CN108898239A - A kind of site selection method for distribution transformer based on data analysis - Google Patents

A kind of site selection method for distribution transformer based on data analysis Download PDF

Info

Publication number
CN108898239A
CN108898239A CN201810530986.1A CN201810530986A CN108898239A CN 108898239 A CN108898239 A CN 108898239A CN 201810530986 A CN201810530986 A CN 201810530986A CN 108898239 A CN108898239 A CN 108898239A
Authority
CN
China
Prior art keywords
distribution transformer
transformer
data
site selection
addressing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810530986.1A
Other languages
Chinese (zh)
Inventor
吕飞
赵筑雨
何文仲
吴显峰
汪林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU QIANZHI INFORMATION Co Ltd
Original Assignee
GUIZHOU QIANZHI INFORMATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU QIANZHI INFORMATION Co Ltd filed Critical GUIZHOU QIANZHI INFORMATION Co Ltd
Priority to CN201810530986.1A priority Critical patent/CN108898239A/en
Publication of CN108898239A publication Critical patent/CN108898239A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

A kind of site selection method for distribution transformer based on data analysis,By passing through the related data and environmental factor to transformer itself when carrying out distribution transformer addressing,The analysis of economic factor,Reasonably optimizing is carried out to the addressing of distribution transformer,It is analyzed to historical data,Prediction to new region future load size,The site selecting method that the comprehensive consideration such as the influence of environmental factor is made after calculating,The method increase the service lifes of distribution transformer,The efficiency and economic benefit used,Prevent and reduces distribution transformer because of the probability of economic loss caused by the accidents such as heavy-overload,Improve the efficiency of network operation and the satisfaction for increasing client for network operation,Improve the rationality of location of distribution transformer,Extend the service life of transformer,Greatly reduce economic loss,And increase utilization benefit,Can distribution transformer carry out addressing installation when carry out using.

Description

A kind of site selection method for distribution transformer based on data analysis
Technical field
The invention belongs to adapted electro-technical fields, and in particular to a kind of distribution transformer addressing side based on data analysis Method.
Background technique
Currently, distribution transformer addressing is the key problem of distribution transforming planning, needs to meet planning load point power demand Meanwhile in conjunction with local economic and technical norms, determines the position of transformer, need to consider during the position addressing of transformer Geography information factor, Social Ecology factor, economic factor etc..During existing distribution transformer addressing, the side of selection Method is simple, and the factor of consideration is unilateral single, it is easy to go wrong during the work of transformer from now on.
Chinese patent (publication number:CN102722765B a kind of site selection method for distribution transformer) is disclosed, is connected using unit Continuous site selecting method combination load point carries out addressing distribution to section transformer, but considers in its calculating and site selecting method local The factors such as geography information, Social Ecology and economy, the distribution transformer configured in subsequent work very likely because Above-mentioned factor is led to the problem of.Accordingly, it is desirable to provide a kind of distribution for comprehensively considering environmental factor, social factor and economic factor Transformer site selecting method.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of site selection method for distribution transformer based on data analysis.
The present invention is achieved by the following technical programs.
A kind of site selection method for distribution transformer based on data analysis provided by the invention, includes the following steps:
Step 1, the related data of collecting zone distribution transformer;
Step 2 analyzes the related data for the region distribution transformer being collected into;
Step 3 establishes site selection model method according to data analysis result;
Step 4 optimizes transformer addressing according to different zones.
Further, in the step 1, the data of the region transformer of collection include transformer type number, the appearance of transformer The time critical data that amount, transformer generate heavy-overload casualty data after installing and using and use.
Further, in the step 1, the related data of the distribution transformer of required collection includes distribution transformer peace The height above sea level of holding position, long-term temperature and humidity.
Further, in the step 1, the related data of the distribution transformer of required collection includes the distribution transformer Big load number of users in institute coverage, the economic total volume generated every year and because accident caused by economic loss it is total Amount.
Further, in the step 2 to the analysis of the data of the region transformer of collection include to missing data and Abnormal data is analyzed, wherein relevant historical events and historical data need to be combined when analyzing data abnormal point It is analyzed.
Further, in the step 3, when establishing distribution transformer site selection model, the load of installation region is carried out first Then number, the economic appearance of distribution transformer are established in analysis prediction according to the compound size in required installation distribution transformer region Amount and economic power supply radius carry out computation modeling.
Further, in the step 4, when carrying out distribution transformer addressing optimization, the environment feelings according to different zones are needed Condition optimizes assessment, one reasonable addressing scheme of final output to the position of addressing.
The beneficial effects of the present invention are:Implementation through the invention, when carrying out distribution transformer addressing by change The analysis of the related data and environmental factor, economic factor of depressor itself carries out reasonably optimizing to the addressing of distribution transformer, It is analyzed to historical data, the prediction to new region future load size, the comprehensive consideration such as influence of environmental factor The site selecting method made after calculating, the method increase the service life of distribution transformer, the efficiency and economic benefit used, Prevent and reduce distribution transformer because of the probability of economic loss caused by the accidents such as heavy-overload, improve network operation efficiency and Client is increased for the satisfaction of network operation, the rationality of location of distribution transformer is improved, extends making for transformer With the service life, greatly reduce economic loss, and increase utilization benefit, can be made when distribution transformer carries out addressing installation With.
Detailed description of the invention
Fig. 1 is the flow diagram of distribution transformer addressing process of the invention.
Specific embodiment
Be described further below technical solution of the present invention, but claimed range be not limited to it is described.
As shown in Figure 1, a kind of site selection method for distribution transformer based on data analysis, includes the following steps:
Step 1, the related data of collecting zone distribution transformer;
Step 2 analyzes the related data for the region distribution transformer being collected into;
Step 3 establishes site selection model method according to data analysis result;
Step 4 optimizes transformer addressing according to different zones.
Further, in the step 1, the data of the region transformer of collection include transformer type number, the appearance of transformer The time critical data that amount, transformer generate heavy-overload casualty data after installing and using and use.
Further, in the step 1, the related data of the distribution transformer of required collection includes distribution transformer peace The height above sea level of holding position, long-term temperature and humidity.
Further, in the step 1, the related data of the distribution transformer of required collection includes the distribution transformer Big load number of users in institute coverage, the economic total volume generated every year and because accident caused by economic loss it is total Amount.
Collected historical data makes analysis and research only for account of the history, when carrying out new addressing, needs pair The relevant historical data and present real time data of new addressing are collected.
Further, in the step 2 to the analysis of the data of the region transformer of collection include to missing data and Abnormal data is analyzed, wherein relevant historical events and historical data need to be combined when analyzing data abnormal point It is analyzed.Due to occur under special historical events abnormal data be in power grid it is easy to appear the problem of, Bu Nengjian The deletion of single carry out data, needs to analyze data, individually proposes to be used as special case analysis, occurs in similar event In the case where need to carry out it special analysis, in addition to the missing values to data and other than exceptional value must handle analysis, also need Relationship between related data in initial data is calculated, emerge from unconspicuous data relationship in data.
For the more convenient relationship found out between hiding factor, using gene expression programming to because Prime factor carries out automatic evolutionary analysis, and gene expression programming is existing by the automatic combined transformation acquisition of computer program The process of relationship between characterization factor data, entire construction process need computer to be automatically performed and extract to close with goal in research height The functional based method of the characterization factor of connection degree newly constructed, timing statistical factors composite construction has:Sum, Ma, Min, Max etc.;Core point The functional based method of cloth combinations of factors construction has:KfGaussian Gaussian kernel, KfLog Log core, KfIdentity linear kernel etc.; Multidimensional operation combinations of factors construction functional based method have+,-, * ,/,>,<, Sin, Log etc., used functional based method is not only Only these cited.
Further, in the step 3, when establishing distribution transformer site selection model, the load of installation region is carried out first Then number, the economic appearance of distribution transformer are established in analysis prediction according to the payload in required installation distribution transformer region Amount and economic power supply radius carry out computation modeling.
Specifically, step 3, when establishing distribution transformer site selection model, the load Analysis of progress installation region first is pre- It surveys, the load prediction of electricity consumption region is analyzed using LSTM time series forecasting analysis model, according to the historical data in other regions It carries out model training and predicts the load in region future using the load Correlative Influence Factors of obtained models coupling new region Maximum, then according to it is required installation distribution transformer region payload reasonable distribution establish with point transformer number, Economic Capacity and economic power supply radius computation modeling determine the number and load of the transformer in the region according to model result.
Further, in the step 4, when progress distribution transformer addressing position determines, the ring according to different zones is needed Border situation optimizes assessment, one reasonable addressing scheme of final output to the position of addressing.The addressing side of the step 3 Method is theoretic reasonable plant-site selection mode, in practical situations, it is also necessary to consider the geographical location circumstances in region locating for addressing, Climatic condition, humane situation etc..
Further, when being determined to addressing position, using Hierarchy Analysis Method by geographical location circumstances, climatic condition, The influence factors such as humane situation are divided into different brackets, and statistics excavates the geographical location ring of the substation site selection position in historical data Each factor is given corresponding score value according to different division ownership, in conjunction with change by border, climatic condition, the factors such as humane situation Depressor addressing, installation such as use to carry out accounting division for every a kind of effect on addressing determines at all kinds of experts, according to Final accounting average value establishes the multiple linear regression equations of the final influence factor of addressing, so that the load of Optimizing Site Selection holds Amount, equipment selection, safeguard procedures etc..
The present invention by when carrying out distribution transformer addressing by related data to transformer itself and environment because The analysis of element, economic factor carries out reasonably optimizing to the addressing of distribution transformer, analyzes to historical data, to new district The prediction of domain future load size, the site selecting method that the comprehensive consideration such as influence of environmental factor is made after calculating, the party Method improves the service life of distribution transformer, the efficiency and economic benefit used, prevents and reduces distribution transformer because of weight The accidents such as overload cause the probability of economic loss, improve the efficiency of network operation and increase client's expiring for network operation Meaning degree improves the rationality of location of distribution transformer, extends the service life of transformer, greatly reduces economic loss, and And increase utilization benefit, can distribution transformer carry out addressing installation when carry out using.

Claims (7)

1. a kind of site selection method for distribution transformer based on data analysis, it is characterised in that include the following steps:
Step 1, the related data of collecting zone distribution transformer;
Step 2 analyzes the related data for the region distribution transformer being collected into;
Step 3 establishes site selection model method according to data analysis result;
Step 4 optimizes transformer addressing according to different zones.
2. the site selection method for distribution transformer as described in claim 1 based on data analysis, it is characterised in that:The step 1 In, the data of the region transformer of collection include that transformer type number, the capacity of transformer, transformer generate after installing and using Heavy-overload casualty data and the time critical data used.
3. the site selection method for distribution transformer as described in claim 1 based on data analysis, it is characterised in that:The step 1 In, the related data of the distribution transformer of required collection include the height above sea level of distribution transformer installation site, long-term temperature with And humidity.
4. the site selection method for distribution transformer as described in claim 1 based on data analysis, it is characterised in that:The step 1 In, the related data of the distribution transformer of required collection includes the big load number of users in the distribution transformer institute coverage Amount, the economic total volume generated every year and because economic loss total amount caused by accident.
5. the site selection method for distribution transformer as described in claim 1 based on data analysis, it is characterised in that:The step 2 In include analyzing missing data and abnormal data to the analysis of the data of the region transformer of collection, wherein right Data exception point need to be analyzed when being analyzed in conjunction with relevant historical events and historical data.
6. the site selection method for distribution transformer as described in claim 1 based on data analysis, it is characterised in that:The step 3 In, when establishing distribution transformer site selection model, then the load Analysis prediction of progress installation region first is matched according to required installation The number, Economic Capacity and economic power supply radius that the compound size in piezoelectric transformer region establishes distribution transformer calculate and are built Mould.
7. the site selection method for distribution transformer as described in claim 1 based on data analysis, it is characterised in that:The step 4 In, when carrying out distribution transformer addressing optimization, the ambient conditions according to different zones is needed to optimize assessment to the position of addressing, One reasonable addressing scheme of final output.
CN201810530986.1A 2018-05-29 2018-05-29 A kind of site selection method for distribution transformer based on data analysis Pending CN108898239A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810530986.1A CN108898239A (en) 2018-05-29 2018-05-29 A kind of site selection method for distribution transformer based on data analysis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810530986.1A CN108898239A (en) 2018-05-29 2018-05-29 A kind of site selection method for distribution transformer based on data analysis

Publications (1)

Publication Number Publication Date
CN108898239A true CN108898239A (en) 2018-11-27

Family

ID=64343519

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810530986.1A Pending CN108898239A (en) 2018-05-29 2018-05-29 A kind of site selection method for distribution transformer based on data analysis

Country Status (1)

Country Link
CN (1) CN108898239A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110570046A (en) * 2019-09-18 2019-12-13 谢国宇 site selection method and system for environment monitoring site
CN110648161A (en) * 2019-08-05 2020-01-03 中移(杭州)信息技术有限公司 Benefit evaluation method and device for commercial site selection and storage medium
CN110751338A (en) * 2019-10-23 2020-02-04 贵州电网有限责任公司 Construction and early warning method for heavy overload characteristic model of distribution transformer area
CN113807013A (en) * 2021-09-17 2021-12-17 中国联合网络通信集团有限公司 Method and device for processing data of sky, electronic equipment and readable storage medium
CN114677048A (en) * 2022-04-22 2022-06-28 北京阿帕科蓝科技有限公司 Demand area mining method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8116916B1 (en) * 2009-10-20 2012-02-14 Southern Company Services, Inc. Homogeneity based diversity prediction method for transformer selection
CN102521509A (en) * 2011-12-13 2012-06-27 重庆市电力公司万州供电局 Method for achieving optimal location of distribution transformer by improved iterative algorithm
CN103310307A (en) * 2013-06-21 2013-09-18 南方电网科学研究院有限责任公司 Power system planning scheme flexibility assessment method based on probability risk assessment
CN104504183A (en) * 2014-12-10 2015-04-08 广州供电局有限公司 Power distribution network intelligent planning system based on automatic optimization
CN104598983A (en) * 2014-12-03 2015-05-06 国家电网公司 Distribution transformer mounting position determining method and device
CN105046368A (en) * 2015-08-11 2015-11-11 国家电网公司 Method for selecting main substation capacity and optimal station address of transformer substation
CN105373969A (en) * 2015-11-26 2016-03-02 广东电网有限责任公司湛江供电局 Power distribution line wind resistance capability assessment method and system
CN107590568A (en) * 2017-09-20 2018-01-16 上海合泽电力工程设计咨询有限公司 A kind of load forecasting method that becomes more meticulous based on space subdivision

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8116916B1 (en) * 2009-10-20 2012-02-14 Southern Company Services, Inc. Homogeneity based diversity prediction method for transformer selection
CN102521509A (en) * 2011-12-13 2012-06-27 重庆市电力公司万州供电局 Method for achieving optimal location of distribution transformer by improved iterative algorithm
CN103310307A (en) * 2013-06-21 2013-09-18 南方电网科学研究院有限责任公司 Power system planning scheme flexibility assessment method based on probability risk assessment
CN104598983A (en) * 2014-12-03 2015-05-06 国家电网公司 Distribution transformer mounting position determining method and device
CN104504183A (en) * 2014-12-10 2015-04-08 广州供电局有限公司 Power distribution network intelligent planning system based on automatic optimization
CN105046368A (en) * 2015-08-11 2015-11-11 国家电网公司 Method for selecting main substation capacity and optimal station address of transformer substation
CN105373969A (en) * 2015-11-26 2016-03-02 广东电网有限责任公司湛江供电局 Power distribution line wind resistance capability assessment method and system
CN107590568A (en) * 2017-09-20 2018-01-16 上海合泽电力工程设计咨询有限公司 A kind of load forecasting method that becomes more meticulous based on space subdivision

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110648161A (en) * 2019-08-05 2020-01-03 中移(杭州)信息技术有限公司 Benefit evaluation method and device for commercial site selection and storage medium
CN110570046A (en) * 2019-09-18 2019-12-13 谢国宇 site selection method and system for environment monitoring site
CN110570046B (en) * 2019-09-18 2022-03-01 谢国宇 Site selection method and system for environment monitoring site
CN110751338A (en) * 2019-10-23 2020-02-04 贵州电网有限责任公司 Construction and early warning method for heavy overload characteristic model of distribution transformer area
CN113807013A (en) * 2021-09-17 2021-12-17 中国联合网络通信集团有限公司 Method and device for processing data of sky, electronic equipment and readable storage medium
CN114677048A (en) * 2022-04-22 2022-06-28 北京阿帕科蓝科技有限公司 Demand area mining method
CN114677048B (en) * 2022-04-22 2024-01-16 北京阿帕科蓝科技有限公司 Method for excavating demand area

Similar Documents

Publication Publication Date Title
CN108898239A (en) A kind of site selection method for distribution transformer based on data analysis
Rajesh et al. Least cost generation expansion planning with wind power plant incorporating emission using differential evolution algorithm
CN104636988A (en) Active power distribution network assessment method
CN105373971A (en) Method of building energy efficiency management on the basis of big data
CN109638964A (en) A kind of polynary electric network information interactive system and method based on edge calculations framework
CN106529708A (en) Distribution network planning system based on cloud platform
CN103996147A (en) Comprehensive evaluation method for power distribution network
CN105226648A (en) A kind of distributed power source distribution network planning method based on large data
CN103198139A (en) Energy consumption analyzing method of user electricity data
Dehghani et al. Multi-stage resilience management of smart power distribution systems: A stochastic robust optimization model
CN104361233A (en) Anti-electric larceny management method under condition of access of distributed generation
CN111738498A (en) Comprehensive energy system robust planning method and system
CN111027741A (en) Method for constructing space-time dimension-oriented generalized load model analysis library
CN115860694A (en) Business expansion process management and control method and system based on instant message technology
CN103607425A (en) Intelligent electricity consumption service method based on UC technology
Sperstad et al. Cost-benefit analysis of battery energy storage in electric power grids: Research and practices
CN104299167A (en) Energy consumption analysis method for user power data of intelligent energy consumption system
CN103150605B (en) Power grid planning auxiliary system
Wu et al. Techno-economic analysis of contingency reserve allocation scheme for combined UHV DC and AC receiving-end power system
CN104484765A (en) Method for evaluating whether urban power supply network reaches world first-class level or not
CN108346009A (en) A kind of power generation configuration method and device based on user model self study
de Macedo et al. Opportunities and challenges of DSM in smart grid environment
CN105335824B (en) Distribution network failure repairing command methods and system based on data center
CN104636848A (en) Project energy management contract system based on energy node control technology
CN111144628A (en) Distributed energy supply type cooling, heating and power load prediction model system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181127

RJ01 Rejection of invention patent application after publication