CN108988338A - The power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically and device automatically - Google Patents

The power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically and device automatically Download PDF

Info

Publication number
CN108988338A
CN108988338A CN201810986651.0A CN201810986651A CN108988338A CN 108988338 A CN108988338 A CN 108988338A CN 201810986651 A CN201810986651 A CN 201810986651A CN 108988338 A CN108988338 A CN 108988338A
Authority
CN
China
Prior art keywords
strong continune
continune component
fpga
switch
power supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810986651.0A
Other languages
Chinese (zh)
Inventor
陈益
宣俊楠
张永明
杨和俊
冯耀宇
徐宇
龚新勇
李磊
胡泽江
周瀛
赵灿辉
马力
李骞
徐肖庆
孙韬
李芳洲
曹俊锋
陈炯
段燕青
杨柳
蒋正杰
童伟
杨鹏杰
甘龙
唐强
余章
陈伟
高杉雪
雷昊
张建华
孙幸立
陈凯
张南辉
阎定强
潘卫东
李滢洁
宋庆
张国斌
王杰鸿
张晓思
李辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd
Original Assignee
Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd filed Critical Kunming Power Supply Bureau of Yunnan Power Grid Co Ltd
Priority to CN201810986651.0A priority Critical patent/CN108988338A/en
Publication of CN108988338A publication Critical patent/CN108988338A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/008Circuit arrangements for ac mains or ac distribution networks involving trading of energy or energy transmission rights
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/04Circuit arrangements for ac mains or ac distribution networks for connecting networks of the same frequency but supplied from different sources
    • H02J3/06Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of power grids for being suitable for open loop power supply based on strong continune component depth-first search to adjust method for electrically automatically, and the method comprising the steps of: step S1, and the operating condition by acquiring supply network is arranged corresponding Sequential Elements and instantiates digraph.Step S2, using the real-time analytical calculation strong continune component of Depth Priority Algorithm.Step S3 changes the completely new strong continune component after the method for operation changes using Depth Priority Algorithm simulation calculation according to the requirement that the method for operation changes.It is electrically operated to issue fast automatic tune electricity order completion tune by step S4 after confirmation simulation result is feasible.Wherein: Sequential Elements include: breaker, for changing graph structure;Transformer, internal strong continune component;Bus, strong continune component auxiliary parameter, for checking graph structure.

Description

The power grid for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Method for electrically and device
Technical field
The present invention relates to a kind of power grids for being suitable for open loop power supply based on strong continune component depth-first search to adjust electricity automatically Method belongs to bulk power grid stabilization, safe and reliable powered operation field operation under open loop operation mode.
Background technique
With the reinforcement of 500 kV racks and the continuous expansion of regional 220 kV power grid scales.220 kV divided power systems Partition running is the certainty of power network development.It is run by power system delamination and subarea, not only can solve 500 kV, 220 kV electromagnetism Looped network thermostabilization problem caused by power flow transfer under route N-1 or N-2 mode, gives full play to the defeated of high voltage order one grade Electric energy power, and electric network composition can be made clear, it is well arranged, it is easy to implement subregion off-the-line, effectively constructs safety and stability the 3rd Road defence line;It can reduce system short-circuit electric current simultaneously, solve the short circuit current excessive problem of partial electric grid.Due to power network development Complexity and diversity unlink existing electromagnetic looped network, realize that layering and zoning operation needs comprehensive considering various effects, such as: When unlink, wherein unlink, how subregion the problems such as.In order to cope with the 220 kV grid short circuit electric currents increasingly increased and subtract Light 500 kV, the operation of 220 kV electromagnetic looped networks are to threat caused by power network safety operation.
Impedance and each not phase of trend distribution when being under the jurisdiction of substation's Loop Closing Operation of different subregions, due to different paths Together, and there are when larger difference, then there can be biggish phase angle difference in cyclization switch ends, circulation is excessive to will also cause equipment mistake Carry even switch trip.For the generation for avoiding such case, this cyclization mode generally uses break-before-make principle to be operated, User will be caused to have a power failure in short-term, and influence power supply continuity.Frequent have a power failure not only reduces the electricity sales amount of Utilities Electric Co., and makes It obtains customer satisfaction to be greatly reduced, even results in legal dispute.
Summary of the invention
The present invention makes in view of the foregoing, a kind of suitable based on the depth-first search of strong continune component the purpose is to provide Power grid for open loop power supply adjusts method for electrically and device automatically, can: avoid cyclization tune electricity from will lead to the route of part substation Will across section cyclization, for close-loop path across 220kV even 500kV transmission line of electricity, closed loop power flow is affected to major network;For confession After power grid open loop operation, when needing to adjust electricity, the entire time for adjusting electricity can be greatly reduced using this method and device, increase electricity Power company electricity sales amount is increased customer satisfaction degree.
The present invention provide it is a kind of based on strong continune component depth-first search be suitable for open loop power supply power grid adjust electricity automatically Method, comprising the following steps:
Step S1, the operating condition by acquiring supply network are arranged corresponding Sequential Elements, instantiate digraph;
Step S2, using the real-time analytical calculation strong continune component of Depth Priority Algorithm;
Step S3, according to the requirement that the method for operation changes, after changing the method for operation using Depth Priority Algorithm simulation calculation Completely new strong continune component;
It is electrically operated to issue fast automatic tune electricity order completion tune by step S4 after confirmation simulation result is feasible.
The technical solution that the present invention further limits are as follows:
Further, step S1 specifically:
The magnanimity supply network operating condition data received are compared, sieve takes corresponding Sequential Elements, has been instantiated as Xiang Tu does discard processing for the related data for being unsatisfactory for requiring.
Further, step S2 specifically:
DFS calculating is done to the digraph of supply network instantiation, finds out its SCC, according to the recursive rule prestored, verifying is passed through It is consistent with actual electric network operating condition that DFS, which calculates the SCC found out,.
Further, step S3 specifically:
According to the predetermined requirement for changing the method for operation, the simulated operation on original supply network, and according to simulated operation as a result, adopting The completely new strong continune component after changing the method for operation is calculated with DFS algorithm simulating, the SCC after verification changes changes with grid requirements Whether the method for operation afterwards is consistent.
It is a kind of based on strong continune component depth-first search be suitable for open loop power supply power grid adjust electric installation, device packet automatically It includes:
Acquisition unit, for acquiring the mass data of reaction supply network operating condition;
Setting unit, the magnanimity supply network operating condition data sieve for will receive take corresponding Sequential Elements;
Arithmetic element is calculated for DFS;
Simulation unit, for checking whether the calculated SCC of DFS is consistent with actual electric network operating condition;For simulated grid Whether the method for operation meets the requirement of grid operation mode change by the calculated SCC of DFS after changing;
Execution unit, for controlling relative breaker, execution is adjusted electrically operated automatically.
The technical solution that the present invention further limits are as follows:
Further, Sequential Elements include: breaker, for changing graph structure;Transformer, internal strong continune component;Bus, by force Connected component auxiliary parameter, for checking digraph structure;
Breaker include: the power side breaker of the power supply point of one's respective area supply network, one's respective area load-center substation inlet wire open Pass, high-voltage side bus interconnection switch, main transformer high side switch, main transformer low-pressure side switch, outlet switch and low-pressure side bus contact Switch, the incoming switch of regional primary station, high-voltage side bus interconnection switch, main transformer high side switch, main transformer low-pressure side are opened Pass, outlet switch and low-pressure side bus interconnection switch;The incoming switch of regional secondary substation, high-voltage side bus interconnection switch, Main transformer high side switch, main transformer low-pressure side switch and low-pressure side bus interconnection switch;
Transformer includes: one's respective area load-center substation main transformer, regional primary station main transformer, regional secondary substation main transformer;
Bus includes: one's respective area load-center substation high-voltage side bus, middle pressure survey bus, low-pressure side bus, regional primary station High-voltage side bus, middle pressure survey bus, low-pressure side bus, regional secondary substation high-voltage side bus, middle pressure and survey bus, low-pressure side mother Line.
Further, device communicates resolver as internal bus using FPGA, and CPU management+protection DSP+FPGA is realized Function, a large amount of calculating, verification, emulation, filtration are completed by CPU management and FPGA;
CPU management is configured mass data feature vector, the type of Sequential Elements using first pair of interface that FPGA is provided.
Further, after the acquisition unit of FPGA receives the network message from external ethernet controller, to network Message carries out protocol layer parsing, and judges whether the network message meets according to the mass data feature vector that CPU management is arranged Feature vector requirement in feature vector table, if not meeting discarding, if met, related effective information is sent to In RxRAM;Setting unit reads related effective information to the Sequential Elements type that FPGA is arranged according to CPU management in RxRAM It extracts, the Sequential Elements of extraction is sent to RxFIFO, and CPU management is sent to by the interface with CPU management.
Further, the arithmetic element of CPU management realizes the reception of Sequential Elements, and according to pre-set supply network The Sequential Elements example of topological recursion figure combination FPGA transmission dissolves supply network digraph;The digraph that example goes out is used real When DFS calculate the SCC of existing supply network, result is sent in SRAM, the simulation unit of CPU management is notified to read CPU's The calculated SCC of arithmetic element;Verifying is compared with power grid actual operating mode in SCC by the simulation unit of CPU;It is adjusted when receiving When the tune electricity order of control center, the computing unit of CPU management is from fortune and according to regulation center tune electricity instruction, on original supply network Simulated operation, and carry out emulation DFS again according to simulated operation result and calculate, the result of calculating is sent in SRAM, is notified The simulation unit of CPU management carries out emulation comparison;It is then adjusted if the verification passes by protection dsp interface to protection DSP hair Electricity order, by the communication interface with FPGA, tells that verifying does not pass through FPGA, is alerted by FPGA and mentioned if verifying does not pass through Awake operation maintenance personnel;
The simulation unit that protection DSP receives CPU management is emulated by opening execution unit after order, starts to do the electric work of tune, together Even if Shi Kaiqi protects program, power grid security is provided protection against, when adjusting the demand of electricity work to be all satisfied, protection DSP passes through CPLD operates corresponding exit relay, completes to adjust electricity work.
Further, DSP passes through local bus with CPU management and connect FPGA, and FPGA externally provides 8 100,000,000 networks and connects Mouthful, each 100,000,000 network interface connects an ethernet controller;Wherein 4 ethernet controllers are respectively independently connected to one Fiber optical transceiver, fiber optical transceiver are connected to external Ethernet optical fiber;Other 4 ethernet controllers are independently connected to respectively From RJ45 network connector, RJ45 network connector is connected to external ethernet.
The present invention can be avoided cyclization tune electricity will lead to part substation route will across section cyclization, while can subtract significantly Few entire time for adjusting electricity, increases Utilities Electric Co.'s electricity sales amount, increases customer satisfaction degree.
Detailed description of the invention
Fig. 1 is that a kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search of the invention is adjusted automatically The process flow diagram of method for electrically;
Fig. 2 is that a kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search of the invention adjusts Denso automatically The structural schematic diagram set;
Fig. 3 adjusts electric installation hardware frame for a kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search automatically Composition.
Fig. 4 adjusts electric installation soft automatically for a kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search Part architecture diagram.
Fig. 5 adjusts electric installation stream for a kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search automatically Cheng Tu.
Specific embodiment
In order to make the objectives, technical solutions and advantages of the present invention clearer, With reference to embodiment and join According to attached drawing, invention is further described in detail.It should be understood that these descriptions are merely illustrative, it is not intended to limit this hair Bright range.Furthermore in the following description, descriptions of well-known structures and technologies are omitted, obscures this hair to avoid unnecessary Bright concept.
A kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts electricity side automatically as shown in Figure 1 Method, comprising steps of
Step S1, the operating condition by acquiring supply network are arranged corresponding Sequential Elements, instantiate digraph
Step S2, using the real-time analytical calculation strong continune component of Depth Priority Algorithm
Step S3, according to the requirement that the method for operation changes, after changing the method for operation using Depth Priority Algorithm simulation calculation Completely new strong continune component.
It is electrically operated to issue fast automatic tune electricity order completion tune by step S4 after confirmation simulation result is feasible.
Wherein: Sequential Elements include:
Breaker, for changing graph structure, comprising: power side breaker, the one's respective area pivot of the power supply point of one's respective area supply network The incoming switch of knob substation, high-voltage side bus interconnection switch, main transformer high side switch, main transformer low-pressure side switch, outlet switch, And low-pressure side bus interconnection switch, the incoming switch of regional primary station, high-voltage side bus interconnection switch, main transformer high-pressure side are opened Pass, main transformer low-pressure side switch, outlet switch and low-pressure side bus interconnection switch;The incoming switch of regional secondary substation, high pressure Side bus interconnection switch, main transformer high side switch, main transformer low-pressure side switch and low-pressure side bus interconnection switch;
Transformer, internal strong continune component, comprising: one's respective area load-center substation main transformer, regional primary station main transformer, area two Secondary transforming plant main transformer;
Bus, strong continune component auxiliary parameter, for checking digraph structure, comprising: one's respective area load-center substation high-pressure side is female Line, middle pressure survey bus, low-pressure side bus, regional primary station high-voltage side bus, middle pressure and survey bus, low-pressure side bus, area Secondary substation high-voltage side bus, middle pressure survey bus, low-pressure side bus.
In step S1, it is oriented that corresponding Sequential Elements instantiation is arranged in the operating condition according to acquisition supply network Figure.Include:
The magnanimity supply network network data that will be received judges whether the network message meets according to predetermined information feature vector Feature vector in feature vector table requires to be compared, and sieve takes corresponding Sequential Elements, is instantiated as digraph, for discontented The related data required enough does discard processing.
It is described to use the real-time analytical calculation strong continune component of Depth Priority Algorithm in step S2.Include:
Real-time DFS is used to calculate the SCC of existing supply network the supply network digraph that example dissolves, verifying is by DFS meter The SCC found out is consistent with actual electric network operating condition.
In step S3, the requirement changed according to the method for operation is searched using depth-first
Rope algorithm simulating calculates the completely new strong continune component after changing the method for operation, comprising:
According to the predetermined requirement for changing the method for operation, the simulated operation on original supply network, and according to simulated operation as a result, adopting The completely new strong continune component after changing the method for operation is calculated with DFS algorithm simulating, the SCC after verification changes changes with grid requirements Whether the method for operation afterwards is consistent.
In step S4, it is electrically operated that fast automatic tune electricity order completion tune is issued after the confirmation simulation result is feasible.
A kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts Denso automatically as shown in Figure 2 It sets, comprising:
Acquisition unit 01, for acquiring the mass data of reaction supply network operating condition
Setting unit 02, the magnanimity supply network operating condition data sieve for will receive take corresponding Sequential Elements
Arithmetic element 03 is calculated for DFS
Simulation unit 04, for checking whether the calculated SCC of DFS is consistent with actual electric network operating condition;For emulating Whether grid operation mode meets the requirement of grid operation mode change by the calculated SCC of DFS after changing
Execution unit 05, for controlling relative breaker, execution is adjusted electrically operated automatically.
Wherein: Sequential Elements include:
Breaker, for changing graph structure, comprising: power side breaker, the one's respective area pivot of the power supply point of one's respective area supply network The incoming switch of knob substation, high-voltage side bus interconnection switch, main transformer high side switch, main transformer low-pressure side switch, outlet switch, And low-pressure side bus interconnection switch, the incoming switch of regional primary station, high-voltage side bus interconnection switch, main transformer high-pressure side are opened Pass, main transformer low-pressure side switch, outlet switch and low-pressure side bus interconnection switch;The incoming switch of regional secondary substation, high pressure Side bus interconnection switch, main transformer high side switch, main transformer low-pressure side switch and low-pressure side bus interconnection switch;
Transformer, internal strong continune component, comprising: one's respective area load-center substation main transformer, regional primary station main transformer, area two Secondary transforming plant main transformer;
Bus, strong continune component auxiliary parameter, for checking digraph structure, comprising: one's respective area load-center substation high-pressure side is female Line, middle pressure survey bus, low-pressure side bus, regional primary station high-voltage side bus, middle pressure and survey bus, low-pressure side bus, area Secondary substation high-voltage side bus, middle pressure survey bus, low-pressure side bus.
Device communicates resolver as internal bus using FPGA, and CPU management+protection DSP+FPGA realizes function, largely It calculates, verification, emulate, filtration is completed by CPU management and FPGA.
The FPGA of device judges whether the network message meets the spy in feature vector table according to predetermined information feature vector Sign vector requires to be compared, and sieve takes corresponding Sequential Elements, CPU management real-time verification calculate the SCC that finds out whether with reality Operation of power networks operating condition is consistent, can also as requested, the simulated operation on original supply network, and according to simulated operation as a result, Whether the method for operation after SCC and grid requirements after verification change change is consistent.Even if DSP is protected to protect program in addition to opening Corresponding exit relay is also operated by CPLD, completes to adjust electricity work.
Embodiment
As shown in figure 3, figure 4 and figure 5, wherein dsp chip uses the special of Ya De promise semiconductor (Analog Devices) company DSP handles the ADSP-BF548 of chip Blackfin series, and fpga chip is using Intel (Intel) company 10 GX Series FPGA chip 10CX220 of Cyclone, CPU management use Freescale (freescale) company PowerPC frame The MPC8313 chip of structure, Ethernet control (PHY) chip using Texas Instruments (Texas Instruments) DP83640, fiber optical transceiver use the AFBR-5803 of Avago Technologies (AVAGO) company, and RJ45 network connector is using safe section The TE-8P8C of electronics (TE Connectivity).Their connection type is to construct 10 MII by FPGA (10CX220) to connect Mouthful, wherein interface 1 is connected by internal bus with CPU management, and interface 2 is connected with protection DSP, and remaining 8 MII interfaces are outer Portion's communication interface, each MII interface connect a PHY(DP83640), the PHY(DP83640 of interface 3 to 6) it is separately connected one Fiber optical transceiver (AFBR-5803), fiber optical transceiver are connected to external ethernet optical fiber.The PHY(DP83640 of interface 7 to 10) It is separately connected one, RJ45 network connector (TE-8P8C), RJ45 network connector is connected to external electrical Ethernet.
After the acquisition unit of FPGA receives the network message from external ethernet controller, network message is assisted Layer parsing is discussed, and judges whether the network message meets feature vector table according to the mass data feature vector that CPU management is arranged In feature vector requirement, if not meeting discarding, if met, related effective information is sent in RxRAM.Setting is single Member reads related effective information to the Sequential Elements type that FPGA is arranged according to CPU management in RxRAM and extracts, and will extract Sequential Elements be sent to RxFIFO, and CPU management is sent to by the interface with CPU management.
The arithmetic element of CPU management realizes the reception of Sequential Elements, and according to pre-set supply network topology recursion Figure combines the Sequential Elements example of FPGA transmission to dissolve supply network digraph;The digraph that example goes out is counted using real-time DFS The SCC for calculating existing supply network, result is sent in SRAM, and the simulation unit of CPU management is notified to read the arithmetic element of CPU Calculated SCC;Verifying is compared with power grid actual operating mode in SCC by the simulation unit of CPU;When receiving regulation center tune When electricity order, the computing unit of CPU management simulates behaviour from fortune and according to regulation center tune electricity instruction on original supply network Make, and carry out emulation DFS again according to simulated operation result and calculate, the result of calculating is sent in SRAM, notifies CPU management Simulation unit carry out emulation comparison;Tune electricity order is then generated to protection DSP by protection dsp interface if the verification passes, If verifying does not pass through, by the communication interface with FPGA, tells that verifying does not pass through FPGA, alerted by FPGA and remind O&M people Member.
After the simulation unit emulation that protection DSP receives CPU management passes through order, execution unit is opened, starts to be tune electrician Make, even if while open protection program, power grid security is provided protection against.When adjusting the demand of electricity work to be all satisfied, DSP is protected Corresponding exit relay is operated by CPLD, completes to adjust electricity work
It should be understood that above-mentioned specific embodiment of the invention is used only for exemplary illustration or explains original of the invention Reason, without constituting limitation of the invention.Therefore, that is done without departing from the spirit and scope of the present invention any repairs Change, equivalent replacement, improvement etc., should be included within protection scope of the present invention.Furthermore appended claims purport of the present invention Covering the whole variations fallen into attached claim scope and boundary or this range and the equivalent form on boundary and is repairing Change example.

Claims (10)

1. a kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically automatically, feature exists In, comprising the following steps:
Step S1, the operating condition by acquiring supply network are arranged corresponding Sequential Elements, instantiate digraph;
Step S2, using the real-time analytical calculation strong continune component of Depth Priority Algorithm;
Step S3, according to the requirement that the method for operation changes, after changing the method for operation using Depth Priority Algorithm simulation calculation Completely new strong continune component;
It is electrically operated to issue fast automatic tune electricity order completion tune by step S4 after confirmation simulation result is feasible.
2. the power grid according to claim 1 for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Method for electrically, which is characterized in that step S1 specifically:
The magnanimity supply network operating condition data received are compared, sieve takes corresponding Sequential Elements, has been instantiated as Xiang Tu does discard processing for the related data for being unsatisfactory for requiring.
3. the power grid according to claim 1 for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Method for electrically, which is characterized in that step S2 specifically:
DFS calculating is done to the digraph of supply network instantiation, finds out its SCC, according to the recursive rule prestored, verifying is passed through It is consistent with actual electric network operating condition that DFS, which calculates the SCC found out,.
4. the power grid according to claim 1 for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Method for electrically, which is characterized in that step S3 specifically:
According to the predetermined requirement for changing the method for operation, the simulated operation on original supply network, and according to simulated operation as a result, adopting The completely new strong continune component after changing the method for operation is calculated with DFS algorithm simulating, the SCC after verification changes changes with grid requirements Whether the method for operation afterwards is consistent.
5. a kind of power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts electric installation automatically, feature exists In described device includes:
Acquisition unit, for acquiring the mass data of reaction supply network operating condition;
Setting unit, the magnanimity supply network operating condition data sieve for will receive take corresponding Sequential Elements;
Arithmetic element is calculated for DFS;
Simulation unit, for checking whether the calculated SCC of DFS is consistent with actual electric network operating condition;For simulated grid Whether the method for operation meets the requirement of grid operation mode change by the calculated SCC of DFS after changing;
Execution unit, for controlling relative breaker, execution is adjusted electrically operated automatically.
6. the power grid according to claim 5 for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Electric installation, which is characterized in that Sequential Elements include: breaker, for changing graph structure;Transformer, internal strong continune component;It is female Line, strong continune component auxiliary parameter, for checking digraph structure;
The breaker include: the power side breaker of the power supply point of one's respective area supply network, one's respective area load-center substation into Wiretap, high-voltage side bus interconnection switch, main transformer high side switch, main transformer low-pressure side switch, outlet switch and low-pressure side bus Incoming switch, high-voltage side bus interconnection switch, the main transformer high side switch, main transformer low pressure of interconnection switch, regional primary station Side switch, outlet switch and low-pressure side bus interconnection switch;The incoming switch of regional secondary substation, high-voltage side bus contact Switch, main transformer high side switch, main transformer low-pressure side switch and low-pressure side bus interconnection switch;
The transformer includes: one's respective area load-center substation main transformer, regional primary station main transformer, regional secondary substation master Become;
The bus includes: one's respective area load-center substation high-voltage side bus, middle pressure survey bus, low-pressure side bus, the primary change in area Power station high-voltage side bus, middle pressure survey bus, low-pressure side bus, regional secondary substation high-voltage side bus, middle pressure and survey bus, low pressure Side bus.
7. the power grid according to claim 5 for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Electric installation, which is characterized in that device communicates resolver as internal bus using FPGA, and CPU management+protection DSP+FPGA is realized Function, a large amount of calculating, verification, emulation, filtration are completed by CPU management and FPGA;
CPU management is configured mass data feature vector, the type of Sequential Elements using first pair of interface that FPGA is provided.
8. the power grid according to claim 7 for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Electric installation, which is characterized in that after the acquisition unit of FPGA receives the network message from external ethernet controller, to network Message carries out protocol layer parsing, and judges whether the network message meets according to the mass data feature vector that CPU management is arranged Feature vector requirement in feature vector table, if not meeting discarding, if met, related effective information is sent to In RxRAM;Setting unit reads related effective information to the Sequential Elements type that FPGA is arranged according to CPU management in RxRAM It extracts, the Sequential Elements of extraction is sent to RxFIFO, and CPU management is sent to by the interface with CPU management.
9. the power grid according to claim 7 for being suitable for open loop power supply based on strong continune component depth-first search is adjusted automatically Electric installation, which is characterized in that the arithmetic element of CPU management realizes the reception of Sequential Elements, and according to pre-set power supply network The Sequential Elements example of network topology recursion figure combination FPGA transmission dissolves supply network digraph;The digraph that example goes out is used Real-time DFS calculates the SCC of existing supply network, and result is sent in SRAM, and the simulation unit of CPU management is notified to read CPU The calculated SCC of arithmetic element;Verifying is compared with power grid actual operating mode in SCC by the simulation unit of CPU;When receiving When the tune electricity order of regulation center, the computing unit of CPU management is from fortune and according to regulation center tune electricity instruction, in original supply network Upper simulated operation, and carry out emulation DFS again according to simulated operation result and calculate, the result of calculating is sent in SRAM, is led to Know that the simulation unit of CPU management carries out emulation comparison;Protection DSP hair then is given by protection dsp interface if the verification passes Electricity order is adjusted, if verifying does not pass through, by the communication interface with FPGA, tells that verifying does not pass through FPGA, simultaneously by FPGA alarm Remind operation maintenance personnel;
The simulation unit that protection DSP receives CPU management is emulated by opening execution unit after order, starts to do the electric work of tune, together Even if Shi Kaiqi protects program, power grid security is provided protection against, when adjusting the demand of electricity work to be all satisfied, protection DSP passes through CPLD operates corresponding exit relay, completes to adjust electricity work.
10. the power grid according to claim 7 for being suitable for open loop power supply based on strong continune component depth-first search is automatic Adjust electric installation, it is characterised in that: DSP passes through local bus with CPU management and connect FPGA, and FPGA externally provides 8 100,000,000 nets Network interface, each 100,000,000 network interface connect an ethernet controller;Wherein 4 ethernet controllers are respectively independently connected to One fiber optical transceiver, fiber optical transceiver are connected to external Ethernet optical fiber;Other 4 ethernet controllers are independently connected To respective RJ45 network connector, RJ45 network connector is connected to external ethernet.
CN201810986651.0A 2018-08-28 2018-08-28 The power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically and device automatically Pending CN108988338A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810986651.0A CN108988338A (en) 2018-08-28 2018-08-28 The power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically and device automatically

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810986651.0A CN108988338A (en) 2018-08-28 2018-08-28 The power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically and device automatically

Publications (1)

Publication Number Publication Date
CN108988338A true CN108988338A (en) 2018-12-11

Family

ID=64547978

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810986651.0A Pending CN108988338A (en) 2018-08-28 2018-08-28 The power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically and device automatically

Country Status (1)

Country Link
CN (1) CN108988338A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110299709A (en) * 2019-07-31 2019-10-01 云南电网有限责任公司瑞丽供电局 A kind of flexible cyclization tune method for electrically and device of protection control unified collocation
CN110445108A (en) * 2019-07-31 2019-11-12 云南电网有限责任公司瑞丽供电局 A kind of cyclization tune electric protection control method improving power supply reliability
CN113487268A (en) * 2021-07-26 2021-10-08 亿海蓝(北京)数据技术股份公司 Ship route identification method and device, electronic equipment and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102608450A (en) * 2012-02-24 2012-07-25 江苏凌创电气自动化股份有限公司 Testing and verifying system appropriate for intelligent transformer substation and verifying method
CN102854856A (en) * 2012-08-29 2013-01-02 北京博电新力电气股份有限公司 Controller based on scenario test of secondary equipment of intelligent substation
CN103472736A (en) * 2013-09-24 2013-12-25 广西电网公司 Load modeling device based on real-time disturbance data
CN104218673A (en) * 2014-08-06 2014-12-17 国网上海市电力公司 Automatic intelligent power grid partitioning method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102608450A (en) * 2012-02-24 2012-07-25 江苏凌创电气自动化股份有限公司 Testing and verifying system appropriate for intelligent transformer substation and verifying method
CN102854856A (en) * 2012-08-29 2013-01-02 北京博电新力电气股份有限公司 Controller based on scenario test of secondary equipment of intelligent substation
CN103472736A (en) * 2013-09-24 2013-12-25 广西电网公司 Load modeling device based on real-time disturbance data
CN104218673A (en) * 2014-08-06 2014-12-17 国网上海市电力公司 Automatic intelligent power grid partitioning method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
吴金全: "有向图的强连通分量及应用", 《软件》 *
苗世洪: "基于割点和路径搜索的输电断面快速识别方法", 《电力系统自动化》 *
蔡丽娟: "面向对象技术的电力网络拓扑分析", 《供配电》 *
陈燕: "求强连通分量的几种算法的实现与分析", 《电脑知识与技术》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110299709A (en) * 2019-07-31 2019-10-01 云南电网有限责任公司瑞丽供电局 A kind of flexible cyclization tune method for electrically and device of protection control unified collocation
CN110445108A (en) * 2019-07-31 2019-11-12 云南电网有限责任公司瑞丽供电局 A kind of cyclization tune electric protection control method improving power supply reliability
CN110445108B (en) * 2019-07-31 2021-10-08 云南电网有限责任公司瑞丽供电局 Loop-closing power-adjusting protection control method for improving power supply reliability
CN113487268A (en) * 2021-07-26 2021-10-08 亿海蓝(北京)数据技术股份公司 Ship route identification method and device, electronic equipment and storage medium
CN113487268B (en) * 2021-07-26 2023-07-18 亿海蓝(北京)数据技术股份公司 Ship route identification method and device, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
Wan et al. An adaptive multiagent approach to protection relay coordination with distributed generators in industrial power distribution system
Coffele et al. An adaptive overcurrent protection scheme for distribution networks
CN105070157B (en) A kind of feeder automation simulation training system
CN106159759B (en) A kind of method for automatically generating secondary system of intelligent substation maintenance safety measure
Dai et al. Risk assessment for cyberattack in active distribution systems considering the role of feeder automation
Vyatkin et al. Towards intelligent smart grid devices with IEC 61850 interoperability and IEC 61499 open control architecture
CN108988338A (en) The power grid for being suitable for open loop power supply based on strong continune component depth-first search adjusts method for electrically and device automatically
CN104821662B (en) A kind of various dimensions intelligent error preventing system and method
CN103151839B (en) Intelligent substation test research system
CN104505941B (en) The monitoring system and the simulative running system of intelligent substation network
CN103529708B (en) The pre-operation analogue system of power distribution network and simulating analysis
CN106154113B (en) Active power distribution network distribution feeder automation Fault Locating Method
CN105429137B (en) The method that distribution network closed loop turns power supply
CN109066612B (en) The switching overvoltage calculation method combined based on electromechanical transient and electro-magnetic transient
CN105205244B (en) Loop Closing Operation analogue system based on electromechanics-electromagnetism hybrid simulation technology
CN102760192B (en) Real-time digital simulator-based power system closed loop verifying platform and method
CN108197716A (en) Secondary equipment of intelligent converting station safety measure previews online and anti-error method for early warning
CN103425847B (en) Based on circuit anticipation modernization system and the method for work thereof of dispatching of power netwoks anti-error system
CN106655168A (en) Method and device for building loop closing model of power distribution network
CN109103879A (en) A kind of full dimension closed loop network appraisal procedure
CN105894920A (en) Fault simulation method of using simulation intelligent electric energy meter
CN107203648A (en) One kind visualization maintenance peace arranges system and method
CN113887157A (en) Active distribution network automatic terminal network closed-loop test method based on RTDS
Wan et al. An multi-agent approach to protection relay coordination with distributed generators in industrial power distribution system
CN110299709A (en) A kind of flexible cyclization tune method for electrically and device of protection control unified collocation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211