active CN109061473B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811123751.7A CN109061473B (en) 2018-09-26 2018-09-26 Wind turbine main control system power grid adaptability field detection system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811123751.7A CN109061473B (en) 2018-09-26 2018-09-26 Wind turbine main control system power grid adaptability field detection system and method

Publications (2)

Publication Number Publication Date
CN109061473A true CN109061473A (en) 2018-12-21
CN109061473B CN109061473B (en) 2020-11-03

Family

ID=64765855

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811123751.7A Active CN109061473B (en) 2018-09-26 2018-09-26 Wind turbine main control system power grid adaptability field detection system and method

Country Status (1)

Country Link
CN (1) CN109061473B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111555306A (en) * 2020-04-29 2020-08-18 云南电网有限责任公司电力科学研究院 System and method for wind turbine generator set to participate in rapid frequency modulation of regional power grid
CN114113870A (en) * 2022-01-28 2022-03-01 西安德纳检验检测有限公司 New energy station power grid adaptability detection method, device and system

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101846707A (en) * 2010-02-04 2010-09-29 艾默生网络能源有限公司 Equipment and method for riding through testing platform at low voltage on low-voltage side
CN203037769U (en) * 2012-12-26 2013-07-03 北京荣华恒信开关技术有限公司 Wind power and photovoltaic grid-connected testing platform
WO2013163266A1 (en) * 2012-04-24 2013-10-31 General Electric Company Power conversion system with open- circuit fault detection and method thereof
CN203287500U (en) * 2013-06-14 2013-11-13 南京国电南自风电自动化技术有限公司 Low voltage ride-through test platform based on parallelly-connected current transformers and voltage-dividing reactors
CN104297685A (en) * 2014-10-27 2015-01-21 国家电网公司 Method for detecting parameters of double-fed wind generating set
CN105652200A (en) * 2014-11-04 2016-06-08 国电龙源电气有限公司 Controllable voltage fluctuation and flicker generation device
EP3043063A1 (en) * 2015-01-08 2016-07-13 Siemens Aktiengesellschaft Islanded testing of a wind turbine generators compliance with fault ride through requirements of a power grid
CN106291363A (en) * 2016-09-26 2017-01-04 武汉承光博德光电科技有限公司 The new forms of energy grid-connected test device of integration
CN106980272A (en) * 2016-01-19 2017-07-25 上海交通大学 A kind of control system of wind turbines hardware in loop simulation and test platform
CN206497189U (en) * 2017-02-16 2017-09-15 中核甘肃风力发电有限公司 A kind of high-performance voltage falling generator used for wind power generation
CN107843838A (en) * 2017-10-24 2018-03-27 国网山西省电力公司电力科学研究院 A kind of detection method of low voltage ride-through capability of wind turbine generator system

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101846707A (en) * 2010-02-04 2010-09-29 艾默生网络能源有限公司 Equipment and method for riding through testing platform at low voltage on low-voltage side
WO2013163266A1 (en) * 2012-04-24 2013-10-31 General Electric Company Power conversion system with open- circuit fault detection and method thereof
CN203037769U (en) * 2012-12-26 2013-07-03 北京荣华恒信开关技术有限公司 Wind power and photovoltaic grid-connected testing platform
CN203287500U (en) * 2013-06-14 2013-11-13 南京国电南自风电自动化技术有限公司 Low voltage ride-through test platform based on parallelly-connected current transformers and voltage-dividing reactors
CN104297685A (en) * 2014-10-27 2015-01-21 国家电网公司 Method for detecting parameters of double-fed wind generating set
CN105652200A (en) * 2014-11-04 2016-06-08 国电龙源电气有限公司 Controllable voltage fluctuation and flicker generation device
EP3043063A1 (en) * 2015-01-08 2016-07-13 Siemens Aktiengesellschaft Islanded testing of a wind turbine generators compliance with fault ride through requirements of a power grid
CN106980272A (en) * 2016-01-19 2017-07-25 上海交通大学 A kind of control system of wind turbines hardware in loop simulation and test platform
CN106291363A (en) * 2016-09-26 2017-01-04 武汉承光博德光电科技有限公司 The new forms of energy grid-connected test device of integration
CN206497189U (en) * 2017-02-16 2017-09-15 中核甘肃风力发电有限公司 A kind of high-performance voltage falling generator used for wind power generation
CN107843838A (en) * 2017-10-24 2018-03-27 国网山西省电力公司电力科学研究院 A kind of detection method of low voltage ride-through capability of wind turbine generator system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111555306A (en) * 2020-04-29 2020-08-18 云南电网有限责任公司电力科学研究院 System and method for wind turbine generator set to participate in rapid frequency modulation of regional power grid
CN111555306B (en) * 2020-04-29 2023-09-01 云南电网有限责任公司电力科学研究院 System and method for participating in regional power grid rapid frequency modulation of wind turbine generator system
CN114113870A (en) * 2022-01-28 2022-03-01 西安德纳检验检测有限公司 New energy station power grid adaptability detection method, device and system
CN114113870B (en) * 2022-01-28 2022-04-26 西安德纳检验检测有限公司 New energy station power grid adaptability detection method, device and system

Also Published As

Publication number Publication date
CN109061473B (en) 2020-11-03

Similar Documents

Publication Publication Date Title
CN107544046A (en) A kind of online error measuring system of voltage transformer and method
CN109001573B (en) Method for determining short-circuit capacity of collector bus of wind power plant
CN105182126B (en) Improved distribution transformer energy efficiency metering detection method
CN106772208B (en) Single three-phase meter integrated reliability test board
CN102508055A (en) Device and method for detecting wind power generation grid-connected system
Elvira-Ortiz et al. Methodology for flicker estimation and its correlation to environmental factors in photovoltaic generation
CN109061473A (en) A kind of Wind turbines master control system grid adaptability filed detection system and method
CN102854389A (en) Transformer winding deformation testing device
CN107942192A (en) A kind of controller switching equipment CT automatic test approach and system
CN107703415B (en) Two-level three-phase four-wire system D-STATCOM main loop switching device open circuit fault positioning method
CN106803671B (en) A kind of photovoltaic plant low voltage ride-through capability appraisal procedure
CN208673143U (en) A kind of Wind turbines master control system grid adaptability filed detection system
CN109387804A (en) The soft lineal statistic method of one kind, metering device accuracy checking method and system
Bala et al. Optimal capacitor allocation using a distribution-analyzer-recorder
CN211453813U (en) Novel transformer differential protection calibration device
Constantin et al. Open loop Q (U) stability investigation in case of PV power plants
CN110031678A (en) Water-cooled generator Insulation Resistance Tester
CN113253155B (en) Load testing device and method for autotransformer
CN206209028U (en) A kind of test connection device of on-the-spot test lightning arrester leakance
Quester et al. Frequency behavior of an MMC test bench system
CN115473263A (en) Voltage source characteristic testing device of network-structured type converter and testing and evaluating method thereof
CN208257425U (en) Direct-current micro-grid power supply system
CN215116684U (en) Detection circuit for variable frequency power supply power curve for high-voltage test
Newell et al. Staged field testing of the Victory Hill static VAR control
Wu et al. Noise Characteristics of a Dry-Type Distribution Transformer Tested In a Semi-Anechoic Room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant