CN109034671A - Factory's producing line target product production duration determines method and device - Google Patents
Factory's producing line target product production duration determines method and device Download PDFInfo
- Publication number
- CN109034671A CN109034671A CN201811038545.6A CN201811038545A CN109034671A CN 109034671 A CN109034671 A CN 109034671A CN 201811038545 A CN201811038545 A CN 201811038545A CN 109034671 A CN109034671 A CN 109034671A
- Authority
- CN
- China
- Prior art keywords
- target product
- duration
- production
- destination number
- production process
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 205
- 238000000034 method Methods 0.000 title claims abstract description 156
- 238000003860 storage Methods 0.000 claims description 9
- 238000004590 computer program Methods 0.000 claims description 7
- 238000009434 installation Methods 0.000 claims description 4
- 238000000605 extraction Methods 0.000 claims description 3
- 238000004364 calculation method Methods 0.000 claims 1
- 239000000284 extract Substances 0.000 description 7
- 238000010586 diagram Methods 0.000 description 4
- 238000010923 batch production Methods 0.000 description 1
- FFBHFFJDDLITSX-UHFFFAOYSA-N benzyl N-[2-hydroxy-4-(3-oxomorpholin-4-yl)phenyl]carbamate Chemical compound OC1=C(NC(=O)OCC2=CC=CC=C2)C=CC(=C1)N1CCOCC1=O FFBHFFJDDLITSX-UHFFFAOYSA-N 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000013507 mapping Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0633—Workflow analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/04—Manufacturing
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Primary Health Care (AREA)
- General Health & Medical Sciences (AREA)
- Health & Medical Sciences (AREA)
- Manufacturing & Machinery (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- General Factory Administration (AREA)
Abstract
A kind of factory's producing line target product production duration determines method and device, wherein the method includes obtaining the destination number of target product to be produced;Determine that production procedure, production procedure include at least one of production process that sequence executes according to target product;The process period of each production process at least one of production process is extracted, process period is duration needed for completing production process;The duration for completing the target product of destination number is determined according to the process period of each production process.Scheme compared with the existing technology may not need the production capacity for calculating production producing line, and the duration for directly determining completion target product can be improved duration and determine efficiency in the case where omitting elements;Also, due to being not necessarily to calculate the production capacity of production producing line, it is possible to reduce the step of updating capacity data library, thus, overcome capacity data library to update the duration error for the product order volume that sets the goal really caused by hysteresis quality.
Description
Technical field
The present invention relates to industrial information administrative skill fields, and in particular to a kind of factory's producing line target product production duration
Determine method and device.
Background technique
Factory completes the production of product by different process step combinations, and every procedure has respective operation time.Work
Factory generally requires to pre-establish the production plan within the scope of the following certain time when producing product, in order to resource
Carry out reasonable distribution and collaboration.The scheduled production scheduling of production line is that being met factory of the task is reasonably planned and is arranged into life
It produces.According to the order volume of target product, in material quantity abundance situation, by the production energy for considering producing line productive target product
Power can determine the duration for completing target product order volume.
In general, in order to improve the production capacity of producing line, production producing line would generally constantly Optimized Iterative, produced in production
After line optimization, the production capacity for producing producing line can also change therewith.In the prior art, in order to calculate the duration of target product order volume,
Frequently with scheme are as follows: production producing line Optimized Iterative after, update producing line database then determined according to producing line database excellent
Production producing line unit time production capacity after changing iteration, and is updated in capacity data library, then, can according to capacity data library come
Determine the duration for completing target product order volume.However, capacity data inventory is updated based on producing line database in hysteresis,
Newest capacity data can not be obtained in time, accordingly, it is difficult to accurately determine the duration for completing target product order volume.In addition,
After producing producing line Optimized Iterative, producing line database, capacity data library are successively updated, completion is then determined according to capacity data library
The duration of target order volume, data operation are relatively complicated.
Therefore, capacity data library how to be overcome to update the duration error for the product order volume that sets the goal really caused by hysteresis quality
As technical problem urgently to be resolved.
Summary of the invention
The technical problem to be solved in the present invention is that capacity data library how to be overcome to update determination mesh caused by hysteresis quality
Mark the duration error of product order volume.
For this purpose, according in a first aspect, the embodiment of the invention discloses a kind of factory's producing line target product production durations to determine
Method, comprising:
Obtain the destination number of target product to be produced;Determine that production procedure, production procedure include suitable according to target product
At least one of production process that sequence executes;Extract the process period of each production process at least one of production process, process week
Phase is duration needed for completing production process;The target product for completing destination number is determined according to the process period of each production process
Duration.
Optionally, the duration packet for completing the target product of destination number is determined according to the process period of each production process
It includes: searching bottleneck beat in each production process, bottleneck beat is the longest production work of process period in each production process
The process period of sequence;The duration for completing the target product of destination number is determined according to destination number and bottleneck beat.
Optionally, determine that completing the duration of the target product of destination number includes: to ask according to destination number and bottleneck beat
Take the sum of bottleneck duration and time in advance as determining the duration for completing the target product of destination number, when bottleneck a length of destination number
With the product of bottleneck beat, time in advance is the sum of the process period of each production process in single production procedure.
Optionally, according to the process period of each production process determine complete destination number target product duration it
Afterwards, further includes: obtain the initial time for producing target product to be produced;The target of destination number is completed in superposition on initial time
The duration of product obtains completing the completion moment of the target product of destination number.
According to second aspect, the embodiment of the invention discloses a kind of factory's producing line target products to produce duration determining device,
Include:
Quantity obtains module, for obtaining the destination number of target product to be produced;Process determining module, for according to mesh
Mark product determines that production procedure, production procedure include at least one of production process that sequence executes;Periodicity extraction module, for mentioning
The process period of each production process at least one of production process is taken, process period is duration needed for completing production process;When
Long determining module, for determining the duration for completing the target product of destination number according to the process period of each production process.
Optionally, duration determining module includes: searching unit, for searching bottleneck beat, bottle in each production process
Neck beat is the process period of the longest production process of process period in each production process;Computing unit, for according to target
Quantity and bottleneck beat determine the duration for completing the target product of destination number.
Optionally, computing unit is used to seek the sum of bottleneck duration and time in advance as the target for determining completion destination number
The duration of product, when bottleneck a length of destination number and bottleneck beat product, time in advance is each production work in single production procedure
The sum of process period of sequence.
Optionally, further includes: initial time module, for obtaining the initial time for producing target product to be produced;Terminate
Moment module, the duration for the target product that destination number is completed in superposition on initial time obtain completing the mesh of destination number
Mark the completion moment of product.
According to the third aspect, the embodiment of the invention discloses a kind of computer installation, including processor, processor is for holding
The computer program stored in line storage realizes following method:
Obtain the destination number of target product to be produced;Determine that production procedure, production procedure include suitable according to target product
At least one of production process that sequence executes;Extract the process period of each production process at least one of production process, process week
Phase is duration needed for completing production process;The target product for completing destination number is determined according to the process period of each production process
Duration.
According to fourth aspect, the embodiment of the invention discloses a kind of computer readable storage mediums, are stored thereon with calculating
Machine program executes the computer program stored in storage medium and is performed the following method of realization:
Obtain the destination number of target product to be produced;Determine that production procedure, production procedure include suitable according to target product
At least one of production process that sequence executes;Extract the process period of each production process at least one of production process, process week
Phase is duration needed for completing production process;The target product for completing destination number is determined according to the process period of each production process
Duration.
Technical solution of the present invention has the advantages that
Factory's producing line target product production duration provided in an embodiment of the present invention determines method and device, to be produced determining
After the production procedure of target product, the process period of each production process at least one of production process, the process period are extracted
The target for completing destination number is then determined according to the process period of each production process for duration needed for completion production process
The duration of product.The scheme of the embodiment of the present invention determines the target for completing destination number by the process period of each production process
The duration of product, scheme compared with the existing technology may not need the production capacity for calculating production producing line, directly determine and complete target production
The duration of product can be improved duration and determine efficiency in the case where omitting elements;Also, due to without calculating production producing line
Production capacity, therefore, it is possible to reduce the step of updating capacity data library, thus, overcome capacity data library to update caused by hysteresis quality
Determine the duration error of target product order volume.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art
Embodiment or attached drawing needed to be used in the description of the prior art be briefly described, it should be apparent that, it is described below
Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor
It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is that a kind of factory's producing line target product production duration disclosed by the embodiments of the present invention determines method flow diagram;
Fig. 2 is the production procedure schematic diagram that exemplary description of the embodiment of the present invention produces certain target product;
Fig. 3 is that a kind of factory's producing line target product disclosed by the embodiments of the present invention produces the structural representation of duration determining device
Figure.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation
Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill
Personnel's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical",
The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to
Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation,
It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ",
" third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase
Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can
To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also indirectly connected through an intermediary, it can be with
It is the connection inside two elements, can be wireless connection, be also possible to wired connection.For those of ordinary skill in the art
For, the concrete meaning of above-mentioned term in the present invention can be understood with concrete condition.
As long as in addition, the non-structure each other of technical characteristic involved in invention described below different embodiments
It can be combined with each other at conflict.
In order to overcome capacity data library to update the duration error for the product order volume that sets the goal really caused by hysteresis quality, this reality
It applies example and discloses a kind of factory's producing line target product production duration and determine method, referring to FIG. 1, for one kind disclosed in the present embodiment
Factory's producing line target product production duration determines method flow diagram, and factory's producing line target product production duration determines method packet
It includes:
Step S100 obtains the destination number of target product to be produced.In general, manufacturer is receiving client's
The quantity of target product to be produced is generally comprised after order, in order information, it is possible thereby to obtain the mesh of target product to be produced
Mark quantity.In a particular embodiment, the mesh of target product to be produced can be obtained in such a way that external input equipment inputs
Quantity is marked, the destination number of target product to be produced can also be obtained in memory by way of data reading.
Step S200 determines production procedure according to target product.In the present embodiment, alleged production procedure includes that sequence executes
At least one of production process.In a particular embodiment, for different products, generally there is different production procedures, production
Production procedure on line is made of the different production process of multiple tracks.The mapping that target product and production procedure can be pre-established is closed
System, and storing in the preset database, referring to FIG. 2, illustrate to produce the production procedure of certain target product, the production procedure by
The production process 1 of sequence execution, production process 2, production process 3 ... production process n composition.Determining target product to be produced
Afterwards, corresponding production procedure can be extracted in the preset database according to target product, thus, it is determined that it is raw sequentially to execute each road
Produce process.
Step S300 extracts the process period of each production process at least one of production process.It is alleged in the present embodiment
The process period of production process is duration needed for completing the production process.In general, process week between different production processes
Phase is different, in the present embodiment, after determining the production procedure of target product, can extract each production process in production procedure
Process period.It should be noted that the chronomere in each process period should be consistent in the present embodiment, for example, can for the second,
Point, hour etc..
Step S400 determines the duration for completing the target product of destination number according to the process period of each production process.
In a particular embodiment, it when executing step S400, is determined according to the process period of each production process and completes destination number
The duration of target product may include: the lookup bottleneck beat in each production process, and bottleneck beat is in each production process
The process period of the longest production process of process period;The target for completing destination number is determined according to destination number and bottleneck beat
The duration of product.Specifically, it since the process period of each production process is different, can find in each production process
The longest production process of process period, using the process period of the production process as bottleneck beat, then, according to destination number and
Bottleneck beat determines the duration for completing the target product of destination number.
In the present embodiment, when determining the duration for completing the target product of destination number, bottleneck duration can be sought and mentioned
The sum of early period completes the duration of the target product of destination number as determining, wherein a length of destination number and bottleneck section when bottleneck
The product of bat, time in advance are the sum of the process period of each production process in single production procedure.In batch production target product mistake
Cheng Zhong, when each process in production procedure is in running order, it is however generally that, one is produced at interval of a bottleneck beat
A target product, therefore, when bottleneck a length of destination number and bottleneck beat product;And initial workpiece target product need to cover production stream
Journey, therefore, time in advance are the sum of the process period of each production process in single production procedure, so, when can seek bottleneck
The sum of long and time in advance completes the duration of the target product of destination number as determining.
In an alternate embodiment of the invention, after executing step S400, further includes: obtain and produce rising for target product to be produced
Begin the moment;The duration that the target product of destination number is completed in superposition on initial time obtains completing the target product of destination number
The completion moment.During factory's producing line scheduling, after the initial time for determining starting productive target product, target will be completed
The duration of the target product of quantity, which is superimposed to initial time, can be obtained the completion moment for completing the target product of destination number.
The present embodiment also discloses a kind of factory's producing line target product production duration determining device, referring to FIG. 3, being this reality
It is raw to apply a kind of factory's producing line target product production duration determining device structural schematic diagram, factory's producing line target product disclosed in example
Producing duration determining device includes:
Quantity obtains the destination number that module 100 is used to obtain target product to be produced;Process determining module 200 is used for root
Determine that production procedure, production procedure include at least one of production process that sequence executes according to target product;Periodicity extraction module 300
For extracting the process period of each production process at least one of production process, process period is taken to complete production process
It is long;Duration determining module 400 is used to determine the target product for completing destination number according to the process period of each production process
Duration.
In an alternate embodiment of the invention, duration determining module includes: searching unit, for searching bottle in each production process
Neck beat, bottleneck beat are the process period of the longest production process of process period in each production process;Computing unit is used for
The duration for completing the target product of destination number is determined according to destination number and bottleneck beat.
In an alternate embodiment of the invention, computing unit completes target for seeking the sum of bottleneck duration and time in advance as determining
The duration of the target product of quantity, when bottleneck a length of destination number and bottleneck beat product, time in advance is in single production procedure
The sum of the process period of each production process.
In an alternate embodiment of the invention, further includes: initial time module, for obtaining the starting for producing target product to be produced
Moment;Finish time module, the duration for the target product that destination number is completed in superposition on initial time obtain completing mesh
Mark the completion moment of the target product of quantity.
In addition, the present embodiment also discloses a kind of computer installation, including processor, processor is for executing in memory
The computer program of storage realizes following method:
Obtain the destination number of target product to be produced;Determine that production procedure, production procedure include suitable according to target product
At least one of production process that sequence executes;Extract the process period of each production process at least one of production process, process week
Phase is duration needed for completing production process;The target product for completing destination number is determined according to the process period of each production process
Duration.
In an alternate embodiment of the invention, the target product for completing destination number is determined according to the process period of each production process
Duration include: in each production process lookup bottleneck beat, bottleneck beat be each production process in process period longest
Production process process period;The duration for completing the target product of destination number is determined according to destination number and bottleneck beat.
In an alternate embodiment of the invention, determined according to destination number and bottleneck beat the target product for completing destination number when
Length includes: the duration for seeking the sum of bottleneck duration and time in advance as the target product for determining completion destination number, bottleneck duration
For the product of destination number and bottleneck beat, time in advance is the sum of the process period of each production process in single production procedure.
In an alternate embodiment of the invention, determining that the target for completing destination number is produced according to the process period of each production process
After the duration of product, further includes: obtain the initial time for producing target product to be produced;Target is completed in superposition on initial time
The duration of the target product of quantity obtains completing the completion moment of the target product of destination number.
It is that can lead to it will be understood by those skilled in the art that realizing all or part of the process in above-described embodiment method
Computer program is crossed to instruct relevant hardware and complete, the program can be stored in a computer-readable storage medium
In, the program is when being executed, it may include such as the process of the embodiment of above-mentioned each method.Wherein, the storage medium can be magnetic
Dish, CD, read-only memory (ROM) or random access memory (RAM) etc..Computer processor is situated between for executing storage
The computer program stored in matter realizes following methods:
Obtain the destination number of target product to be produced;Determine that production procedure, production procedure include suitable according to target product
At least one of production process that sequence executes;Extract the process period of each production process at least one of production process, process week
Phase is duration needed for completing production process;The target product for completing destination number is determined according to the process period of each production process
Duration.
In an alternate embodiment of the invention, the target product for completing destination number is determined according to the process period of each production process
Duration include: in each production process lookup bottleneck beat, bottleneck beat be each production process in process period longest
Production process process period;The duration for completing the target product of destination number is determined according to destination number and bottleneck beat.
In an alternate embodiment of the invention, determined according to destination number and bottleneck beat the target product for completing destination number when
Length includes: the duration for seeking the sum of bottleneck duration and time in advance as the target product for determining completion destination number, bottleneck duration
For the product of destination number and bottleneck beat, time in advance is the sum of the process period of each production process in single production procedure.
In an alternate embodiment of the invention, determining that the target for completing destination number is produced according to the process period of each production process
After the duration of product, further includes: obtain the initial time for producing target product to be produced;Target is completed in superposition on initial time
The duration of the target product of quantity obtains completing the completion moment of the target product of destination number.
The production of factory's producing line target product disclosed in the present embodiment duration determines method and device, is determining target to be produced
After the production procedure of product, the process period of each production process at least one of production process is extracted, which has been
At duration needed for production process, then, the target product for completing destination number is determined according to the process period of each production process
Duration.The scheme of the embodiment of the present invention determines the target product for completing destination number by the process period of each production process
Duration, scheme compared with the existing technology may not need the production capacity for calculating production producing line, directly determines and complete target product
Duration can be improved duration and determine efficiency in the case where omitting elements;Also, due to being not necessarily to calculate the production capacity of production producing line,
Therefore, it is possible to reduce the step of updating capacity data library, thus, overcome capacity data library to update determination mesh caused by hysteresis quality
Mark the duration error of product order volume.
Obviously, the above embodiments are merely examples for clarifying the description, and does not limit the embodiments.It is right
For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of variation or
It changes.There is no necessity and possibility to exhaust all the enbodiments.And it is extended from this it is obvious variation or
It changes still within the protection scope of the invention.
Claims (10)
1. a kind of factory's producing line target product production duration determines method characterized by comprising
Obtain the destination number of target product to be produced;
Determine that production procedure, the production procedure include at least one of production process that sequence executes according to the target product;
The process period of each production process at least one of production process is extracted, the process period is to complete production work
Duration needed for sequence;
The duration for completing the target product of the destination number is determined according to the process period of each production process.
2. factory's producing line target product production duration as described in claim 1 determines method, which is characterized in that described according to institute
The process period for stating each production process determines that the duration for completing the target product of the destination number includes:
Bottleneck beat is searched in each production process, the bottleneck beat is the longest life of process period in each production process
Produce the process period of process;
The duration for completing the target product of the destination number is determined according to the destination number and the bottleneck beat.
3. factory's producing line target product production duration as claimed in claim 2 determines method, which is characterized in that described according to institute
It states destination number and the bottleneck beat determines that completing the duration of the target product of the destination number includes: to seek bottleneck duration
With the sum of time in advance as determining the duration for completing the target product of the destination number, when bottleneck a length of number of targets
The product of amount and the bottleneck beat, the time in advance are the sum of the process period of each production process in single production procedure.
4. factory's producing line target product production duration as claimed in any one of claims 1-3 determines method, which is characterized in that
After the duration of the target product for determining the completion destination number according to the process period of each production process,
Further include:
Obtain the initial time for producing target product to be produced;
The duration that the target product for completing the destination number is superimposed on the initial time obtains completing the target
The completion moment of the target product of quantity.
5. a kind of factory's producing line target product produces duration determining device characterized by comprising
Quantity obtains module, for obtaining the destination number of target product to be produced;
Process determining module, for determining that production procedure, the production procedure include what sequence executed according to the target product
At least one of production process;
Periodicity extraction module, for extracting the process period of each production process at least one of production process, the work
The sequence period is duration needed for completing production process;
Duration determining module, for determining the target for completing the destination number according to the process period of each production process
The duration of product.
6. factory's producing line target product as claimed in claim 5 produces duration determining device, which is characterized in that the duration is true
Cover half block includes:
Searching unit, for searching bottleneck beat in each production process, the bottleneck beat is work in each production process
The process period of sequence period longest production process;
Computing unit, for determining the target product for completing the destination number according to the destination number and the bottleneck beat
Duration.
7. factory's producing line target product as claimed in claim 6 produces duration determining device, which is characterized in that the calculating is single
Member is for seeking the duration of the sum of bottleneck duration and time in advance as the target product for determining the completion destination number, the bottle
The product of a length of destination number and bottleneck beat when neck, the time in advance are each production process in single production procedure
The sum of process period.
8. factory's producing line target product as described in claim 5-7 any one produces duration determining device, which is characterized in that
Further include:
Initial time module, for obtaining the initial time for producing target product to be produced;
Finish time module, for being superimposed the duration of the target product for completing the destination number on the initial time
Obtain completing the completion moment of the target product of the destination number.
9. a kind of computer installation, which is characterized in that including processor, the processor is based on executing and storing in memory
Calculation machine program realizes the method such as claim 1-4 any one.
10. a kind of computer readable storage medium, is stored thereon with computer program, which is characterized in that stored in storage medium
Computer program be performed the method as described in claim 1-4 any one of realization.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811038545.6A CN109034671A (en) | 2018-09-06 | 2018-09-06 | Factory's producing line target product production duration determines method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811038545.6A CN109034671A (en) | 2018-09-06 | 2018-09-06 | Factory's producing line target product production duration determines method and device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109034671A true CN109034671A (en) | 2018-12-18 |
Family
ID=64623790
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811038545.6A Pending CN109034671A (en) | 2018-09-06 | 2018-09-06 | Factory's producing line target product production duration determines method and device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109034671A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109670717A (en) * | 2018-12-25 | 2019-04-23 | 深圳百胜扬工业电子商务平台发展有限公司 | The scheduling method and device of target product |
CN109685619A (en) * | 2018-12-25 | 2019-04-26 | 深圳百胜扬工业电子商务平台发展有限公司 | Reservation formula product trading data processing method, apparatus and system |
CN110154025A (en) * | 2019-05-24 | 2019-08-23 | 深圳百胜扬工业电子商务平台发展有限公司 | Verify the whether reasonable method and apparatus of the process step combinations based on manipulator operation |
CN110376977A (en) * | 2019-06-05 | 2019-10-25 | 广州明珞汽车装备有限公司 | A kind of calculation method of cycle period, system, device and storage medium |
CN111142482A (en) * | 2019-12-10 | 2020-05-12 | 深圳市铭华航电工艺技术有限公司 | Production resource management method, device, equipment and readable medium |
CN111369132A (en) * | 2020-03-02 | 2020-07-03 | 深圳百胜扬工业电子商务平台发展有限公司 | Manipulator operation process processing method and device based on non-traditional VSM |
CN111427323A (en) * | 2020-04-22 | 2020-07-17 | Oppo(重庆)智能科技有限公司 | Capacity bottleneck monitoring method, device, equipment and storage medium |
CN112180851A (en) * | 2020-09-03 | 2021-01-05 | 日立楼宇技术(广州)有限公司 | Method and device for controlling production line, computer equipment and storage medium |
CN112817319A (en) * | 2021-01-08 | 2021-05-18 | 刘连英 | AGV dispatching method and system and computer readable storage medium |
TWI823328B (en) * | 2021-09-09 | 2023-11-21 | 日商歐姆龍股份有限公司 | Management device and management method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105045236A (en) * | 2015-07-21 | 2015-11-11 | 江苏云道信息技术有限公司 | Assembly line production scheduling method and system |
CN106327084A (en) * | 2016-08-26 | 2017-01-11 | 广东坚美铝型材厂(集团)有限公司 | Aluminum section product order completion time calculation system and method |
CN106447189A (en) * | 2016-09-26 | 2017-02-22 | 李昌材 | Method and system for calculating working hours in production scheduling |
CN107784445A (en) * | 2017-10-31 | 2018-03-09 | 福建摩尔软件有限公司 | A kind of statistical method of man-hour loss |
CN107797530A (en) * | 2016-09-05 | 2018-03-13 | 发那科株式会社 | Numerical control device, control system, control method and control program |
-
2018
- 2018-09-06 CN CN201811038545.6A patent/CN109034671A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105045236A (en) * | 2015-07-21 | 2015-11-11 | 江苏云道信息技术有限公司 | Assembly line production scheduling method and system |
CN106327084A (en) * | 2016-08-26 | 2017-01-11 | 广东坚美铝型材厂(集团)有限公司 | Aluminum section product order completion time calculation system and method |
CN107797530A (en) * | 2016-09-05 | 2018-03-13 | 发那科株式会社 | Numerical control device, control system, control method and control program |
CN106447189A (en) * | 2016-09-26 | 2017-02-22 | 李昌材 | Method and system for calculating working hours in production scheduling |
CN107784445A (en) * | 2017-10-31 | 2018-03-09 | 福建摩尔软件有限公司 | A kind of statistical method of man-hour loss |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109685619A (en) * | 2018-12-25 | 2019-04-26 | 深圳百胜扬工业电子商务平台发展有限公司 | Reservation formula product trading data processing method, apparatus and system |
CN109670717A (en) * | 2018-12-25 | 2019-04-23 | 深圳百胜扬工业电子商务平台发展有限公司 | The scheduling method and device of target product |
CN110154025B (en) * | 2019-05-24 | 2022-02-18 | 深圳百胜扬工业电子商务平台发展有限公司 | Method and device for verifying whether process combination based on manipulator operation is reasonable |
CN110154025A (en) * | 2019-05-24 | 2019-08-23 | 深圳百胜扬工业电子商务平台发展有限公司 | Verify the whether reasonable method and apparatus of the process step combinations based on manipulator operation |
CN110376977A (en) * | 2019-06-05 | 2019-10-25 | 广州明珞汽车装备有限公司 | A kind of calculation method of cycle period, system, device and storage medium |
CN110376977B (en) * | 2019-06-05 | 2020-10-27 | 广州明珞汽车装备有限公司 | Method, system, device and storage medium for calculating cycle period |
CN111142482A (en) * | 2019-12-10 | 2020-05-12 | 深圳市铭华航电工艺技术有限公司 | Production resource management method, device, equipment and readable medium |
CN111369132A (en) * | 2020-03-02 | 2020-07-03 | 深圳百胜扬工业电子商务平台发展有限公司 | Manipulator operation process processing method and device based on non-traditional VSM |
CN111427323A (en) * | 2020-04-22 | 2020-07-17 | Oppo(重庆)智能科技有限公司 | Capacity bottleneck monitoring method, device, equipment and storage medium |
CN111427323B (en) * | 2020-04-22 | 2021-09-24 | Oppo(重庆)智能科技有限公司 | Capacity bottleneck monitoring method, device, equipment and storage medium |
CN112180851A (en) * | 2020-09-03 | 2021-01-05 | 日立楼宇技术(广州)有限公司 | Method and device for controlling production line, computer equipment and storage medium |
CN112180851B (en) * | 2020-09-03 | 2022-03-08 | 日立楼宇技术(广州)有限公司 | Method and device for controlling production line, computer equipment and storage medium |
CN112817319A (en) * | 2021-01-08 | 2021-05-18 | 刘连英 | AGV dispatching method and system and computer readable storage medium |
TWI823328B (en) * | 2021-09-09 | 2023-11-21 | 日商歐姆龍股份有限公司 | Management device and management method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109034671A (en) | Factory's producing line target product production duration determines method and device | |
CN109670717A (en) | The scheduling method and device of target product | |
CN103577474B (en) | The update method and system of a kind of database | |
CN107590603B (en) | Based on the dispatching method and system for improving change neighborhood search and differential evolution algorithm | |
CN102902573B (en) | Task processing method and device based on shared resources | |
CN105095484B (en) | A kind of data zipper method | |
CN105069524B (en) | Planned dispatching optimization method based on big data analysis | |
CN106815644A (en) | Machine learning method and from node | |
US11295254B2 (en) | Flexible product manufacturing planning | |
CN104063441A (en) | Database operation maintenance system and data operation maintenance method thereof | |
JP7160574B2 (en) | Processor, method and program | |
CN106687875A (en) | Systems and methods for process design and analysis | |
CN110648124B (en) | Method and apparatus for concurrently executing transactions in a blockchain | |
CN109508451A (en) | A kind of list data comparison processing method and processing device | |
CN104662564B (en) | Data analysis set-up and program | |
CN109740113A (en) | Hyper parameter threshold range determines method, apparatus, storage medium and electronic equipment | |
CN110928261A (en) | Distributed estimation scheduling method and system for distributed heterogeneous flow shop | |
CN110176272A (en) | A kind of protein disulfide prediction technique for matching information based on multisequencing connection | |
CN109359760B (en) | Logistics path optimization method and device and server | |
US20140163933A1 (en) | Manufacturing line designing apparatus and manufacturing line designing method | |
CN108710541A (en) | A kind of execution method and device of timed task | |
CN103793625A (en) | System and method for aligning genome sequence | |
Kreutter et al. | Multistep retrosynthesis combining a disconnection aware triple transformer loop with a route penalty score guided tree search | |
JP2012128818A (en) | Manufacturing process improvement support system, manufacturing process improvement support, and manufacturing process improvement program | |
JP2010282466A (en) | Plant information control system and association program |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181218 |