CN108960560A - A kind of construction personnel's execution management method therefor - Google Patents
A kind of construction personnel's execution management method therefor Download PDFInfo
- Publication number
- CN108960560A CN108960560A CN201810407407.4A CN201810407407A CN108960560A CN 108960560 A CN108960560 A CN 108960560A CN 201810407407 A CN201810407407 A CN 201810407407A CN 108960560 A CN108960560 A CN 108960560A
- Authority
- CN
- China
- Prior art keywords
- construction
- personnel
- period
- curve
- data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063118—Staff planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Abstract
The present invention relates to a kind of construction personnel's execution management method therefors, including the following contents: 101, constructing the construction data-base of construction trade;102, obtain the construction data of construction personnel: motion bracelet detects construction personnel in the construction data of construction period at interval of the T1 time, while the construction data and current detection number being saved into record sheet;103, it analyzes the construction data of construction personnel and is managed: the construction data record sheet of background process center reading motion bracelet, generate the aim curve for the construction data that time interval is T1, compare aim curve and datum curve variation tendency, in turn, the construction personnel of substantial deviation datum curve is listed to replace the construction period.The present invention obtains the construction data of construction personnel and generates aim curve, compare aim curve and datum curve variation tendency, the construction personnel of substantial deviation datum curve is listed to replace the construction period, and then by repeatedly exchanging so that the construction personnel to be exchanged to the period best to its energy.
Description
Technical field
The present invention relates to building trade technical fields, more particularly to a kind of construction personnel's execution management method therefor.
Background technique
In traditional building trade, general (such as work in three shifts) in such a way that fixed shift takes turns to is constructed, it is specified that one
The fixed period, and then constructed or rested in turn by each construction team, since human body is in each period energy and everyone body
Gap may result in some construction personnel and construct in some construction period with the body of overstrain, and then is easy to cause
Construction safety accident.After all since building operation environment is there are high risk sexual, reasonable arrangement construction time and time of having a rest are needed, it is no
Worker then be may result in since overwork construction causes accident or construction personnel to go to non-one's own side's construction area in the construction period
It rests and causes accident.
Summary of the invention
The purpose of the present invention is to provide a kind of construction personnel's execution management method therefors, can well solve construction personnel's
The construction period arranges unreasonable problem.
To achieve the goals above, the present invention provides following technical schemes:
A kind of construction personnel's execution management method therefor provided by the invention, specifically includes the following contents:
101, construct the construction data-base of construction trade: the motion bracelet detection construction personnel based on built-in acceleration sensor exists
The construction data including acceleration and vibration of hand when construction trains each work post and is constructing period construction data at any time
The datum curve of variation, wherein time interval T1;
102, obtain the construction data of construction personnel: motion bracelet detects construction personnel's applying in the construction period at interval of the T1 time
Number evidence, while the construction data and current detection number being saved into record sheet;
103, it analyzes the construction data of construction personnel and is managed: reading the motion bracelet of construction personnel in background process center
Construction data record sheet generates the aim curve for the construction data that time interval is T1, compares aim curve and datum curve becomes
Change trend lists the construction personnel of substantial deviation datum curve in turn to select in turn to the construction period for having neither part nor lot in construction
When the aim curve of the construction personnel and datum curve being taken to deviate construction of the situation the smallest construction period as the construction personnel
Section.
Further, in step 103, background process center also calculates the period of aim curve, in turn, is based on each construction
The period of the aim curve of personnel forms the new construction team of several period summation equilibriums, and the number between each new construction team
Gap is kept in a certain range.
Compared with prior art, the invention has the following advantages that
A kind of construction personnel's execution management method therefor of the invention, the motion bracelet building based on built-in acceleration sensor is each to be applied
The construction data datum curve of work work post obtains the construction data of construction personnel and generates aim curve, compare aim curve with
Datum curve variation tendency lists the construction personnel of substantial deviation datum curve to replace the construction period, and then by multiple
It exchanges so that the construction personnel to be exchanged to the period best to its energy;The period of aim curve is calculated, each constructor is based on
The period of the aim curve of member forms the new construction team of several period summation equilibriums, so as to applying for each construction team of reasonable distribution
Work ability guarantees that the ability of each construction period is balanced.
Below by embodiment, technical scheme of the present invention will be described in further detail.
Specific embodiment
The embodiment of the present invention is illustrated below, it should be understood that embodiment described herein be merely to illustrate and
It explains the present invention, is not intended to limit the present invention.
Embodiment 1
A kind of construction personnel's execution management method therefor provided in this embodiment, specifically includes the following contents:
Step 101, the construction data-base for constructing construction trade: the motion bracelet based on built-in acceleration sensor detects constructor
Member in construction hand include acceleration and vibration construction data, train each work post construction period construction data with
The datum curve of time change, wherein time interval T1.
Step 102, the construction data for obtaining construction personnel: motion bracelet detects construction personnel at interval of the T1 time and is constructing
The construction data of period, while the construction data and current detection number being saved into record sheet.
Step 103, the construction data for analyzing construction personnel are simultaneously managed: the fortune of background process center reading construction personnel
It starts the construction data record sheet of ring, generates the aim curve for the construction data that time interval is T1, compare aim curve and base
Directrix curve variation tendency lists the construction personnel of substantial deviation datum curve in turn so as to the construction period for having neither part nor lot in construction,
In turn, the aim curve and datum curve for choosing the construction personnel deviate the situation the smallest construction period as the construction personnel's
It constructs the period.
In step 103, background process center also calculates the period of aim curve, in turn, the mesh based on each construction personnel
The period of mark curve forms the new construction team of several period summation equilibriums, and the number gap between each new construction team is kept
In a certain range (within the people of such as 1,3 or 5).
Motion bracelet based on built-in acceleration sensor constructs the construction data datum curve of each construction trade, obtains
The construction data of construction personnel simultaneously generates aim curve, compares aim curve and datum curve variation tendency, lists substantial deviation
The construction personnel of datum curve is exchanged the construction personnel to its essence by repeatedly exchanging to replace the construction period
The power best period;The period of aim curve is calculated, construction ability is represented with this, aim curve based on each construction personnel
Period form the new construction teams of several period summation equilibriums, so as to the construction ability of each construction team of reasonable distribution, guarantee
The ability of each construction period is balanced, conducive to stable construction rate is kept.
It should be appreciated that the above embodiment of the present invention and example, be to be not intended to limit this hair for description and interpretation purpose
Bright range.The scope of the present invention is defined by claim, rather than by above-described embodiment and example definition.
Claims (2)
1. a kind of construction personnel's execution management method therefor, which is characterized in that specifically include the following contents:
101, construct the construction data-base of construction trade: the motion bracelet detection construction personnel based on built-in acceleration sensor exists
The construction data including acceleration and vibration of hand when construction trains each work post and is constructing period construction data at any time
The datum curve of variation, wherein time interval T1;
102, obtain the construction data of construction personnel: motion bracelet detects construction personnel's applying in the construction period at interval of the T1 time
Number evidence, while the construction data and current detection number being saved into record sheet;
103, it analyzes the construction data of construction personnel and is managed: reading the motion bracelet of construction personnel in background process center
Construction data record sheet generates the aim curve for the construction data that time interval is T1, compares aim curve and datum curve becomes
Change trend lists the construction personnel of substantial deviation datum curve in turn to select in turn to the construction period for having neither part nor lot in construction
When the aim curve of the construction personnel and datum curve being taken to deviate construction of the situation the smallest construction period as the construction personnel
Section.
2. a kind of construction personnel's execution management method therefor according to claim 1, which is characterized in that in the step 103, backstage
Processing center also calculates the period of aim curve, and in turn, the period of the aim curve based on each construction personnel forms several
The new construction team of period summation equilibrium, and the number gap between each new construction team is kept in a certain range.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810407407.4A CN108960560A (en) | 2018-04-28 | 2018-04-28 | A kind of construction personnel's execution management method therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810407407.4A CN108960560A (en) | 2018-04-28 | 2018-04-28 | A kind of construction personnel's execution management method therefor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108960560A true CN108960560A (en) | 2018-12-07 |
Family
ID=64499082
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810407407.4A Withdrawn CN108960560A (en) | 2018-04-28 | 2018-04-28 | A kind of construction personnel's execution management method therefor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108960560A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109670795A (en) * | 2018-12-28 | 2019-04-23 | 广州易宝信息技术有限公司 | Project management system based on big data |
-
2018
- 2018-04-28 CN CN201810407407.4A patent/CN108960560A/en not_active Withdrawn
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109670795A (en) * | 2018-12-28 | 2019-04-23 | 广州易宝信息技术有限公司 | Project management system based on big data |
CN109670795B (en) * | 2018-12-28 | 2023-06-09 | 广州易宝信息技术有限公司 | Engineering management system based on big data |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Bromley | 1 Constructing Apocalypticism: Social and Cultural Elements of Radical Organization | |
Ismail et al. | Leadership in construction: Leadership styles practiced in construction project–A review | |
CN108960560A (en) | A kind of construction personnel's execution management method therefor | |
Hollnagel | Becoming resilient | |
CN109636789A (en) | The part of rail clip based on image segmentation lacks detection method and device | |
Thareja et al. | The quality brilliance thru’brilliant people | |
Crabtree | Alberto Vergara, La danza hostil: poderes subnacionales y Estado central en Bolivia y Perú (1952–2012)(Lima: Instituto de Estudios Peruanos, 2015), pp. 308, pb. | |
Noer | Henry Kissinger's Philosophy of History | |
Huber | “When I get that feeling…”-Emotion and Emancipation in Childhood and Youth | |
Yates | Uncertainty and chaos. | |
English | Six Sigma and Total Information Quality Management (TIQM); TIQM is a quality management system that focuses on business effectiveness and customer satisfaction, whether performed as a Six Sigma project or not. | |
Ting | Research of Campus Security Awareness Diffusion Based on Lotka-Volterra Model | |
Modis | Reply to Martino's comments on “The normal, the natural, and the harmonic” | |
Ward | Exploring the benefit of participatory drama and storytelling workshops for people with young onset dementia and their carers | |
Sen et al. | Columnas: The Honors Program Newsletter at Bentley University | |
Butsaban | A comparative study of economic development planning organizations of South Korea and Thailand during 1960-1980 | |
Decelle et al. | The Restricted Boltzmann Machine: from the statistical physics of disordered systems to a practical and interpretative generative machine learning. | |
KOYAMA | Leadership in Diversity Management Implementation of PM Theory | |
Weisskopf | Book Review: Slaves to Fashion: Poverty and Abuse in the New Sweatshops Robert JS Ross; Ann Arbor: University of Michigan Press, 2004, xii+ 396 pp., $19.95 (paperback) | |
Guo et al. | Efficiency-centered maintenance (EFCM) | |
London | 4.13 Can Meta-Interpretive Learning outperform Deep Reinforcement Learning of Evaluable Game Strategies? | |
Kennedy et al. | Prediction variance properties of bridge designs | |
Pringle | WORKPOINT MANAGEMENT | |
CN107590649A (en) | A kind of technology forms a partnership management mode | |
Sanders | Strategic database planning. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20181207 |
|
WW01 | Invention patent application withdrawn after publication |