CN108957670A - A kind of working procedure of lightguide cable link - Google Patents

A kind of working procedure of lightguide cable link Download PDF

Info

Publication number
CN108957670A
CN108957670A CN201710407269.5A CN201710407269A CN108957670A CN 108957670 A CN108957670 A CN 108957670A CN 201710407269 A CN201710407269 A CN 201710407269A CN 108957670 A CN108957670 A CN 108957670A
Authority
CN
China
Prior art keywords
optical cable
cable
optical
length
fiber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710407269.5A
Other languages
Chinese (zh)
Inventor
孙朝晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhe Tian Communication Engineering Co Ltd
Original Assignee
Zhejiang Zhe Tian Communication Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zhe Tian Communication Engineering Co Ltd filed Critical Zhejiang Zhe Tian Communication Engineering Co Ltd
Priority to CN201710407269.5A priority Critical patent/CN108957670A/en
Publication of CN108957670A publication Critical patent/CN108957670A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G02OPTICS
    • G02BOPTICAL ELEMENTS, SYSTEMS OR APPARATUS
    • G02B6/00Light guides; Structural details of arrangements comprising light guides and other optical elements, e.g. couplings
    • G02B6/46Processes or apparatus adapted for installing or repairing optical fibres or optical cables
    • GPHYSICS
    • G02OPTICS
    • G02BOPTICAL ELEMENTS, SYSTEMS OR APPARATUS
    • G02B6/00Light guides; Structural details of arrangements comprising light guides and other optical elements, e.g. couplings
    • G02B6/46Processes or apparatus adapted for installing or repairing optical fibres or optical cables
    • G02B6/48Overhead installation
    • GPHYSICS
    • G02OPTICS
    • G02BOPTICAL ELEMENTS, SYSTEMS OR APPARATUS
    • G02B6/00Light guides; Structural details of arrangements comprising light guides and other optical elements, e.g. couplings
    • G02B6/46Processes or apparatus adapted for installing or repairing optical fibres or optical cables
    • G02B6/50Underground or underwater installation; Installation through tubing, conduits or ducts

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Light Guides In General And Applications Therefor (AREA)

Abstract

The invention belongs to communication construction technical fields, refer in particular to a kind of working procedure of lightguide cable link, it is examined including single-deck, route repetition measurement, optical cable matches disk, routing prepares, laying is laid, connect installation and relaying measurement, single-deck is examined: the collection of single-deck data, the repetition measurement of cable length, the loss measurement of optical cable single-deck and the insulation of optical cable protective layer check and the inspection of other related equipment, optical cable after inspection, related equipment should keep a record, cable jacket stripping is handled, the strengthening core of optical cable and metal sheath connecting processing, the connecting of optical fiber, the monitoring that optical fiber is continuously lost;7th step, optical fiber remain the receiving processing of length, the encapsulation process of fiber cable joint sheath, the installation of fiber cable joint is fixed, advantage is: the step of working procedure of optical cable, is simple, the construction period of optical cable is greatly shortened in the case where ensuring the construction quality, human and material resources and financial resources are greatly saved, the economic benefit of engineering is significantly improved.

Description

A kind of working procedure of lightguide cable link
Technical field
The invention belongs to communication construction technical fields, refer in particular to a kind of working procedure of lightguide cable link.
Background technique
Currently, the step of construction method of traditional lightguide cable link is various, in order to ensure construction quality, construction period compares It is long, lead to optical cable construction inefficiency, needs to spend more human and material resources and financial resources.
Summary of the invention
The object of the present invention is to provide a kind of working procedures of lightguide cable link.
The object of the present invention is achieved like this:
A kind of working procedure of lightguide cable link, including single-deck is examined, routing repetition measurement, optical cable prepare with disk, routing, laying cloth It puts, connect installation and relaying measurement,
(1) single-deck is examined: the collection of single-deck data, the repetition measurement of cable length, optical cable single-deck loss measurement and optical cable shield The insulation of layer checks and the inspection of other related equipment, and the optical cable, related equipment after inspection should keep a record, and in cable disk subscript Listed price number, outer end end not, length, formula and use paragraph;
(2) repetition measurement: alignment is routed: setting starting point, turning, middle straight line bar;Ranging: 100 meters or 50 meters measurement ground Actual range;Staking: it beats for 100 meters and counts stake, 1000 meters are played emphasis stake, turning marking machine stake;Scribing line: lime powder or lime are used Powder scribing line positioning;Draw: urban district is drawn with 1: 500 or 1: 1000, and countryside is drawn with 1: 2000, and plane is drawn with 1: 500-5000 System, section are drawn with 1: 50-100;Registration: length, position, drawing, facility, protection and the data information of reinforcing;
(3) optical cable matches disk: the calculating for laying length of configuration direction and optical cable, and the length that lays of optical cable is that L=L buries+L The slope pipe+L frame+L water+L, L bury as optical fiber cable for direct burial lay length, and L pipe is duct optical cable lay length, and L frame is that aerial optical cable is laid Length, L water are subaqueous cable lay length, and the slope L is climbing fiber cable laying length;
(4) routing prepares;
(5) laying is laid: the erection of suspension type optical cable: respectively being installed and is led at the beginning of reel side and the terminal of traction side One large size pulley or snatch block are installed to rope and two wire guide pulley wheels, and in the suitable position of electric pole, then on messenger wire One guide pulley is installed every 20~30m, one guide pulley of every installation, which takes advantage of a situation traction rope, penetrates guide pulley, takes people Work or dragger are drawn in end point, and optical cable traction finishes, then are hung optical cable in messenger wire with Optical hanger by one end On, remove guide pulley;
Or wound form is set up: when optical cable laying is at electric pole, operator is served with the lifting seat of truck, it is complete Binding curved at stretching on bar, fixed and move on to optical cable wrapping machine on bar installs, and optical cable wrapping machine is rolled by a friction Wheel drives binding casket to rotate around messenger wire and optical cable, realizes optical cable laying, around, prick and be once automatically performed;
(6) connect installation: the first step gets out optical cable and related utensil;Second step determines splice locations;Third step, general The processing of cable jacket stripping;4th step, the strengthening core of optical cable and metal sheath connecting processing;The connecting of 5th step, optical fiber;6th The monitoring that step, optical fiber are continuously lost;7th step, optical fiber remain the receiving processing of length;The sealing of 8th step, fiber cable joint sheath Processing;The installation of 9th step, fiber cable joint is fixed;
(7) relaying measurement: the test of the characteristic test of optical fiber complete attenuation and copper wire electrical property.
In the above-mentioned technical solutions, the laying is laid in working procedure, and the bending radius of optical cable should be not less than optical cable 15 times of outer diameter, work progress should be not less than 20 times;The maximum allowable tension of optical cable is not to be exceeded in the tractive force for laying optical cable 80%, moment maximum drawbar pull must not exceed the maximum allowable tension of optical cable, and main tractive force acts on the reinforcement of optical cable On core.
In the above-mentioned technical solutions, in the connecting installation process, fiber cable joint is remained and light in connection protective cap Fine remaining should be stopped, and optical cable part-remaining is generally no less than 4m, and final remaining length should be no less than 60cm in connection protective cap.
The present invention is prominent and beneficial compared with prior art to be had the technical effect that
1, the step of working procedure of optical cable of the invention is simple, and optical cable is greatly shortened in the case where ensuring the construction quality Construction period, greatly save human and material resources and financial resources, significantly improve the economic benefit of engineering.
Specific embodiment
With specific embodiment, the invention will be further described below:
A kind of working procedure of lightguide cable link, including single-deck is examined, routing repetition measurement, optical cable prepare with disk, routing, laying cloth It puts, connect installation and relaying measurement,
(1) single-deck is examined: the collection of single-deck data, the repetition measurement of cable length, optical cable single-deck loss measurement and optical cable shield The insulation of layer checks and the inspection of other related equipment, and the optical cable, related equipment after inspection should keep a record, and in cable disk subscript Listed price number, outer end end not, length, formula and use paragraph;
Optical cable is before laying, it is necessary to single-deck inspection is carried out, to specification, the journey of the optical cable and connection equipment of transporting to scene Formula, quantity checked, checked, the measurement of visual examination and photoelectricity key property, and confirmation optical cable, the quantity of equipment, quality reach To design document or contracted related requirement, the single-deck of optical cable is examined, to duration, the construction quality for ensuring engineering, to guarantor In communication quality, economic benefit of engineering, maintenance use and the route service life of card from now on, there is immeasurable influence.
(2) repetition measurement: alignment is routed: setting starting point, turning, middle straight line bar;Ranging: 100 meters or 50 meters measurement ground Actual range;Staking: it beats for 100 meters and counts stake, 1000 meters are played emphasis stake, turning marking machine stake;Scribing line: lime powder or lime are used Powder scribing line positioning;Draw: urban district is drawn with 1: 500 or 1: 1000, and countryside is drawn with 1: 2000, and plane is drawn with 1: 500-5000 System, section are drawn with 1: 50-100;Registration: length, position, drawing, facility, protection and the data information of reinforcing;
The routing repetition measurement of lightguide cable link, is the top priority after lightguide cable link engineering formally goes into operation, and repetition measurement is with construction drawing Be designed as foundation, essential measurement, review carried out to routing along the line, with determine fiber cable laying specific route location, zhang Measure the correct distance on ground, provide necessary data with disk, laying and protection location etc. for optical cable, to it is high-quality, complete work on schedule The construction task of journey plays guarantee effect.
(3) optical cable matches disk: the calculating for laying length of configuration direction and optical cable, and the length that lays of optical cable is that L=L buries+L The slope pipe+L frame+L water+L, L bury as optical fiber cable for direct burial lay length, and L pipe is duct optical cable lay length, and L frame is that aerial optical cable is laid Length, L water are subaqueous cable lay length, and the slope L is climbing fiber cable laying length;Optical cable with disk be for reasonable employment optical cable, It reduces fiber cable joint and reduces splicing loss, achieve the purpose that save optical cable and improve fiber-optic transmission project quality.
(4) routing prepares;
(5) laying is laid: the erection of suspension type optical cable: respectively being installed and is led at the beginning of reel side and the terminal of traction side One large size pulley or snatch block are installed to rope and two wire guide pulley wheels, and in the suitable position of electric pole, then on messenger wire One guide pulley is installed every 20~30m, one guide pulley of every installation, which takes advantage of a situation traction rope, penetrates guide pulley, takes people Work or dragger are drawn in end point, and optical cable traction finishes, then are hung optical cable in messenger wire with Optical hanger by one end On, remove guide pulley;
Or wound form is set up: when optical cable laying is at electric pole, operator is served with the lifting seat of truck, it is complete Binding curved at stretching on bar, fixed and move on to optical cable wrapping machine on bar installs, and optical cable wrapping machine is rolled by a friction Wheel drives binding casket to rotate around messenger wire and optical cable, realizes optical cable laying, around, prick and be once automatically performed;Winding method sets up both quality It is good and laborsaving time saving, become a kind of ideal erection mode, reel is erected with hydraulic jack bracket in truck rear portion, truck It slowly moves forward, optical cable is sent out by delivery hose and guide, and the draught line being also secured on guide pulls winding Machine is mobile with vehicle, this form of construction work saving of labor, time saving, laborsaving, and it is very high to set up efficiency.
(6) connect installation: the first step gets out optical cable and related utensil;Second step determines splice locations;Third step, general The processing of cable jacket stripping;4th step, the strengthening core of optical cable and metal sheath connecting processing;The connecting of 5th step, optical fiber;6th The monitoring that step, optical fiber are continuously lost;7th step, optical fiber remain the receiving processing of length;The sealing of 8th step, fiber cable joint sheath Processing;The installation of 9th step, fiber cable joint is fixed;
Before cable connection, formula, the end that should check optical cable be not errorless;Optical cable should maintain a good state;Optical fiber transmission property Well, sheath insulation against ground is qualified;Connection protective cap inner fiber serial number should make permanent marker, when the optical cable of both direction is from connecing When end protective cover the same side enters, reply cable end does not make unified permanent marks;Cable connection should create good building ring Border, generally should the operation in vehicle or connector tent, to prevent dust from influencing: sleet sky construction open work should be avoided;When When environment temperature is lower than zero degree, temperature-boosting measure should be taken, to ensure the flexibility of optical fiber and the normal work of welder, and The normal operating of construction personnel;The junction loss of fibre-optical splice should be lower than internal control index, the average connection damage of every optical-fibre channel Consumption, should reach the specified value of design document.
(7) relaying measurement: the test of the characteristic test of optical fiber complete attenuation and copper wire electrical property.
Above-mentioned laying is laid in working procedure, and the bending radius of optical cable should be not less than 15 times of cable outer diameter, is constructed Journey should be not less than 20 times;The tractive force for laying optical cable is not to be exceeded the 80% of the maximum allowable tension of optical cable, moment maximum drawbar pull It must not exceed the maximum allowable tension of optical cable, and main tractive force acts on the strengthening core of optical cable.
In above-mentioned connecting installation process, fiber cable joint is remaining and the remaining of connection protective cap inner fiber should be stopped, light Cable is remaining to be generally no less than 4m, and final remaining length should be no less than 60cm in connection protective cap.
Above-described embodiment is only presently preferred embodiments of the present invention, is not limited the scope of the invention according to this, therefore: it is all according to The equivalence changes that structure of the invention, shape, principle are done, should all be covered by within protection scope of the present invention.

Claims (3)

1. a kind of working procedure of lightguide cable link, it is characterised in that: examined including single-deck, routing repetition measurement, optical cable are with disk, routing standard Standby, laying lays, connects installation and relaying measurement,
(1) single-deck is examined: the collection of single-deck data, the repetition measurement of cable length, optical cable single-deck loss measurement and optical cable protective layer Insulation checks and the inspection of other related equipment, and the optical cable, related equipment after inspection should keep a record, and in cable disk subscript listed price Number, outer end end not, length, formula and use paragraph;
(2) repetition measurement: alignment is routed: setting starting point, turning, middle straight line bar;Ranging: 100 meters or 50 meters measurement ground are practical Distance;Staking: it beats for 100 meters and counts stake, 1000 meters are played emphasis stake, turning marking machine stake;Scribing line: it is drawn with lime powder or pulverized limestone Line positioning;Draw: urban district is drawn with 1: 500 or 1: 1000, and countryside is drawn with 1: 2000, and plane is drawn with 1: 500-5000, is broken It is drawn with 1: 50-100 in face;Registration: length, position, drawing, facility, protection and the data information of reinforcing;
(3) optical cable matches disk: the calculating for laying length of configuration direction and optical cable, and the length that lays of optical cable is that L=L buries+L pipe+L The slope frame+L water+L, L bury as optical fiber cable for direct burial lay length, and L pipe is duct optical cable lay length, and L frame is aerial optical cable lay length, L water is subaqueous cable lay length, and the slope L is climbing fiber cable laying length;
(4) routing prepares;
(5) laying is laid: the erection of suspension type optical cable: respectively installing guide line at the beginning of reel side and the terminal of traction side With two wire guide pulley wheels, and one large size pulley or snatch block are installed in the suitable position of electric pole, then on messenger wire every 20~30m install a guide pulley, one guide pulley of every installation, which takes advantage of a situation traction rope, penetrates guide pulley, take manually or Person's dragger is drawn in end point, and optical cable traction finishes, then is hung optical cable on messenger wire with Optical hanger by one end, is taken Lower guide pulley;
Or wound form is set up: when optical cable laying is at electric pole, being served operator with the lifting seat of truck, is completed bar On curved, the fixed binding and move on to optical cable wrapping machine on bar of stretching install, optical cable wrapping machine passes through a friction idler wheel band Dynamic binding casket is rotated around messenger wire and optical cable, realizes optical cable laying, around, prick and be once automatically performed;
(6) connect installation: the first step gets out optical cable and related utensil;Second step determines splice locations;Third step, by optical cable The processing of sheath stripping;4th step, the strengthening core of optical cable and metal sheath connecting processing;The connecting of 5th step, optical fiber;6th step, The monitoring that optical fiber is continuously lost;7th step, optical fiber remain the receiving processing of length;8th step, fiber cable joint sheath sealing at Reason;The installation of 9th step, fiber cable joint is fixed;
(7) relaying measurement: the test of the characteristic test of optical fiber complete attenuation and copper wire electrical property.
2. a kind of working procedure of lightguide cable link according to claim 1, it is characterised in that: the laying lays construction In process, the bending radius of optical cable should be not less than 15 times of cable outer diameter, and work progress should be not less than 20 times;Lay leading for optical cable The 80% of the maximum allowable tension of optical cable is not to be exceeded in gravitation, and moment maximum drawbar pull must not exceed the maximum allowable tension of optical cable, And main tractive force acts on the strengthening core of optical cable.
3. a kind of working procedure of lightguide cable link according to claim 1, it is characterised in that: the connecting installation In process, fiber cable joint is remaining and the remaining of connection protective cap inner fiber should be stopped, and optical cable part-remaining is generally no less than 4m, connection protective cap Interior final remaining length should be no less than 60cm.
CN201710407269.5A 2017-05-19 2017-05-19 A kind of working procedure of lightguide cable link Pending CN108957670A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710407269.5A CN108957670A (en) 2017-05-19 2017-05-19 A kind of working procedure of lightguide cable link

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710407269.5A CN108957670A (en) 2017-05-19 2017-05-19 A kind of working procedure of lightguide cable link

Publications (1)

Publication Number Publication Date
CN108957670A true CN108957670A (en) 2018-12-07

Family

ID=64495028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710407269.5A Pending CN108957670A (en) 2017-05-19 2017-05-19 A kind of working procedure of lightguide cable link

Country Status (1)

Country Link
CN (1) CN108957670A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109814221A (en) * 2019-03-18 2019-05-28 合肥鎏通网络科技有限公司 A kind of optical cable telecommunication line is sunken cord preprocess method
CN111965777A (en) * 2020-06-30 2020-11-20 上海宝冶集团有限公司 Protective binding laying method for temperature measurement sensor optical cable

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110001100A1 (en) * 2009-07-06 2011-01-06 Hien Electric Industries, Ltd. Tool and method for installing new cable
CN103219674A (en) * 2013-05-08 2013-07-24 内蒙古兴泰建筑有限责任公司 Laying method of optical cable and wire cable
CN104746874A (en) * 2015-03-25 2015-07-01 成龙建设集团有限公司 Construction site online safety monitoring system construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110001100A1 (en) * 2009-07-06 2011-01-06 Hien Electric Industries, Ltd. Tool and method for installing new cable
CN103219674A (en) * 2013-05-08 2013-07-24 内蒙古兴泰建筑有限责任公司 Laying method of optical cable and wire cable
CN104746874A (en) * 2015-03-25 2015-07-01 成龙建设集团有限公司 Construction site online safety monitoring system construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙颖: "《光纤通信》", 31 August 2014 *
赵继勇 等: "《光缆线路工程》", 31 December 1992 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109814221A (en) * 2019-03-18 2019-05-28 合肥鎏通网络科技有限公司 A kind of optical cable telecommunication line is sunken cord preprocess method
CN111965777A (en) * 2020-06-30 2020-11-20 上海宝冶集团有限公司 Protective binding laying method for temperature measurement sensor optical cable

Similar Documents

Publication Publication Date Title
CN107792790A (en) Installation and application for the aerial cableway of mountain region construction material transport
CN104555737B (en) The telecommunication of overhead and gantry cranes and position detecting device
CN108957670A (en) A kind of working procedure of lightguide cable link
CN103241586A (en) Opened cable conveyor, transformation method and novel cable laying construction method
KR101314638B1 (en) Electric wire tension method using portable winch
CN105527683B (en) A kind of outdoor optical cable jumper and its laying method
CN102593759B (en) One-pulling-two expansion and construction process of large-section lead
JP2011015585A (en) Device and method for installing new cable
CN205210354U (en) Air -sweeping type optical cable branch box
CN204256230U (en) A kind of self-supporting skeleton type leading-in optic cable
JPS6267505A (en) Method for laying optical cable to aerial
CN205484949U (en) Optical fiber patch cord is used to open air
CN107167891B (en) Optical cable operation and maintenance device
CN102619339B (en) Construction method for multi-beam steel stranded wires to pass through long and thin narrow space at high altitude
CN211089984U (en) Communication system for long and large tunnel construction
CN204666897U (en) A kind of buried monitoring connector box
CN207652599U (en) Web-transporting device applied to underground workshop
CN202393957U (en) Butterfly-shaped introduced optical cable for pipeline
CN102147515A (en) Optical cable line interlayer embracing type disc reserving frame
CN217954814U (en) Optical cable laying device
CN206421075U (en) Novel optical cable connector box and remaining cable protection device
CN206906665U (en) Wound form fixture and its covered wire cable make somebody a mere figurehead frock
CN209861051U (en) Pipeline camera device
KR20170067983A (en) Electric Power Transmission Cable Laying Method Between Long Span Tower
CN104422986A (en) Optical fiber transmission line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181207

WD01 Invention patent application deemed withdrawn after publication