CN108933687A - A kind of power consumption control method and device - Google Patents
A kind of power consumption control method and device Download PDFInfo
- Publication number
- CN108933687A CN108933687A CN201710380127.4A CN201710380127A CN108933687A CN 108933687 A CN108933687 A CN 108933687A CN 201710380127 A CN201710380127 A CN 201710380127A CN 108933687 A CN108933687 A CN 108933687A
- Authority
- CN
- China
- Prior art keywords
- target single
- veneer
- single board
- shutdown
- network equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/08—Configuration management of networks or network elements
- H04L41/0803—Configuration setting
- H04L41/0823—Configuration setting characterised by the purposes of a change of settings, e.g. optimising configuration for enhancing reliability
- H04L41/0833—Configuration setting characterised by the purposes of a change of settings, e.g. optimising configuration for enhancing reliability for reduction of network energy consumption
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L1/00—Arrangements for detecting or preventing errors in the information received
- H04L1/22—Arrangements for detecting or preventing errors in the information received using redundant apparatus to increase reliability
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/06—Management of faults, events, alarms or notifications
- H04L41/0654—Management of faults, events, alarms or notifications using network fault recovery
- H04L41/0663—Performing the actions predefined by failover planning, e.g. switching to standby network elements
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/06—Management of faults, events, alarms or notifications
- H04L41/0681—Configuration of triggering conditions
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/08—Configuration management of networks or network elements
- H04L41/0803—Configuration setting
- H04L41/0823—Configuration setting characterised by the purposes of a change of settings, e.g. optimising configuration for enhancing reliability
- H04L41/0836—Configuration setting characterised by the purposes of a change of settings, e.g. optimising configuration for enhancing reliability to enhance reliability, e.g. reduce downtime
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/08—Configuration management of networks or network elements
- H04L41/0893—Assignment of logical groups to network elements
Abstract
The embodiment of the present application provides a kind of power consumption control method and device, is related to field of communication technology, for carrying out power consumption control to the network equipment.This method is applied to the network equipment including N number of veneer, and the N is greater than or equal to 2, the method includes:If the power consumption parameter of the network equipment meets preset condition, according to shutdown precedence information, the target single board of selection shutdown highest priority from preset M veneer;Wherein, the shutdown precedence information is used to indicate the shutdown priority of each veneer in the preset M veneer, and the M is less than or equal to the N;Judge that the target single board whether there is the standby board in normal condition, however, it is determined that there are the standby boards, then the corresponding business of the target single board are transferred to the standby board;The target single board is subjected to shutdown processing.
Description
Technical field
The invention relates to field of communication technology more particularly to a kind of power consumption control methods and device.
Background technique
In the communication technology, with the growth of bandwidth capacity, equipment of the core network, convergence switching equipment and routing device
The specification of the equal network equipments is increasing, and power consumption is also increasing.Bigger power consumption means bigger power supply capacity and heat dissipation
Demand, but some central machine rooms can not provide bigger power supply capacity and heat-sinking capability at present, if carrying out machine in a short time
Housing reform is made, and biggish cost pressure can be brought.However, in practical applications, these network equipments are not typically achieved maximum work
Rate, by taking interchanger as an example, the 60-70% of the operating power consumption of data core switch usually only maximum power dissipation, if according to maximum
Power consumption is that center computer room configures power supply capacity and heat-sinking capability, not only will increase deployed with devices cost, while be will also result in certain
The wasting of resources.Therefore, in order to realize the iterative method of computer room infrastructure, the cost and risk of deployed with devices is reduced, it can be with
The power consumption of the network equipment is controlled.
Currently, most of power consumption control method is both in server, for example, can be adjusted by CPU voltage,
The methods of core shutdown, CPU suspend mode reduce the power consumption of CPU, to realize the power consumption control to server.But since network is set
Standby and server framework and in terms of there are biggish differences, for example, the CPU power consumption of the network equipment only accounts for whole function
Small percentage (usually less than 10%) in consumption, and the larger proportion that CPU power consumption accounts in overall power in server (is usually above
90%).Therefore, the network equipment can not be suitable for for the power consumption control method of server, needed a kind of applied to the network equipment
Power consumption control method.
Summary of the invention
Embodiments herein provides a kind of power consumption control method and device, for carrying out power consumption control to the network equipment,
To reduce the cost and risk of deployed with devices.
In order to achieve the above objectives, embodiments herein adopts the following technical scheme that:
In a first aspect, providing a kind of power consumption control method, applied to the network equipment including N number of veneer, N is greater than or equal to
2, this method includes:If the power consumption parameter of the network equipment meets preset condition, according to shutdown precedence information, from preset M
The target single board of selection shutdown highest priority in a veneer;Wherein, shutdown precedence information is used to indicate preset M veneer
In each veneer shutdown priority, M be less than or equal to N;It is spare in normal condition to judge that target single board whether there is
Veneer, however, it is determined that there are the standby boards, then the corresponding business of target single board are transferred to the standby board;By target single board into
Row shutdown processing.
In above-mentioned technical proposal, the network equipment is when determining that its power consumption parameter meets preset condition, according to shutdown priority
Information, the target single board of selection shutdown highest priority from preset M veneer, and be in just determining that target single board exists
When the standby board of normal state, then the corresponding business of target single board is transferred to standby board, later closes target single board
Disconnected processing to realize the power consumption control to the network equipment, while may also be ensured that the power consumption of the network equipment does not exceed machine
The power supply in room, heat-sinking capability are transformed computer room gradually according to practical business demand, reduce the cost pressure of deployed with devices
Power.
With reference to first aspect, in the first possible implementation of the first aspect, judge that target single board whether there is
After standby board in normal condition, this method further includes:If it is determined that target single board, which is not present, is in the standby of normal condition
With veneer, then the corresponding shutdown priority of target single board is reduced;Alternatively, if the corresponding business of target single board is transferred to this not successfully
Standby board then reduces the corresponding shutdown priority of target single board.In above-mentioned possible implementation, the network equipment is determining mesh
It marks veneer and the standby board in normal condition is not present, or in the corresponding business of target single board to be transferred to this not successfully spare
When veneer, by reducing the corresponding shutdown priority of target single board, the invalid judgement of shutdown priority can be reduced, guarantees shutdown
The freshness and accuracy of priority.
With reference to first aspect or the first possible implementation of first aspect, second in first aspect are possible
Implementation in, the corresponding business of target single board includes Added Business and/or business has been established, by the corresponding industry of target single board
Business is transferred to the standby board, including:If the corresponding business of target single board includes Added Business, Added Business is established
On the standby board;If the corresponding business of target single board includes that business has been established, business migration will have been established to the spare list
On plate.In above-mentioned possible implementation, by by Added Business and/or the spare list that business is transferred to target single board having been established
On plate, to guarantee Added Business and/or the continuity of business has been established, thus as far as possible when carrying out power consumption control to the network equipment
Reduce the influence to user.
Any possible implementation into second of possible implementation of first aspect with reference to first aspect,
In a third possible implementation of the first aspect, this method further includes:According to each veneer in preset M veneer
Specified parameter determines shutdown precedence information;Wherein, specified parameter includes at least one in following parameter:Service priority
SI, whether be standby board B, maximum capacity MC, maximum power dissipation MP, maximum efficiency MEE, real-time traffic RT, new flow increasing NIT,
Real time power consumption RP sequence, real-time energy efficiency REE sequence, shutdown SDF number of failure.In above-mentioned possible implementation, provide several
Kind may determine the specified parameter of the corresponding shutdown priority of veneer, so that the network equipment specifies parameter to determine that shutdown is excellent according to this
First grade information guarantees the corresponding validity for turning off priority of each veneer in M veneer.
The third possible implementation with reference to first aspect, in the 4th kind of possible implementation of first aspect
In, according to the specified parameter of each veneer in preset M veneer, before determining shutdown precedence information, this method further includes:
According to the corresponding preset strategy of veneer each in preset M veneer, the specified parameter of each veneer is determined.Above-mentioned possible reality
In existing mode, when determining the specified parameter of each veneer, according to the demand of actual scene and application effect, selected for each veneer
Different specified parameters is selected, to improve the accuracy of the corresponding shutdown priority of each veneer, and then improves power consumption control
Validity.
The 4th kind of possible implementation with reference to first aspect, in the 5th kind of possible implementation of first aspect
In, if preset strategy includes business preference strategy, specified parameter is included at least:It is one or more in SI, MC, RT, NIT;
Alternatively, specified parameter includes at least if preset strategy includes power consumption preference strategy:It is one or more in MP, RP sequence;Or
Person, if preset strategy includes energy efficiency priority strategy, specified parameter is included at least:It is one or more in MEE, REE sequence;Or
Person, if preset strategy includes strategy based on static parameter, specified parameter is included at least:It is one or more in MC, MP;Or
Person, if preset strategy includes strategy based on dynamic parameter, specified parameter is included at least:One in RT, RP sequence, SDF number
Item is multinomial.It in above-mentioned possible implementation, provides under several different preset strategies, the specific ginseng that specified parameter includes
Number information, to can be improved each when determining the shutdown priority of veneer according to the corresponding specified parameter of different preset strategies
The accuracy of the corresponding shutdown priority of veneer.
Any possible implementation into the 5th kind of possible implementation of first aspect with reference to first aspect,
In the sixth possible implementation of the first aspect, target single board is subjected to shutdown processing, including:Target single board is carried out
Deactivation processing;Alternatively, target single board is carried out enabled processing.In above-mentioned possible implementation, several differences are provided
Shutdown processing mode, handled by carrying out different shutdown to different veneers, can be improved and power consumption is carried out to the network equipment
The validity of control.
Second aspect provides a kind of network equipment, which includes N number of veneer, and N is greater than or equal to 2, which sets
It is standby to further include:Selecting unit, if the power consumption parameter for the network equipment meets preset condition, according to shutdown precedence information,
The target single board of selection shutdown highest priority from preset M veneer;Wherein, shutdown precedence information is used to indicate default
M veneer in each veneer shutdown priority, M be less than or equal to N;Judging unit, for whether judging target single board
In the presence of the standby board for being in normal condition;Buanch unit is used for if it is determined that there are the standby boards, then by target single board correspondence
Business be transferred to the standby board;Processing unit, for target single board to be carried out shutdown processing.
In conjunction with second aspect, in the first possible implementation of the second aspect, which further includes:It determines
Unit, for if it is determined that it is corresponding then to reduce target single board there is no the standby board in normal condition for target single board
Turn off priority;Alternatively, determination unit drops if being transferred to the standby board not successfully for the corresponding business of target single board
The corresponding shutdown priority of low target veneer.
In conjunction with the possible implementation of the first of second aspect or second aspect, second in second aspect may
Implementation in, the corresponding business of target single board includes Added Business and/or business has been established, and buanch unit is specifically used for:
If the corresponding business of target single board includes Added Business, Added Business is established on the standby board;If target single board pair
The business answered includes that business has been established, then will have been established on business migration to the standby board.
In conjunction with second aspect to second aspect second of possible implementation in any possible implementation,
In the third possible implementation of the second aspect, which further includes:Determination unit, for according to preset M
The specified parameter of each veneer in a veneer determines shutdown precedence information;Wherein, specified parameter include in following parameter extremely
One item missing:It service priority SI, whether is standby board B, maximum capacity MC, maximum power dissipation MP, maximum efficiency MEE, real-time streams
Measure RT, new flow increasing NIT, real time power consumption RP sequence, real-time energy efficiency REE sequence, shutdown SDF number of failure.
In conjunction with the third possible implementation of second aspect, in the 4th kind of possible implementation of second aspect
In, determination unit is also used to:According to the corresponding preset strategy of veneer each in preset M veneer, the finger of each veneer is determined
Determine parameter.
In conjunction with the 4th kind of possible implementation of second aspect, in the 5th kind of possible implementation of second aspect
In, if preset strategy includes business preference strategy, specified parameter is included at least:It is one or more in SI, MC, RT, NIT;
Alternatively, specified parameter includes at least if preset strategy includes power consumption preference strategy:It is one or more in MP, RP sequence;Or
Person, if preset strategy includes energy efficiency priority strategy, specified parameter is included at least:It is one or more in MEE, REE sequence;Or
Person, if preset strategy includes strategy based on static parameter, specified parameter is included at least:It is one or more in MC, MP;Or
Person, if preset strategy includes strategy based on dynamic parameter, specified parameter is included at least:One in RT, RP sequence, SDF number
Item is multinomial.
In conjunction with second aspect to second aspect kind of possible implementation in any possible implementation,
In kind of possible implementation of second aspect, processing unit is specifically used for:Target single board is subjected to deactivation processing;Or
Target single board is carried out enabled processing by person.
The third aspect provides a kind of network equipment, and the network equipment includes processor, memory, communication interface and bus, deposits
Store code and data in reservoir, processor, memory and communication interface are connected by bus, in processor run memory
Code makes the network equipment execute above-mentioned first aspect to any one of the 6th kind of possible implementation of first aspect institute
The power consumption control method of offer.
The another aspect of the application provides a kind of computer readable storage medium, in the computer readable storage medium
It is stored with instruction, when run on a computer, so that computer executes power consumption control method provided by above-mentioned various aspects.
The another aspect of the application provides a kind of computer program product comprising instruction, when it runs on computers
When, so that computer executes power consumption control method provided by above-mentioned various aspects.
It is to be appreciated that device, computer storage medium or the calculating of any power consumption control method of above-mentioned offer
Machine program product is used to execute corresponding method presented above, and therefore, the attainable beneficial effect of institute can refer to
Beneficial effect in corresponding method provided by text, details are not described herein again.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of the network equipment provided by the embodiments of the present application;
Fig. 2 is a kind of flow chart of power consumption control method provided by the embodiments of the present application;
Fig. 3 is the flow chart of another power consumption control method provided by the embodiments of the present application;
Fig. 4 is the flow chart of another power consumption control method provided by the embodiments of the present application;
Fig. 5 is the schematic diagram that a kind of pair of network equipment provided by the embodiments of the present application carries out power consumption control;
Fig. 6 is a kind of structural schematic diagram of the system of network core layer provided by the embodiments of the present application;
Fig. 7 is a kind of structural schematic diagram of the master control borad of the network equipment provided by the embodiments of the present application;
Fig. 8 is the structural schematic diagram of the master control borad of another network equipment provided by the embodiments of the present application.
Specific embodiment
Fig. 1 provides a kind of structural schematic diagram of network equipment for the embodiment of the present application, which can be core net
Equipment, convergence switching equipment or routing device etc..By taking the network equipment is interchanger as an example, to the structure of the network equipment into
Row introduces explanation, and referring to Fig. 1, which may include master control borad, network board, interface board and business board.Wherein, master control
Plate is properly termed as mainboard again, mainly includes central processing unit (Central Processor Unit, CPU), memory, chipset
With caching etc. components, master control borad be the control centre of the network equipment, using various interfaces (for example, for install CPU socket,
For the slot etc. according to memory) and connection whole network equipment various pieces, for command and control each section work.
Network board can be the veneer for separating the data forwarding function of business board, is mainly responsible for the data inside net equipment and turns
Network board, is separated the pressure that can mitigate business board by hair, and the network equipment is made to have higher forwarding performance, while
Improve the reliability of the network equipment.For business board for distinguishing different types of service, a network equipment may include multiple
Business board, each business board can carry different business.Interface board is mainly used for realizing sending and receiving for data, generally may be used
To include Optical Fiber Interface Board and electrical interface plate etc..
Fig. 2 is a kind of flow chart of power consumption control method provided by the embodiments of the present application, and this method is applied to include N number of list
In the network equipment of plate, referring to fig. 2, this method includes following steps.
Step 201:If the power consumption parameter of the network equipment meets preset condition, according to shutdown precedence information, from default
M veneer in selection shutdown highest priority target single board.Wherein, shutdown precedence information is used to indicate preset M
The shutdown priority of each veneer in veneer, M are less than or equal to N.
Wherein, the power consumption parameter of the network equipment meet preset condition be referred to as the network equipment power consumption reach power consumption envelope
A power consumption threshold value is arranged for network device in advance, when the power consumption of the network equipment reaches the power consumption threshold value, i.e., to this in top
The network equipment carries out power consumption control, so that the power consumption of the network equipment is no more than the power consumption threshold value.The power consumption threshold value can be according to tool
The power consumption situation of the network equipment of body and the parameters such as the power supply of central machine room and heat dissipation are configured, the embodiment of the present application pair
This is not especially limited.
In addition, veneer is referred to as module, it is a kind of insertion equipment that cannot be used alone, different veneers has not
Same function.For example, some veneers are used to add or change the type of network connection, some veneers are for increasing or decreasing port
Quantity, some veneers are used to add for product or remove additional function.Veneer includes but is not limited to line card, port adapter
With network adapter etc., but the veneer does not include that can be inserted into receiver (for example, SFP, SFP+, XFP) or modular electric power
Supply.The energy-efficient treatment of different veneers has different modes in the network equipment, and unification is indicated using " shutdown " in the application,
In practical application, shutdown may be lower electricity, reset etc. and a kind of or a series of will affect service quality but reduce power consumption and effect is aobvious
The energy saving means of work.Here energy saving means usually do not include supply voltage adjustment, CPU frequency modulation and voltage modulation and efficiency Ethernet constant pitch
It can the lesser means of effect.
Furthermore preset M veneer is the veneer that can be turned off in the network equipment, and only to there are standby in the embodiment of the present application
Shutdown processing is carried out with the veneer of veneer, if there is no standby boards or standby board to be in not service state for certain veneer,
Shutdown processing is not done to the veneer.The shutdown that shutdown precedence information is used to indicate each veneer in preset M veneer is preferential
Grade, the shutdown priority can refer to the sequencing of shutdown, the shutdown priority of each veneer can by the network equipment according to
A possibility that network reliability, the business significance level (i.e. service priority) of carrying, shutdown are implemented and reduction power consumption effect
Etc. dynamically safeguarded.Wherein, it for there is the lower veneer of service priority of standby board and carrying, corresponds to
Shutdown priority may be higher.In addition, initial shutdown precedence information can be comprehensive by human configuration or by the network equipment
The parameters such as service priority, veneer power are closed to be determined.
Specifically, when the power consumption of the network equipment reaches power consumption threshold value, the network equipment can according to shutdown precedence information,
It determines the shutdown priority of each veneer in preset M veneer, and the veneer for turning off highest priority is selected as target list
Plate.
Step 202:Judge that target single board whether there is the standby board in normal condition, however, it is determined that there are spare lists
The corresponding business of target single board is then transferred to standby board by plate.
Wherein, target single board can have one or more standby board, after network equipment selection target veneer, net
Network equipment may determine that in one or more standby board of target single board, if there is the spare list in normal condition
Plate, however, it is determined that there is the standby board in normal condition, then the corresponding business of target single board is transferred on standby board.Tool
Body, the corresponding business of target single board may include Added Business, at least one of business have been established, therefore, the network equipment
The corresponding business of target single board is transferred to standby board, may include:If target single board includes Added Business, the network equipment
Added Business is established on standby board;If target single board includes that business has been established, the network equipment will have been established business and move
It moves on standby board.
In addition, the network equipment can be with when the network equipment determines that target single board has the standby board in normal condition
The state of target single board is adjusted to pre- off state, pre- off state refers to after being chosen to be the veneer that will be turned off, and
Before carrying out shutdown processing, the target single board state in which.When target single board is under pre- off state, target single board is no longer
Receive Added Business, and business has been established gradually to migrate to standby board.
Step 203:Target single board is subjected to shutdown processing.
When the corresponding business of target single board is successfully transferred on standby board by the network equipment, the network equipment can be by mesh
Mark veneer carries out shutdown processing.Specifically, the network equipment can carry out deactivation processing to target single board, or to target single board
Enabled processing is carried out, lower electricity either is carried out to target single board, is resetted or a series of be will affect service quality but reduce power consumption
And effective energy saving means, to realize the power consumption control to the network equipment.In practical applications, specific shutdown is handled
Mode is related with specific veneer, and the embodiment of the present application is not construed as limiting this.
Further, referring to Fig. 3, judge that target single board whether there is the standby board in normal condition in the network equipment
Later, this method can also include:Step 204a or step 204b.
Step 204a:If it is determined that the standby board in normal condition is not present in target single board, then target single board pair is reduced
The shutdown priority answered.
When the network equipment determines that the standby board in normal condition is not present in target single board, i.e. target single board shutdown is lost
It loses, the network equipment can reduce the corresponding shutdown priority of target single board.Specifically, the network equipment can be corresponding by target single board
Shutdown priority be reduced to it is minimum, or by the corresponding shutdown priority of target single board reduce certain grade (for example, reduce by one
Grade is perhaps multistage) or according to corresponding shutdown priority of other predetermined manners reduction target single board etc..Later, network
Equipment can realize the network equipment according to method described in step 201- step 203 according to the shutdown precedence information newly obtained
Power consumption control.
Step 204b:If the corresponding business of target single board is transferred to standby board not successfully, it is corresponding to reduce target single board
Shutdown priority.
During the corresponding business of target single board is transferred to standby board by the network equipment, if target single board is corresponding new
Increasing business establishes failure on standby board or corresponding business migration to the standby board that has been established of target single board fails, then
The corresponding business of target single board is transferred to standby board, i.e. target single board shutdown failure not successfully, so that the network equipment can drop
The corresponding shutdown priority of low target veneer.The network equipment reduce target single board it is corresponding shutdown priority method can with it is upper
The method stated in step 204a is consistent, and details are not described herein for the embodiment of the present application.
Specifically, the network equipment can recorde target if the corresponding business of target single board is transferred to standby board not successfully
Veneer turns off turkey, and when the shutdown frequency of failure reaches predetermined number of times, reduces the corresponding shutdown priority of target single board.
The predetermined number of times can be once, be also possible to repeatedly, the embodiment of the present application is not construed as limiting this.Target is reduced in the network equipment
After the corresponding shutdown priority of veneer, the network equipment can be according to the shutdown precedence information newly obtained, according to step 201-
The power consumption control of the realization network equipment of method described in step 203.
Further, referring to fig. 4, this method further includes:Step 200.Wherein, step 200 and above-mentioned steps 201- step
203 in no particular order sequentially can be located at step 201 for before by step 200 in Fig. 4 and be illustrated.
Step 200:According to the specified parameter of each veneer in preset M veneer, shutdown precedence information is determined.
Wherein, specified parameter includes at least one in following parameter:Service priority (Service Importance,
It SI), whether is standby board (Backup, B), maximum capacity (Maximum Capacity, MC), maximum power dissipation (Maximum
Power, MP), maximum efficiency (Maximum Energy Efficiency, MEE), real-time traffic (Realtime Traffic,
RT), new flow increasing (New Incoming Traffic, NIT), real time power consumption (Realtime Power, RP) sequence, real-time energy
Imitate (Realtime Energy Efficiency, REE) sequence, shutdown failure (Shutdown Failure, SDF) number.
Service priority SI is used to indicate the significance level of the business of veneer carrying.Maximum capacity MC, the maximum work of veneer
Consumption MP and maximum efficiency MEE belong to static parameter, can determine after veneer determines.Real-time traffic RT is properly termed as real-time industry
Business occupancy, new flow increasing NIT is properly termed as Added Business occupancy, and new flow increasing NIT can refer in a period of time newly
The uninterrupted of increasing.Real-time traffic RT, real time power consumption RP and real-time energy efficiency REE belong to dynamic parameter, run in the network equipment
Cheng Zhonghui dynamically changes.
When specified parameter includes multiple in the above parameter, since the unit of different parameters is different, and numerical value difference compared with
Greatly, Multiple factors can not directly be integrated and obtain shutdown precedence information, therefore it can be normalized.The application is real
Apply in example and first once sorted to the single parameter of each veneer, further according to each single parameter marshalling and weight coefficient product and
A comprehensive score is obtained, then the comprehensive score of multiple veneers is ranked up, obtains final shutdown precedence information.
For example, be illustrated so that specified parameter includes all of above parameter as an example, the corresponding weight system of above-mentioned all parameters
Number can be expressed as a~j, then the corresponding comprehensive score Score of t-th of veneertIt can be shown below, the value of t is 1
~M.Later, the comprehensive score of M veneer is ranked up to get excellent to the shutdown for the shutdown priority for being used to indicate M veneer
First grade information.
Scoret=a*SIt+b*Bt+c*MCt+d*MPt+e*MEEt+f*RTt+g*NITt+h*RPt+i*REEt+j*SDFt
In formula, SIt、Bt、MCt、MPt、MEEt、RTt、NITt、RPt、REEtAnd SDFtIndicate each single ginseng of t-th of veneer
Several sequences.
Further, its corresponding finger can also be determined for each veneer according to the demand of actual scene and application effect
Determine parameter, as different veneers selects different parameter combinations, determines that veneer is corresponding according to the parameter combination of selection later
Turn off priority.Specifically, determining shutdown precedence information in the specified parameter according to each veneer in preset M veneer
Before, the network equipment can also determine the finger of each veneer according to the corresponding preset strategy of veneer each in preset M veneer
Determine parameter.
Wherein, if preset strategy includes business preference strategy, specified parameter at least may include:In SI, MC, RT, NIT
It is one or more.When carrying out comprehensive score calculating according to above-mentioned formula, the power for the parameter that can not include by specified parameter
It is denoted as zero again.For example, then weight coefficient b, d, e, h, i and j is 0 when the specified parameter only includes SI, MC, RT and NIT.
Alternatively, if preset strategy includes power consumption preference strategy, specified parameter at least may include:In MP, RP sequence
It is one or more.Equally, when carrying out comprehensive score calculating according to above-mentioned formula, the parameter that can not include by specified parameter
Weight is denoted as zero.For example, then weight coefficient a, b, c, e, f, g, i and j is 0 when the specified parameter only includes that MP and RP sorts.
Alternatively, if preset strategy includes energy efficiency priority strategy, specified parameter at least may include:In MEE, REE sequence
It is one or more.Equally, when carrying out comprehensive score calculating according to above-mentioned formula, the parameter that can not include by specified parameter
Weight be denoted as zero.For example, then weight coefficient a, b, c, d, f, g, h and j is when the specified parameter only includes that MEE and REE sorts
0。
Alternatively, specified parameter at least may include if preset strategy includes strategy based on static parameter:In MC, MP
It is one or more.Equally, when carrying out comprehensive score calculating according to above-mentioned formula, the parameter that can not include by specified parameter
Weight is denoted as zero.For example, then weight coefficient a, b, e, f, g, h, i and j is 0 when the specified parameter only includes MC and MP.Further
, if only with strategy based on static parameter, it, can be by target single board when carrying out Dynamic Maintenance to shutdown precedence information
The trigger condition successfully as Dynamic Maintenance whether is turned off, and when target single board shutdown is unsuccessful, it is corresponding to reduce target single board
Shutdown priority, so as to reduce the number judged in vain.
Alternatively, specified parameter at least may include if preset strategy includes strategy based on dynamic parameter:RT, RP sequence,
It is one or more in SDF number.It equally, can be by specified parameter not when carrying out comprehensive score calculating according to above-mentioned formula
Including the weight of parameter be denoted as zero.For example, the specified parameter only include RT, RP sequence and SDF times it is several when, then weight coefficient a,
B, c, e, g, h and i are 0.Further, for strategy based on dynamic parameter, the network equipment can recorde target single board shutdown and lose
Event is lost, and the target single board shutdown turkey of record and other parameters is combined to weight obtain corresponding shutdown priority together
Sequence.
It should be noted that preset strategy be above-mentioned business preference strategy, power consumption preference strategy, energy efficiency priority strategy,
When strategy based on static parameter, any strategy based on dynamic parameter in strategy, specific ginseng that corresponding specified parameter includes
Number can also be different from the above-mentioned parameter enumerated, for example, corresponding specified parameter may include one in the parameter enumerated or
Person is multiple, also may include unlisted other parameters, and the embodiment of the present application is not specifically limited in this embodiment.In addition, the default plan
Also may include other strategy slightly other than including the above-mentioned several strategies enumerated, the embodiment of the present application equally to this not
It limits.
Specifically, the network equipment can carry out the power consumption of the network equipment according to the schematic diagram of power consumption control shown in fig. 5
Control.Firstly, the network equipment judges whether its power consumption parameter reaches power consumption threshold value, terminate if not up to power consumption threshold value, if reaching
Next step judgement is then carried out to power consumption threshold value.Specifically, judge whether there is the preset veneer turned off, if it does not exist then into
Row alerts and terminates to execute;Newest shutdown precedence information, the target list of selection shutdown highest priority are then read if it exists
Plate.Secondly, judging that target single board whether there is the standby board in normal condition, shutdown failure thing is then recorded if it does not exist
Part re-starts the judgement of power consumption control;Pre- off state then is set by target single board if it exists, target single board is corresponding
On business migration to the standby board.For example, establishing Added Business on standby board, business migration will have been established to spare
On veneer.Finally, judging whether the corresponding business of target single board migrates success, shutdown failure thing is recorded if not migrating failure
Part;Shutdown processing is carried out to target single board if migrating successfully, to terminate the process of this power consumption control.
Further, power consumption control method provided by the embodiments of the present application can be applied not only to single network equipment, also
It can be applied to the network system of two or more equipment formation.In practical applications, for the needs of reliability, network
Core layer, convergence layer often constitute one by two or more equipment, and there are the systems of certain redundancy backup.There are redundancies for this
The system of backup can also carry out power consumption control by provided power consumption control method through the foregoing embodiment, by using the program
Power consumption control is carried out, the power consumption control between striding equipment may be implemented, while ensuring that individual device meets power supply, cooling requirements.
For example, the system of network core layer as shown in FIG. 6, by taking the system includes two independently-powered equipment as an example into
Row explanation.Each equipment in Fig. 6 may include multiple modules, and is mutually backups by two modules that double-head arrow dotted line connects
Relationship, two modules are located in the different network equipments, primary module are indicated in Fig. 6 with solid line boxes, with dotted line side
Frame indicates spare module.Specifically, when the power consumption parameter of certain equipment meets the power consumption parameter of preset condition or two equipment
It is all satisfied preset condition, then can judge spare module by method provided by the embodiments of the present application, and carry out to spare module
Shutdown processing, i.e. selection target module simultaneously carry out shutdown processing to object module.Wherein, judge spare module and to stand-by set of dies
The detailed process that block carries out shutdown processing can be carried out with reference to selection target veneer in the embodiment of the present application and to target single board
The description of processing is turned off, the embodiment of the present application repeats no more this.
In power consumption control method provided by the embodiments of the present application, the network equipment is determining that its power consumption parameter meets preset condition
When, according to the shutdown precedence information for being used to indicate the shutdown priority of each veneer in preset M veneer, from preset M
The target single board of selection shutdown highest priority in a veneer, and it is spare in normal condition to judge that target single board whether there is
Veneer, however, it is determined that there are standby boards, then the corresponding business of target single board are transferred to standby board, later by target single board into
Row shutdown processing, to realize the power consumption control to the network equipment.Meanwhile in the transition period of business development, using the application reality
The power consumption control method for applying example offer, on the one hand may insure that the power consumption of the network equipment does not exceed the power supply of computer room, heat radiation energy
On the other hand power also ensures the normal operation of business, so as to so that computer room is gradually transformed according to practical business demand, drop
The cost pressure of low deployed with devices.
It is above-mentioned that mainly scheme provided by the embodiments of the present application is described from the angle of network element.It is understood that
In order to realize the above functions, it comprises execute the corresponding hardware configuration of each function and/or soft for network element, such as the network equipment etc.
Part module.Those skilled in the art should be readily appreciated that, described in conjunction with the examples disclosed in the embodiments of the present disclosure
Network element and algorithm steps, the application can be realized with the combining form of hardware or hardware and computer software.Some function is studied carefully
Unexpectedly it is executed in a manner of hardware or computer software driving hardware, the specific application and design constraint depending on technical solution
Condition.Professional technician can use different methods to achieve the described function each specific application, but this
Kind is realized it is not considered that exceeding scope of the present application.
The embodiment of the present application can carry out the division of functional module according to above method example to the network equipment, for example, can
With each functional module of each function division of correspondence, two or more functions can also be integrated in a processing module
In.Above-mentioned integrated module both can take the form of hardware realization, can also be realized in the form of software function module.It needs
It is noted that be schematical, only a kind of logical function partition to the division of module in the embodiment of the present application, it is practical real
It is current that there may be another division manner.
In the case where each function division of use correspondence each functional module, Fig. 7 shows involved in above-described embodiment
And the network equipment master control borad a kind of possible structural schematic diagram, the master control borad 300 of the network equipment includes:Selecting unit
301, judging unit 302, buanch unit 303 and processing unit 304.Wherein, selecting unit 301 is for executing in Fig. 2-Fig. 4
Step 201;Judging unit 302, which is used to execute in the step 202 of Fig. 2-Fig. 4, judges that target single board whether there is in normal condition
Standby board the step of;It, will in step 202 of the buanch unit 303 for executing Fig. 2-Fig. 4 if it is determined that there are the standby board
The step of corresponding business of target single board is transferred to the standby board;Processing unit 304, for executing the step in Fig. 2-Fig. 4
203.Further, the network equipment 300 further includes:Determination unit 305;Wherein it is determined that unit 305 is used to execute the step in Fig. 3
Step 200 in rapid 204a or step 204b and Fig. 4.All related contents for each step that above method embodiment is related to
The function description of corresponding function module can be quoted, details are not described herein.
In hardware realization, above-mentioned selecting unit 301, judging unit 302, processing unit 304 and determination unit 305 can be with
For the processor of master control borad in the network equipment.
Shown in Fig. 8, the master control borad 310 of the network equipment involved in above-described embodiment for providing for embodiments herein
A kind of possible logical construction schematic diagram.The master control borad 310 of the network equipment includes:Processor 312, communication interface 313, storage
Device 311 and bus 314.Processor 312, communication interface 313 and memory 311 are connected with each other by bus 314.Applying
Embodiment in, processor 312 is used to carry out control management to the movement of the master control borad 310 of the network equipment, for example, processor
312 for executing the step 201- step 203 in Fig. 2-Fig. 4, the step 204a in Fig. 3 or the step in step 204b, Fig. 4
200, and/or for other processes of techniques described herein.Communication interface 313 is used to support the master control borad of the network equipment
310 are communicated.Memory 311, the program code and data of the master control borad 310 for storage networking device.
Wherein, processor 312 can be central processor unit CPU, general processor, and digital signal processor is dedicated
Integrated circuit, field programmable gate array or other programmable logic device, transistor logic, hardware component or its
Any combination.It, which may be implemented or executes, combines various illustrative logic blocks described in present disclosure, module
And circuit.The processor is also possible to realize the combination of computing function, such as combines comprising one or more microprocessors, number
Word signal processor and the combination of microprocessor etc..Bus 314 can be Peripheral Component Interconnect standard (Peripheral
Component Interconnect, PCI) bus or expanding the industrial standard structure (Extended Industry Standard
Architecture, EISA) bus etc..The bus can be divided into address bus, data/address bus, control bus etc..For convenient for
It indicates, is only indicated with a thick line in Fig. 8, it is not intended that an only bus or a type of bus.
In another embodiment of the application, a kind of computer readable storage medium, computer-readable storage medium are also provided
Computer executed instructions are stored in matter, when at least one processor of equipment executes the computer executed instructions, equipment is held
Power consumption control method provided by any diagram in row Fig. 2-Fig. 4.
In another embodiment of the application, a kind of computer program product is also provided, which includes
Computer executed instructions, the computer executed instructions store in a computer-readable storage medium;At least one processing of equipment
Device can read the computer executed instructions from computer readable storage medium, at least one processor executes computer execution
Instruction is so that equipment implements power consumption control method provided by any diagram in Fig. 2-Fig. 4.
In the embodiment of the present application, the network equipment is when determining that its power consumption parameter meets preset condition, according to being used to indicate
The shutdown precedence information of the shutdown priority of each veneer in preset M veneer selects shutdown from preset M veneer
The target single board of highest priority, and judge that target single board whether there is the standby board in normal condition, however, it is determined that exist
The corresponding business of target single board is then transferred to standby board, target single board is carried out shutdown processing later, with reality by standby board
Now to the power consumption control of the network equipment.Meanwhile in the transition period of business development, using power consumption control provided by the embodiments of the present application
On the one hand method processed may insure that the power consumption of the network equipment does not exceed the power supply of computer room, heat-sinking capability, on the other hand also ensure
The normal operation of business, so as to reduce the cost of deployed with devices so that computer room is gradually transformed according to practical business demand
Pressure.
Finally it should be noted that:The above, the only specific embodiment of the application, but the protection scope of the application is simultaneously
Not limited to this, any change or replacement within the technical scope of the present application should all cover the protection model in the application
Within enclosing.Therefore, the protection scope of the application should be based on the protection scope of the described claims.
Claims (15)
1. a kind of power consumption control method, which is characterized in that applied to the network equipment including N number of veneer, the N is greater than or equal to
2, the method includes:
If the power consumption parameter of the network equipment meets preset condition, according to shutdown precedence information, from preset M veneer
The target single board of middle selection shutdown highest priority;Wherein, the shutdown precedence information is used to indicate the preset M list
The shutdown priority of each veneer in plate, the M are less than or equal to the N;
Judge that the target single board whether there is the standby board in normal condition, however, it is determined that there are the standby boards, then
The corresponding business of the target single board is transferred to the standby board;
The target single board is subjected to shutdown processing.
2. the method according to claim 1, wherein the judgement target single board whether there is in normal
After the standby board of state, the method also includes:
If it is determined that the standby board in normal condition is not present in the target single board, then it is corresponding to reduce the target single board
Shutdown priority;Alternatively,
If the corresponding business of the target single board is transferred to the standby board not successfully, it is corresponding to reduce the target single board
Turn off priority.
3. method according to claim 1 or 2, which is characterized in that the corresponding business of the target single board includes newly-increased industry
It is engaged in and/or has been established business, it is described that the corresponding business of the target single board is transferred to the standby board, including:
If the corresponding business of the target single board includes the Added Business, the Added Business is established in the spare list
On plate;
If the corresponding business of the target single board include it is described business has been established, by the business migration that has been established to described standby
With on veneer.
4. method according to claim 1-3, which is characterized in that the method also includes:
According to the specified parameter of each veneer in the preset M veneer, the shutdown precedence information is determined;Wherein, institute
Stating specified parameter includes at least one in following parameter:It service priority SI, whether is standby board B, maximum capacity MC, most
Big power consumption MP, it maximum efficiency MEE, real-time traffic RT, new flow increasing NIT, real time power consumption RP sequence, real-time energy efficiency REE sequence, closes
SDF number of disconnected failure.
5. according to the method described in claim 4, it is characterized in that, described according to each veneer in the preset M veneer
Specified parameter, before determining the shutdown precedence information, the method also includes:
According to the corresponding preset strategy of veneer each in the preset M veneer, the specified parameter of each veneer is determined.
6. according to the method described in claim 5, it is characterized in that, if the preset strategy includes business preference strategy, institute
Specified parameter is stated to include at least:It is one or more in SI, MC, RT, NIT;Alternatively,
If the preset strategy includes power consumption preference strategy, the specified parameter is included at least:MP, RP sequence in one or
It is multinomial;Alternatively,
If the preset strategy includes energy efficiency priority strategy, the specified parameter includes at least one in MEE, REE sequence
Or it is multinomial;Alternatively,
If the preset strategy includes strategy based on static parameter, the specified parameter include at least one in MC, MP or
It is multinomial;Alternatively,
If the preset strategy includes strategy based on dynamic parameter, the specified parameter is included at least:RT, RP sequence, SDF times
It is one or more in number.
7. method according to claim 1-6, which is characterized in that described to carry out the target single board at shutdown
Reason, including:
The target single board is subjected to deactivation processing;Alternatively, the target single board is carried out enabled processing.
8. a kind of network equipment, which is characterized in that the network equipment includes N number of veneer, and the N is greater than or equal to 2, the net
Network equipment further includes:
Selecting unit, if the power consumption parameter for the network equipment meets preset condition, according to shutdown precedence information, from
The target single board of selection shutdown highest priority in preset M veneer;Wherein, the shutdown precedence information is used to indicate institute
The shutdown priority of each veneer in preset M veneer is stated, the M is less than or equal to the N;
Judging unit, for judging that the target single board whether there is the standby board in normal condition;
Buanch unit, for if it is determined that there are the standby boards, being then transferred to the corresponding business of the target single board described
Standby board;
Processing unit, for the target single board to be carried out shutdown processing.
9. the network equipment according to claim 8, which is characterized in that the network equipment further includes:
Determination unit, for if it is determined that the target single board then reduces institute there is no the standby board in normal condition
State the corresponding shutdown priority of target single board;Alternatively,
Determination unit, if being transferred to the standby board not successfully for the corresponding business of the target single board, reduce described in
The corresponding shutdown priority of target single board.
10. the network equipment according to claim 8 or claim 9, which is characterized in that the corresponding business of the target single board includes new
Increasing business and/or business has been established, the buanch unit is specifically used for:
If the corresponding business of the target single board includes the Added Business, the Added Business is established in the spare list
On plate;
If the corresponding business of the target single board include it is described business has been established, by the business migration that has been established to described standby
With on veneer.
11. according to the described in any item network equipments of claim 8-10, which is characterized in that the network equipment further includes:
Determination unit determines the shutdown priority for the specified parameter according to each veneer in the preset M veneer
Information;Wherein, the specified parameter includes at least one in following parameter:Service priority SI, whether be standby board B,
Maximum capacity MC, maximum power dissipation MP, maximum efficiency MEE, real-time traffic RT, new flow increasing NIT, real time power consumption RP sort, in real time
Efficiency REE sequence, shutdown SDF number of failure.
12. the network equipment according to claim 11, which is characterized in that the determination unit is also used to:
According to the corresponding preset strategy of veneer each in the preset M veneer, the specified parameter of each veneer is determined.
13. the network equipment according to claim 12, which is characterized in that if the preset strategy includes the preferential plan of business
Slightly, then the specified parameter includes at least:It is one or more in SI, MC, RT, NIT;Alternatively,
If the preset strategy includes power consumption preference strategy, the specified parameter is included at least:MP, RP sequence in one or
It is multinomial;Alternatively,
If the preset strategy includes energy efficiency priority strategy, the specified parameter is included at least:One in MEE, REE sequence
Or it is multinomial;Alternatively,
If the preset strategy includes strategy based on static parameter, the specified parameter is included at least:One in MC, MP or
It is multinomial;Alternatively,
If the preset strategy includes strategy based on dynamic parameter, the specified parameter is included at least:RT, RP sequence, SDF times
It is one or more in number.
14. according to the described in any item network equipments of claim 8-13, which is characterized in that the processing unit is specifically used for:
The target single board is subjected to deactivation processing;Alternatively, the target single board is carried out enabled processing.
15. a kind of network equipment, which is characterized in that the network equipment includes processor, memory, communication interface and bus,
Store code and data in the memory, the processor, the memory and the communication interface are connected by the bus
It connects, the code that the processor runs in the memory makes the network equipment execute any one of the claims 1-7
The power consumption control method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710380127.4A CN108933687B (en) | 2017-05-25 | 2017-05-25 | Power consumption control method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710380127.4A CN108933687B (en) | 2017-05-25 | 2017-05-25 | Power consumption control method and device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108933687A true CN108933687A (en) | 2018-12-04 |
CN108933687B CN108933687B (en) | 2020-12-18 |
Family
ID=64450126
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710380127.4A Active CN108933687B (en) | 2017-05-25 | 2017-05-25 | Power consumption control method and device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108933687B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111796647A (en) * | 2020-06-30 | 2020-10-20 | 联想(北京)有限公司 | Detection method and electronic equipment |
CN111914000A (en) * | 2020-06-22 | 2020-11-10 | 华南理工大学 | Server power capping method and system based on power consumption prediction model |
CN112214315A (en) * | 2020-09-23 | 2021-01-12 | 深圳云天励飞技术股份有限公司 | Chip control method and device, artificial intelligence chip and terminal equipment |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2009076092A2 (en) * | 2007-12-10 | 2009-06-18 | Whirlpool Corporation | Remote user interface for an appliance network |
CN102665261A (en) * | 2012-05-21 | 2012-09-12 | 大唐移动通信设备有限公司 | Power-saving method and system for hardware service processing node plate |
CN103002494A (en) * | 2012-12-25 | 2013-03-27 | 上海寰创通信科技股份有限公司 | Device and method for energy-saving control of household long term evolution (LET) router |
CN103744767A (en) * | 2013-12-31 | 2014-04-23 | 上海斐讯数据通信技术有限公司 | Temperature control method of core switch equipment |
CN103763740A (en) * | 2014-01-26 | 2014-04-30 | 上海大唐移动通信设备有限公司 | Method and device for balancing loads of single boards |
CN103916261A (en) * | 2013-01-09 | 2014-07-09 | 华为技术有限公司 | Method for determining the number of network devices needing to be in energy-saving mode and control device |
CN106612519A (en) * | 2015-10-27 | 2017-05-03 | 大唐移动通信设备有限公司 | Single board backup method and device for radio network controller (RNC) |
CN106656580A (en) * | 2016-11-29 | 2017-05-10 | 华为技术有限公司 | Business state migration method and device |
-
2017
- 2017-05-25 CN CN201710380127.4A patent/CN108933687B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2009076092A2 (en) * | 2007-12-10 | 2009-06-18 | Whirlpool Corporation | Remote user interface for an appliance network |
CN102665261A (en) * | 2012-05-21 | 2012-09-12 | 大唐移动通信设备有限公司 | Power-saving method and system for hardware service processing node plate |
CN103002494A (en) * | 2012-12-25 | 2013-03-27 | 上海寰创通信科技股份有限公司 | Device and method for energy-saving control of household long term evolution (LET) router |
CN103916261A (en) * | 2013-01-09 | 2014-07-09 | 华为技术有限公司 | Method for determining the number of network devices needing to be in energy-saving mode and control device |
CN103744767A (en) * | 2013-12-31 | 2014-04-23 | 上海斐讯数据通信技术有限公司 | Temperature control method of core switch equipment |
CN103763740A (en) * | 2014-01-26 | 2014-04-30 | 上海大唐移动通信设备有限公司 | Method and device for balancing loads of single boards |
CN106612519A (en) * | 2015-10-27 | 2017-05-03 | 大唐移动通信设备有限公司 | Single board backup method and device for radio network controller (RNC) |
CN106656580A (en) * | 2016-11-29 | 2017-05-10 | 华为技术有限公司 | Business state migration method and device |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111914000A (en) * | 2020-06-22 | 2020-11-10 | 华南理工大学 | Server power capping method and system based on power consumption prediction model |
CN111914000B (en) * | 2020-06-22 | 2024-03-26 | 华南理工大学 | Server power capping method and system based on power consumption prediction model |
CN111796647A (en) * | 2020-06-30 | 2020-10-20 | 联想(北京)有限公司 | Detection method and electronic equipment |
CN111796647B (en) * | 2020-06-30 | 2022-11-18 | 联想(北京)有限公司 | Detection method and electronic equipment |
CN112214315A (en) * | 2020-09-23 | 2021-01-12 | 深圳云天励飞技术股份有限公司 | Chip control method and device, artificial intelligence chip and terminal equipment |
CN112214315B (en) * | 2020-09-23 | 2024-03-29 | 深圳云天励飞技术股份有限公司 | Chip control method and device, artificial intelligent chip and terminal equipment |
Also Published As
Publication number | Publication date |
---|---|
CN108933687B (en) | 2020-12-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9684364B2 (en) | Technologies for out-of-band power-based task scheduling for data centers | |
US20160378570A1 (en) | Techniques for Offloading Computational Tasks between Nodes | |
CN102150393B (en) | Method and device for power management of network | |
CN107409053B (en) | Active Ethernet power supply method and system | |
WO2015023191A1 (en) | Power balancing to increase workload density and improve energy efficiency | |
EP2922254A1 (en) | Method for establishing control channel, forwarding point and controller | |
CN108933687A (en) | A kind of power consumption control method and device | |
CN105516292A (en) | Hot standby method of cloud platform of intelligent substation | |
EP2852113B1 (en) | Load sharing method and device, and single board | |
CN114371912A (en) | Virtual network management method of data center and data center system | |
CN102811152A (en) | Method for realizing real-time transaction and data exchange of multiple main bus network communication | |
CN105763488B (en) | Data center aggregation core switch and backboard thereof | |
CN105430028A (en) | Service calling method, service providing method, and node | |
CN103188099B (en) | A kind of backup method of multi-application system, Apparatus and system | |
CN101853185B (en) | Blade server and service dispatching method thereof | |
CN103299298A (en) | Service processing method and system | |
Yuan et al. | Disaggregated optical data center in a box network using parallel OCS topologies | |
CN115633037A (en) | Method, device, virtual gateway equipment, medium and system for forwarding data packet | |
CN109343688A (en) | A kind of OCP current range adjusting method, device, terminal and storage medium | |
CN209328011U (en) | Fly control communication system | |
CN112383471A (en) | Method, device and equipment for managing knife box link and machine readable storage medium | |
EP4239453A1 (en) | Network chip management method and apparatus, communication device, and storage medium | |
CN219247874U (en) | Power line routing service device | |
CN116048413B (en) | IO request processing method, device and system for multipath storage and storage medium | |
Chung et al. | An3: A low-cost, circuit-switched datacenter network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |