CN108988318A CN201810621800.3A CN201810621800A CN108988318A CN 108988318 A CN108988318 A CN 108988318A CN 201810621800 A CN201810621800 A CN 201810621800A CN 108988318 A CN108988318 A CN 108988318A
Authority
CN
China
Prior art keywords
unit
node
subregion
starting
restored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810621800.3A
Other languages
Chinese (zh)
Inventor
方嵩
彭嵩
阮志杰
杨涌新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Zhongshan Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Zhongshan Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Zhongshan Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201810621800.3A priority Critical patent/CN108988318A/en
Publication of CN108988318A publication Critical patent/CN108988318A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • Y04S10/52Outage or fault management, e.g. fault detection or location

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of methods of partition recovery containing micro-grid power system, and micro-grid power system will be contained by, which including the following steps:, is reduced to a network topological diagram;Probability and time, calculating subregion decision function value that node to be restored is successfully recovered by different subregions, which are solved, using Mini-routing primarily determines the affiliated subregion of node to be restored;It tests and adjusts to division result;The unit starting sequential optimization model in each subregion is established, Mixed integer linear programming is translated into, is solved using linear programming for solution device ILOG CPLEX;According to division result and unit starting sequential optimization as a result, formulating system black-start scheme.Method of the invention it is achieved that quick subregion and unit starting sequential optimization after having a power failure on a large scale containing micro-grid power system, accelerate system black starting-up process.

Description

A kind of method of partition recovery containing micro-grid power system
Technical field
The present invention relates to black starting-up technical fields, more particularly, to a kind of method of partition recovery containing micro-grid power system.
Background technique
With the development of regional power grid interconnection and extra-high voltage alternating current-direct current engineering, electric network composition is constantly complicated, influences power grid peace Stable factor is increasing entirely, and risk of having a power failure on a large scale increases.Reasonable black-start scheme is formulated to quickly extensive after large-scale blackout Multiple load power supply reduces economic loss and guarantees that social stability is of great significance.There are multiple black starting-up power supplys in system In the case of, subregion usually is carried out to whole network, each subregion independent parallel restores, to improve the feasibility of recovery scheme and reliable Property.
Under the international background of energy shortage, the new energy power generation technologies such as photovoltaic, wind-powered electricity generation and micro-capacitance sensor technology are grown rapidly, Profound influence is produced to conventional electric power system pattern.Do not have the tradition of black start-up ability using microgrid as backup power source transformation Unit can increase the black starting-up power supply of system, alleviate the insufficient embarrassment of regional power grid black starting-up power supply.On this basis to mistake Electric region carries out subregion and helps speed up system black starting-up process using parallel recovery plan.
Existing research is seldom related to the power system blackstart of microgrid participation mainly for the black starting-up of traditional power grid, Parallel recovery plan can not just be implemented in the case where black starting-up power supply is deficient.The optimization of unit starting sequence inside each subregion In the start-up course of rare meter and unit, method for solving mostly uses the intelligent optimization algorithms such as particle swarm algorithm, genetic algorithm, solves Speed is difficult to be protected.
Summary of the invention
The present invention in order to overcome at least one of the drawbacks of the prior art described above, provides a kind of subregion containing micro-grid power system Restoration methods realize quick subregion and unit starting sequential optimization after having a power failure on a large scale containing micro-grid power system, accelerate system Black starting-up process.
In order to solve the above technical problems, the technical solution adopted by the present invention is that: a kind of partition recovery containing micro-grid power system Method, comprising the following steps:
S1. a network topological diagram is reduced to according to the parameter characteristic containing micro-grid power system;
S2. the probability and time that node to be restored is successfully recovered by different black starting-up nodes are solved using Mini-routing, Thus subregion decision function value is calculated, primarily determines the affiliated subregion of node to be restored;
S3. examine power generation capacity and the load of each subregion whether in a basic balance, if there is serious unbalanced situation, Then borderline node is repartitioned;
S4. the unit starting sequential optimization model in each subregion is established, mixed integer linear programming is translated into and asks Topic is solved using linear programming for solution device ILOG CPLEX;
S5. according to unit starting sequential optimization in division result and subregion as a result, formulating system black-start scheme, realization divides Area's parallel recovery.
Further, the simplification step of electric power networks includes: in the S1 step
S11. generator node all in power grid topology model, load bus and power transformation tiny node are abstracted as nothing in figure The node of difference, to same processing can be made with the microgrid of black starting-up;
S12. all transmission lines of electricity and transformer branch are abstracted as the side of Weighted Coefficients in network;
S13. the operating time of the starting time, the recovery time of power transformation tiny node and power equipment of generator node counts Enter the weight on side;
S14. if there is double loop, then merged, ignore shunt capacitance branch.
Further, the step of affiliated subregion of node to be restored is determined in the S2 step include:
S21. obtained point is simplified as start node using node to be restored, obtained node is simplified as mesh using black starting-up power supply Node is marked, is scanned for respectively to different destination nodes from start node, acquires minimal path sets;
S22. non cross link transformation is carried out to minimal path sets using " leave out and leave " algorithm, obtains mutual exclusive minimal path Collection, solves the probability that node to be restored is successfully recovered by different black starting-up nodes, formula are as follows:
In formula, k is node serial number, and z is subregion label, and R (k, z) is k node by the successful probability of z partition recovery, Si' the The mutual exclusive minimal path of i item, m are the item number of non cross link minimal path;
S23. subregion decision function value is calculated, subregion decision function is established as follows:
F (k, z)=α tav(k,z)-βR(k,z)
In formula, tav(k, z) be k node by z partition recovery when average path recovery time, i.e., all roads in minimal path sets The average value of diameter recovery time, α, β are weight coefficient;
S24. the subregion decision function value that node more to be restored is restored by different black starting-up nodes, node to be restored is returned Enter the smallest subregion of subregion decision function value.
Further, the unit starting sequential optimization model in the S4 step in each subregion is as follows:
In formula, MkTo be activated unit quantity in subregion k;PjmaxStablize for unit j and contributes;PjstartStart institute for unit j Need power;tjstartStart the time for unit j.
Further, the Optimized model needs to meet following constraint condition:
1. the linearisation constraint of unit starting process:
In formula, binary decision variableFor limitingValue range, binary decision variableBy secondary variable And ujtIt is converted into a secondary variable,ujtIndicate unit j in the shape of t moment State, t ∈ { 0,1 ..., T }, NkFor black starting-up power supply in subregion k and the total quantity of unit to be restored, l=Nk-Mk+1,Nk-Mk+ 2,…,Nk(black starting-up unit), i=1,2 ..., Nk(all units), j=1,2 ..., Mk(being activated unit), RriFor unit Climbing rate, PimaxFor unit maximum output;
2. the unit starting crash time constrains:
In formula, tjstartFor the starting time of unit j, TCH,jFor unit thermal starting maximum crash time, TCC,jIt is cold for unit Start the minimum critical time;
3. unit starting power constraint:
In formula, RriFor unit climbing rate, PjstartFor unit starting power,When to start climbing from zero moment to unit Between,It contributes the time for set steady;
4. security constraint and microgrid constraint:
Need to consider the energy storage shape of voltage and reactive balance security constraint problem and microgrid when formulating black-start scheme The related constraints such as state, this partially restrained are configured according to the actual demand of safety check.
Compared with prior art, beneficial effect is: one kind method of partition recovery containing micro-grid power system provided by the invention, Microgrid is included in the formulation of power system blackstart scheme, using Paralleled recovery scheme, accelerates system recovering process.It will Inside each subregion unit starting sequential optimization problem is converted into Mixed integer linear programming, model meter and the starting of unit Process can use linear programming for solution device ILOG CPLEX solution, ensure solving speed and feasibility.
Detailed description of the invention
Fig. 1 is the flow chart of the method for partition recovery containing micro-grid power system of the invention.
Fig. 2 is the network topological diagram simplified in the present invention.
Fig. 3 is the search tree that minimal path sets are sought in the present invention.
Fig. 4 is unit output function linearization schematic diagram in the present invention.
Fig. 5 is that unit starting power function linearizes schematic diagram in the present invention.
Specific embodiment
Attached drawing only for illustration, is not considered as limiting the invention;In order to better illustrate this embodiment, attached Scheme certain components to have omission, zoom in or out, does not represent the size of actual product;To those skilled in the art, The omitting of some known structures and their instructions in the attached drawings are understandable.Being given for example only property of positional relationship is described in attached drawing Illustrate, is not considered as limiting the invention.
As shown in Figure 1, a kind of method of partition recovery containing micro-grid power system, comprising the following steps:
Step 1. is reduced to a network topological diagram according to the parameter characteristic containing micro-grid power system;
Wherein, the simplification step of electric power networks includes:
S11. generator node all in power grid topology model, load bus and power transformation tiny node are abstracted as nothing in figure The node of difference, to same processing can be made with the microgrid of black starting-up;
S12. all transmission lines of electricity and transformer branch are abstracted as the side of Weighted Coefficients in network;
S13. the operating time of the starting time, the recovery time of power transformation tiny node and power equipment of generator node counts Enter the weight on side;
S14. if there is double loop, then merged, ignore shunt capacitance branch.
Step 2. using Mini-routing solve probability that node to be restored is successfully recovered by different black starting-up nodes and when Between, subregion decision function value is thus calculated, primarily determines the affiliated subregion of node to be restored;
Wherein it is determined that the step of node to be restored affiliated subregion, includes:
S21. obtained point is simplified as start node using node to be restored, obtained node is simplified as mesh using black starting-up power supply Node is marked, is scanned for respectively to different destination nodes from start node, acquires minimal path sets;
In conjunction with Fig. 2, using point 1 as start node, using point 4 as destination node, successively searched to point 4 from point 1 for root node Rope whole minimal path, search tree are as shown in Fig. 3.By search tree result it is found that putting 1 to the minimal path sets for putting 4 are as follows: [x1x4x7, x1x3x6,x2x5x3x4x7,x2x5x6];
S22. non cross link transformation is carried out to minimal path sets using " leave out and leave " algorithm, obtains mutual exclusive minimal path Collection, solves the probability that node to be restored is successfully recovered by different black starting-up nodes.
Explanation carries out non cross link transformation to minimal path sets and solves node to be restored by some black starting-up section by taking Fig. 2 as an example The process for the probability that point is successfully recovered:
A) minimal path sets matrix S is defined, a n-dimensional vector E is defined to each minimal pathi(x1,x2,…,xn),
B) it calculates
H1=(1 00100 1)
H2=(2 01 101 1)
H3=(21 2 21 1 2)
H4=(2 22222 2)
C) compare HjAnd EjIf HjE in upper certain nonzero element positionsjElement be zero, then by they in HjIn position The descending position for writing down them of number is set, marked as P1,P2,…,Pr.EjTo HjIt is decomposed into two vector Ej(Pr) andE is replaced with 1 and -1 respectivelyjTo flow control Pr0 on position.If Ej(Pr) in there is 1 position to contain any Ei(i < j) all have 1 position, just leave out Ej(Pr), if each EiThere are the position of 1 (- 1) at least one and E in (i < j)j (Pr) in position -1 (1) it is corresponding, be left with Ej(Pr), it is not also left if do not left out, continues to decompose.It is right? Make similar processing.Wherein, " 1 " indicates Plant in good condition, and " -1 " indicates equipment fault, and " 0 " indicates to be free of this equipment.
Fig. 2 finally obtains the minimal path matrix of non cross link are as follows:
D) probability that node to be restored is successfully recovered by different black starting-up nodes is calculated:
In formula, k is node serial number, and z is subregion label, and R (k, z) is k node by the successful probability of z partition recovery, S 'iThe The mutual exclusive minimal path of i item, m are the item number of non cross link minimal path;
Fig. 2 interior joint 1 is expressed as by the probability that the success of node 4 restores:
In formula, p (xi)=piFor equipment i work normally probability,For the probability of equipment i failure.
S23. subregion decision function value is calculated, subregion decision function is established as follows:
F (k, z)=α tav(k,z)-βR(k,z)
In formula, tav(k, z) be k node by z partition recovery when average path recovery time, i.e., all roads in minimal path sets The average value of diameter recovery time, α, β are weight coefficient;
S24. the subregion decision function value that node more to be restored is restored by different black starting-up nodes, node to be restored is returned Enter the smallest subregion of subregion decision function value.
Whether step 3. examines the power generation capacity of each subregion and load in a basic balance, if there is serious unbalanced feelings Condition then repartitions borderline node.
Step 4. establishes the unit starting sequential optimization model in each subregion, is translated into mixed integer linear programming Problem is solved using linear programming for solution device ILOG CPLEX;
Wherein, the unit starting sequential optimization model in each subregion is as follows:
In formula, MkTo be activated unit quantity in subregion k;PjmaxStablize for unit j and contributes;PjstartStart institute for unit j Need power;tjstartStart the time for unit j.
In addition, converting the linearization process of Mixed integer linear programming for nonlinear optimal problem, steps are as follows:
S41. unit output function linearization.As shown in figure 4, introducing binary decision variableBecome with linear decision Amount(starting to climb from zero moment to unit),(unit climbing),(set steady power output) is by unit output function Pigen (t) it is defined as linear quadratic form, expression formula is as follows:
In formula, TictpTo start to synchronous required time, R from unitriFor unit creep speed, PimaxGo out for unit maximum Power, binary decision variableFor limitingValue range;
S42. unit starting power function linearizes.As shown in figure 5, introducing binary decision variableBecome with linear decision Amount(from zero moment to unit starting),(unit starting) is by unit starting power function Pigen(t) it is defined as linear quadratic shape Formula, expression formula are as follows:
S43. T binary decision variable u is introducedjt, will be in above-mentioned formulaFurther conversion, draws Enter binary decision variableWithTwo secondary variables are converted into a secondary variable, expression formula is as follows:
In formula, ujtUnit j is indicated in the state of t moment, 1 has been turned on for unit, and 0 is inactive for unit.
Specifically, Optimized model needs to meet following constraint condition:
1. the linearisation constraint of unit starting process:
In formula, binary decision variableFor limitingValue range, binary decision variableBy secondary variableWith ujtIt is converted into a secondary variable,ujtIndicate unit j t moment state, T ∈ { 0,1 ..., T }, NkFor black starting-up power supply in subregion k and the total quantity of unit to be restored, l=Nk-Mk+1,Nk-Mk+2,…, Nk(black starting-up unit), i=1,2 ..., Nk(all units), j=1,2 ..., Mk(being activated unit), RriFor unit climbing Rate, PimaxFor unit maximum output;
2. the unit starting crash time constrains:
In formula, tjstartFor the starting time of unit j, TCH,jFor unit thermal starting maximum crash time, TCC,jIt is cold for unit Start the minimum critical time;
3. unit starting power constraint:
In formula, RriFor unit climbing rate, PjstartFor unit starting power,When to start climbing from zero moment to unit Between,It contributes the time for set steady;
4. security constraint and microgrid constraint:
Need to consider the energy storage shape of voltage and reactive balance security constraint problem and microgrid when formulating black-start scheme The related constraints such as state, this partially restrained are configured according to the actual demand of safety check.
Step 5. is according to unit starting sequential optimization in division result and subregion as a result, formulating system black-start scheme, in fact Existing Paralleled restores.
Obviously, the above embodiment of the present invention be only to clearly illustrate example of the present invention, and not be pair The restriction of embodiments of the present invention.For those of ordinary skill in the art, may be used also on the basis of the above description To make other variations or changes in different ways.There is no necessity and possibility to exhaust all the enbodiments.It is all this Made any modifications, equivalent replacements, and improvements etc., should be included in the claims in the present invention within the spirit and principle of invention Protection scope within.

Claims (5)

1. a kind of method of partition recovery containing micro-grid power system, which comprises the following steps:
S1. a network topological diagram is reduced to according to the parameter characteristic containing micro-grid power system;
S2. the probability and time that node to be restored is successfully recovered by different black starting-up nodes are solved using Mini-routing, thus Subregion decision function value is calculated, primarily determines the affiliated subregion of node to be restored;
S3. examine power generation capacity and the load of each subregion whether in a basic balance, it is if there is serious unbalanced situation, then right Borderline node is repartitioned;
S4. the unit starting sequential optimization model in each subregion is established, Mixed integer linear programming is translated into, benefit It is solved with linear programming for solution device ILOG CPLEX;
S5. according to unit starting sequential optimization in division result and subregion as a result, formulating system black-start scheme, realization subregion is simultaneously Row restores.
2. one kind method of partition recovery containing micro-grid power system according to claim 1, which is characterized in that the S1 step The simplification step of electric power networks includes: in rapid
S11. generator node all in power grid topology model, load bus and power transformation tiny node are abstracted as indifference in figure Node, to same processing can be made with the microgrid of black starting-up;
S12. all transmission lines of electricity and transformer branch are abstracted as the side of Weighted Coefficients in network;
S13. the operating time of the starting time, the recovery time of power transformation tiny node and power equipment of generator node is included in side Weight;
S14. if there is double loop, then merged, ignore shunt capacitance branch.
3. one kind method of partition recovery containing micro-grid power system according to claim 1, which is characterized in that the S2 step The step of affiliated subregion of node to be restored is determined in rapid include:
S21. obtained point is simplified as start node using node to be restored, obtained node is simplified as target section using black starting-up power supply Point is scanned for respectively to different destination nodes from start node, acquires minimal path sets;
S22. non cross link transformation is carried out to minimal path sets using " leave out and leave " algorithm, obtains mutual exclusive minimal path sets, asks Solve the probability that node to be restored is successfully recovered by different black starting-up nodes, formula are as follows:
In formula, k is node serial number, and z is subregion label, and R (k, z) is k node by the successful probability of z partition recovery, S 'iI-th mutually Incompatible minimal path, m are the item number of non cross link minimal path;
S23. subregion decision function value is calculated, subregion decision function is established as follows:
F (k, z)=α tav(k,z)-βR(k,z)
In formula, tav(k, z) be k node by z partition recovery when average path recovery time, i.e., all paths are extensive in minimal path sets The average value of multiple time, α, β are weight coefficient;
Node to be restored is included into point by the S24. subregion decision function value that node more to be restored is restored by different black starting-up nodes The smallest subregion of area's decision function value.
4. one kind method of partition recovery containing micro-grid power system according to claim 3, which is characterized in that the S4 step Unit starting sequential optimization model in rapid in each subregion is as follows:
In formula, MkTo be activated unit quantity in subregion k;PjmaxStablize for unit j and contributes;PjstartFunction needed for starting for unit j Rate;tjstartStart the time for unit j.
5. one kind method of partition recovery containing micro-grid power system according to claim 4, which is characterized in that the optimization Model needs to meet following constraint condition:
1. the linearisation constraint of unit starting process:
In formula, binary decision variableFor limitingValue range, binary decision variableBy secondary variableAnd ujtTurn Change a secondary variable into,ujtIndicate state of the unit j in t moment, t ∈ { 0,1 ..., T }, NkFor black starting-up power supply in subregion k and the total quantity of unit to be restored, l=Nk-Mk+1,Nk-Mk+2,…,Nk (black starting-up unit), i=1,2 ..., Nk(all units), j=1,2 ..., Mk(being activated unit), RriFor unit climbing rate, PimaxFor unit maximum output;
2. the unit starting crash time constrains:
In formula, tjstartFor the starting time of unit j, TCH,jFor unit thermal starting maximum crash time, TCC,jFor unit cold start-up The minimum critical time;
3. unit starting power constraint:
In formula, RriFor unit climbing rate, PjstartFor unit starting power,To start the time of climbing from zero moment to unit, It contributes the time for set steady;
4. security constraint and microgrid constraint:
Need to consider voltage and reactive balance security constraint problem and the energy storage state of microgrid etc. when formulating black-start scheme Related constraint, this partially restrained are configured according to the actual demand of safety check.
CN201810621800.3A 2018-06-15 2018-06-15 A kind of method of partition recovery containing micro-grid power system Pending CN108988318A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810621800.3A CN108988318A (en) 2018-06-15 2018-06-15 A kind of method of partition recovery containing micro-grid power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810621800.3A CN108988318A (en) 2018-06-15 2018-06-15 A kind of method of partition recovery containing micro-grid power system

Publications (1)

Publication Number Publication Date
CN108988318A true CN108988318A (en) 2018-12-11

Family

ID=64541347

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810621800.3A Pending CN108988318A (en) 2018-06-15 2018-06-15 A kind of method of partition recovery containing micro-grid power system

Country Status (1)

Country Link
CN (1) CN108988318A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110334862A (en) * 2019-06-30 2019-10-15 南京理工大学 Consider the electric system partition zone optimizing algorithm of recovery time
CN111953006A (en) * 2019-05-14 2020-11-17 清华大学 Black start method and system for power system
CN113452021A (en) * 2021-07-06 2021-09-28 武汉大学 Power grid restoration partitioning method considering unit grouping and active power balance

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015090375A1 (en) * 2013-12-18 2015-06-25 Abb Technology Ltd Microgrid black-start
CN105656040A (en) * 2016-03-22 2016-06-08 国网山东省电力公司潍坊供电公司 Power grid restoring capacity calculation method considering black-start process
CN106684906A (en) * 2016-11-23 2017-05-17 国网浙江省电力公司电动汽车服务分公司 Power system parallel recovery method used after blackouts
WO2017132113A1 (en) * 2016-01-25 2017-08-03 S&C Electric Company Energization control for establishing microgrids

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015090375A1 (en) * 2013-12-18 2015-06-25 Abb Technology Ltd Microgrid black-start
WO2017132113A1 (en) * 2016-01-25 2017-08-03 S&C Electric Company Energization control for establishing microgrids
CN105656040A (en) * 2016-03-22 2016-06-08 国网山东省电力公司潍坊供电公司 Power grid restoring capacity calculation method considering black-start process
CN106684906A (en) * 2016-11-23 2017-05-17 国网浙江省电力公司电动汽车服务分公司 Power system parallel recovery method used after blackouts

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
WEI SUN等: "《Optimal Generator Start-Up Strategy for Bulk Power System Restoration》", 《IEEE TRANSACTIONS ON POWER SYSTEMS》 *
林振智等: "《基于复杂网络社团结构的恢复子系统划分算法》", 《电力系统自动化》 *
梁海平等: "《计及节点恢复成功率的黑启动分区恢复方案优化》", 《电工技术学报》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111953006A (en) * 2019-05-14 2020-11-17 清华大学 Black start method and system for power system
CN111953006B (en) * 2019-05-14 2022-01-07 清华大学 Black start method and system for power system
CN110334862A (en) * 2019-06-30 2019-10-15 南京理工大学 Consider the electric system partition zone optimizing algorithm of recovery time
CN110334862B (en) * 2019-06-30 2022-10-04 南京理工大学 Power system partition optimization algorithm considering recovery time
CN113452021A (en) * 2021-07-06 2021-09-28 武汉大学 Power grid restoration partitioning method considering unit grouping and active power balance
CN113452021B (en) * 2021-07-06 2022-06-03 武汉大学 Power grid restoration partitioning method considering unit grouping and active power balance

Similar Documents

Publication Publication Date Title
CN103296677B (en) A kind of online bulk power grid recovers aid decision-making system
CN105098762B (en) A kind of isolated island division methods containing distributed power distribution network
CN106026092B (en) It is a kind of for the power distribution network isolated island division methods containing distributed generation resource
CN106503839B (en) Hierarchical planning method for offshore wind farm annular current collection network
CN105656040B (en) A kind of power system restoration power computational methods for considering black starting-up process
CN107256448B (en) Risk assessment method fusing element level and system level of photovoltaic power station
CN108988318A (en) A kind of method of partition recovery containing micro-grid power system
CN103746366B (en) A kind of power system recovery method based on pitch point importance
CN112491050A (en) Main and distribution network accident recovery processing method based on index set weight
CN106981875A (en) The restoration methods of distribution network failure containing DG of meter and plan isolated island
CN112398678A (en) Operation mode topological structure feature extraction method suitable for multi-source heterogeneous power grid
CN108631278B (en) The Optimal Configuration Method of breaker and fault current limiter in a kind of looped network formula direct-current micro-grid
CN105356466A (en) Layered cooperative control and dynamic decision-making method for large-scale power transmission network frame restoration
CN109768543B (en) Elastic bottom-preserving net rack search modeling method based on mixed integer linear programming
CN113346484B (en) Power distribution network elastic lifting method and system considering transient uncertainty
CN103296678B (en) A kind of online bulk power grid recovers aid decision-making method
Ji et al. Research on self healing technology of smart distribution network based on multi Agent system
CN110061495B (en) Method for identifying core network of power system based on cut constraint
CN114818379B (en) Information physical active power distribution system interactive planning method considering multidimensional uncertainty
CN115549075A (en) Power supply recovery method and system for power distribution network containing micro-grid
CN113991722A (en) Multi-feed-in direct current short-circuit ratio calculation method and device, storage medium and calculation equipment
Zhang Review of the development of power system out-of-step splitting control and some thoughts on the impact of large-scale access of renewable energy
CN112103942B (en) Bottom protection net rack mixed integer programming method considering N-1 safety constraint
Yuan et al. Stochastic optimal operation of the VSC-MTDC system with FACTS devices to integrate wind power
CN117578567A (en) Intelligent power distribution network rapid island division method based on look-ahead greedy algorithm

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211

RJ01 Rejection of invention patent application after publication