CN109024554A - Construction method of double-high-pressure mixing-spraying pile waterproof curtain - Google Patents

Construction method of double-high-pressure mixing-spraying pile waterproof curtain Download PDF

Info

Publication number
CN109024554A
CN109024554A CN201810617872.0A CN201810617872A CN109024554A CN 109024554 A CN109024554 A CN 109024554A CN 201810617872 A CN201810617872 A CN 201810617872A CN 109024554 A CN109024554 A CN 109024554A
Authority
CN
China
Prior art keywords
pile
stake
pressure
drill bit
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810617872.0A
Other languages
Chinese (zh)
Inventor
杨忠年
李发达
李克先
万勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qindao University Of Technology
Original Assignee
Qindao University Of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qindao University Of Technology filed Critical Qindao University Of Technology
Priority to CN201810617872.0A priority Critical patent/CN109024554A/en
Publication of CN109024554A publication Critical patent/CN109024554A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention relates to a construction method of a double high-pressure mixing-spraying pile waterproof curtain, which comprises the following steps: step one, measuring and lofting; step two: the long spiral pile machine is positioned by adopting a drill bit with a special structure; step three: preparing cement paste; step four: the drill bit rotates clockwise at a constant rotating speed and sprays high-pressure cement slurry at the same time, so that the soil body is stirred in situ; with the rotation of the long screw pile driver, the high-pressure grouting machine and the air compressor continuously supply water slurry and air; step five: when the long screw pile driver drills to a preset position, stopping the operation of the drilling machine, and spraying high-pressure cement paste while rotating in the anticlockwise direction while lifting a drill bit; and lifting the drill bit away from the ground to finish the construction of the double high-pressure stirring and spraying pile. The construction method of the double-high-pressure mixing-spraying pile fundamentally solves the problem that the rotary spraying pile cannot be constructed in the residual hard soil layer and the residual weathered stratum, and the vertical waterproof curtain is formed by mutual engagement of the piles, so that the construction method has great application value in the aspects of seepage prevention and water stopping of the foundation pit of the excavated station and foundation reinforcement.

Description

The construction method of double high-pressure stirring-spraying pile water-stop curtains
Technical field
The invention belongs to the construction methods of foundation pit sealing, and in particular to a kind of construction party of double high-pressure stirring-spraying pile water-stop curtains Method.
Background technique
With the development of urban track traffic, the excavation of subway station faces foundation ditch strengthening and sealing problem.It is existing to stir It is complicated to topography and extremely limited and right containing applications such as hard stratum, boulder bed, miscellaneous fills except jackstone, basement rock to mix stake Stratum it is poor for applicability;On the one hand the pile quality of stake is unable to get guarantee after mixing pile construction, and another aspect stake is stirred not Uniformly.A kind of construction method for remaining hard stratum, residual weathered stratum foundation pit sealing is needed at present.
Summary of the invention
The present invention makes double high-pressure stirring-spraying piles be suitable for processing by improving drill bit and construction method in order to solve problem above Mud, muck soil, cohesive soil, clay, sandy soil, artificial earth fill are especially the strengthening of foundation for remaining hard stratum, residual weathered stratum And water-stop curtain construction problem, fundamentally improve the pile radius of pile body and the uniformity of stake.
The present invention uses following technical scheme in order to solve the above problem:
A kind of construction method of double high-pressure stirring-spraying pile water-stop curtains, construction procedure are as follows:
Step 1: the center spacing control of surveying and locating, stake and stake is in 0.3-0.5d (diameter that d is stake) range;
Step 2: long spire stake machine moves to pile driving position and is adjusted pile body, fixed pile;Long spire stake machine is using following The drill bit of structure: a pair of rectangular blade and a pair of rectangular lower blade being arranged including bit matrix, on bit matrix, The length of blade is greater than the length of lower blade, and blade and inferior lobe on piece are respectively provided with the antisymmetric tooth head in left and right;Bit matrix End setting bore tooth, the inside of bit matrix is arranged double high pressure water slurry channels, the bottom setting of blade and lower blade with The nozzle of double high pressure water slurry channel perforations;
Step 3: preparing cement slurry, uses when for high-pressure injection pump mud jacking;
Step 4: double high pressure cements in the output end of high-pressure grout injector and the output end and bit matrix of air compressor Starch channel connection;Start long spire stake machine, high-pressure grout injector and air compressor, the cement slurry and air of high-pressure grout injector compression The air of compressor compresses forms high pressure water mud in drill bit, and drill bit is rotated in the forward direction with constant rotational speed, sprays height in rotation Compressed water slurry makes the soil body be agitated in situ;
Step 5: when long spire stake machine drill to predetermined position, stopping drilling machine operation, reversed to revolve while drill bit is lifted Turn, sprays high pressure water mud in rotation;The construction of double high-pressure stirring-spraying piles is completed on drill bit lift-off ground;
Step 6: drilling machine displacement repeats step 2 to step 5, completes all piles position into next pile stake position Construction.
The construction method of double high-pressure stirring-spraying piles, using long spire stake machine, with high-pressure injection pump by cement slurry through drill pipe bore It is delivered to nozzle special on drill bit, while compressed air is delivered to the nozzle on drill bit through drilling rod exit orifice and penetrates together with cement slurry Out;In drilling rod rotary course, blade on drill bit by soil carry out action of forced stirring, cement slurry and compressed air with bit to The injection of the surrounding soil body, forms the mixture of soil and cement slurry, and consolidation pile body is formed after hardening;This method be suitable for except jackstone, The location strengthening of foundation of the rich groundwaters such as various complex terrain hard stratums, boulder bed, miscellaneous fill except basement rock and sealing curtain Curtain construction.
The present invention by using the double high-pressure stirring-spraying pile drill bits guarantee construction stake diameters of special designing and carries out action of forced stirring to soil, High pressure water mud is projected from nozzle, forms the above high-pressure jet punching failure soil body of second level, realizes that slurries are delivered at a distance, Under blade action of forced stirring and high-pressure jet collective effect, pile body cement grout is made to stir evenly to form a cylindrical consolidation Body, i.e., double high-pressure stirring-spraying piles;It is mutually twisted and is coagulated together between double high-pressure stirring-spraying piles, there is certain intensity and impermeability, It is configured to the water-stop curtain of antiseepage.
The blade of double high-pressure stirring-spraying pile drill bits is designed using bilateral symmetry, and blade is rectangle;When in view of bit Blade is to the stirring capacity of soil, and blade arrangement is up big and down small mode, and the length of blade design is different available different straight The stake of diameter;Tooth head is welded on blade, and in order to guarantee that double high-pressure stirring-spraying piles preferably cut soil, tooth head uses the antisymmetric side in left and right Formula design;Nozzle design is in the bottom surface of blade, cement slurry destruction soil body from projecting in nozzle while bit stirs Effect.
Double high-pressure stirring-spraying pile construction methods of the invention fundamentally solve rotary churning pile and are remaining hard stratum, residual weathering Stratum can not construction problem, vertical water-stop curtain is formed by being mutually twisted for stake, excavate station pit it is anti-blend sealing and There is biggish application value in terms of foundation stabilization.
Detailed description of the invention
Fig. 1 is the flow chart of the double high-pressure stirring-spraying pile waterproof curtain construction methods of the present invention;
Fig. 2 is the plan view of mixing pile of the present invention;
Fig. 3 is the structural schematic diagram of drill bit of the present invention;
Wherein: 1, bit matrix;2, blade;3, lower blade;4 and 5 be tooth head;6, tooth is bored;7, double high pressure water mud are logical Road;8 and 9 nozzles;10, ring flange.
Specific embodiment
Combined with specific embodiments below and attached drawing is described in further details the present invention.
Referring to flow chart 1, the construction method of double high-pressure stirring-spraying piles prepares before constructing: live three supplies and one leveling, i.e. access are led to Water is powered on, and construction site is smooth.
Step 1: surveying and locating determines construction area full-page proof according to the figure that lays out pile, and carries out stake position by design pilespacing in every region Setting-out, as shown in Figure 1, the control of the center spacing of stake and stake is in 0.3-0.5d (diameter that d is stake) range;
Step 2: long spire stake machine moves to pile driving position and is adjusted pile body, fixed pile;
Long spire stake machine uses the drill bit of following structures: as shown in Fig. 2, including bit matrix 1, the basic cross section of drill bit For circle, a pair of rectangular blade 2 of setting and a pair of rectangular lower blade 3, the length of blade 2 on bit matrix 1 Greater than the length of lower blade 3, the antisymmetric tooth head 4 in left and right and tooth head 5, i.e. tooth head 4 and 5 central symmetry of tooth head is arranged in blade 2, Symmetric points are fallen on the crosspoint of blade 2 and bit matrix 1;The antisymmetric tooth head 4 in left and right and tooth head are also provided on lower blade 3 5, symmetric points are fallen on the crosspoint of lower blade 3 and bit matrix 1.The end setting alloy of bit matrix 1 bores tooth 6, drill bit base Double high pressure water slurry channels 7 are arranged in the inside of body 1, and bottom setting and the double high pressure water slurry channels of blade 2 and lower blade 3 pass through Logical nozzle 8 and 9;Ring flange 10 is arranged in the upper end of bit matrix 1, connect with drilling rod.
Step 3: preparing cement slurry, cement slurry is prepared by the match ratio of design in first pulp storage tank, by what is prepared Cement slurry is used when flowing into standby high-pressure injection pump mud jacking in second pulp storage tank from first pulp storage tank;
Step 4: the output end of high-pressure grout injector and the output end of air compressor pass through high pressure steel wire spiral rubber hose respectively It is connected to double high pressure water slurry channels in bit matrix;Start long spire stake machine, high-pressure grout injector and air compressor, high pressure The cement slurry of slip casting machine compression and the air of air compressor compression form high pressure water mud simultaneously in double high pressure water slurry channels It is sprayed from nozzle, drill bit is rotated clockwise with constant rotational speed, is sprayed high pressure water mud in rotation, is made the soil body in situ It is agitated;
Step 5: when long spire stake machine drill to predetermined position, stop drilling machine operation, while drill bit is lifted, counterclockwise Direction rotates, and sprays high pressure water mud in rotation;The construction of double high-pressure stirring-spraying piles is completed on drill bit lift-off ground;
Step 6: drilling machine displacement repeats step 2 to step 5, completes all piles position into next pile stake position Construction.
Concrete engineering example: metro station uses cut and cover tunneling, and the incorporation engineering geologic aspects station underground water is rich Rich and stratum earthing is mostly miscellaneous fill, artificial earth fill.Double high-pressure stirring-spraying piles are constructed in such a way that jump is beaten between stake and stake, stake Overlap distance with stake is 25cm, and driving depth 9.8m, stake diameter is 1m, tests Compressive Strength of Soil-cement Mixture after pile 28d.Scene Coring 3, unconfined compression strength test result is S1 1.65MPa, 2.68MPa, 1.62MPa, and S1 average value is 1.98MPa;S2 are 2.74MPa, 2.79MPa, 2.59MPa, and S2 average value is 2.71MPa;S3 for 2.27MPa, 2.03MPa, 2.11MPa, S3 average value are 2.14MPa;Ordinary cement mixing pile pile body unconfined compressive strength is in 0.5- Between 1.2MPa.
Double high-pressure stirring-spraying pile engineering methods of the invention fundamentally solve rotary churning pile and are remaining hard stratum, residual weathered stratum Can not construction problem, to form vertical water-stop curtain by being mutually twisted between stake, station pit is anti-to blend sealing and ground excavating It is applied successfully in reinforcing.
The above content is specific engineering construction example is combined, further detailed description of the invention, in practice not It can assert that specific implementation of the invention is only limited to these instructions.The construction technical staff of the technical field of the invention is come It says, without departing from the inventive concept of the premise, several simple deductions appropriate can also be made and replacement, above structure are all answered It is considered as belonging to protection scope of the present invention.

Claims (2)

1. a kind of construction method of double high-pressure stirring-spraying pile water-stop curtains, which comprises the following steps:
Step 1: the center spacing of surveying and locating, stake and stake controls within the scope of 0.3-0.5d, d is the diameter of stake;
Step 2: long spire stake machine moves to pile driving position and is adjusted pile body, fixed pile;Long spire stake machine uses following structures Drill bit: a pair of rectangular blade and a pair of rectangular lower blade, upper leaf are set including bit matrix, on bit matrix The length of piece is greater than the length of lower blade, and blade and inferior lobe on piece are respectively provided with the antisymmetric tooth head in left and right;The end of bit matrix Tooth, the double high pressure water slurry channels of inside setting of bit matrix, bottom setting and the double height of blade and lower blade are bored in end setting The nozzle of compressed water slurry channel perforation;
Step 3: preparing cement slurry, uses when for high-pressure grout injector mud jacking;
Step 4: double high pressure water mud in the output end of high-pressure grout injector and the output end and bit matrix of air compressor are logical Road connection;Start long spire stake machine, high-pressure grout injector and air compressor, the cement slurry of high-pressure grout injector compression and air compression The air of machine compression forms high pressure water mud in drill bit, and drill bit is rotated in the forward direction with constant rotational speed, sprays high pressure water in rotation Mud makes the soil body be agitated in situ;
Step 5: when long spire stake machine drill to predetermined position, stop drilling machine operation, while drill bit is lifted, reversely rotate, side It rotates side and sprays high pressure water mud;The construction of double high-pressure stirring-spraying piles is completed on drill bit lift-off ground;
Step 6: drilling machine displacement repeats step 2 to step 5, completes the construction of all piles position into next pile stake position.
2. construction method according to claim 1, which is characterized in that the length of upper leaf piece is (diameter-matrix of stake Diameter)/2.
CN201810617872.0A 2018-06-15 2018-06-15 Construction method of double-high-pressure mixing-spraying pile waterproof curtain Pending CN109024554A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810617872.0A CN109024554A (en) 2018-06-15 2018-06-15 Construction method of double-high-pressure mixing-spraying pile waterproof curtain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810617872.0A CN109024554A (en) 2018-06-15 2018-06-15 Construction method of double-high-pressure mixing-spraying pile waterproof curtain

Publications (1)

Publication Number Publication Date
CN109024554A true CN109024554A (en) 2018-12-18

Family

ID=64609660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810617872.0A Pending CN109024554A (en) 2018-06-15 2018-06-15 Construction method of double-high-pressure mixing-spraying pile waterproof curtain

Country Status (1)

Country Link
CN (1) CN109024554A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577865A (en) * 2018-12-28 2019-04-05 青岛理工大学 Double-high-pressure mixing and spraying pile drill bit and using method thereof
CN109723057A (en) * 2018-12-29 2019-05-07 青岛理工大学 Soil body reinforcing method for double-high-pressure stirring and spraying construction
CN109882073A (en) * 2019-03-21 2019-06-14 青岛理工大学 Variable-diameter double-high-pressure mixing and spraying pile and diameter changing method thereof
CN110331698A (en) * 2019-06-11 2019-10-15 徐州工程学院 A kind of system that polyurethane formation curtain was constructed and be rapidly injected to casement

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101012649A (en) * 2007-02-15 2007-08-08 中国京冶工程技术有限公司 Bidirectional helix extruding-enlarging pile construction method and bidirectional helix closed extruding-enlarging aiguille
CN102286985A (en) * 2011-07-11 2011-12-21 中交一航局第四工程有限公司 Method for constructing dual high-pressure jet grouting pile waterproof curtain
CN102505919A (en) * 2011-12-29 2012-06-20 山河智能装备股份有限公司 Bearizing drilling bit
CN102677666A (en) * 2012-05-03 2012-09-19 山东鸿泰建设集团有限公司 Concrete piling process and drilling machine special for same
CN103362461A (en) * 2013-07-08 2013-10-23 阙列东 Long spiral drilling machine and drill bit thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101012649A (en) * 2007-02-15 2007-08-08 中国京冶工程技术有限公司 Bidirectional helix extruding-enlarging pile construction method and bidirectional helix closed extruding-enlarging aiguille
CN102286985A (en) * 2011-07-11 2011-12-21 中交一航局第四工程有限公司 Method for constructing dual high-pressure jet grouting pile waterproof curtain
CN102505919A (en) * 2011-12-29 2012-06-20 山河智能装备股份有限公司 Bearizing drilling bit
CN102677666A (en) * 2012-05-03 2012-09-19 山东鸿泰建设集团有限公司 Concrete piling process and drilling machine special for same
CN103362461A (en) * 2013-07-08 2013-10-23 阙列东 Long spiral drilling machine and drill bit thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杜世伟: "搅喷桩止水帷幕的工程应用研究", 《工业建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577865A (en) * 2018-12-28 2019-04-05 青岛理工大学 Double-high-pressure mixing and spraying pile drill bit and using method thereof
CN109723057A (en) * 2018-12-29 2019-05-07 青岛理工大学 Soil body reinforcing method for double-high-pressure stirring and spraying construction
CN109882073A (en) * 2019-03-21 2019-06-14 青岛理工大学 Variable-diameter double-high-pressure mixing and spraying pile and diameter changing method thereof
CN110331698A (en) * 2019-06-11 2019-10-15 徐州工程学院 A kind of system that polyurethane formation curtain was constructed and be rapidly injected to casement

Similar Documents

Publication Publication Date Title
AU2020103672A4 (en) Construction method of rotary drilling hole-forming and jet mixing cement-soil occlusion curtain piles
CN101962949B (en) Long spiral double-pipe high-pressure stir-jet grouting pile construction method and device
CN109024554A (en) Construction method of double-high-pressure mixing-spraying pile waterproof curtain
CN104929114A (en) High pressure jet grouting pile waterproof curtain construction device and method
CN203452083U (en) Rotary expanding pile construction equipment and grout feeding device
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN104631480B (en) Adopt the method that jet grouting pile driving machine carries out water seal for deep foundation pit curtain construction
CN104988910A (en) Reducing swing-injected agitating pile
CN204753574U (en) High pressure jet grouting pile stagnant water curtain construction equipment
CN101429766A (en) Ground strengthened high pressure rotary spraying pile construction technique
CN109610470A (en) A kind of base pit stand construction using three axes agitating pile machine
CN106996105A (en) Down-the-hole impacts jet mixing pile constructing process and equipment
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN108005682A (en) A kind of shield tunnel reinforcement means
CN102979091B (en) Method for constructing cement jet grouting pile with fine aggregate concrete core
CN112761166A (en) Construction method for shallow foundation pit of combined support of piles and pre-grouting steel pipes based on SMW (soil mixing wall) construction method
CN107366282A (en) A kind of tunnel arch foot partial high pressure rotary churning pile reinforcement technique
CN114808990A (en) High-pressure pre-filling karst cave pile foundation construction method
CN107740434A (en) It is a kind of to be used for sandy gravel, the construction method of dolomite crushed zone dam foundation ditch water protecting curtain
CN112281827A (en) High-pressure air-disturbed cement-soil mixing pile construction process
CN108755671B (en) Construction method of triaxial mixing pile of water-rich gravel layer
CN101649614A (en) Variable-diameter multi-direction anchor pile
CN110984126B (en) Construction method for pre-reinforcing and then forming hole of easy-collapse stratum into cast-in-place pile
CN211713954U (en) Cast-in-situ bored pile in deep fine sand stratum
CN108894247A (en) A kind of Metro Connection Passage periphery soil body subsidence pressure circle spray reinforcement structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181218

RJ01 Rejection of invention patent application after publication