CN108921386A CN201810581723.3A CN201810581723A CN108921386A CN 108921386 A CN108921386 A CN 108921386A CN 201810581723 A CN201810581723 A CN 201810581723A CN 108921386 A CN108921386 A CN 108921386A
Authority
CN
China
Prior art keywords
line
line walking
attendant
efficiency
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810581723.3A
Other languages
Chinese (zh)
Inventor
刘均
姚明
唐海峰
张勇
王佩敏
解大
吴昊
莫颖涛
王昭夏
曹勇
张海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shanghai Electric Power Co Ltd
Original Assignee
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanghai Electric Power Co Ltd filed Critical State Grid Shanghai Electric Power Co Ltd
Priority to CN201810581723.3A priority Critical patent/CN108921386A/en
Publication of CN108921386A publication Critical patent/CN108921386A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06398Performance of employee with respect to a job function
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

A kind of line walking efficiency automatic examination method for power-line patrolling, belongs to inspection field.It is calculated from day line walking efficiency, moon line walking efficiency and year line walking efficiency respectively by the working efficiency of quantization line attendant, passes through the digital intuitive working efficiency for embodying line attendant, the error of line walking is analyzed simultaneously, line walking error is considered, so that calculation method is more rigorous, accurately.The proper implementation of this method, the line walking efficiency for facilitating rational evaluation power-line patrolling person have energetically effect to line attendant's work, can guarantee that line attendant more efficiently carries out line walking.

Description

A kind of line walking efficiency automatic examination method for power-line patrolling
Technical field
The present invention relates to electric inspection process fields, and in particular, to a kind of line walking efficiency calculation method.
Background technique
" electric power be industry leading ", the fast and stable development of not power industry, just not no national economy is lasting, steady Step, rapid growth.And the effect of transmission line of electricity and its surrounding devices is very crucial in transmission system.In practice, power line Road and equipment are subjected to the effect of normal mechanical load and electric load due to being chronically exposed among the Nature, but also It is subjected to the infringement of the external force such as filth, lightning stroke, high wind, flood, landslide, depression, earthquake and bird pest.Many factors will promote on route Each component ageing, fatigue, oxidation and corrosion such as find and eliminate not in time, it is possible to can develop into various failures, to electric power The safety and stabilization of system constitute a threat to.Based on such consideration, how safe, reliable, efficient carry out inspection, problem is existed It is found in the shortest time and solves just to seem increasingly important.So, the quantization of line walking efficiency is just necessary, can be raising Routing inspection efficiency provides data foundation, is formed and is motivated to inspector, improves the efficiency of inspection.
Summary of the invention
In view of the above technical problems, the object of the present invention is to provide a kind of line walking efficiency automatic examinations for power-line patrolling Method.
To achieve the above object, the present invention is realized according to following technical scheme:
A kind of line walking efficiency automatic examination method for power-line patrolling, including following technology segment:
1, day line walking efficiency
When power-line patrolling personnel administration land be divided into monolithic when, line attendant day line walking efficiency calculation mode be
ηD=1/T (1)
In formula:T is that power-line patrolling person makes an inspection tour region the time it takes, unit h;ηDIt is imitated for the day line walking of line attendant Rate.
The value of T can be obtained by amounting to the number of acquisition line attendant's position coordinates in grid:
T=(N-1) Δ t (2)
The region of power-line patrolling personnel administration is when being divided into N block, line attendant day line walking efficiency calculation mode be
In formula:ηDFor the day line walking efficiency of line attendant;TiRegion unit i the time it takes, unit are maked an inspection tour for power-line patrolling person For h;αiFor weight occupied by region unit i.
2, moon line walking efficiency
Analysis based on the line attendant that obtains above day line walking efficiency as a result, power-line patrolling personnel moon line walking efficiency calculation Mode is
In formula:ηMFor the moon line walking efficiency of line attendant;The number of days of N ' expression this month power-line patrolling person participation line walking task;ηDi For power-line patrolling person i-th of line walking day day line walking efficiency;βiFor weight of i-th of line walking day occupied by this middle of the month.
3, year line walking efficiency
Similarly, the moon line walking efficiency analysis based on the line attendant obtained above is as a result, the year line walking of power-line patrolling personnel is imitated Rate calculation is
In formula:ηYFor the year line walking efficiency of line attendant;N " indicates that this year power-line patrolling person participates in the months of line walking task;ηMi For power-line patrolling person i-th of line walking moon moon line walking efficiency;γiFor the weight that i-th of line walking moon is occupied in this year.
4, consider line walking error
Line patrolling management system is to the judge of the final line walking efficiency of line attendant also by relative error ε*The range accounted for, Because when this parameter reflects line attendant's line walking and the laminating degree of cut cable, reflecting the conscientious degree of his work indirectly:
5, return path judges
In view of the subjective initiative of line attendant, learn that there may be one section not patrol path by Intelligent line patrolling device at it Afterwards, line attendant has certain probability that can return to position when deviateing cut cable, compensates to path is not patrolled.At this point, just needing pair Its return path situation is judged.
Compared with prior art, the present invention having the advantages that:
A kind of line walking efficiency calculation method of the present invention, this method quantify the work effect of line attendant with the algorithm of science Rate is calculated from day line walking efficiency, moon line walking efficiency and year line walking efficiency respectively, passes through digital intuitive embodiment line attendant's Working efficiency, while the error of line walking is analyzed, line walking error is considered, so that calculation method is more rigorous, accurately.
Detailed description of the invention
Fig. 1 does not patrol path computing schematic diagram for of the invention;
Fig. 2 is that path of not patrolling of the invention returns calculating schematic diagram;
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical solution in the embodiment of the present invention is further described.
A kind of line walking efficiency automatic examination method for power-line patrolling, particular technique part are as follows:
1, day line walking efficiency
When power-line patrolling personnel administration land be divided into monolithic when, line attendant day line walking efficiency calculation mode be
ηD=1/T (1)
In formula:T is that power-line patrolling person makes an inspection tour region the time it takes, unit h;ηDIt is imitated for the day line walking of line attendant Rate.
The value of T can be obtained by amounting to the number of acquisition line attendant's position coordinates in grid:
T=(N-1) Δ t (2)
The region of power-line patrolling personnel administration is when being divided into N block, line attendant day line walking efficiency calculation mode be
In formula:ηDFor the day line walking efficiency of line attendant;TiRegion unit i the time it takes, unit are maked an inspection tour for power-line patrolling person For h;αiFor weight occupied by region unit i.
2, moon line walking efficiency
Analysis based on the line attendant that obtains above day line walking efficiency as a result, power-line patrolling personnel moon line walking efficiency calculation Mode is
In formula:ηMFor the moon line walking efficiency of line attendant;The number of days of N ' expression this month power-line patrolling person participation line walking task;ηDi For power-line patrolling person i-th of line walking day day line walking efficiency;βiFor weight of i-th of line walking day occupied by this middle of the month.
3, year line walking efficiency
Similarly, the moon line walking efficiency analysis based on the line attendant obtained above is as a result, the year line walking of power-line patrolling personnel is imitated Rate calculation is
In formula:ηYFor the year line walking efficiency of line attendant;N " indicates that this year power-line patrolling person participates in the months of line walking task;ηMi For power-line patrolling person i-th of line walking moon moon line walking efficiency;γiFor the weight that i-th of line walking moon is occupied in this year.
4, consider line walking error
Line patrolling management system is to the judge of the final line walking efficiency of line attendant also by relative error ε*The range accounted for, Because when this parameter reflects line attendant's line walking and the laminating degree of cut cable, reflecting the conscientious degree of his work indirectly:
5, return path judges
In view of the subjective initiative of line attendant, learn that there may be one section not patrol path by Intelligent line patrolling device at it Afterwards, line attendant has certain probability that can return to position when deviateing cut cable, compensates to path is not patrolled.At this point, just needing pair Its return path situation is judged.
Compared with prior art, the present invention having the advantages that:
A kind of line walking efficiency calculation method of the present invention, this method quantify the work effect of line attendant with the algorithm of science Rate is calculated from day line walking efficiency, moon line walking efficiency and year line walking efficiency respectively, passes through digital intuitive embodiment line attendant's Working efficiency, while the error of line walking is analyzed, line walking error is considered, so that calculation method is more rigorous, accurately.
Fig. 1 does not patrol path computing schematic diagram for of the invention.As shown in Figure 1, connecting since the motion profile of line attendant has Continuous property, it is believed that do not patrol path and be classified into several segmentations for having certain length, such as lε1And lε2.With lε1For, system is from line attendant In the historical data for uploading latitude and longitude coordinates, meeting formula d is found outij≥dsupPoint range (a1,b1),(a2,b2),(a3,b3)…(an, bn) do not patrol the point range of the cut cable as line attendant, in addition, separately adding two o'clock (a from beginning to end0,b0) and (an+1,bn+1) it is used as boundary Judge a little.There is (a0,b0) and (a1,b1), (an,bn) and (an+1,bn+1) linear equation be:
And have parallel with cut cable and at a distance of dsupLdEquation is:
Joint type (7) and formula (9), formula (8) and formula (9) respectively, can acquire two intersecting point coordinates is (a0.5,b0.5) and (an+0.5,bn+0.5).Their value is respectively:
The two intersection points are line attendant's non-line walking portion boundary point in actual work.Therefore, the distance of this point-to-point transmission It is exactly not patrol cable length caused by this deviation cut cable of the line attendant.Distance can pass through formula therebetweenIt acquires.
Fig. 2 is that path of not patrolling of the invention returns calculating schematic diagram.As shown in Figure 2, first have to find line attendant deviate and Point coordinate (a of line walking maximum distance when returning cut cablei,bi) and (aj,bj), with (ai,bi) for, specific algorithm is:First By system record in front of and after discontinuous point n point position merging suspicion maximum distance point set P.The value of n depends on line attendant and exists One back gauge d of cut cablesupWithin change nyctitropic number, take under normal circumstances n be line attendant deviate cut cable when final stage Coordinate points quantity on dull path.
The point being placed in P at this time is (ai-1,bi-1) and (ai,bi).In order to seek out most distant point when line walking, connect The projected length got off by this two o'clock on cut cable:
Wherein, xi-1As projected length;And di-1And diRespectively (ai-1,bi-1) and (ai,bi) arrive institute's inspection cut cable Distance.
It is d since inspector's maximum can inspect rangesup, therefore when by being located at these to inspector on cut cable Accessible inspection range is compared, and just can obtain most distant point:
IfThen illustrate (ai,bi) it is most distant point, otherwise then indicate (ai-1, bi-1) it is most distant point.When there is n element (a in P1,b1),(a2,b2),(a3,b3)…(ai,bi) up-to-date style (13) becomes:
Thus the most distant point that just can obtain line attendant both sides after deviateing and returning cut cable, accordingly again to the two Point judges effective line walking distance of the cut cable, and can acquire whether it cover cut cable does not patrol path, if It does not cover, and leaves and how much do not patrol path distance.
With (ai,bi) and (aj,bj) for, it can be in the hope of the projector distance x of point-to-point transmission by formula (12)ij, which is original That originally leaves does not always patrol path length.Then calculate two o'clock covering inspects range:
To inspecting range di,jAnd length x is not patrolledijDifference is sought, can show that line attendant makes up situation to do not patrol path:
Δ d=xij-di,j (16)
As Δ d≤0, line patrolling management system will be considered to smoothly complete the line walking work at this, and there is no do not patrol feelings Condition.As Δ d≤0, system then thinks that length is Δ d there are still path is not patrolled.

Claims (2)

1. a kind of line walking efficiency automatic examination method for power-line patrolling, it is characterized in that the line walking efficiency automatic examination side Method includes at least:
(1) day line walking efficiency:
When power-line patrolling personnel administration land be divided into monolithic when, line attendant day line walking efficiency calculation mode be
ηD=1/T (1)
In formula:T is that power-line patrolling person makes an inspection tour region the time it takes, unit h;ηDFor the day line walking efficiency of line attendant.
(2) moon line walking efficiency:
Analysis based on the line attendant that obtains above day line walking efficiency as a result, power-line patrolling personnel moon line walking efficiency calculation mode For
In formula:ηMFor the moon line walking efficiency of line attendant;The number of days of N ' expression this month power-line patrolling person participation line walking task;ηDiFor electricity Day line walking efficiency of the power line attendant i-th of line walking day;βiFor weight of i-th of line walking day occupied by this middle of the month.
(3) year line walking efficiency:
Similarly, by the moon line walking efficiency analysis of the line attendant obtained above as a result, the year of power-line patrolling personnel is based on line walking efficiency Calculation mode is
In formula:ηYFor the year line walking efficiency of line attendant;N " indicates that this year power-line patrolling person participates in the months of line walking task;ηMiFor electricity Moon line walking efficiency of the power line attendant at i-th of line walking moon;γiFor the weight that i-th of line walking moon is occupied in this year.
(4) consider line walking error:
Line patrolling management system is to the judge of the final line walking efficiency of line attendant also by relative error ε*The range accounted for, because When this parameter reflects line attendant's line walking and the laminating degree of cut cable, the conscientious degree of his work is reflected indirectly:
(5) return path judges:
In view of the subjective initiative of line attendant, after it is learnt by Intelligent line patrolling device and not to patrol path there may be one section, Line attendant has certain probability that can return to position when deviateing cut cable, compensates to path is not patrolled.
2. the line walking efficiency automatic examination method described in accordance with the claim 1 for power-line patrolling, it is characterized in that described When not patrolling path and compensating of line attendant, needs to judge its return path situation.
CN201810581723.3A 2018-06-07 2018-06-07 A kind of line walking efficiency automatic examination method for power-line patrolling Pending CN108921386A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810581723.3A CN108921386A (en) 2018-06-07 2018-06-07 A kind of line walking efficiency automatic examination method for power-line patrolling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810581723.3A CN108921386A (en) 2018-06-07 2018-06-07 A kind of line walking efficiency automatic examination method for power-line patrolling

Publications (1)

Publication Number Publication Date
CN108921386A true CN108921386A (en) 2018-11-30

Family

ID=64419011

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810581723.3A Pending CN108921386A (en) 2018-06-07 2018-06-07 A kind of line walking efficiency automatic examination method for power-line patrolling

Country Status (1)

Country Link
CN (1) CN108921386A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7020619B2 (en) * 2000-08-28 2006-03-28 Thompson Daniel J Method, system, and computer software program product for analyzing the efficiency of a complex process
CN105321051A (en) * 2015-11-26 2016-02-10 国网安徽省电力公司检修公司 Extra-high voltage substation intelligent operation and maintenance management and method for generating report thereof
CN106485406A (en) * 2016-09-28 2017-03-08 国网河南汝阳县供电公司 A kind of intelligent substation inspection system and method for inspecting
CN106707301A (en) * 2016-12-27 2017-05-24 银江股份有限公司 Positioning data based service line patrol assessment method
CN107749091A (en) * 2017-09-30 2018-03-02 石家庄学院 Power distribution patrol method and terminal device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7020619B2 (en) * 2000-08-28 2006-03-28 Thompson Daniel J Method, system, and computer software program product for analyzing the efficiency of a complex process
CN105321051A (en) * 2015-11-26 2016-02-10 国网安徽省电力公司检修公司 Extra-high voltage substation intelligent operation and maintenance management and method for generating report thereof
CN106485406A (en) * 2016-09-28 2017-03-08 国网河南汝阳县供电公司 A kind of intelligent substation inspection system and method for inspecting
CN106707301A (en) * 2016-12-27 2017-05-24 银江股份有限公司 Positioning data based service line patrol assessment method
CN107749091A (en) * 2017-09-30 2018-03-02 石家庄学院 Power distribution patrol method and terminal device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
崔志文: "变电站新型巡视模式的分析与研究", 《山东工业技术》 *

Similar Documents

Publication Publication Date Title
CN104200288B (en) A kind of equipment fault Forecasting Methodology based on dependency relation identification between factor and event
CN106017551A (en) Intelligent transmission line integrated monitoring analysis and early warning method
US20140172329A1 (en) System and method for wind generation forecasting
CN108508505A (en) Heavy showers and thunderstorm forecasting procedure based on multiple dimensioned convolutional neural networks and system
Jeon et al. Short-term density forecasting of wave energy using ARMA-GARCH models and kernel density estimation
Zhang et al. Quantitative resilience assessment under a tri-stage framework for power systems
CN110645940A (en) Dynamic prediction system and method for clearance distance between wire and tree
JP5989754B2 (en) Prediction device
Kettle Unexpected vertical wind speed profiles in the boundary layer over the southern North Sea
CN106886564B (en) Method and device for correcting NWP (non-Newtonian Web Page) wind energy spectrum based on spatial clustering
Rezaei et al. A probabilistic framework based on statistical learning theory for structural reliability analysis of transmission line systems
CN110175422A (en) A kind of multicycle rail defects and failures trend forecasting method based on data mining
CN116151610A (en) Method for simulating risk exposure space of disaster-bearing body on underlying surface of heterogeneous city
CN112926863B (en) Six-large-early-warning-center-based comprehensive power grid disaster monitoring system
El Alani et al. Short term solar irradiance forecasting using artificial neural network for a semi-arid climate in Morocco
CN112215416B (en) Intelligent planning inspection route system and method
Meng et al. Tropical cyclone intensity probabilistic forecasting system based on deep learning
Zhou et al. A comprehensive survey for deep-learning-based abnormality detection in smart grids with multimodal image data
CN108921386A (en) A kind of line walking efficiency automatic examination method for power-line patrolling
Hamzic et al. Multistage cascade predictor of structural elements movement in the deformation analysis of large objects based on time series influencing factors
Kaitouni et al. Implementing a Digital Twin-based fault detection and diagnosis approach for optimal operation and maintenance of urban distributed solar photovoltaics
Luna Carlosama et al. Potential of Photovoltaic Generation in the Putumayo Department of Colombia
Wang et al. Research on Comprehensive Evaluation and Early Warning of Transmission Lines’ Operation Status Based on Dynamic Cloud Computing
Ogliari et al. Photovoltaic plant output power forecast by means of hybrid artificial neural networks
CN106651166B (en) Natural disaster risk processing method and system based on Internet of things

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181130