CN109028682A CN201810801180.1A CN201810801180A CN109028682A CN 109028682 A CN109028682 A CN 109028682A CN 201810801180 A CN201810801180 A CN 201810801180A CN 109028682 A CN109028682 A CN 109028682A
Authority
CN
China
Prior art keywords
spiral
heat exchanger
ice
bracket
exchanger tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810801180.1A
Other languages
Chinese (zh)
Inventor
邹雨菲
罗晋湘
姜梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810801180.1A priority Critical patent/CN109028682A/en
Publication of CN109028682A publication Critical patent/CN109028682A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25CPRODUCING, WORKING OR HANDLING ICE
    • F25C1/00Producing ice
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25CPRODUCING, WORKING OR HANDLING ICE
    • F25C5/00Working or handling ice
    • F25C5/02Apparatus for disintegrating, removing or harvesting ice
    • F25C5/04Apparatus for disintegrating, removing or harvesting ice without the use of saws

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Thermal Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The invention discloses a kind of spirals of not additionaling power to produce ice production apparatus, including Ice Storage Tank, heat exchanger, compressor, condenser, expansion valve and spiral deicer, water and refrigerant are realized in heat exchanger internal circulation heat-exchanging and produce ice, and clear up ice pellets by spiral deicer.One end of spiral band is connect with holder pivots in the present invention, there are gaps between bracket and end plate, gap of the water flow between bracket and end plate can't generate flow resistance when entering in heat exchanger tube, structure is simple, easy for installation, ice making and deicing efficiency are greatly improved, the service life of spiral deicer is extended.

Description

A kind of spiral production ice production apparatus of not additionaling power
Technical field
The present invention relates to ice making equipment technical fields, produce ice production apparatus more particularly to a kind of spiral of not additionaling power.
Background technique
Ice making equipment is a kind of relatively conventional instrument, by making refrigerant circulation heat absorption and heat release in pipeline reach system Ice effect.But ice making equipment in the prior art is easy to be adhered to ice pellets on heat exchange tube wall during ice making, causes Heat transmitting hinders, and the efficiency of ice making is influenced, so that expection is not achieved in ice-making capacity in Ice Storage Tank.
French Publication No. FR25545209, US publication are US4174750 and Chinese Publication No. CN2214239Y, The patent application document of CN2465140Y discloses the twisted strip that rotation is installed in heat exchanger tube, and twisted strip is in heat exchanger tube It is rotated under fluid driven, is constantly collided with pipe friction, the soil release of tube wall will be attached to, grow dirt can not;Due to The reaction of twisted strip flows to the fluid deflector of streamlined flow, increases heat-transfer pipe heat transfer coefficient in tubes, plays reinforcing and passes The effect of heat.But the method that twisted strip is fixed on heat transfer pipe fluid upstream end is used in above-mentioned patent application document, this There are flow resistances for kind fixing means greatly, can not be mounted on common heat exchanger, service life is short and manufacturing cost is high Problem can not be promoted in actual production.
Therefore, how to provide that a kind of structure is simple, flow resistance is small, adaptable and not additionaling power with long service life Spiral produce ice production apparatus, be those skilled in the art's technical problem urgently to be resolved.
Summary of the invention
That the object of the present invention is to provide a kind of structures is simple, flow resistance is small, adaptable and with long service life not outer The spiral of power is added to produce ice production apparatus.
To achieve the above object, the present invention provides following schemes:
Ice production apparatus is produced the invention discloses a kind of spiral of not additionaling power, including Ice Storage Tank, heat exchanger, compressor, cold Condenser, expansion valve and spiral deicer are provided with heat exchanger tube and end plate, the left and right ends of the heat exchanger tube in the heat exchanger It is erected on an end plate, refrigerant inlet, refrigerant exit, flow inlet and ice pellets outlet is provided on the heat exchanger, The both ends of the heat exchanger tube go out with the flow inlet and the ice pellets outlet, the refrigerant inlet and the refrigerant respectively Mouth is set between two end plates, and the outlet of the Ice Storage Tank is connected to the flow inlet, the outlet of the Ice Storage Tank Ice-make cycle pump is provided on pipeline between the flow inlet, the entrance of the Ice Storage Tank and ice pellets outlet connect Logical, the refrigerant exit is sequentially communicated with the compressor, the condenser, the expansion valve and the refrigerant inlet, described Spiral deicer includes spiral band and bracket, and the spiral band is set in the heat exchanger tube, the spiral band One end is connect with the holder pivots, and the bracket and the end plate are relatively fixed, is existed between the bracket and the end plate Gap.
Preferably, the bracket is fixed on the end plate of the heat exchanger tube side.
Preferably, do not include the compressor, the expansion valve is replaced with into refrigerating medium circulating pump, the condenser is replaced It is changed to cooler.
Preferably, the spiral band is flaky polymer material, and the inner wall of the spiral band and the heat exchanger tube is deposited In gap.
Preferably, hanger is provided on the bracket, it is opposite with the heat exchanger tube that the hanger is fixed on the bracket Side is provided with connecting rod between the hanger and the spiral band, one end of the connecting rod is fixedly connected with the spiral band, The other end of the connecting rod and the hanger are rotatablely connected.
Preferably, the connecting rod and the hanger are rotatablely connected by bearing.
The present invention achieves following technical effect compared with the existing technology:
One end of spiral band is connect with holder pivots in the present invention, rather than is rotatablely connected with end plate, and water flow is from bracket Gap between end plate can't generate flow resistance when entering in heat exchanger tube, structure is simple, easy for installation, greatly improve Ice making and deicing efficiency, extend the service life of spiral deicer;Since spiral band is automatic under the driving of water flow Rotation, thus do not have to additionaling power, save the energy.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is that the spiral of not additionaling power of the invention produces the structural schematic diagram of ice production apparatus embodiment 1;
Fig. 2 is that the spiral of not additionaling power of the invention produces the structural schematic diagram of ice production apparatus embodiment 2;
Description of symbols: 1 Ice Storage Tank, 2 Ice Storage Tanks flow into pipe, and 3 heat exchanger effusers, 4 heat exchanger tubes, 5 heat exchangers, 6 go out Mouth pipe, 7 compressors, 8 end plates, 9 spiral deicers, 10 condensers, 11 expansion valves, 12 heat exchangers, which flow into, manages, 13 inlet tubes, and 14 Ice-make cycle pump, 15 Ice Storage Tank effusers, 16 refrigerating medium circulating pumps, 17 coolers.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
That the object of the present invention is to provide a kind of structures is simple, flow resistance is small, adaptable and with long service life not outer The spiral of power is added to produce ice production apparatus.
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
Embodiment 1,
As shown in Figure 1, the present embodiment provides a kind of spirals of not additionaling power to produce ice production apparatus, including Ice Storage Tank 1, heat exchanger 5, compressor 7, condenser 10, expansion valve 11 and spiral deicer 9.It is provided with heat exchanger tube 4 and end plate 8 in heat exchanger 5, exchanges heat The left and right ends of pipe 4 are erected on end plate 8.Refrigerant inlet, refrigerant exit, flow inlet and ice are provided on heat exchanger 5 Grain outlet.
The both ends of heat exchanger tube 4 are set to two with flow inlet and ice pellets outlet, refrigerant inlet and refrigerant exit respectively Between a end plate 8.The outlet of Ice Storage Tank 1 is connected to by Ice Storage Tank effuser 15 with the entrance of ice-make cycle pump 14, ice-make cycle The outlet of pump 14 flows into pipe 12 by heat exchanger and is connected to flow inlet, and the entrance of Ice Storage Tank 1 flows into pipe 2 by Ice Storage Tank and changes Hot device effuser 3 and ice pellets outlet, refrigerant exit are connected to by outlet 6 with compressor 7, compressor 7 and condenser 10, Expansion valve 11 is sequentially communicated by pipeline, and expansion valve 11 is connected to by inlet tube 13 with refrigerant inlet.Spiral deicer 9 includes Spiral band and bracket, spiral band are set in heat exchanger tube 4.One end of spiral band is connect with holder pivots, bracket and end Plate 8 is relatively fixed.There are gaps between bracket and end plate 8, so that water flow passes through.Spiral band is preferably flaky polymer material There are gaps for the inner wall of matter, spiral band and heat exchanger tube 4, in order to the rotation of spiral band.
When carrying out ice making work, make to accommodate suitable water in Ice Storage Tank 1 first, water is conveyed by ice-make cycle pump 14 To heat exchanger 5, at heat exchanger tube 4 with the refrigerant heat exchanger outside heat exchanger tube 4 and congeal into ice, spiral band rushing in water flow at this time It hits down and is relatively rotated with heat exchanger tube 4, the edge of spiral band is contacted with the ice pellets on 4 inner wall of heat exchanger tube and by ice pellets from heat exchanger tube It is scraped off on 4 tube wall, the ice pellets being scraped off is back in Ice Storage Tank 1 with non-condensing water, forms water circulation.It is followed in water While ring, refrigerant circulation is also carried out.Heat exchanger tube 4 after low-temperature refrigerant enters heat exchanger 5, between two end plates 8 Outer absorption heat simultaneously evaporates gasification, is transported at condenser 10 after the compression of compressor 7, releases heat and is condensed into liquid State, then by again flowing into heat exchanger 5 after the decompression cooling of expansion valve 11, form refrigerant circulation.Ice pellets in Ice Storage Tank 1 not Disconnected accumulation stops refrigerant circulation and water is kept to recycle certain time, it is ensured that ice pellets in heat exchanger tube 4 until ice-making process terminates Stop water circulation after being cleaned.
Gap of the water flow between bracket and end plate 8 can't generate flow resistance when entering in heat exchanger tube 4, thus greatly Ground improves ice making and deicing efficiency.Meanwhile bracket and end plate 8 are relatively fixed, mount and dismount more convenient.Due to spiral Tie rotates automatically under the driving of water flow, thus does not have to additionaling power, has saved the energy.
Further, hanger is provided in the present embodiment on bracket, hanger is fixed on the opposite side of bracket Yu heat exchanger tube 4, Connecting rod is provided between hanger and spiral band, one end of connecting rod is fixedly connected with spiral band, the other end and hanger of connecting rod Rotation connection.By the way that connecting rod is arranged, the distance between bracket and end plate 8 are expanded, the area of passage of water flow is increased, to make In heat exchanger tube 4 flow velocity of water flow faster, with improve ice making and deicing efficiency.It can be rotated and be connected by bearing between connecting rod and hanger It connects, it can also be using other rotation connection modes such as spherical hinges.
Further, bracket can be set on the end plate 8 on 4 right side of heat exchanger tube, and connecting rod applies spiral band and draws at this time Power.
Embodiment 2,
As shown in Fig. 2, the present embodiment provides a kind of spiral production ice production apparatus of not additionaling power, in structure and embodiment 1 Structure it is roughly the same, difference is: not including compressor 7 in the present embodiment, expansion valve 11 is replaced with refrigerating by the present embodiment Condenser 10 is replaced with cooler 17 by agent circulating pump 16.
The water cycle process of the present embodiment is same as Example 1, but the present embodiment is by the refrigerant circulation mistake in embodiment 1 Journey replaces with refrigerating medium cyclic process.Specifically, the refrigerating medium in heat exchanger 5 flows to cold by outlet 6 in the present embodiment But device 17 release heat at cooler 17 and reduce temperature, and pass through inlet tube 13 under the driving of refrigerating medium circulating pump 16 It is back in heat exchanger 5, forms refrigerating medium circulation.
Apply that a specific example illustrates the principle and implementation of the invention in this specification, above embodiments Explanation be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, According to the thought of the present invention, there will be changes in the specific implementation manner and application range.In conclusion in this specification Appearance should not be construed as limiting the invention.

Claims (6)

1. a kind of spiral of not additionaling power produces ice production apparatus, which is characterized in that including Ice Storage Tank, heat exchanger, compressor, condensation Device, expansion valve and spiral deicer are provided with heat exchanger tube and end plate in the heat exchanger, and the left and right ends of the heat exchanger tube are equal It is erected on an end plate, refrigerant inlet, refrigerant exit, flow inlet and ice pellets outlet, institute is provided on the heat exchanger State the both ends of heat exchanger tube respectively with the flow inlet and the ice pellets outlet, the refrigerant inlet and the refrigerant exit Be set between two end plates, the outlet of the Ice Storage Tank is connected to the flow inlet, the outlet of the Ice Storage Tank with Ice-make cycle pump, the entrance of the Ice Storage Tank and the ice pellets outlet are provided on pipeline between the flow inlet, The refrigerant exit is sequentially communicated with the compressor, the condenser, the expansion valve and the refrigerant inlet, the spiral Deicer includes spiral band and bracket, and the spiral band is set in the heat exchanger tube, one end of the spiral band It is connect with the holder pivots, the bracket and the end plate are relatively fixed, and there are gaps between the bracket and the end plate.
2. the spiral of not additionaling power according to claim 1 produces ice production apparatus, which is characterized in that the bracket is fixed on institute It states on the end plate of heat exchanger tube side.
3. the spiral of not additionaling power according to claim 1 produces ice production apparatus, which is characterized in that do not include the compression Machine, replaces with refrigerating medium circulating pump for the expansion valve, and the condenser is replaced with cooler.
4. the spiral of not additionaling power according to claim 1 produces ice production apparatus, which is characterized in that the spiral band is piece There are gaps for the inner wall of shape macromolecule material, the spiral band and the heat exchanger tube.
5. the spiral of not additionaling power according to claim 1 produces ice production apparatus, which is characterized in that be provided on the bracket Hanger, the hanger are fixed on the opposite side of the bracket Yu the heat exchanger tube, set between the hanger and the spiral band It is equipped with connecting rod, one end of the connecting rod is fixedly connected with the spiral band, and the other end of the connecting rod and the hanger rotate Connection.
6. the spiral of not additionaling power according to claim 5 produces ice production apparatus, which is characterized in that the connecting rod is hung with described Frame is rotatablely connected by bearing.
CN201810801180.1A 2018-07-20 2018-07-20 A kind of spiral production ice production apparatus of not additionaling power Pending CN109028682A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810801180.1A CN109028682A (en) 2018-07-20 2018-07-20 A kind of spiral production ice production apparatus of not additionaling power

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810801180.1A CN109028682A (en) 2018-07-20 2018-07-20 A kind of spiral production ice production apparatus of not additionaling power

Publications (1)

Publication Number Publication Date
CN109028682A true CN109028682A (en) 2018-12-18

Family

ID=64644540

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810801180.1A Pending CN109028682A (en) 2018-07-20 2018-07-20 A kind of spiral production ice production apparatus of not additionaling power

Country Status (1)

Country Link
CN (1) CN109028682A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113669973A (en) * 2021-08-24 2021-11-19 李子明 Fluid ice preparation equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4174750A (en) * 1978-04-18 1979-11-20 Nichols Billy M Tube cleaner having anchored rotatable spiral member
CN2214239Y (en) * 1995-01-10 1995-12-06 湘潭大学 Flushing device for descaling and scale prevention of heat transfer tube
CN202835973U (en) * 2012-08-15 2013-03-27 煤炭科学研究总院沈阳研究院 Ice slurry preparing device capable of continuously scrapping ice crystals particles in a plurality of groups of pipe walls
CN203798245U (en) * 2014-04-25 2014-08-27 南京高和环境工程有限公司 Automatic descaling heat exchange system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4174750A (en) * 1978-04-18 1979-11-20 Nichols Billy M Tube cleaner having anchored rotatable spiral member
CN2214239Y (en) * 1995-01-10 1995-12-06 湘潭大学 Flushing device for descaling and scale prevention of heat transfer tube
CN202835973U (en) * 2012-08-15 2013-03-27 煤炭科学研究总院沈阳研究院 Ice slurry preparing device capable of continuously scrapping ice crystals particles in a plurality of groups of pipe walls
CN203798245U (en) * 2014-04-25 2014-08-27 南京高和环境工程有限公司 Automatic descaling heat exchange system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113669973A (en) * 2021-08-24 2021-11-19 李子明 Fluid ice preparation equipment
CN113669973B (en) * 2021-08-24 2022-12-02 李子明 Fluid ice preparation equipment

Similar Documents

Publication Publication Date Title
CN1311207C (en) Environmentally-friendly heat pump
CN101078580A (en) Heat pump hot water machine set of water-containing internal circulation heat-exchanging loop
CN202675964U (en) Heat superconductor water source heat exchanger
JP7016812B2 (en) Air conditioner
CN101187515A (en) Wind source heat pump installed with defrosting heat exchanging tube
CN106767115B (en) heat exchanger tube and heat exchanger
CN110131924A (en) Return air residual heat in mine gradient utilization system
CN110360769B (en) Heat pump system with phase-change energy tower and heat exchange method thereof
CN102445098A (en) Hot superconductor water source heat exchanger
CN101338958B (en) Air conditioner heat exchange type condensator and spray evaporative cooling system
CN109028682A (en) A kind of spiral production ice production apparatus of not additionaling power
CN102121768A (en) Heat exchange apparatus with heat pipe soaking device for refrigeration air conditioning system
CN103175359A (en) Small-sized compact type dynamic ice slurry making system
CN106225334A (en) A kind of vertically coiled pipe falling film evaporation condenser and method
CN205957341U (en) Outer machine of water wind combined cooling formula air conditioner and air conditioning unit
CN209399808U (en) Pneumatics energy heat-exchange system
CN201974081U (en) Heat-exchanging device with heat-pipe thermal spreader for refrigerative air-conditioning system
CN208042264U (en) A kind of photovoltaic and photothermal tunnel accumulation of heat winterization system
CN207081148U (en) A kind of cold and hot buffer tank suitable for air-conditioning system
CN206919470U (en) A kind of freezer refrigerating and the dual-purpose device that heats
CN206113416U (en) Space can heating machine
CN205741082U (en) A kind of blast furnace slag quenching water bootstrap system
CN203274391U (en) Small and compact dynamic ice slurry making system
CN203928488U (en) Air-cooled heat pump water chiller-heater units
CN214172555U (en) Heat pump water heater system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181218