CN109056555A - Pre-pressing bracket construction method - Google Patents

Pre-pressing bracket construction method Download PDF

Info

Publication number
CN109056555A
CN109056555A CN201810834305.0A CN201810834305A CN109056555A CN 109056555 A CN109056555 A CN 109056555A CN 201810834305 A CN201810834305 A CN 201810834305A CN 109056555 A CN109056555 A CN 109056555A
Authority
CN
China
Prior art keywords
bracket
ballast
weight
construction method
pressing bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810834305.0A
Other languages
Chinese (zh)
Inventor
汪平
熊卫士
张庆明
刘平
韩立国
王曙光
汪岳健
李慧英
周波
朱可
万飞
冉鹏
武创刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd
Chongqing Construction Engineering Group Co Ltd
Original Assignee
CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd, Chongqing Construction Engineering Group Co Ltd filed Critical CHONGQING TRAFFIC BUILDING (GROUP) Co Ltd
Priority to CN201810834305.0A priority Critical patent/CN109056555A/en
Publication of CN109056555A publication Critical patent/CN109056555A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Mechanical Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses pre-pressing bracket construction methods, comprising: production ballast bag, the arrangement of measuring point, ballast unload weight, bracket adjustment.Pre-pressing bracket construction method in the present invention, by designing reasonable process, the construction efficiency of pre-pressing bracket can be improved, surcharge preloading real-time monitoring is carried out to bracket, it is accurate to calculate bracket absolute altitude, the influence for eliminating ground, bracket itself inelastic deformation is conducive to soffit alignment control, guarantees construction safety, improves Cast-in-situ Beam quality.

Description

Pre-pressing bracket construction method
Technical field
The present invention relates to construction equipment or other building auxiliary equipment technical fields more particularly to pre-pressing bracket construction parties Method.
Background technique
In building construction, highway and railroad bridge and civic building engineering, the appurtenant work of many main bodys all uses bracket Method construction, pre-pressing bracket is an important link in rack construction.How rationally, efficient, safety simulation concrete structure, Installation quality and integrated carrying ability to checking bracket are of great significance.
Summary of the invention
In the prior art for solution, the skill the defects of step reasonability, high efficiency, safety of the presence of pre-pressing bracket method Art problem, technical scheme is as follows:
Pre-pressing bracket construction method in the present invention, comprising the following steps:
Step S101 makes ballast bag, using braided bag special sand loading;
Step S102, the arrangement of measuring point after installing bed die on bracket, lay observation point, record in bed die lower surface Measure the original absolute altitude of observation point;
Step S103, ballast, lifting cooperation are first pressed against at nearly support manually in bed die upper surface pile ballast bag, then according to Secondary to arrange to the position far from support, stacking sequence, first layer stacks next layer after stacking again, and three-level ballast, which is followed successively by, to be set 75%, 100%, the 120% of beam load weight is counted, after the completion of every grade of load, first stops next stage load, and at interval of 12h pairs Bracket settling amount is once monitored, and when the settling amount average value of monitoring point 12h is less than 2mm, then carries out next stage load;
Step S104 unloads weight, first unloads weight according to ballast after ballast sequence, the sequence that weight is unloaded after first ballast is unloaded It carries, and unloading weight process, time interval according to ballast is inversely to carry out, and is measured simultaneously after ballast bag is all unsnatched to observation point Perform record;
Step S105, bracket adjustment calculate deformation of timbering according to the measurement data recorded in step S103, step S104 Value determines and adjusts bracket absolute altitude in conjunction with designed elevation.
Further, in step S102, the position of monitoring point is located at 1/2 among bed die, is often all provided at 3 points across longitudinal, Each 1, span centre 1 at support.
Further, further comprising the steps of in step S104:
From third level ballast after 3 days, pre-pressing bracket, which meets one of following requirements, can carry out unloading weight:
First is that each measuring point settling amount average value is less than 1mm;
Second is that continuous measuring point settling amount average value each three times is accumulative to be less than 5mm.
Further, further comprising the steps of in the step S104: disposably to be unloaded when unloading weight, and in bracket two sides pair Claim, is balanced, synchronous unloading.
Pre-pressing bracket construction method in the present invention, compared with prior art, it has the advantage that:
The construction effect of pre-pressing bracket can be improved by designing reasonable process in pre-pressing bracket construction method in the present invention Rate carries out surcharge preloading real-time monitoring to bracket, accurate to calculate bracket absolute altitude, eliminates ground, bracket itself inelastic deformation It influences, is conducive to soffit alignment control, guarantee construction safety, improve Cast-in-situ Beam quality.
Detailed description of the invention
Fig. 1 is the flow diagram of pre-pressing bracket construction method in the present invention;
Fig. 2 is the schematic diagram of ballast sequence of the present invention.
Specific embodiment
Below in conjunction with attached drawing of the invention, technical solution of the present invention is clearly and completely described.Based on this hair Embodiment in bright, every other implementation obtained by those of ordinary skill in the art without making creative efforts Example, shall fall within the protection scope of the present invention.
As shown in Figure 1, the pre-pressing bracket construction method in the present invention, comprising the following steps:
Step S101 makes ballast bag, using braided bag special sand loading;
Step S102, the arrangement of measuring point after installing bed die on bracket, lay observation point, record in bed die lower surface Measure the original absolute altitude of observation point;
Step S103, ballast, lifting cooperation is manually in bed die upper surface pile ballast bag, as shown in Fig. 2, being first pressed against nearly branch It at seat, then is successively arranged to the position far from support, stacking sequence, first layer stacks next layer, three-level pressure after stacking again It is followed successively by 75%, 100%, the 120% of design beam load weight, after the completion of every grade of load again, first stops next stage load, and every Interval 12h once monitors bracket settling amount, when the settling amount average value of monitoring point 12h is less than 2mm, then carries out next Grade load;
Step S104 unloads weight, first unloads weight according to ballast after ballast sequence, the sequence that weight is unloaded after first ballast is unloaded It carries, and unloading weight process, time interval according to ballast is inversely to carry out, and is measured simultaneously after ballast bag is all unsnatched to observation point Perform record;
Step S105, bracket adjustment calculate deformation of timbering according to the measurement data recorded in step S103, step S104 Value determines and adjusts bracket absolute altitude in conjunction with designed elevation.It is determined according to the deformation of timbering value surveyed above in conjunction with designed elevation With adjustment bottom elevation: beam bottom mould absolute altitude=design bottom elevation+rack elasticity deformation values.According to showing that data adjust in time The absolute altitude of beam bottom bracket, template has reached design requirement absolute altitude.
Further, in step S102, the position of monitoring point is located at 1/2 among bed die, is often all provided at 3 points across longitudinal, Each 1, span centre 1 at support.
Further, further comprising the steps of in step S104:
From third level ballast after 3 days, pre-pressing bracket, which meets one of following requirements, can carry out unloading weight:
First is that each measuring point settling amount average value is less than 1mm;
Second is that continuous measuring point settling amount average value each three times is accumulative to be less than 5mm.
Further, further comprising the steps of in the step S104: disposably to be unloaded when unloading weight, and in bracket two sides pair Claim, is balanced, synchronous unloading.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (4)

1. pre-pressing bracket construction method, which comprises the following steps:
Step S101 makes ballast bag, using braided bag special sand loading;
Step S102, the arrangement of measuring point after installing bed die on bracket, lay observation point, record measurement in bed die lower surface The original absolute altitude of observation point;
Step S103, ballast, lifting cooperation manually in bed die upper surface pile ballast bag, be first pressed against at nearly support, then successively to Position far from support arranges, and stacking sequence, first layer stacks next layer after stacking again, and three-level ballast is followed successively by design beam 75%, 100%, the 120% of load weight after the completion of every grade of load, first stops next stage load, and at interval of 12h to bracket Settling amount is once monitored, and when the settling amount average value of monitoring point 12h is less than 2mm, then carries out next stage load;
Step S104 unloads weight, first unloads weight according to ballast after ballast sequence, and the sequence that weight is unloaded after first ballast is unloaded, and It is inversely to carry out that weight process, time interval, which are unloaded, according to ballast, and observation point is measured and performed after ballast bag is all unsnatched Record;
Step S105, bracket adjustment calculate deformation of timbering value, really according to the measurement data recorded in step S103, step S104 Fixed and adjustment bracket absolute altitude.
2. pre-pressing bracket construction method according to claim 1, which is characterized in that in step S102, the position of monitoring point It is located at 1/2 among bed die, is often all provided at 3 points across longitudinal, each 1, span centre 1 at support.
3. pre-pressing bracket construction method according to claim 1, which is characterized in that further include following step in step S104 It is rapid:
From third level ballast after 3 days, pre-pressing bracket, which meets one of following requirements, can carry out unloading weight:
First is that each measuring point settling amount average value is less than 1mm;
Second is that continuous measuring point settling amount average value each three times is accumulative to be less than 5mm.
4. pre-pressing bracket construction method according to claim 1, which is characterized in that further include following in the step S104 Step: disposably unloading when unloading weight, and in symmetrical, balanced, the synchronous unloading in bracket two sides.
CN201810834305.0A 2018-07-26 2018-07-26 Pre-pressing bracket construction method Pending CN109056555A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810834305.0A CN109056555A (en) 2018-07-26 2018-07-26 Pre-pressing bracket construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810834305.0A CN109056555A (en) 2018-07-26 2018-07-26 Pre-pressing bracket construction method

Publications (1)

Publication Number Publication Date
CN109056555A true CN109056555A (en) 2018-12-21

Family

ID=64836553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810834305.0A Pending CN109056555A (en) 2018-07-26 2018-07-26 Pre-pressing bracket construction method

Country Status (1)

Country Link
CN (1) CN109056555A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576235A (en) * 2020-05-30 2020-08-25 河南省第一建筑工程集团有限责任公司 BIM-based No. 0 block longitudinal prestressed pipeline positioning construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090126957A (en) * 2008-06-05 2009-12-09 주식회사 후레씨네코리아 Pre-loading apparatus for upper structure unit of a bridge and bending method of upper structure unit using thereof
CN103590341A (en) * 2013-11-19 2014-02-19 成军 Method for constructing large-span multi-arch solid-web uniform-section circular arc stone-built arch bridge
CN107201827A (en) * 2016-03-16 2017-09-26 中铁十五局集团有限公司 Support pre-pressing construction method based on settlement observation
CN107905109A (en) * 2017-11-21 2018-04-13 重庆建工市政交通工程有限责任公司 The loads such as the cast-in-place platform simulation of great-leap-forward bridge are segmented precompressed construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090126957A (en) * 2008-06-05 2009-12-09 주식회사 후레씨네코리아 Pre-loading apparatus for upper structure unit of a bridge and bending method of upper structure unit using thereof
CN103590341A (en) * 2013-11-19 2014-02-19 成军 Method for constructing large-span multi-arch solid-web uniform-section circular arc stone-built arch bridge
CN107201827A (en) * 2016-03-16 2017-09-26 中铁十五局集团有限公司 Support pre-pressing construction method based on settlement observation
CN107905109A (en) * 2017-11-21 2018-04-13 重庆建工市政交通工程有限责任公司 The loads such as the cast-in-place platform simulation of great-leap-forward bridge are segmented precompressed construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
LSHA506: "满堂支架的预压方案", 《百度文库》 *
四川省公路学会工程施工专业委员会编辑委员: "《桥梁、隧道、道路、水港 2016年学术交流会论文集》", 30 June 2016 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576235A (en) * 2020-05-30 2020-08-25 河南省第一建筑工程集团有限责任公司 BIM-based No. 0 block longitudinal prestressed pipeline positioning construction method

Similar Documents

Publication Publication Date Title
CN105369738B (en) Prepressing method of flushing type bridge rubber raft
CN103437291B (en) Monolithic water tank precompressed construction technology
CN103669114B (en) Ballast bed base prefabricated slab and application thereof
CN102477717B (en) A kind of bridge pushing construction method
CN110777669A (en) High-speed rail continuous beam short line matching prefabricated cantilever assembly line shape control method
CN204298825U (en) Foundation ditch builds elephant trunk supporting and regulating device
CN102322071A (en) Universal base structure of main transformer of 220kV substation
CN107245951A (en) Across bilateral while closure construction method in cable-stayed bridge
Gräbe et al. The effects of under-sleeper pads on sleeper-ballast interaction
CN111337175B (en) Full-section pouring monitoring system and monitoring method
CN103669228B (en) Self-propelled moveable formwork camber method of adjustment
CN107336346A (en) A kind of beam making bench
CN109056555A (en) Pre-pressing bracket construction method
CN103572774B (en) Leveling ruler plain cushion panel seat slurry processes
CN113268094A (en) Bridge prestress tension construction monitoring cloud management device and method
CN212294351U (en) Water bag pre-pressing construction equipment for viaduct cast-in-place beam support system
CN101435181B (en) Concrete double-case subsection beam construction method
CN202164623U (en) Universal foundation structure of 220 kV transformer substation main transformer
Lan et al. Research on the suspender replacement process of arch bridge based on the measured displacement correction
CN202809400U (en) Precast slab for ballast bed base
CN115130177A (en) Ballastless track stress analysis method based on concrete shrinkage and creep model
CN206982971U (en) A kind of beam making bench
CN212375727U (en) System for regulating and controlling positions of truss nodes of steel-concrete composite truss bridge
CN108385454A (en) A kind of railway plate-type ballastless track working drawing review operational method
CN108385542A (en) A kind of fine linear quadratic control construction method of bridge linear

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221

RJ01 Rejection of invention patent application after publication