CN108952758A - A kind of layer of sand slip casting earth's surface lifting control method based on borehole collapse and induction splitting - Google Patents

A kind of layer of sand slip casting earth's surface lifting control method based on borehole collapse and induction splitting Download PDF

Info

Publication number
CN108952758A
CN108952758A CN201810670494.2A CN201810670494A CN108952758A CN 108952758 A CN108952758 A CN 108952758A CN 201810670494 A CN201810670494 A CN 201810670494A CN 108952758 A CN108952758 A CN 108952758A
Authority
CN
China
Prior art keywords
drilling
layer
slip casting
earth
splitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810670494.2A
Other languages
Chinese (zh)
Other versions
CN108952758B (en
Inventor
韩伟伟
刘人太
王雪亮
李克先
李卫
张建伟
姜鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Metro Line 1 Line Co Ltd
Shandong University
Shandong University of Science and Technology
China Railway Engineering Consulting Group Co Ltd
Original Assignee
Qingdao Metro Line 1 Line Co Ltd
Shandong University
Shandong University of Science and Technology
China Railway Engineering Consulting Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Metro Line 1 Line Co Ltd, Shandong University, Shandong University of Science and Technology, China Railway Engineering Consulting Group Co Ltd filed Critical Qingdao Metro Line 1 Line Co Ltd
Priority to CN201810670494.2A priority Critical patent/CN108952758B/en
Publication of CN108952758A publication Critical patent/CN108952758A/en
Application granted granted Critical
Publication of CN108952758B publication Critical patent/CN108952758B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Abstract

Control method is lifted for the earth's surface based on induction splitting and drilling of collapsing the present invention provides a kind of.Layer of sand transverse passage-way front pre-grouting is crossed for subway engineering to reinforce, and is drilled by laying to collapse to induce splitting drilling and collapse, realization control slurries trend and the purpose for reducing earth's surface lifting.By induction splitting drilling, lower target stabilization zone reservoir stress, control slurries trend prevents earth's surface running pulp;By drilling of collapsing, uplift buffer area is created, reduces earth's surface lifting.The two cooperates pipe canopy, both can guarantee slip casting effect while can be effectively controlled earth's surface lifting.

Description

A kind of layer of sand slip casting earth's surface lifting control method based on borehole collapse and induction splitting
Technical field
The invention mainly relates to the controls that earth's surface during a kind of transverse passage-way layer of sand grouting and reinforcing for subway engineering is lifted Method.
Background technique
In recent years, China's subway engineering puts into construction in succession, and various geological disaster controls become key urgently to be resolved and ask Topic.Layer of sand grouting and reinforcing is the common technical problem faced in a kind of Metro Construction especially in coastal cities.Under wear The transverse passage-way pre-grouting of municipal highway reinforces difficulty maximum, and Major Difficulties are as follows:
(1) water supply line, combustion gas handle money, electric power piping lane and sewage conduct etc. are generally laid along municipal highway, for slip casting Caused earth's surface lifting requires more harsh.
(2) transverse passage-way buried depth is shallower, and enough only slurry stratum, slurries are lacked during slip casting and are easier to from earth's surface running pulp; Final grouting pressure is not high simultaneously, and slip casting effect is bad.
(3) layer of sand compressibility itself is not high, and slip casting is easy to cause earth's surface lifting excessive, and slip casting difficulty is larger.
Therefore, it is badly in need of a kind of method that both can guarantee slip casting effect while can be effectively controlled earth's surface lifting.
Summary of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the present invention provides one kind for based on induction splitting and drilling of collapsing Earth's surface be lifted control method.By induction splitting drilling, lower target stabilization zone reservoir stress, control slurries trend prevents Earth's surface running pulp;By drilling of collapsing, uplift buffer area is created, reduces earth's surface lifting.The two cooperates pipe canopy, both can guarantee Slip casting effect can be effectively controlled earth's surface lifting simultaneously.
The technical scheme adopted by the invention is that:
A kind of layer of sand slip casting earth's surface lifting control method based on borehole collapse and induction splitting, primarily directed to ground ironworker Journey crosses the reinforcing of layer of sand transverse passage-way front pre-grouting, is drilled by laying to collapse to induce splitting drilling and collapse, realization control slurries Trend and the purpose for reducing earth's surface lifting.
Further, collapsing induction splitting drilling, is laid in below inlet well, issues in grouting pressure influence Raw to collapse, surrounding formation stress reduces, bad student's plane of weakness, provides splitting space for slurries, induction slurries generate horizontal splitting with Partial stowage is compacted, and control slurries spread running pulp to earth's surface, carries out reducing earth's surface lifting.
Further, collapsing drilling is laid in above inlet well at pipeline, and drilling of collapsing is lifted on stratum It can collapse under the influence of rising, form a buffer area, absorb stratum deformation, reducing influences earth's surface and pipeline.
Further, casing, ring flange and valve are respectively mounted in each collapsing induction splitting drilling and drilling of collapsing Door can carry out switch adjustment according to running pulp situation and earth's surface lifting during slip casting, the solidification of dual slurry Local Instantaneous is avoided to cause Earth's surface be lifted suddenly.
Further, specific construction method is as follows:
(1) drilling of multiple sequences is bored in the transversal cross-section in channel, including collapse induction splitting drilling, multilayer slip casting Hole, collapsing hole;Drilling is horizontal drilling, and aperture depth is lower than desired drilling depth, and the sealing casing in each drilling, In casing outer end mounting flange and valve;
(2) induction splitting of collapsing will be laid and drill whole drilling wells to specified segmentation depth, keep valve in the open state;
(3) according to the sequence from centre to two sides, first layer injected hole is crept into specified segmentation depth and is carried out one by one Slip casting;After the completion of first layer mortar depositing construction, by this layer of slip casting hole drill, all drilling makes valve be in open shape to segmentation depth again State, the inlet well of this layer is used as induction splitting drilling of collapsing at this time;
(4) according to the sequence from centre to two sides, the drilling of the second layer is crept into specified segmentation depth and is carried out one by one Slip casting, the drilling of the second layer is as inlet well at this time;Likewise, after the completion of second layer mortar depositing construction, by this layer of slip casting hole drill All drilling keeps valve in the open state, the inlet well of this layer is bored as induction splitting of collapsing at this time to segmentation depth again Hole uses;
(6) drilling that next layer is successively carried out according to step (4), until this section of slip casting is completed;
(7) face is drilled and creeps into row segmentation depth progress slip casting;After first section long whole slip casting, repeat above-mentioned Process carries out next segment length's mortar depositing construction.
Further, during above-mentioned slip casting, it is lifted excessive situation if there is earth's surface or pipeline, can be bored collapsing All drilling keeps the valve in collapsing hole in the open state, then carries out according still further to the above process to corresponding segmentation depth in hole Slip casting;Before each bored grouting, situation is lifted according to earth's surface, the drilling that can will collapse carries out repeating cleaning bottom of hole.
Further, in the step (3): if induction splitting drilling of collapsing occurs to close valve when running pulp is serious; When carrying out next bored grouting, then it will collapse and splitting drilling induced to be placed in opening state.
Further, in the step (4): during slip casting, if occur can will be right when running pulp is serious for first layer drilling The valve answered is closed;When carrying out next bored grouting, then the hole is placed in opening state.
Further, the collapsing induction splitting drilling is located at the lower section of first layer injected hole, first layer slip casting hole location In the lower section of second layer injected hole, the collapsing hole is located at the top of all injected holes.
Beneficial effects of the present invention are as follows:
The present invention lowers target stabilization zone reservoir stress by induction splitting drilling, and control slurries trend prevents earth's surface from running Slurry;By drilling of collapsing, uplift buffer area is created, reduces earth's surface lifting.The two cooperates pipe canopy, both can guarantee that slip casting was imitated Fruit can be effectively controlled earth's surface lifting simultaneously.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide further understanding of the present application, and the application's shows Meaning property embodiment and its explanation are not constituted an undue limitation on the present application for explaining the application.
Fig. 1 are as follows: collapse induction splitting drilling schematic diagram;
Fig. 2 are as follows: collapse drilling schematic diagram;
Fig. 3 are as follows: the schematic diagram of integral construction;
Fig. 4 are as follows: sealing casing, the schematic diagram of ring flange and valve are installed in drilling.
Specific embodiment
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination;
In order to facilitate narration, if there is "upper", "lower" printed words in the present invention, the upper and lower with attached drawing itself is only indicated To consistent, restriction effect is not played to structure, it is only for convenient for the description present invention and simplify description, rather than indicate or dark Show that signified equipment or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as pair Limitation of the invention.
As background technique is introduced, the transverse passage-way pre-grouting for wearing municipal highway down in the prior art reinforces difficulty most Greatly, Major Difficulties are as follows:
(1) water supply line, combustion gas handle money, electric power piping lane and sewage conduct etc. are generally laid along municipal highway, for slip casting Caused earth's surface lifting requires more harsh.
(2) transverse passage-way buried depth is shallower, and enough only slurry stratum, slurries are lacked during slip casting and are easier to from earth's surface running pulp; Final grouting pressure is not high simultaneously, and slip casting effect is bad.
(3) layer of sand compressibility itself is not high, and slip casting is easy to cause earth's surface lifting excessive, and slip casting difficulty is larger.Therefore, anxious The method for needing one kind both to can guarantee slip casting effect while can be effectively controlled earth's surface lifting.
In a kind of typical embodiment of the application, layer of sand transverse passage-way front pre-grouting is crossed mainly for subway engineering and is added Gu it is drilled by laying to collapse to induce splitting drilling and collapse, realization control slurries trend and the purpose for reducing earth's surface lifting.
When construction, several common drillings can be done in advance below inlet well, that is, induction splitting drilling of collapsing is led to slip casting and bored When the slip casting of hole, induction splitting drilling of collapsing is collapsed under the influence of grouting pressure, and surrounding formation stress reduces, and bad student is weak Face provides splitting space for slurries, and induction slurries generate horizontal splitting and partial stowage is compacted, and control slurries are spread to earth's surface to be run Slurry carries out reducing earth's surface lifting.Fig. 1 is shown in induction splitting drilling of collapsing;
It, can be above inlet well, close to danger in order to further control earth's surface lifting when slip casting causes earth's surface lifting excessive Dangerous pipeline position, the bigger common horizontal drilling of one round diameter of construction, that is, drilling of collapsing.During slip casting, stratum moves up lifting, Lead to borehole collapse, form a buffer area, absorb stratum deformation, reducing influences earth's surface and pipeline.Fig. 2 is shown in drilling of collapsing;
The present invention lowers target stabilization zone reservoir stress by induction splitting drilling, and control slurries trend prevents earth's surface from running Slurry;By drilling of collapsing, uplift buffer area is created, reduces earth's surface lifting.The two cooperates pipe canopy, both can guarantee that slip casting was imitated Fruit can be effectively controlled earth's surface lifting simultaneously.
Below with reference to case history, the present invention is further described.
Grouting program uses protrusive segmenting slip casting, and slurries use cement soluble glass paste, and drilling arrangement is shown in that Fig. 3 includes A Sequence drilling, the drilling of B sequence, the drilling of C sequence and drilling of collapsing, wherein the drilling of A sequence is induction splitting drilling of collapsing, and the drilling of B sequence is slip casting Drilling also serves as collapsing induction splitting drilling, and the drilling of C sequence is inlet well.Specific implementation step is as follows:
(1) show first by Fig. 3 and carry out aperture (including the drilling of A sequence, the drilling of B sequence, the drilling of C sequence and collapsing drill), the drilling It is horizontal drilling, the depth 2m of each aperture, and the sealing casing in each drilling, mounting flange and valve, specifically Structure is shown in Fig. 4;
In Fig. 4, casing is mounted in drilling, the input terminal mounting flange and valve of casing;The drilling of B sequence, the drilling of C sequence As the injected hole used time, Grouting Pipe passes through corresponding casing, carries out slip casting.
(2) A sequence is drilled into whole drilling wells to specified segmentation depth, the valve for making A sequence drill is in the open state, and A sequence is bored Hole is as induction splitting drilling of collapsing;The drilling method of A sequence drilling, which can be, from left to right to be crept into, and is also possible to from centre It is crept into the sequence of two sides.
(3) according to the sequence from centre to two sides, B sequence drilling drilling to specified segmentation depth is simultaneously infused simultaneously one by one Slurry, at this time B sequence drilling are used as inlet well.During slip casting, if inciting somebody to action when running pulp is serious occurs in the drilling of some corresponding A sequence Valve is closed;When carrying out next bored grouting, then the A sequence is drilled and is placed in opening state.
(4) after the completion of the construction of B sequence bored grouting, B sequence is drilled and is all crept into segmentation depth, valve is made to be in open shape State, at this time B sequence drilling are used as induction splitting drilling of collapsing;
(5) according to the sequence from centre to two sides, C sequence drilling drilling to specified segmentation depth and is subjected to slip casting one by one, C sequence drilling at this time is used as inlet well.During slip casting, if the drilling of B sequence occurs to close valve when running pulp is serious.It carries out When next bored grouting, then B sequence is drilled and is placed in opening state.
(6) slip casting is carried out finally, face is drilled and creeps into row segmentation depth.
After (7) first sections long whole slip casting, repeats the above process and carry out next segment length's mortar depositing construction.
(8) during above-mentioned slip casting, it is lifted excessive situation if there is earth's surface or pipeline, can will collapse drilling all Drilling keeps the valve in collapsing hole in the open state, then carries out slip casting according still further to the above process to corresponding segmentation depth.Often Before a bored grouting, situation is lifted according to earth's surface, the drilling that can will collapse carries out repeating cleaning bottom of hole.
It further illustrates, above only by taking two layers of slip casting (drilling of B sequence, the drilling of C sequence) as an example, the explanation of progress can To carry out multilayer slip casting as needed.
Collapsing recited above drills due to the distribution close to pipeline, substantially its distribution form is linear point Cloth;
A sequence drilling recited above is set to the lower section of pipe canopy;The drilling of B sequence, the drilling of C sequence are set to above pipe canopy;And C sequence Drilling is located at B sequence drilling top.
The foregoing is merely preferred embodiment of the present application, are not intended to limit this application, for the skill of this field For art personnel, various changes and changes are possible in this application.Within the spirit and principles of this application, made any to repair Change, equivalent replacement, improvement etc., should be included within the scope of protection of this application.

Claims (9)

1. a kind of layer of sand slip casting earth's surface based on borehole collapse and induction splitting is lifted control method, which is characterized in that for ground Ironworker's journey crosses the reinforcing of layer of sand transverse passage-way front pre-grouting, is drilled by laying to collapse to induce splitting drilling and collapse, realization control Slurries trend and the purpose for reducing earth's surface lifting.
2. the layer of sand slip casting earth's surface as described in claim 1 based on borehole collapse and induction splitting is lifted control method, special Sign is that the collapsing induction splitting drilling is laid in below inlet well.
3. the layer of sand slip casting earth's surface as described in claim 1 based on borehole collapse and induction splitting is lifted control method, special Sign is that the collapsing drilling is laid in above inlet well at pipeline.
4. the layer of sand slip casting earth's surface as described in claim 1 based on borehole collapse and induction splitting is lifted control method, special Sign is, is respectively mounted casing, ring flange and valve, slip casting process in each collapsing induction splitting drilling and drilling of collapsing In can according to running pulp situation and earth's surface lifting carry out switch adjustment, avoid dual slurry Local Instantaneous solidify caused by earth's surface lift suddenly It rises.
5. the layer of sand slip casting earth's surface as described in claim 1 based on borehole collapse and induction splitting is lifted control method, special Sign is, specific as follows:
(1) drilling of multiple sequences is bored in the transversal cross-section in channel, including induction splitting of collapsing drills, multilayer injected hole, collapses Collapse hole;Drilling is horizontal drilling, and aperture depth is lower than desired drilling depth, and the sealing casing in each drilling, is covering Pipe outer end mounting flange and valve;
(2) induction splitting of collapsing will be laid and drill whole drilling wells to specified segmentation depth, keep valve in the open state;
(3) according to the sequence from centre to two sides, first layer injected hole is crept into specified segmentation depth one by one and carries out slip casting; After the completion of first layer mortar depositing construction, by this layer of slip casting hole drill, all drilling keeps valve in the open state to depth is segmented again, this When this layer inlet well as collapse induction splitting drilling use;
(4) according to the sequence from centre to two sides, the drilling of the second layer is crept into specified segmentation depth one by one and carries out slip casting, The drilling of the second layer is as inlet well at this time;Likewise, after the completion of second layer mortar depositing construction, again all by this layer of slip casting hole drill Drilling keeps valve in the open state, the inlet well of this layer is used as induction splitting drilling of collapsing at this time to segmentation depth;
(6) drilling that next layer is successively carried out according to step (4), until this section of slip casting is completed;
(7) face is drilled and creeps into row segmentation depth progress slip casting;After first section long whole slip casting, repeat the above process Carry out next segment length's mortar depositing construction.
6. the layer of sand slip casting earth's surface as claimed in claim 5 based on borehole collapse and induction splitting is lifted control method, special Sign is, during above-mentioned slip casting, excessive situation is lifted if there is earth's surface or pipeline, and can will collapse all drillings that drills To corresponding segmentation depth, keeps the valve in collapsing hole in the open state, then carry out slip casting according still further to the above process;Each brill Before the slip casting of hole, situation is lifted according to earth's surface, the drilling that can will collapse carries out repeating cleaning bottom of hole.
7. the layer of sand slip casting earth's surface as claimed in claim 5 based on borehole collapse and induction splitting is lifted control method, special Sign is, in the step (3): if induction splitting drilling of collapsing occurs to close valve when running pulp is serious;It carries out next When bored grouting, then it will collapse and splitting drilling induced to be placed in opening state.
8. the layer of sand slip casting earth's surface as claimed in claim 5 based on borehole collapse and induction splitting is lifted control method, special Sign is, in the step (4): during slip casting, if first layer drilling occurs to close corresponding valve when running pulp is serious It closes;When carrying out next bored grouting, then the hole is placed in opening state.
9. the layer of sand slip casting earth's surface as claimed in claim 5 based on borehole collapse and induction splitting is lifted control method, special Sign is that the collapsing induction splitting drilling is located at the lower section of first layer injected hole, and first layer injected hole is located at second layer note The lower section in hole is starched, the collapsing hole is located at the top of all injected holes.
CN201810670494.2A 2018-06-26 2018-06-26 Sand layer grouting ground surface lifting control method based on borehole collapse and induced splitting Active CN108952758B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810670494.2A CN108952758B (en) 2018-06-26 2018-06-26 Sand layer grouting ground surface lifting control method based on borehole collapse and induced splitting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810670494.2A CN108952758B (en) 2018-06-26 2018-06-26 Sand layer grouting ground surface lifting control method based on borehole collapse and induced splitting

Publications (2)

Publication Number Publication Date
CN108952758A true CN108952758A (en) 2018-12-07
CN108952758B CN108952758B (en) 2020-11-06

Family

ID=64486797

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810670494.2A Active CN108952758B (en) 2018-06-26 2018-06-26 Sand layer grouting ground surface lifting control method based on borehole collapse and induced splitting

Country Status (1)

Country Link
CN (1) CN108952758B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112963119A (en) * 2021-02-03 2021-06-15 山东大学 Induced splitting grouting reinforcement method suitable for silt silty soil stratum

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094658A (en) * 2011-02-01 2011-06-15 北京交通大学 Method for directed induction fracturing grouting in shallow tunnel
CN103867208A (en) * 2014-03-12 2014-06-18 西安建筑科技大学 Method for controlling deformation of ground surface and pipelines in process of tunnel and underground works construction

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094658A (en) * 2011-02-01 2011-06-15 北京交通大学 Method for directed induction fracturing grouting in shallow tunnel
CN103867208A (en) * 2014-03-12 2014-06-18 西安建筑科技大学 Method for controlling deformation of ground surface and pipelines in process of tunnel and underground works construction

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘光辉等: "隧道注浆加固配套系统研究", 《民营科技》 *
李金明: "注浆加固技术在青岛地铁不良地质地段中的应用", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112963119A (en) * 2021-02-03 2021-06-15 山东大学 Induced splitting grouting reinforcement method suitable for silt silty soil stratum

Also Published As

Publication number Publication date
CN108952758B (en) 2020-11-06

Similar Documents

Publication Publication Date Title
CN102926770B (en) Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN110397428B (en) Displacement coalbed methane yield increasing method for coalbed methane jointly mined by vertical well and U-shaped butt well
CN103835648B (en) One improves rock stratum performance mine shaft rising boring technique by surface grout injection
He et al. Development and prospect of separated zone oil production technology
CN104631438B (en) Long auger guncreting uplift pile construction method
CN103321622A (en) Sand draining and oil extracting method in manner of integrating injection and extraction for thermal producing well and device thereof
CN105804786B (en) A kind of weak seam bottom plate layer-through drilling pressure rushes anti-reflection method
CN109488370B (en) Underground limestone water exploration and drainage drilling construction method
CN105297736B (en) Sequential deepening grouting construction technology and device for soil covering layer on karst cave in karst area
CN105443098A (en) Coal mine underground borehole segmented fixed hydraulic fracturing fixation hole device and method
CN108104814A (en) High iron content underground reservoir is promoted restorative procedure by the artificial of Surface cracking
CN110616728A (en) Construction method of emergency well for emergency rescue outside pit
CN109025940B (en) CO for tight oil reservoir2Fracturing oil displacement integrated oil extraction method
CN110700853A (en) Shallow soil covering shield tunnel reinforcing method based on weak stratum
CN103615226A (en) Drilling and fracturing method by hydraulic jetting
CN108952758A (en) A kind of layer of sand slip casting earth's surface lifting control method based on borehole collapse and induction splitting
CN106907152A (en) A kind of soil type inlet well arrangement and grouting method
CN104929565A (en) Double-layered grouting guide pipe
CN107313743A (en) One kind is using coal bed gas well to seat earth water barrier weak area band method for repairing and mending
CN110984917A (en) Production-increasing water-controlling sand-preventing well completion method for low-permeability reservoir
CN105986792A (en) Method for increasing recovery ratio of shallow layer reservoir
CN205618144U (en) Double -barrelled formula multilayer acidizing water injection string
CN204627527U (en) A kind of double-deck grouting pipe
CN204591208U (en) A kind of double-deck grouting pipe
CN104594369A (en) High-pressure group hole replacement grouting method and structure in karst region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant