CN108952771A - Existing rigid structures zero are worn under one kind deforms construction method - Google Patents

Existing rigid structures zero are worn under one kind deforms construction method Download PDF

Info

Publication number
CN108952771A
CN108952771A CN201710388603.7A CN201710388603A CN108952771A CN 108952771 A CN108952771 A CN 108952771A CN 201710388603 A CN201710388603 A CN 201710388603A CN 108952771 A CN108952771 A CN 108952771A
Authority
CN
China
Prior art keywords
zero
excavation
under
deformation
rigid structures
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710388603.7A
Other languages
Chinese (zh)
Inventor
张双双
赵宏威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201710388603.7A priority Critical patent/CN108952771A/en
Publication of CN108952771A publication Critical patent/CN108952771A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

Existing rigid structures zero are worn under one kind deforms construction method, it is characterized by: wearing existing rigid structures zero under described deforms construction method, under wear before the external slip casting of excavation, under wear section excavation internal injection realize " earlier zero deformation of excavation '; automation deformation monitoring is passed through using jack top power in excavation; pass through jack top power and realize " compensation jacking " in excavating; realize zero deformation in excavating; its after-pouring secondary lining realizes the construction for tightly cutting existing rigid structures " zero deformation ".Advantages of the present invention: wearing existing rigid structures zero and deform construction method under of the present invention, realizes the control target of zero deformation using slip casting plus step excavation and jack that compensation deformation is arranged.Construction is simple, it is easy to operate, the safety for wearing construction is improved down, can be used in each engineering construction.

Description

Existing rigid structures zero are worn under one kind deforms construction method
Technical field
The present invention relates to
Background technique
Currently, both wired construction work closely has a large capacity and a wide range, how to realize down and wear " zero of existing rigid building in construction Deformation " is the critical issue for needing to solve in construction.
Summary of the invention
The purpose of the present invention is realizing zero deformation of rigid building, using slip casting plus step excavation and compensation deformation is set Jack realize control target, provided and worn existing rigid structures zero deformation construction method under one kind.
The present invention provides wear existing rigid structures zero under one kind to deform construction method, it is characterised in that: under described Wear existing rigid structures zero and deform construction method, under wear before the external slip casting of excavation, under wear the excavation internal injection of section and realize " earlier zero deformation of excavation ', pass through jack top power by automation deformation monitoring using jack top power and realize in excavation " compensation jacking " in excavation, realizes zero deformation in excavating, after-pouring secondary lining, realizes and tightly cuts existing rigidity and construct The construction of object " zero deformation ".
Before wearing under, the soil body carries out grouting and reinforcing within the scope of 2 meters outside outline excavation;Just branch is all made of profile steel frame, indulges It is 0.5m to spacing;Just branch is with a thickness of 35cm, two lining tops, base plate thickness 80cm, side wall thicknesses 70cm;
Under wear the deep hole grouting of section;Under wear building up station construction before, first to the soil needed below building up station in reinforcing scope Body carries out advanced deep hole grouting reinforcing, and deep hole grouting carries out in two times in the longitudinal direction, reinforces 16m, the overlap joint of slip casting twice for the first time 2m, range of grouting be tunnel excavation line within the scope of and outer 2m within the scope of soil layer;Deep hole grouting uses cement-silicate dual slurry, just Pressure is 0.5~0.75MPa, final pressure 1.0MPa;After the injected hole of one slip casting section has all been infused, bores 2~3 holes and slip casting is imitated Fruit carries out coring inspection, it is desirable that test specimen soil body unconfined compressive strength is not less than 0.8MPa.
Under wear section tunnel excavation using 4 pilot tunnel step excavations, each pilot tunnel is using performed core-soil sidesteps excavation;Just branch It is used uniformly profile steel frame, along excavation one row's 120t self-locking jack of longitudinal every 1.5 meters of settings;The side wall at station is worn under One row's jack is set with reversed beam position;After preliminary bracing closing cyclization, apply and just push up power, makes just to prop up and both wired base tops Tightly.
The automatic monitoring implemented in work progress is implemented to give application jack top power according to Deformation Monitoring, it is ensured that " zero deformation " of work progress existing structure.
Two linings are performed after first Zhi Guantong immediately, jack is locked, guarantees that jack plays always before two linings reach intensity Effect;Side wall false stull is removed paragraph by paragraph, sets up support replacement in time after concrete reaches intensity.
Advantages of the present invention:
Existing rigid structures zero are worn under of the present invention and deform construction method, using slip casting plus step excavation and are arranged The jack of compensation deformation realizes the control target of zero deformation.Construction is simple, it is easy to operate, it improves down and wears construction Safety can be used in each engineering construction.
Specific embodiment
Embodiment 1
It present embodiments provides and wears the existing deformation of rigid structures zero construction method under one kind, it is characterised in that: is described Under wear existing rigid structures zero and deform construction method, under wear before the external slip casting of excavation, under wear section excavation internal injection it is real Existing " earlier zero deformation of excavation ', it is real to be passed through by automation deformation monitoring using jack top power for jack top power in excavation " compensation jacking " in now excavating, realizes zero deformation in excavating, and after-pouring secondary lining realizes and tightly cuts existing rigid structure Build the construction of object " zero deformation ".
Before wearing under, the soil body carries out grouting and reinforcing within the scope of 2 meters outside outline excavation;Just branch is all made of profile steel frame, indulges It is 0.5m to spacing;Just branch is with a thickness of 35cm, two lining tops, base plate thickness 80cm, side wall thicknesses 70cm;
Under wear the deep hole grouting of section;Under wear building up station construction before, first to the soil needed below building up station in reinforcing scope Body carries out advanced deep hole grouting reinforcing, and deep hole grouting carries out in two times in the longitudinal direction, reinforces 16m, the overlap joint of slip casting twice for the first time 2m, range of grouting be tunnel excavation line within the scope of and outer 2m within the scope of soil layer;Deep hole grouting uses cement-silicate dual slurry, just Pressure is 0.5~0.75MPa, final pressure 1.0MPa;After the injected hole of one slip casting section has all been infused, bores 2~3 holes and slip casting is imitated Fruit carries out coring inspection, it is desirable that test specimen soil body unconfined compressive strength is not less than 0.8MPa.
Under wear section tunnel excavation using 4 pilot tunnel step excavations, each pilot tunnel is using performed core-soil sidesteps excavation;Just branch It is used uniformly profile steel frame, along excavation one row's 120t self-locking jack of longitudinal every 1.5 meters of settings;The side wall at station is worn under One row's jack is set with reversed beam position;After preliminary bracing closing cyclization, apply and just push up power, makes just to prop up and both wired base tops Tightly.
The automatic monitoring implemented in work progress is implemented to give application jack top power according to Deformation Monitoring, it is ensured that " zero deformation " of work progress existing structure.
Two linings are performed after first Zhi Guantong immediately, jack is locked, guarantees that jack plays always before two linings reach intensity Effect;Side wall false stull is removed paragraph by paragraph, sets up support replacement in time after concrete reaches intensity.
Embodiment 2
It present embodiments provides and wears the existing deformation of rigid structures zero construction method under one kind, it is characterised in that: is described Under wear existing rigid structures zero and deform construction method, under wear before the external slip casting of excavation, under wear section excavation internal injection it is real Existing " earlier zero deformation of excavation ', it is real to be passed through by automation deformation monitoring using jack top power for jack top power in excavation " compensation jacking " in now excavating, realizes zero deformation in excavating, and after-pouring secondary lining realizes and tightly cuts existing rigid structure Build the construction of object " zero deformation ".
Before wearing under, the soil body carries out grouting and reinforcing within the scope of 2 meters outside outline excavation;Just branch is all made of profile steel frame, indulges It is 0.5m to spacing;Just branch is with a thickness of 35cm, two lining tops, base plate thickness 80cm, side wall thicknesses 70cm;
Under wear the deep hole grouting of section;Under wear building up station construction before, first to the soil needed below building up station in reinforcing scope Body carries out advanced deep hole grouting reinforcing, and deep hole grouting carries out in two times in the longitudinal direction, reinforces 16m, the overlap joint of slip casting twice for the first time 2m, range of grouting be tunnel excavation line within the scope of and outer 2m within the scope of soil layer;Deep hole grouting uses cement-silicate dual slurry, just Pressure is 0.5~0.75MPa, final pressure 1.0MPa;After the injected hole of one slip casting section has all been infused, bores 2~3 holes and slip casting is imitated Fruit carries out coring inspection, it is desirable that test specimen soil body unconfined compressive strength is not less than 0.8MPa.
The automatic monitoring implemented in work progress is implemented to give application jack top power according to Deformation Monitoring, it is ensured that " zero deformation " of work progress existing structure.
Two linings are performed after first Zhi Guantong immediately, jack is locked, guarantees that jack plays always before two linings reach intensity Effect;Side wall false stull is removed paragraph by paragraph, sets up support replacement in time after concrete reaches intensity.
Embodiment 3
It present embodiments provides and wears the existing deformation of rigid structures zero construction method under one kind, it is characterised in that: is described Under wear existing rigid structures zero and deform construction method, under wear before the external slip casting of excavation, under wear section excavation internal injection it is real Existing " earlier zero deformation of excavation ', it is real to be passed through by automation deformation monitoring using jack top power for jack top power in excavation " compensation jacking " in now excavating, realizes zero deformation in excavating, and after-pouring secondary lining realizes and tightly cuts existing rigid structure Build the construction of object " zero deformation ".
Before wearing under, the soil body carries out grouting and reinforcing within the scope of 2 meters outside outline excavation;Just branch is all made of profile steel frame, indulges It is 0.5m to spacing;Just branch is with a thickness of 35cm, two lining tops, base plate thickness 80cm, side wall thicknesses 70cm;
Under wear the deep hole grouting of section;Under wear building up station construction before, first to the soil needed below building up station in reinforcing scope Body carries out advanced deep hole grouting reinforcing, and deep hole grouting carries out in two times in the longitudinal direction, reinforces 16m, the overlap joint of slip casting twice for the first time 2m, range of grouting be tunnel excavation line within the scope of and outer 2m within the scope of soil layer;Deep hole grouting uses cement-silicate dual slurry, just Pressure is 0.5~0.75MPa, final pressure 1.0MPa;After the injected hole of one slip casting section has all been infused, bores 2~3 holes and slip casting is imitated Fruit carries out coring inspection, it is desirable that test specimen soil body unconfined compressive strength is not less than 0.8MPa.
Under wear section tunnel excavation using 4 pilot tunnel step excavations, each pilot tunnel is using performed core-soil sidesteps excavation;Just branch It is used uniformly profile steel frame, along excavation one row's 120t self-locking jack of longitudinal every 1.5 meters of settings;Worn under station side wall and Row's jack is arranged in reversed beam position;After preliminary bracing closing cyclization, apply and just push up power, makes just to prop up tight with both wired base tops.

Claims (5)

1. wearing existing rigid structures zero under one kind deforms construction method, it is characterised in that: wear existing rigidity under described and construct Object zero deforms construction method, under wear before the external slip casting of excavation, under wear the excavation internal injection of section and realize that " earlier the zero of excavation becomes Shape ', pass through jack top power by automation deformation monitoring using jack top power and realize " the compensation top in excavating in excavation Rise ", realize zero deformation in excavating, after-pouring secondary lining realizes and tightly cuts applying for existing rigid structures " zero deformation " Work.
2. wearing existing rigid structures zero under described in accordance with the claim 1 deforms construction method, it is characterised in that: wear it under Before, the soil body carries out grouting and reinforcing within the scope of 2 meters outside outline excavation;Just branch is all made of profile steel frame, longitudinal pitch 0.5m;Just branch With a thickness of 35cm, two lining tops, base plate thickness 80cm, side wall thicknesses 70cm;
Under wear the deep hole grouting of section;Under wear building up station construction before, first to the soil body needed below building up station in reinforcing scope into Row advanced deep hole grouting is reinforced, and deep hole grouting carries out in two times in the longitudinal direction, reinforces 16m for the first time, and slip casting twice overlaps 2m, note Starch range be tunnel excavation line within the scope of and outer 2m within the scope of soil layer;Deep hole grouting uses cement-silicate dual slurry, and first pressing is 0.5~0.75MPa, final pressure 1.0MPa;After the injected hole of one slip casting section all infuse, 2~3 holes of brill to slip casting effect into Row coring is examined, it is desirable that test specimen soil body unconfined compressive strength is not less than 0.8MPa.
3. wearing existing rigid structures zero under described in accordance with the claim 1 deforms construction method, it is characterised in that: under wear a section tunnel Road, which excavates, uses 4 pilot tunnel step excavations, and each pilot tunnel is excavated using performed core-soil sidesteps;Just branch is used uniformly fashioned iron steel Frame, along excavation one row's 120t self-locking jack of longitudinal every 1.5 meters of settings;Side wall and the reversed beam position setting one at station are worn under Arrange jack;After preliminary bracing closing cyclization, apply and just push up power, makes just to prop up tight with both wired base tops.
4. wearing existing rigid structures zero under described in accordance with the claim 1 deforms construction method, it is characterised in that: work progress The middle automatic monitoring implemented is implemented to give application jack top power according to Deformation Monitoring, it is ensured that work progress existing structure " zero deformation ".
5. wearing existing rigid structures zero under described in accordance with the claim 1 deforms construction method, it is characterised in that: first Zhi Guantong Perform two linings immediately afterwards, jack is locked, guarantees that jack plays a role always before two linings reach intensity;Side wall is removed paragraph by paragraph False stull sets up support replacement after concrete reaches intensity in time.
CN201710388603.7A 2017-05-27 2017-05-27 Existing rigid structures zero are worn under one kind deforms construction method Pending CN108952771A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710388603.7A CN108952771A (en) 2017-05-27 2017-05-27 Existing rigid structures zero are worn under one kind deforms construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710388603.7A CN108952771A (en) 2017-05-27 2017-05-27 Existing rigid structures zero are worn under one kind deforms construction method

Publications (1)

Publication Number Publication Date
CN108952771A true CN108952771A (en) 2018-12-07

Family

ID=64494587

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710388603.7A Pending CN108952771A (en) 2017-05-27 2017-05-27 Existing rigid structures zero are worn under one kind deforms construction method

Country Status (1)

Country Link
CN (1) CN108952771A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3968655A (en) * 1973-07-13 1976-07-13 Mcglothlin William K Method of reinforcing tunnels before excavation
US4084384A (en) * 1976-09-13 1978-04-18 Shosei Serata Advanced slot stress control method of underground excavation
CN101126318A (en) * 2007-09-28 2008-02-20 中铁二局股份有限公司 Shield construction method for three-line parallel under-passing trunk railway tunnel
CN101131090A (en) * 2007-10-09 2008-02-27 中铁二局股份有限公司 Construction method for shallow soil-covered river bed under shield tunnel
CN101858222A (en) * 2010-05-25 2010-10-13 北京城建设计研究总院有限责任公司 Method for controlling deformation in zero-distance tunneling of new tunnel under existing subway construction
CN106050245A (en) * 2016-08-03 2016-10-26 中铁第勘察设计院集团有限公司 Supporting structure for zero distance underneath pass of existing station of rectangular tunnel section and construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3968655A (en) * 1973-07-13 1976-07-13 Mcglothlin William K Method of reinforcing tunnels before excavation
US4084384A (en) * 1976-09-13 1978-04-18 Shosei Serata Advanced slot stress control method of underground excavation
CN101126318A (en) * 2007-09-28 2008-02-20 中铁二局股份有限公司 Shield construction method for three-line parallel under-passing trunk railway tunnel
CN101131090A (en) * 2007-10-09 2008-02-27 中铁二局股份有限公司 Construction method for shallow soil-covered river bed under shield tunnel
CN101858222A (en) * 2010-05-25 2010-10-13 北京城建设计研究总院有限责任公司 Method for controlling deformation in zero-distance tunneling of new tunnel under existing subway construction
CN106050245A (en) * 2016-08-03 2016-10-26 中铁第勘察设计院集团有限公司 Supporting structure for zero distance underneath pass of existing station of rectangular tunnel section and construction method

Similar Documents

Publication Publication Date Title
CN107355226B (en) Broken area hole section processing structure of TBM construction tunnel fault
CN105649089B (en) A kind of excavation of foundation pit closes on existing shallow foundation protection structure construction method
CN106050245A (en) Supporting structure for zero distance underneath pass of existing station of rectangular tunnel section and construction method
CN103410161B (en) Oblique control slip casting steel anchor tube framework and construction method thereof
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN105156121A (en) Construction method of large-cross section loess tunnel cave entering shallow buried section
CN204703160U (en) Two anchoring section prestressed anchor Cable Structure
CN103256060A (en) Moisture rich and weak mylonite large section tunnel surrounding rock consolidation and excavation method
CN102312672A (en) Fast large-cross-section tunnel construction method adapting to complicated and variable geological conditions
CN105735322A (en) Design and construction method of rigid-flexible composite anti-seepage recoverable supporting structure
CN111305877B (en) Construction method for strong rockburst section tunnel in high-altitude area
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN105370290A (en) Rectifying and reinforcing method of shield tunnels
CN107725056A (en) One kind passes through silly stratum tunnel loopful quick grouting construction method in advance
CN105065037A (en) Double-layer arch center support construction method for highway soft rock tunnel
CN110005439A (en) A kind of construction method in the nearly excessively leading tunnel of spacing of shield
CN105114098A (en) Method for treating unfavorable geology segment of diversion tunnel and major-diameter diversion tunnel structure
CN207111103U (en) A kind of benching tunnelling method excavation supporting structure of weak surrounding rock large cross-section tunnel double -side approach three
CN110700853A (en) Shallow soil covering shield tunnel reinforcing method based on weak stratum
CN109653212A (en) Close on the irregular deep basal pit group comprehensive support structure and construction method of high-speed railway
CN102425155A (en) Method for reinforcing overlying shallow rockmass in mined-out area
CN109681214B (en) Construction method for reinforcing stratum through full-section grouting
CN104989419A (en) Tunnel early-stage support clearance-intrusion processing method and construction ancillary equipment of tunnel early-stage support clearance-intrusion processing method
CN204716253U (en) Circular major diameter diversion tunnel structure
Ding et al. Analysis of the influence of soft soil grouting on the metro tunnel based on field measurement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181207

RJ01 Rejection of invention patent application after publication