- CN108952754A CN108952754A CN201811059873.4A CN201811059873A CN108952754A CN 108952754 A CN108952754 A CN 108952754A CN 201811059873 A CN201811059873 A CN 201811059873A CN 108952754 A CN108952754 A CN 108952754A
- Authority
- CN
- China
- Prior art keywords
- lining
- trolley
- master module
- supporting table
- rubber strip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/003—Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Abstract
The present invention provides a kind of lining-up construction joint anticracking bridging arrangement and construction method, including lining-up trolley master module, the tail portion of lining-up trolley master module is fixed with supporting table, the upper surface of supporting table is parallel with the upper surface of lining-up trolley master module, and the upper surface of supporting table is lower than the upper surface of lining-up trolley master module, rubber strip is equipped on the upper surface of supporting table, and the thickness of rubber strip is greater than the difference in height between supporting table and lining-up trolley master module upper surface.It is overlapped firmly with to solve existing tunnel lining-up construction joint and easily leads at construction joint generation crack, traffic safety is seriously threatened after coming into operation, trolley upper end master module overlaps firmly with casting concrete, lap-joint's leakiness, it is also easy to produce spillage, and hard overlap joint will cause the problems such as trolley upper end master module deforms, lap-joint is caused to generate faulting of slab ends.Belong to railway tunnel especially Railway Tunnel construction field.
Description
Technical field
The present invention relates to a kind of lining-up construction joint anticracking bridging arrangement and lining-up construction joint lapping construction methods, belong to railway
Tunnel especially Railway Tunnel construction field.
Background technique
In today that national economic development flourishes, high-speed railway has become the important pushing hands promoted economic development,
High-speed railway traffic also has become the important mode of transportation of national trip.Essential group as high-speed railway of Tunnel Engineering
At part, occurs many lining cutting chip off-falling phenomenons in recent years, high risk is brought to the safe operation of high-speed railway.
Currently, Tunnel Second Lining, which is all made of hydraulic lining trolley, pours completion, there is following operating condition in the construction process:
1, it is provided at the vertical, horizontal construction joint between secondary lining, between secondary lining and inverted arch parapet circumferential and vertical
The buried rubber fastening band in, according to lining cutting inside edge 200mm, after being centrally located, embedment front and back each 150mm of lining cutting paragraph, in
Buried rubber fastening band cuts the lining cutting at construction joint, weakens to lining cutting globality at construction joint.
2, after the completion of upper group of secondary lining concreting, lining trolley demoulding is just completed after about 18~20h, through live strong
Degree verifying, lining concrete intensity about 5~7Mpa when demoulding, concrete strength be not high.
3, after the lining of the following group two trolley is in place, rigid overlap joint, the lap of splice about 100mm, to prevent from applying are taken with upper group of lining cutting
Spillage in casting process at work seam often takes the pressure for increasing hydraulic cylinder, makes lining trolley upper group of lining cutting closely connected as far as possible,
In the case where upper group of strength of lining be not high, constantly pressurization will cause group concrete at construction joint and be crushed, and form crescent
Crack after coming into operation, under the effect of the power brought by train high-speed cruising Repeated Compression air, is cut by crescent crack
Concrete there can possibly be formed chip off-falling, jeopardize traffic safety.
Summary of the invention
It is an object of the invention to: a kind of lining-up construction joint anticracking bridging arrangement and construction method are provided, it is existing to solve
Lining-up construction joint in tunnel overlaps firmly easily leads to generation crack at construction joint, and traffic safety, trolley are seriously threatened after coming into operation
Upper end master module overlaps firmly with casting concrete, lap-joint's leakiness, is also easy to produce spillage, and hard overlap joint will cause trolley upper end
The problems such as master module deforms, and lap-joint is caused to generate faulting of slab ends.
To solve the above problems, such a lining-up construction joint anticracking bridging arrangement of proposed adoption, including lining-up trolley main mould
Plate, the tail portion of lining-up trolley master module are fixed with supporting table, the upper surface of supporting table and the upper surface phase of lining-up trolley master module
In parallel, and the upper surface of supporting table is lower than the upper surface of lining-up trolley master module, is equipped with rubber strip on the upper surface of supporting table,
And the thickness of rubber strip is greater than the difference in height between supporting table and lining-up trolley master module upper surface.
In aforementioned lining-up trolley, the width of the rubber strip is 100-150mm, with a thickness of 40-60mm;
In aforementioned lining-up trolley, the upper surface of supporting table is set in the horizontal direction with the upper surface of lining-up trolley master module
It sets, and there are the difference in height of 20mm between the upper surface of supporting table and the upper surface of lining-up trolley master module, the rubber strip is
With a thickness of the rectangular rubber item of 40mm, the compressible amount of rubber strip is at least the 50% of rubber strip thickness;
In aforementioned lining-up trolley, the supporting table is that the design radian circumferential direction along lining-up trolley master module tail portion welds installation
Angle steel or channel steel, one end of supporting table is fixedly welded on the tail portion of lining-up trolley master module, is provided on the downside of supporting table tiltedly
Support, one end of diagonal brace are fixedly welded on the other end of the supporting table, and the other end of diagonal brace is also fixedly welded on lining-up trolley master
The tail portion of template;
The present invention also provides a kind of lining-up construction joint anticracking lapping construction methods, and the specific method is as follows:
When tunnel lining-up is constructed, mobile lining-up trolley makes lining-up trolley master module be moved to the underface of the following group lining-up, rubber
Adhesive tape is located at the underface of upper group of lining-up, slowly jacks lining-up trolley hydraulic cylinder, rubber strip and lining-up trolley master module are gradually
Rising, rubber strip is first in contact with upper group of lining-up, then continues to jack, until lining-up trolley master module rises to design position,
At this point, rubber strip is compressed, and closely overlaps with the lower end of upper group of lining-up, that is, realizes and handled with the soft overlap joint of upper group of lining-up, institute
Stating group lining-up is the upper group of secondary lining-up concrete poured, and the following group lining-up is the secondary lining-up coagulation of the following group to be poured
Soil.
In the above method, when tunnel lining-up is constructed, lining-up trolley is moved first, so that between upper group of lining-up and the following group lining-up
The side flush of construction joint and lining-up trolley master module;
Preferably, two side lower part of trolley and the overlap joint of inverted arch parapet are also constructed according to the method described above.
Compared with prior art, advantage of the present invention is as follows:
1, it is handled using soft overlap joint, lining trolley is effectively avoided effectively to evade platform with the direct overlap joint of casting concrete
Vehicle Leading Edge Deformation avoids that faulting of slab ends occurs, meanwhile, it can also be effectively prevent the generation in crescent crack, deposited when eliminating high-speed rail operation
Security risk, guarantee high-speed rail operation security;
2, it after compressible rubber strip is compressed, is closely overlapped with the upper group of concrete poured, construction can be effectively controlled
Seam is in spillage in casting process, it is ensured that construction joint does not occur honeycomb or chip off-falling, guarantees closely knit at construction joint;
3, compressible rubber strip is reusable, low in cost.
Detailed description of the invention
Fig. 1 is the schematic view of the front view before lining-up trolley of the present invention is in place;
Fig. 2 is the schematic view of the front view after lining-up trolley of the present invention is in place, at this point, the decrement of rubber strip is
50%.
Wherein, the expression of appended drawing reference 1 lining-up trolley master module, 2 expression supporting tables, 3 expression rubber strips, 4 expression diagonal braces, 5
Lining-up is organized in expression, 6 indicate the following group lining-up, buried rubber fastening band in 7 expressions.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the present invention is made into one below in conjunction with attached drawing
The detailed description of step, it should be understood that described herein specific examples are only used to explain the present invention, is not used to limit this hair
It is bright.
Embodiment
Referring to Figures 1 and 2, the present embodiment provides a kind of lining-up construction joint anticracking bridging arrangements, including lining-up trolley main mould
Plate 1, the tail portion of lining-up trolley master module 1 are fixed with supporting table 2, and supporting table 2 is the design arc along 1 tail portion of lining-up trolley master module
The angle steel or channel steel of the circumferential welding installation of degree, one end of supporting table 2 is fixedly welded on the tail portion of lining-up trolley master module 1, bottom
According to the steel plate reinforcement of 100cm spacing welding t=10mm, specifically, the downside of supporting table 2 is provided with diagonal brace 4, and the one of diagonal brace 4
End is fixedly welded on the other end of the supporting table 2, and the other end of diagonal brace 4 is also fixedly welded on the tail of lining-up trolley master module 1
Portion, the upper surface of supporting table 2 and the upper surface of lining-up trolley master module 1 are horizontally disposed, and the upper surface of supporting table 2
Lower than the upper surface 20mm of lining-up trolley master module 1, rubber strip 3 is equipped on the upper surface of supporting table 2, rubber strip 3 is width
For 100-150mm, with a thickness of the rectangular rubber item of 40mm, the compressible amount of rubber strip is at least the 50% of rubber strip thickness.
Carrying out lining-up construction joint anticracking using above-mentioned lining-up trolley, overlapped that construction method is as follows:
When tunnel lining-up is constructed, mobile lining-up trolley makes lining-up trolley master module 1 be moved to the underface of the following group lining-up,
Rubber strip 3 is located at the underface of upper group of lining-up, the side of construction joint and lining-up trolley master module 1 between upper group of lining-up and the following group lining-up
Face flush slowly jacks lining-up trolley hydraulic cylinder, and rubber strip 3 and lining-up trolley master module 1 are gradually increasing, and rubber strip 3 is first
It is in contact with upper group of lining-up, then continues to jack, until lining-up trolley master module 1 rises to design position (lining-up trolley main mould
The lower end surface flush of 1 upper surface of plate and the following group lining-up design position), at this point, rubber strip 3 is compressed, and with upper group of lining-up
Lower end closely overlaps, that is, realizes and handle with the soft overlap joint of upper group of lining-up, the upper group of lining-up is the upper group of secondary lining-up poured
Concrete, the following group lining-up are the secondary lining-up concrete of the following group to be poured, the overlap joint of trolley two side lower parts and inverted arch parapet
Also it constructs according to the method described above.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.
Claims (7)
1. a kind of lining-up construction joint anticracking bridging arrangement, including lining-up trolley master module (1), it is characterised in that: lining-up trolley master
The tail portion of template (1) is fixed with supporting table (2), and the upper surface of supporting table (2) is equal with the upper surface of lining-up trolley master module (1)
Row, and the upper surface of supporting table (2) is lower than the upper surface of lining-up trolley master module (1), is equipped on the upper surface of supporting table (2)
Rubber strip (3), and the thickness of rubber strip (3) is greater than the height between supporting table (2) and lining-up trolley master module (1) upper surface
Difference.
2. a kind of lining-up construction joint anticracking bridging arrangement according to claim 1, it is characterised in that: the rubber strip (3)
Width is 100-150mm, with a thickness of 40-60mm.
3. a kind of lining-up construction joint anticracking bridging arrangement according to claim 1, it is characterised in that: the supporting table (2) is
Along the angle steel or channel steel of the design radian circumferential direction welding installation of lining-up trolley master module (1) tail portion, one end welding of supporting table (2)
It is fixed on the tail portion of lining-up trolley master module (1), is provided on the downside of supporting table (2) diagonal brace (4), one end welding of diagonal brace (4)
It is fixed on the other end of the supporting table (2), the other end of diagonal brace (4) is also fixedly welded on the tail of lining-up trolley master module (1)
Portion.
4. a kind of lining-up construction joint anticracking bridging arrangement according to claim 2, it is characterised in that: the upper end of supporting table (2)
Face and the upper surface of lining-up trolley master module (1) are horizontally disposed, and the upper surface of supporting table (2) and lining-up trolley master
There are the difference in height of 20mm between the upper surface of template (1), the rubber strip (3) is the rectangular rubber item with a thickness of 40mm, rubber
The compressible amount of adhesive tape is at least the 50% of rubber strip thickness.
5. carrying out lining-up construction joint anticracking overlapped construction method using lining-up trolley any in claim 1-4, feature exists
In the specific method is as follows:
When tunnel lining-up is constructed, mobile lining-up trolley makes lining-up trolley master module (1) be moved to the underface of the following group lining-up, rubber
Adhesive tape (3) is located at the underface of upper group of lining-up, slowly jacks lining-up trolley hydraulic cylinder, rubber strip (3) and lining-up trolley main mould
Plate (1) is gradually increasing, and rubber strip (3) is first in contact with upper group of lining-up, then continues to jack, until lining-up trolley master module (1)
Design position is risen to, at this point, rubber strip (3) is compressed, and closely overlaps with the lower end of upper group of lining-up, that is, is realized and upper group of block
The soft overlap joint processing of lining, the upper group of lining-up are the upper group of secondary lining-up concrete poured, and the following group lining-up is wait pour
The secondary lining-up concrete of the following group.
6. method according to claim 5, it is characterised in that: when tunnel lining-up is constructed, lining-up trolley is moved first, so that on
The side flush of construction joint and lining-up trolley master module (1) between group lining-up and the following group lining-up, then slowly jacks lining-up platform
Vehicle hydraulic cylinder.
7. method according to claim 5, it is characterised in that: the overlap joint of two side lower part of trolley and inverted arch parapet is also according to above-mentioned
Method is constructed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811059873.4A CN108952754A (en) | 2018-09-12 | 2018-09-12 | A kind of lining-up construction joint anticracking bridging arrangement and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811059873.4A CN108952754A (en) | 2018-09-12 | 2018-09-12 | A kind of lining-up construction joint anticracking bridging arrangement and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108952754A true CN108952754A (en) | 2018-12-07 |
Family
ID=64476413
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811059873.4A Pending CN108952754A (en) | 2018-09-12 | 2018-09-12 | A kind of lining-up construction joint anticracking bridging arrangement and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108952754A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114251110A (en) * | 2021-12-30 | 2022-03-29 | 中铁十九局集团第六工程有限公司 | Cast lining lapping device, tunnel lining trolley and tunnel construction method |
CN114941258A (en) * | 2022-06-23 | 2022-08-26 | 中铁十八局集团有限公司 | Anti-cracking construction method for concrete track bed slab of CRTS I type double-block ballastless track of high-speed railway tunnel |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205778915U (en) * | 2016-05-25 | 2016-12-07 | 中国水利水电第十四工程局有限公司 | A kind of soft bridging arrangement of concrete lining trolley |
CN206513379U (en) * | 2017-02-18 | 2017-09-22 | 中铁华铁工程设计集团有限公司 | Lining construction reserves the Tunnel Second Lining formwork jumbo of V-groove structure |
CN107448216A (en) * | 2017-09-25 | 2017-12-08 | 中铁十七局集团第工程有限公司 | A kind of tunnel trolley seaming die anti-crack device |
CN207554074U (en) * | 2017-12-20 | 2018-06-29 | 中铁五局集团第二工程有限责任公司 | A kind of soft bridging arrangement of tunnel lining trolley |
CN208734341U (en) * | 2018-09-12 | 2019-04-12 | 中铁二局第一工程有限公司 | A kind of lining-up construction joint anticracking bridging arrangement |
-
2018
- 2018-09-12 CN CN201811059873.4A patent/CN108952754A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205778915U (en) * | 2016-05-25 | 2016-12-07 | 中国水利水电第十四工程局有限公司 | A kind of soft bridging arrangement of concrete lining trolley |
CN206513379U (en) * | 2017-02-18 | 2017-09-22 | 中铁华铁工程设计集团有限公司 | Lining construction reserves the Tunnel Second Lining formwork jumbo of V-groove structure |
CN107448216A (en) * | 2017-09-25 | 2017-12-08 | 中铁十七局集团第工程有限公司 | A kind of tunnel trolley seaming die anti-crack device |
CN207554074U (en) * | 2017-12-20 | 2018-06-29 | 中铁五局集团第二工程有限责任公司 | A kind of soft bridging arrangement of tunnel lining trolley |
CN208734341U (en) * | 2018-09-12 | 2019-04-12 | 中铁二局第一工程有限公司 | A kind of lining-up construction joint anticracking bridging arrangement |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114251110A (en) * | 2021-12-30 | 2022-03-29 | 中铁十九局集团第六工程有限公司 | Cast lining lapping device, tunnel lining trolley and tunnel construction method |
CN114941258A (en) * | 2022-06-23 | 2022-08-26 | 中铁十八局集团有限公司 | Anti-cracking construction method for concrete track bed slab of CRTS I type double-block ballastless track of high-speed railway tunnel |
CN114941258B (en) * | 2022-06-23 | 2023-05-23 | 中铁十八局集团有限公司 | Anti-cracking construction method for CRTS I type double-block ballastless track concrete track slab of high-speed railway tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106087757B (en) | A high position in box beam erection falls beam construction method | |
CN102152392B (en) | Hydraulic device for moulding board of precast beam | |
CN108952754A (en) | A kind of lining-up construction joint anticracking bridging arrangement and construction method | |
CN105134253A (en) | Tunnel inverted arch combined integrated template and method for concreting construction | |
CN208105050U (en) | A kind of wet seam construction formwork of bridge | |
CN102926504B (en) | Construction method of steel and concrete overlapped beam combined part | |
CN202658532U (en) | Bridge wet joint construction template | |
CN208734341U (en) | A kind of lining-up construction joint anticracking bridging arrangement | |
CN110029674A (en) | A kind of bracing demolition and basement construction method for deep basal pit | |
CN202132071U (en) | Filling and sealing mould for roadway slope expansion for pillarless mining for fully mechanized sublevel caving face | |
CN105134250A (en) | Support disassembly-free and direct lining method for weak surrounding rock subway station | |
CN104452825A (en) | Post-cast strip replacing supporting structure used for disassembling building envelope support | |
CN203821878U (en) | Integral horizontal moving device for building with foundation | |
CN205115970U (en) | Cement concrete way face mould board and braced system in way engineering of airport field | |
CN212985234U (en) | Soft overlap joint device of tunnel lining | |
CN218116062U (en) | Fabricated support formwork for fluid casting | |
CN212130509U (en) | Slurry leakage prevention structure for template tail of tunnel secondary lining trolley | |
CN205243526U (en) | Two hinge ear structure tunnel secondary lining end mould construction installation equipment | |
CN114294019A (en) | Cast lining lapping device, tunnel lining trolley and tunnel construction method | |
CN109355987A (en) | Groove-shape rail bending track device and method | |
CN205399216U (en) | Mould is demolishd in step to ballastless track precast box girder end mould | |
CN212105895U (en) | Additional member adapted to curved and straight line tunnel for preventing lining joint from staggering and leaking slurry | |
CN107554692B (en) | A kind of method for loading of ship side structure body | |
CN104153386B (en) | Pile foundation support table periphery facade bed course tool-type punching block and construction method thereof | |
CN207582971U (en) | Pump line bearing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |