CN108994522A - A method of mismatch is docked using jack centering pipeline - Google Patents

A method of mismatch is docked using jack centering pipeline Download PDF

Info

Publication number
CN108994522A
CN108994522A CN201811156536.7A CN201811156536A CN108994522A CN 108994522 A CN108994522 A CN 108994522A CN 201811156536 A CN201811156536 A CN 201811156536A CN 108994522 A CN108994522 A CN 108994522A
Authority
CN
China
Prior art keywords
segment pipe
jack
port
pipe
concordant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811156536.7A
Other languages
Chinese (zh)
Inventor
姜兆双
王伟林
张辉
程琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN201811156536.7A priority Critical patent/CN108994522A/en
Publication of CN108994522A publication Critical patent/CN108994522A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • B23K37/04Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
    • B23K37/053Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work aligning cylindrical work; Clamping devices therefor
    • B23K37/0533Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work aligning cylindrical work; Clamping devices therefor external pipe alignment clamps

Landscapes

  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

A method of mismatch being docked using jack centering pipeline, belongs to the large and medium-sized Tube formation technical field of industry.Step: the first segment pipe (1) is grouped with the second segment pipe (2), in group to interface (3) position elder generation welding flattening one end (4);Jack (5) is fixed on to the port position fixed point (6) of the second segment pipe (2) of deformation, jack (5) other end hangs over the symmetric position fixed point (7) of the pipeline;Jack (5) hand-manipulated, the second segment pipe (2) port of jack (5) with dynamic deformation, keeps the second segment pipe (2) port gradually concordant with the first segment pipe (1) port;After the first segment pipe (1) is concordant with the second segment pipe (2) port, welding adjusts concordant pipe end (8);Jack (5) are unloaded, adjustment deformation position is further continued for, until the first segment pipe (1) has been welded and fixed with the second segment pipe (2) correction.The advantage is that it is simple to operation, and do not have to the auxiliary materials such as support rod, pipe string efficiency is substantially increased, material is saved, reduces construction cost.

Description

A method of mismatch is docked using jack centering pipeline
Technical field
The invention belongs to the large and medium-sized Tube formation technical fields of industry, in particular, provide a kind of use jack centering pipeline The method for docking mismatch.
Background technique
When industrial large and medium-sized Tube formation, for deformable duct, branch support shield inside pipeline is generally mostly used, and cooperate thousand Jin top is adjusted correction, consumes a large amount of backing materials, while it is slower to operate jack, time-consuming.
Summary of the invention
The purpose of the present invention is to provide a kind of methods using jack centering pipeline docking mismatch to sintering large flue Group is in the process, and using jack (bottle gouard moved by hands) operation adjustment pipe deforming, centering pipeline docks mismatch, and achieves success. It realizes simple to operation, and does not have to the auxiliary materials such as support rod, substantially increase pipe string efficiency, save material, drop Low construction cost has been gained most valuable experience for similar construction later.
The present invention is when group is to pipeline, first welding flattening one end, and it is larger that jack (bottle gouard moved by hands) is then fixed on deformation The port position of size pipeline, the jack other end hang over the symmetric position of the pipeline, then jack hand-manipulated, and jack, which drives, to be become Shape pipeline keeps pipe end gradually concordant to pipe end with another group, after two pipe ends are concordant, is welded and fixed.It unloads down Chain is further continued for adjusting other deformation positions, until two groups have been welded and fixed pipeline correction.Specific step is as follows:
The first step, the first segment pipe 1 are grouped with the second segment pipe 2, in group to 3 position elder generation welding flattening one end of interface 4 (Fig. 1);
Jack (bottle gouard moved by hands) 5 is fixed on the port position fixed point 6 of the second segment pipe 2 of deformation, jack by second step 5 other ends hang over the symmetric position fixed point 7 (Fig. 2) of the pipeline;
Third step, jack 5 hand-manipulated, second segment pipe 2 port of the jack 5 with dynamic deformation make 2 port of the second segment pipe Gradually (Fig. 3) concordant with 1 port of the first segment pipe;
4th step, after the first segment pipe 1 is concordant with 2 port of the second segment pipe, welding adjusts concordant pipe end 8.It unloads Jack 5 is further continued for adjusting other deformation positions, until (Fig. 4) has been welded and fixed in the first segment pipe 1 and the correction of the second segment pipe 2.
This method is simple to operation, and does not have to the auxiliary materials such as support rod, substantially increases pipe string efficiency, saves Material reduces construction cost, achieves good economic benefit for company.
Detailed description of the invention
Fig. 1 is the first segment pipe and second segment pipe string figure.
Fig. 2 is the station diagram that jack is mounted on second segment pipe deforming.
Fig. 3 is operation jack, corrects second segment pipe deforming figure.
Fig. 4 is that figure is welded and fixed after second segment pipe deforming corrects.
In figure, the first segment pipe 1, the second segment pipe 2, group are solid to interface 3, welding flattening one end 4, jack 5, port position Fixed point 6, symmetric position fixed point 7, welding adjust concordant pipe end 8.
Specific embodiment
Fig. 1-Fig. 4 is a kind of specific embodiment of the invention.Specific embodiment is as follows:
The first step, the first segment pipe 1 are grouped with the second segment pipe 2, in group to 3 position elder generation welding flattening one end of interface 4;
Jack (bottle gouard moved by hands) 5 is fixed on the port position fixed point 6 of the second segment pipe 2 of deformation, jack by second step 5 other ends hang over the symmetric position fixed point 7 of the pipeline;
Third step, jack 5 hand-manipulated, second segment pipe 2 port of the jack 5 with dynamic deformation make 2 port of the second segment pipe It is gradually concordant with 1 port of the first segment pipe;
4th step, after the first segment pipe 1 is concordant with 2 port of the second segment pipe, welding adjusts concordant pipe end 8.It unloads Jack 5 is further continued for adjusting other deformation positions, until the first segment pipe 1 has been welded and fixed with the correction of the second segment pipe 2.

Claims (1)

1. a kind of method using jack centering pipeline docking mismatch, which is characterized in that specific step is as follows:
The first step, the first segment pipe (1) are grouped with the second segment pipe (2), in group to interface (3) position elder generation welding flattening one It holds (4);
Jack (5), is fixed on the port position fixed point (6) of the second segment pipe (2) of deformation by second step, and jack (5) is another End hangs over the symmetric position fixed point (7) of the pipeline;
Third step, jack (5) hand-manipulated, the second segment pipe (2) port of jack (5) with dynamic deformation make the second segment pipe (2) Port is gradually concordant with the first segment pipe (1) port;
4th step, after the first segment pipe (1) is concordant with the second segment pipe (2) port, welding adjusts concordant pipe end (8); Jack (5) are unloaded, adjustment deformation position is further continued for, until the first segment pipe (1) has been welded and fixed with the second segment pipe (2) correction.
CN201811156536.7A 2018-09-28 2018-09-28 A method of mismatch is docked using jack centering pipeline Pending CN108994522A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811156536.7A CN108994522A (en) 2018-09-28 2018-09-28 A method of mismatch is docked using jack centering pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811156536.7A CN108994522A (en) 2018-09-28 2018-09-28 A method of mismatch is docked using jack centering pipeline

Publications (1)

Publication Number Publication Date
CN108994522A true CN108994522A (en) 2018-12-14

Family

ID=64590438

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811156536.7A Pending CN108994522A (en) 2018-09-28 2018-09-28 A method of mismatch is docked using jack centering pipeline

Country Status (1)

Country Link
CN (1) CN108994522A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06106344A (en) * 1992-09-28 1994-04-19 Nkk Corp Manufacture of girder structure
CN201737639U (en) * 2010-03-25 2011-02-09 深圳市特辰科技有限公司 Integral inverted hoist
CN102061681A (en) * 2010-12-14 2011-05-18 中国水电建设集团十五工程局有限公司 Fixed dual-hoisting point cantilever track type joist truss installing method
CN103921027A (en) * 2014-04-22 2014-07-16 上海电气核电设备有限公司 Penetration piece tube base connector welding deformation monitoring device and method
CN104942410A (en) * 2015-07-16 2015-09-30 上海振华重工(集团)股份有限公司 Ultra-narrow gap TIG (tungsten inert gas) hot wire welding method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06106344A (en) * 1992-09-28 1994-04-19 Nkk Corp Manufacture of girder structure
CN201737639U (en) * 2010-03-25 2011-02-09 深圳市特辰科技有限公司 Integral inverted hoist
CN102061681A (en) * 2010-12-14 2011-05-18 中国水电建设集团十五工程局有限公司 Fixed dual-hoisting point cantilever track type joist truss installing method
CN103921027A (en) * 2014-04-22 2014-07-16 上海电气核电设备有限公司 Penetration piece tube base connector welding deformation monitoring device and method
CN104942410A (en) * 2015-07-16 2015-09-30 上海振华重工(集团)股份有限公司 Ultra-narrow gap TIG (tungsten inert gas) hot wire welding method

Similar Documents

Publication Publication Date Title
CN108994522A (en) A method of mismatch is docked using jack centering pipeline
CN205187330U (en) Tyre gripping device
CN105782567A (en) Mounting device for glass steel pipeline
CN203711539U (en) Steel pipe straightening machine
CN105480715A (en) Picking device of objects on conveyor belt
CN103964201A (en) Suction lifting type article carrying device
CN204711878U (en) A kind of fixture of anchor stone oil pipe
CN209193050U (en) A kind of automatic charging device of solar panel silk-screen printing
CN204265060U (en) A kind of cross bar device for discharging
CN204486523U (en) A kind of pipe fitting apparatus for bending
CN207043807U (en) Clamp system
CN207325690U (en) A kind of electric cooker shell rounding hemming device
CN206732863U (en) A kind of Pneumatic clamping tool
CN204019154U (en) A kind of conduit coupling processing tool
CN205237107U (en) Thin wall product presss from both sides tight structure
CN204237123U (en) Ship belt frame fold mechanism
CN203900497U (en) Single-blade hose processing equipment
CN209439235U (en) Longitudinal flange assembly line
CN205187338U (en) Many specifications pipe material pay -off hand
CN203862739U (en) Finishing tube straightening machine
CN203617247U (en) Chip plasma surface treating device
CN204280401U (en) The conveyer feed bin of the bonding material of a kind of anti-inwall
CN208325779U (en) A kind of intelligence send a bag manipulator
CN203887496U (en) Automatic six-nut conveying and tightening device
CN217915360U (en) Manipulator clamp

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181214

WD01 Invention patent application deemed withdrawn after publication