CN109056504A - A kind of bridge precast beam low hydration heat is prefabricated to use internal lining pipe and its method for prefabricating - Google Patents

A kind of bridge precast beam low hydration heat is prefabricated to use internal lining pipe and its method for prefabricating Download PDF

Info

Publication number
CN109056504A
CN109056504A CN201811074836.0A CN201811074836A CN109056504A CN 109056504 A CN109056504 A CN 109056504A CN 201811074836 A CN201811074836 A CN 201811074836A CN 109056504 A CN109056504 A CN 109056504A
Authority
CN
China
Prior art keywords
prefabricated
internal lining
lining pipe
inner sleeve
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811074836.0A
Other languages
Chinese (zh)
Other versions
CN109056504B (en
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou New Nanhu Technology Co Ltd
Original Assignee
Xuzhou New Nanhu Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou New Nanhu Technology Co Ltd filed Critical Xuzhou New Nanhu Technology Co Ltd
Priority to CN201811074836.0A priority Critical patent/CN109056504B/en
Publication of CN109056504A publication Critical patent/CN109056504A/en
Application granted granted Critical
Publication of CN109056504B publication Critical patent/CN109056504B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • B28B11/246Underwater curing
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of bridge precast beam low hydration heat of the present invention is prefabricated to disclose one kind by that will pour scope control in a certain range with internal lining pipe and its method for prefabricating, the heat of hydration is balanced, and by repeatedly pouring, weakens the prefabricated of the thermogenetic stress of whole aquation and use internal lining pipe and its method for prefabricating.It will not leave behind hole, integral strength is unaffected.It is characterized in that being provided with multiple spiral laminations on the outside of the outer tube, and the spiral lamination of same row is one group, inner sleeve is placed in outer tube, the inner sleeve and outer tube are homocentric, the inner sleeve pipe diameter is the half of housing pipe diameter, prefabricated chamber is equipped between the inner sleeve pipe outer wall and outer sleeve inner wall, four demarcation plates are angularly placed in prefabricated intracavitary, and prefabricated chamber is divided into equal-sized four parts, the demarcation plate side is connected with inner sleeve pipe outer wall, the other side is connected with outer sleeve inner wall, and the separation plate surface is equipped with link slot.

Description

A kind of bridge precast beam low hydration heat is prefabricated to use internal lining pipe and its method for prefabricating
Technical field
A kind of bridge precast beam low hydration heat of the present invention is prefabricated to use internal lining pipe and its method for prefabricating, is related to a kind of bridge bearing Internal lining pipe and its method for prefabricating when framework is prefabricated, belong to road and bridge construction field.In particular to a kind of by the way that range will be poured Control in a certain range, enables the heat of hydration to be balanced, and by repeatedly pouring, and weakens that whole aquation is thermogenetic to answer The prefabricated of power uses internal lining pipe and its method for prefabricating.
Background technique
Currently, in order to shorten the period, a large amount of load-bearing framework is all that synchronous progress is prefabricated, so during bridge construction After transport to scene and be combined, shorten the construction period, especially in short Super Engineering of some span large-engineering periods, by It is huge in structure size, it needs to combine by exterior sheathing and reinforcing bar when carrying out prefabricated, then once be poured using concrete Completion is built, but since concrete generates big calorimetric when carrying out hydrated, position biggish for dimensional thickness, inside and outside temperature difference Increase, is easy cracking, it is therefore desirable to constantly cool down, so that the heat of hydration is quickly spread, but since medium position is difficult to It reaches, therefore there are risks, it is existing to be implanted into steel pipe in concrete, fluid is injected into steel pipe, and hot friendship is carried out by fluid Change so that middle portion temperature declines, but the hole that steel pipe is reserved at middle part so that integral strength declines, and steel pipe and concrete it Between combination, heat transfer it is poor, and section is smaller, the thermal Finite that can take away poor to the support of concrete, cannot be gradually Break up heat of hydration bring stress.
Publication number CN204983667U discloses a kind of built-in type circulating cooling for reducing the mass concrete heat of hydration Pipe, it is characterised in that: the built-in type circulating cooling pipe includes the cooling water pipe being placed in concrete and is placed in outside concrete First connection water pipe, the second connection water pipe, the cooling water pipe are by a plurality of lateral cooling water pipe and a plurality of longitudinal cooling water pipe Composition, a plurality of transverse direction cooling water pipe is distributed parallelly in concrete, and the section of every lateral cooling water pipe is matrix pattern, a plurality of Longitudinal cooling water pipe is distributed between adjacent two lateral cooling water pipelines, and two adjacent transverse cooling water pipes are connected; The water outlet that the water inlet port of cooling water pipe connect water pipe with first connects, and cooling water pipeline water outlet port connect water pipe with second Metal end connection, second connection water pipe water outlet with first connect water pipe water inlet pipe pass through water circulating pump connection, the party Method is taken away the heat of hydration by water body flow, but since size is big, the thermal Finite that tube body can be taken away, the alleviation to the heat of hydration Effect is general, and at the construction field (site), and the installation sealing and flow control of tube body are more complex.
Summary of the invention
In order to improve above situation, a kind of bridge precast beam low hydration heat of the present invention is prefabricated to use internal lining pipe and its method for prefabricating Scope control will be poured in a certain range by providing a kind of pass through, and the heat of hydration is balanced, and by repeatedly pouring, It weakens the prefabricated of the whole thermogenetic stress of aquation and uses internal lining pipe and its method for prefabricating.It will not leave behind hole, integral strength is not It is impacted.
A kind of bridge precast beam low hydration heat of the present invention is prefabricated to be achieved in that a kind of bridge of the present invention is pre- with internal lining pipe Beam low hydration heat processed is prefabricated to be made of with internal lining pipe outer tube, engaging lug, reinforcing bar, inner sleeve, demarcation plate and spiral lamination, described outer Outside of sleeve is provided with multiple spiral laminations, and the spiral lamination of same row is one group, and inner sleeve is placed in outer tube, the inner sleeve and Outer tube is homocentric, and the inner sleeve pipe diameter is the half of housing pipe diameter, sets between the inner sleeve pipe outer wall and outer sleeve inner wall There is a prefabricated chamber, four demarcation plates are angularly placed in prefabricated intracavitary, and prefabricated chamber are divided into equal-sized four parts, the separation Plate side is connected with inner sleeve pipe outer wall, and the other side is connected with outer sleeve inner wall, and the separation plate surface is equipped with link slot, institute Stating link slot is arc groove, and multiple engaging lugs are angularly placed on outer tube lateral wall, the engaging lug and outer tube one at Type.
The invention further relates to a kind of prefabricated method for prefabricating with internal lining pipe of bridge precast beam low hydration heat, including following step It is rapid:
(1) it is fixed one by one by multiple engaging lugs on the external sleeve outer wall of reinforcing bar first, and then internal lining pipe is fixed, so Prefab-form is erected on the outside of internal lining pipe afterwards;
(2) secondly filled the water into internal lining pipe, when prefabricated chamber and inner sleeve in fill water;
(3) then to injecting concrete between template and internal lining pipe;
(4) two opposite in one's duty water of prefabricated chamber are extracted out, then inwardly injects concrete;
(5) water in inner sleeve is extracted out, inwardly injects concrete;
(6) finally the in one's duty water of prefabricated chamber remaining two is gradually extracted out, and is implanted sequentially concrete.
Beneficial effect.
One, the heat of hydration can be made to keep balance, improve cooling effect.
Two, the thermogenetic stress of whole aquation can be weakened.
Three, it will not leave behind hole, integral strength is unaffected.
Detailed description of the invention
Fig. 1 is a kind of prefabricated structural schematic diagram with internal lining pipe of bridge precast beam low hydration heat of the present invention.
Fig. 2 is a kind of prefabricated three-dimensional structure diagram with internal lining pipe of bridge precast beam low hydration heat of the present invention.
In attached drawing
Wherein part are as follows: prefab-form (1), outer tube (2), concrete (3), engaging lug (4), reinforcing bar (5), inner sleeve (6), point Partition (7), spiral lamination (8).
Specific embodiment:
A kind of bridge precast beam low hydration heat of the present invention is prefabricated to be achieved in that a kind of bridge precast beam of the present invention with internal lining pipe Low hydration heat is prefabricated to use internal lining pipe by outer tube (2), engaging lug (4), reinforcing bar (5), inner sleeve (6), demarcation plate (7) and spiral lamination (8) it forms, is provided with multiple spiral laminations (8) on the outside of the outer tube (2), and the spiral lamination (8) of same row is one group, inner sleeve (6) it is placed in outer tube (2), the inner sleeve (6) and outer tube (2) are homocentric, and inner sleeve (6) diameter is outer tube (2) The half of diameter is equipped with prefabricated chamber between inner sleeve (6) outer wall and outer tube (2) inner wall, four demarcation plates (7) are angularly It is placed in prefabricated intracavitary, and prefabricated chamber is divided into equal-sized four parts, demarcation plate (7) side and inner sleeve (6) outer wall It is connected, the other side is connected with outer tube (2) inner wall, and demarcation plate (7) surface is equipped with link slot, and the link slot is arc Shape slot, multiple engaging lugs (4) are angularly placed on outer tube (2) lateral wall, the engaging lug (4) and outer tube (2) one at Type.
The invention further relates to a kind of prefabricated method for prefabricating with internal lining pipe of bridge precast beam low hydration heat, including following step It is rapid:
(1) multiple engaging lugs (4) on outer tube (2) outer wall are fixed one by one by reinforcing bar (5) first, so to internal lining pipe into Row is fixed, and then prefab-form (1) is erected on the outside of internal lining pipe;
(2) secondly filled the water into internal lining pipe, when prefabricated chamber and inner sleeve (6) in fill water;
(3) concrete (3) then are injected between template and internal lining pipe;
(4) two opposite in one's duty water of prefabricated chamber are extracted out, then inwardly injection concrete (3);
(5) water in inner sleeve (6) is extracted out, inwardly injects concrete (3);
(6) finally the in one's duty water of prefabricated chamber remaining two is gradually extracted out, and is implanted sequentially concrete (3).
It is provided with multiple spiral laminations (8) on the outside of the outer tube (2), and the design that the spiral lamination (8) of same row is one group, energy It is enough to enter concrete (3) in spiral lamination (8) when concrete (3) pours, and then increase outer tube (2) and concrete (3) Bonding strength;
Four demarcation plates (7) are angularly placed in prefabricated intracavitary, and prefabricated chamber are divided into equal-sized four parts of design, can To it is prefabricated it is intracavitary repeatedly poured, and then weaken the whole thermogenetic stress of aquation;
Demarcation plate (7) surface is equipped with link slot, and the link slot is the design of arc groove, can increase demarcation plate (7) and The bonded area of concrete (3) improves bonding strength
The engaging lug (4) and outer tube (2) integrally formed design can be improved the prefabricated preceding fixing-stable to internal lining pipe Property;
When pouring, the design to being poured between prefab-form (1) and internal lining pipe in advance can be in advance to internal lining pipe and prefabricated molds Plate (1) carries out pouring connection, pour by several times to internal lining pipe inside convenient for postorder;
When to being poured in internal lining pipe, prefabricated chamber is poured in two times, and inner sleeve (6) among prefabricated chamber two-step pouring into The design that pours of row can cool down to intermediate heat, so that after middle portion temperature decline, then complete whole to pour work Make;
The present invention will not leave hole after the completion of pouring, and then integral strength is unaffected, and by repeatedly pouring, weaken The whole thermogenetic stress of aquation;
Scope control will be poured in a certain range by reaching, and the heat of hydration is balanced, and by repeatedly pouring, be weakened whole The purpose of the thermogenetic stress of the aquation of body.

Claims (7)

1. a kind of bridge precast beam low hydration heat is prefabricated to use internal lining pipe, it is characterized in that: by outer tube, engaging lug, reinforcing bar, inner sleeve Pipe, demarcation plate and spiral lamination composition, the outer tube outside is provided with multiple spiral laminations, and the spiral lamination of same row is one group, interior Casing is placed in outer tube, and prefabricated chamber is equipped between the inner sleeve pipe outer wall and outer sleeve inner wall, and four demarcation plates are angularly set In prefabricated intracavitary, and prefabricated chamber is divided into equal-sized four parts, the demarcation plate side is connected with inner sleeve pipe outer wall, separately Side is connected with outer sleeve inner wall, and multiple engaging lugs are angularly placed on outer tube lateral wall, the engaging lug and outer tube It is integrally formed.
2. a kind of bridge precast beam low hydration heat according to claim 1 is prefabricated to use internal lining pipe, it is characterised in that in described Casing and outer tube are homocentric, and the inner sleeve pipe diameter is the half of housing pipe diameter.
3. a kind of bridge precast beam low hydration heat according to claim 1 is prefabricated to use internal lining pipe, it is characterised in that described point Baffle surface is equipped with link slot.
4. a kind of bridge precast beam low hydration heat according to claim 1 is prefabricated to use internal lining pipe, it is characterised in that the company Access slot is arc groove.
5. a kind of prefabricated method for prefabricating with internal lining pipe of bridge precast beam low hydration heat, it is characterised in that the following steps are included:
(1) it is fixed one by one by multiple engaging lugs on the external sleeve outer wall of reinforcing bar first, and then internal lining pipe is fixed, so Prefab-form is erected on the outside of internal lining pipe afterwards;
(2) secondly filled the water into internal lining pipe, when prefabricated chamber and inner sleeve in fill water;
(3) then to injecting concrete between template and internal lining pipe;
(4) two opposite in one's duty water of prefabricated chamber are extracted out, then inwardly injects concrete;
(5) water in inner sleeve is extracted out, inwardly injects concrete;
(6) finally the in one's duty water of prefabricated chamber remaining two is gradually extracted out, and is implanted sequentially concrete.
6. the prefabricated method for prefabricating with internal lining pipe of a kind of bridge precast beam low hydration heat according to claim 5, feature It when being to pour, pours, internal lining pipe and prefab-form can be poured in advance between prefab-form and internal lining pipe in advance Connection is built, internal lining pipe inside pour by several times convenient for postorder.
7. the prefabricated method for prefabricating with internal lining pipe of a kind of bridge precast beam low hydration heat according to claim 5, feature When being to be poured in the internal lining pipe, prefabricated chamber is poured in two times, and inner sleeve among prefabricated chamber two-step pouring into The design that pours of row can cool down to intermediate heat, so that after middle portion temperature decline, then complete whole to pour work Make.
CN201811074836.0A 2018-09-14 2018-09-14 Lining pipe for low-hydration-heat prefabrication of bridge precast beam and prefabricating method thereof Active CN109056504B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811074836.0A CN109056504B (en) 2018-09-14 2018-09-14 Lining pipe for low-hydration-heat prefabrication of bridge precast beam and prefabricating method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811074836.0A CN109056504B (en) 2018-09-14 2018-09-14 Lining pipe for low-hydration-heat prefabrication of bridge precast beam and prefabricating method thereof

Publications (2)

Publication Number Publication Date
CN109056504A true CN109056504A (en) 2018-12-21
CN109056504B CN109056504B (en) 2020-12-25

Family

ID=64762612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811074836.0A Active CN109056504B (en) 2018-09-14 2018-09-14 Lining pipe for low-hydration-heat prefabrication of bridge precast beam and prefabricating method thereof

Country Status (1)

Country Link
CN (1) CN109056504B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111535157A (en) * 2020-05-11 2020-08-14 中国建筑第七工程局有限公司 High pier capable of reducing hydration heat of mass concrete and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010031285A1 (en) * 2010-07-13 2012-01-19 H.S.W. Ingenieurbüro GmbH Thermo-active earth-contacted concrete component for heating- and cooling extraction or heat- and cooling storage, has concrete body, heat transducer pipes and drain mass provided between concrete body and heat transducer pipes
CN102758534A (en) * 2012-07-30 2012-10-31 中建商品混凝土有限公司 Method for cooling mass concrete
CN205296162U (en) * 2015-12-29 2016-06-08 中国电建集团中南勘测设计研究院有限公司 Condenser tube and applied this condenser tube's layering roller compacted concrete structure
CN206279530U (en) * 2016-12-20 2017-06-27 中国电建集团贵阳勘测设计研究院有限公司 A kind of cooling water pipe optimization device of concrete cooling
CN206801032U (en) * 2017-02-23 2017-12-26 华西能源工程有限公司 A kind of mass concrete cracking-proof system
CN107558504A (en) * 2017-08-16 2018-01-09 中交四航工程研究院有限公司 A kind of construction method for controlling concrete component cracking

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010031285A1 (en) * 2010-07-13 2012-01-19 H.S.W. Ingenieurbüro GmbH Thermo-active earth-contacted concrete component for heating- and cooling extraction or heat- and cooling storage, has concrete body, heat transducer pipes and drain mass provided between concrete body and heat transducer pipes
CN102758534A (en) * 2012-07-30 2012-10-31 中建商品混凝土有限公司 Method for cooling mass concrete
CN205296162U (en) * 2015-12-29 2016-06-08 中国电建集团中南勘测设计研究院有限公司 Condenser tube and applied this condenser tube's layering roller compacted concrete structure
CN206279530U (en) * 2016-12-20 2017-06-27 中国电建集团贵阳勘测设计研究院有限公司 A kind of cooling water pipe optimization device of concrete cooling
CN206801032U (en) * 2017-02-23 2017-12-26 华西能源工程有限公司 A kind of mass concrete cracking-proof system
CN107558504A (en) * 2017-08-16 2018-01-09 中交四航工程研究院有限公司 A kind of construction method for controlling concrete component cracking

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111535157A (en) * 2020-05-11 2020-08-14 中国建筑第七工程局有限公司 High pier capable of reducing hydration heat of mass concrete and construction method thereof
CN111535157B (en) * 2020-05-11 2021-06-01 中国建筑第七工程局有限公司 High pier capable of reducing hydration heat of mass concrete and construction method thereof

Also Published As

Publication number Publication date
CN109056504B (en) 2020-12-25

Similar Documents

Publication Publication Date Title
CN203256730U (en) Prefabricated energy pile device for embedding heat transmission pipe
US10655892B2 (en) Heat transfer pipe embedded in a prefabricated pipe pile and embedding method
CN105544608A (en) Pipe-joint steel shell and concrete combined structure for immersed tunnel and manufacturing method thereof
CN103649666A (en) Thermal energy storage and plant, method and use thereof
CN103485332B (en) A kind of construction method of precast energy pile
CN107626891A (en) A kind of preparation method of diesel engine water oil-piping casting mold and water oil-piping
CN111042112A (en) Novel pipe distribution type drilling and pouring energy pile and construction method thereof
CN109056504A (en) A kind of bridge precast beam low hydration heat is prefabricated to use internal lining pipe and its method for prefabricating
CN104295004A (en) UHPC-CFST combination column structure and construction method thereof
CN103498470B (en) A kind of hexagon precast energy pile and preparation method thereof
CN112878507A (en) Reinforced full grouting sleeve and casting molding method thereof
CN203347203U (en) Multi-functional super-thick bulked concrete steel tube support system
CN109853775B (en) Modularized wall enclosure structure
CN109724277B (en) Geothermal well heat exchange device
CN103438738A (en) Communicating pipe pressure-bearing water-storage type heat exchanger and manufacture process thereof
CN104453236B (en) Circulating water natural cooling system for controlling large-volume concrete cracks and construction method
CN208518216U (en) A kind of grout sleeve
CN106351235A (en) Assembled type four-combined-round-steel-pipe concrete inner support structure and manufacturing method
CN113191043B (en) Hydraulic tunnel lining concrete temperature crack control strong constraint method and temperature control system
CN206052758U (en) The attachment structure of a small-sized clump of piles and cushion cap
CN205224781U (en) Cooling tower pond structure of in cold areas prestressing without bondn structure
CN107740543A (en) A kind of connection of double and muscle full grout sleeve and double and muscle connection method
CN110080466A (en) Grouting sleeve and preparation method and application thereof
CN103557726A (en) Heating multi-pipe heat-conducting shell-tube-type water storage heat exchanger and manufacturing process thereof
CN204849831U (en) Novel well bore preformed block

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 221000 1-501, loftc building, West Greenland Business City, Hanyuan Avenue, Yunlong District, Xuzhou City, Jiangsu Province

Applicant after: XUZHOU XINNANHU TECHNOLOGY Co.,Ltd.

Address before: Block F, Tongchuang new block, science and Technology Park, China University of mining and technology, 221000 Jiefang South Road, Quanshan District, Xuzhou City, Jiangsu Province

Applicant before: XUZHOU XINNANHU TECHNOLOGY Co.,Ltd.

GR01 Patent grant
GR01 Patent grant