CN108894187A - A kind of hydraulic engineering waterproof construction method - Google Patents
A kind of hydraulic engineering waterproof construction method Download PDFInfo
- Publication number
- CN108894187A CN108894187A CN201810930656.1A CN201810930656A CN108894187A CN 108894187 A CN108894187 A CN 108894187A CN 201810930656 A CN201810930656 A CN 201810930656A CN 108894187 A CN108894187 A CN 108894187A
- Authority
- CN
- China
- Prior art keywords
- construction
- waterproof
- concrete
- backfill
- carries out
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/16—Sealings or joints
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention discloses a kind of hydraulic engineering waterproof construction methods,First confirm that construction area,Then the preparation of material and facility is carried out,In earth excavation work progress,It is communicated by intercom communication apparatus,Earth excavation is once completed,Work efficiency is high,It shortens the construction period,In backfill work progress,The soil that backfill uses the digging in-situ earthwork to generate,It economizes on resources,It reduces and cost is transported into the earthwork,Divide three layers of backfill,Mechanical lay a good foundation is more stable,In the work progress of formwork for placing,Construction personnel carries out grid cage production at the scene,Next step process construction is carried out after testing staff's acceptance(check) again,Underlying strength is high,Long service life,The construction method poured using segmentation,Good forming effect,Waterproof structural course is to be allowed to hardening in the coating film waterproof material that hard layer surface applies to form film waterproof material,Good water-proof effect,Finally strictly carried out an acceptance inspection according to examination article,Short time limit,It is suitble to promote the use of.
Description
Technical field
The invention belongs to hydraulic engineering waterproof construction technology fields, and more specifically more particularly to a kind of hydraulic engineering is anti-
Water construction method.
Background technique
Sharp engineering is one of current highly important infrastructure project.It is related to during water conservancy construction much more very
Process and construction procedure.Wherein an important ring is waterproofing work.It, generally can be along road direction in irrigation and water conservancy work progress
Flume is arranged, so that peasant easily uses.Water flow is flowed along channel direction in flume.If water in flume compared with
It is more, may be to exosmosis, penetration range is wider, it is possible to cause the soft of road foundation, be unfavorable for the peace of vehicle on road
Full traveling.In particular for some Important Sections, waterproofing work is particularly important.
For this purpose, application No. is CN201710726324.7 to disclose a kind of hydraulic engineering waterproof construction method, belong to water conservancy
Engineering field, including step:Excavate groove:The groove that being used to, waterproof membrane and flume are set is excavated beside road, makes groove
In rectangular configuration, groove forms top plane, side elevation and baseplane;Plane is wherein pushed up close to the roadbed of road and lower than road
Road surface;Water-tight device is set:It is laid with waterproof membrane at groove, make a part fitting side elevation of waterproof membrane and forms vertical section,
A part fitting baseplane of waterproof membrane is set to form horizontal segment;Backfill:It bankets into groove and covers waterproof membrane, and reserved placement
The position of flume;Flume construction:Flume is set at reserved position, gap is filled and led up, and by soil compaction.This water
Sharp engineering waterproofing construction method can be to playing good waterproof action between flume and road.It can be widely applied for farmland
The occasions such as water conservancy, road water conservancy, bridge opening, tunnel.
But above scheme still has certain defect, long construction period, engineering construction intensity is low, and lacking has centainly
Limitation.
Summary of the invention
The purpose of the present invention is to solve disadvantages existing in the prior art, and a kind of hydraulic engineering waterproof proposed is applied
Work method.
To achieve the above object, the present invention provides the following technical solutions:A kind of hydraulic engineering waterproof provided by the invention is applied
Work method, specifically comprises the following steps:
S1:Confirm construction area, and insert safe isolation belt at the 10m range of distance construction region, improves security performance;
S2:The preparation of material and facility, according to engineering agreement content, by pipe of concrete, cement needed for engineering, sand, stone
Raw material and site operation mechanical equipment tissue are marched into the arena, it is also necessary to carry out safety education to site operation personnel, and to need to answer
The raw material of inspection are rechecked, and qualified rear allows to use;
S3:Earth excavation construction, excavates the earthwork using excavating machinery, to plan-position, grade of side slope and absolute altitude
Check is measured, so that measurement error is no more than 3/1000ths, control error is no more than 5/1000ths of design requirement, and machinery is dug
When native, hand fit is needed, is communicated by intercom communication apparatus, earth excavation is once completed, and basic bottom is using artificial clear
It transports, after earth excavation, field survey personnel carry out soil investigation, soil exploration, and carry out prospecting record work;
S4:Backfill construction, carries out after foundation engineering acceptance(check), and backfill is generated using the digging in-situ earthwork
Soil, point three layers of backfill, machinery compacting;
S5:The construction of formwork for placing, selecting diameter specifications for the grade III steel of 8mm is reinforced steel, according to field surveys institute
Foundation width and height determine reinforcing bar length, construction personnel carries out grid cage production at the scene, the height of grid cage is not
Less than 0.25m, after grid cage is worked out, next step process construction is carried out after testing staff's acceptance(check) again;
S6:Pour C20
a:When pouring basis, elevation line is popped up on the both side plate of foundation trench in advance, with elevation control size, surpasses error not
3 percent are crossed, the construction method poured using segmentation, every segment length control is arranged in 6-8m distance every section of junction portion
Vertical template baffle plate pours C20 along foundation length direction paragraph by paragraph, so that foundation bottom is constituted continuous basic bottom beam, wherein shaking
Dynamic stick inserts point with quincunx insertion, and spacing 30-50cm when vibrating, " fast to insert ", " pulling out slowly ", to prevent coagulation scholar surface from first shaking
It is real, and layering, segregation phenomenon occur for lower surface concrete, when preventing from pulling out fastly, concrete has little time to supplement, leaving space, vibrating head insertion
It should be twitched up and down after concrete, amplitude 5-10cm, to exclude air in concrete, when vibration no longer sinks depending on concrete surface in level, no
Occurs bubble again, surface glows grey pulp-water, and vibrating head does not allow to control and reserve between vibrating head and template against template when vibrating
At least spacing of 40cm avoids vibrating head collision slab;
b:Staying for built-in fitting is set, and built-in fitting is embedded bar anchor, and built-in fitting is made pre- using being directly welded on structural member reinforcing bar
Embedded part and structure reinforcing bars firm welding guarantee that pre-buried size meets drawing requirement, reserved opening, and make pipe of concrete and reserved
Hole docking makes wooden frame mould according to design size, and after the installation of frame mould, receiving forms after pouring, and hole surrounding has reinforced reinforcing bar,
After pouring, mark warning sign is inserted, quiescing personnel construct in warning alert at least 36 hours;
S7:After C20 molding, cleared up by form removable, and to the basic bottom beam of construction site;
S8:Armored concrete upper surface after molding carries out the construction of Waterproof structural course, waterproof knot in the step S7
Structure layer is to be allowed to hardening in the coating film waterproof material that hard layer surface applies to form film waterproof material, and hard layer is made of metal steel
It is anti-to form film in hard layer coating film waterproof material, after hardening for one of plate, nonmetallic rigid plastics processed or bentonite plate
Water layer, quiescing personnel construct in warning alert at least 24 hours after coating film waterproof material, guarantee waterproof layer Forming Quality;
S9:Testing staff carries out waterproof performance test and examination, is strictly carried out an acceptance inspection according to examination article.
Technical effect and advantage of the invention:A kind of hydraulic engineering waterproof construction method of the present invention, changes traditional waterproof
Construction method first confirms that construction area, and the preparation for then carrying out material and facility passes through in earth excavation work progress
Intercom communication apparatus is communicated, and earth excavation is once completed, and work efficiency is high, is shortened the construction period, in backfill work progress
In, the soil that backfill uses the digging in-situ earthwork to generate economizes on resources, and reduces the earthwork transporting cost, and point three layers of backfill are mechanical
Lay a good foundation is more stable, and in the work progress of formwork for placing, construction personnel carries out grid cage production, testing staff at the scene
Next step process construction is carried out after acceptance(check) again, underlying strength is high, then long service life carries out pouring C20 and built-in fitting
Construction, using the construction method that pours of segmentation, good forming effect, after C20 molding, then by form removable, and to construction site
Basic bottom beam cleared up, Waterproof structural course be the coating film waterproof material that hard layer surface apply be allowed to harden form film
Waterproof layer, good water-proof effect finally strictly carry out an acceptance inspection according to examination article, and short time limit is suitble to promote the use of.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, below in conjunction with specific embodiment, to this
Invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, not
For limiting the present invention.Based on the embodiments of the present invention, those of ordinary skill in the art are not before making creative work
Every other embodiment obtained is put, shall fall within the protection scope of the present invention.
A kind of hydraulic engineering waterproof construction method provided by the invention, specifically includes following production stage:
S1:Confirm construction area, and insert safe isolation belt at the 10m range of distance construction region, improves security performance;
S2:The preparation of material and facility, according to engineering agreement content, by pipe of concrete, cement needed for engineering, sand, stone
Raw material and site operation mechanical equipment tissue are marched into the arena, it is also necessary to carry out safety education to site operation personnel, and to need to answer
The raw material of inspection are rechecked, and qualified rear allows to use;
S3:Earth excavation construction, excavates the earthwork using excavating machinery, to plan-position, grade of side slope and absolute altitude
Check is measured, so that measurement error is no more than 3/1000ths, control error is no more than 5/1000ths of design requirement, and machinery is dug
When native, hand fit is needed, is communicated by intercom communication apparatus, earth excavation is once completed, and basic bottom is using artificial clear
It transports, after earth excavation, field survey personnel carry out soil investigation, soil exploration, and carry out prospecting record work;
S4:Backfill construction, carries out after foundation engineering acceptance(check), and backfill is generated using the digging in-situ earthwork
Soil, point three layers of backfill, machinery compacting;
S5:The construction of formwork for placing, selecting diameter specifications for the grade III steel of 8mm is reinforced steel, according to field surveys institute
Foundation width and height determine reinforcing bar length, construction personnel carries out grid cage production at the scene, the height of grid cage is not
Less than 0.25m, after grid cage is worked out, next step process construction is carried out after testing staff's acceptance(check) again;
S6:Pour C20
a:When pouring basis, elevation line is popped up on the both side plate of foundation trench in advance, with elevation control size, surpasses error not
3 percent are crossed, the construction method poured using segmentation, every segment length control is arranged in 6-8m distance every section of junction portion
Vertical template baffle plate pours C20 along foundation length direction paragraph by paragraph, so that foundation bottom is constituted continuous basic bottom beam, wherein shaking
Dynamic stick inserts point with quincunx insertion, and spacing 30-50cm when vibrating, " fast to insert ", " pulling out slowly ", to prevent coagulation scholar surface from first shaking
It is real, and layering, segregation phenomenon occur for lower surface concrete, when preventing from pulling out fastly, concrete has little time to supplement, leaving space, vibrating head insertion
It should be twitched up and down after concrete, amplitude 5-10cm, to exclude air in concrete, when vibration no longer sinks depending on concrete surface in level, no
Occurs bubble again, surface glows grey pulp-water, and vibrating head does not allow to control and reserve between vibrating head and template against template when vibrating
At least spacing of 40cm avoids vibrating head collision slab;
b:Staying for built-in fitting is set, and built-in fitting is embedded bar anchor, and the later period, can if necessary to set up other structures in engineering
By the built-in fitting that extends come auxiliary construction, built-in fitting makes built-in fitting and structural steel using being directly welded on structural member reinforcing bar
Muscle firm welding guarantees that pre-buried size meets drawing requirement, reserved opening, and makes pipe of concrete and reserved hole docking, root
Wooden frame mould is made according to design size, after the installation of frame mould, receiving forms after pouring, and hole surrounding has reinforced reinforcing bar, after pouring,
Mark warning sign is inserted, quiescing personnel construct in warning alert at least 36 hours;
S7:After C20 molding, cleared up by form removable, and to the basic bottom beam of construction site;
S8:Armored concrete upper surface after molding carries out the construction of Waterproof structural course, waterproof knot in the step S7
Structure layer is to be allowed to hardening in the coating film waterproof material that hard layer surface applies to form film waterproof material, and hard layer is made of metal steel
It is anti-to form film in hard layer coating film waterproof material, after hardening for one of plate, nonmetallic rigid plastics processed or bentonite plate
Water layer, quiescing personnel construct in warning alert at least 24 hours after coating film waterproof material, guarantee waterproof layer Forming Quality;
S9:Testing staff carries out waterproof performance test and examination, is strictly carried out an acceptance inspection according to examination article.
In summary:A kind of hydraulic engineering waterproof construction method of the present invention, changes traditional waterproof construction method, first really
Recognize construction area, then carry out material and facility preparation, in earth excavation work progress, by intercom communication apparatus into
Row communication, earth excavation are once completed, and work efficiency is high, are shortened the construction period, and in backfill work progress, backfill is using scene
The soil that earth excavation generates, economizes on resources, and reduces the earthwork transporting cost, and point three layers of backfill, mechanical lay a good foundation is more stable,
In the work progress of formwork for placing, construction personnel carries out grid cage production at the scene, carries out again after testing staff's acceptance(check)
The construction of next step process, underlying strength is high, then long service life is carried out the construction for pouring C20 and built-in fitting, poured using segmentation
The construction method built, good forming effect after C20 molding, then by form removable, and carry out the basic bottom beam of construction site clear
Reason, Waterproof structural course are to be allowed to hardening in the coating film waterproof material that hard layer surface applies to form film waterproof material, waterproof effect
It is good, it is finally strictly carried out an acceptance inspection according to examination article, short time limit is suitble to promote the use of.
Finally it should be noted that:The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention,
Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, still may be used
To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features,
All within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in of the invention
Within protection scope.
Claims (3)
1. a kind of hydraulic engineering waterproof construction method, it is characterised in that:Including steps are as follows:
S1:Confirm construction area, and inserts safe isolation belt at the 10m range of distance construction region;
S2:The preparation of material and facility, according to engineering agreement content, by pipe of concrete, cement needed for engineering, sand, stone former material
Material and site operation mechanical equipment tissue are marched into the arena;
S3:Earth excavation construction, excavates the earthwork using excavating machinery, carries out to plan-position, grade of side slope and absolute altitude
Measurement is checked, and so that measurement error is no more than 3/1000ths, control error is no more than 5/1000ths of design requirement, and machinery is cut the earth
When, hand fit is needed, is communicated by intercom communication apparatus, earth excavation is once completed, and basic bottom uses and manually clears,
After earth excavation, field survey personnel carry out soil investigation, soil exploration, and carry out prospecting record work;
S4:Backfill construction, carries out after foundation engineering acceptance(check), the soil that backfill uses the digging in-situ earthwork to generate, point
Three layers of backfill, machinery compacting;
S5:The construction of formwork for placing, selecting diameter specifications for the grade III steel of 8mm is reinforced steel, resulting according to field surveys
Foundation width and height determine reinforcing bar length, and construction personnel carries out grid cage production at the scene, and the height of grid cage is not less than
0.25m after grid cage is worked out, carries out next step process construction again after testing staff's acceptance(check);
S6:Pour C20
a:When pouring basis, elevation line is popped up on the both side plate of foundation trench in advance, with elevation control size, error is made to be no more than hundred
/ tri-, the construction method poured using segmentation, in 6-8m distance, it is vertical to be arranged every section of junction portion for every segment length control
Template baffle plate, pour C20 along foundation length direction paragraph by paragraph, foundation bottom made to constitute continuous basic bottom beam;
b:Staying for built-in fitting is set, and built-in fitting is embedded bar anchor, and built-in fitting makes built-in fitting using being directly welded on structural member reinforcing bar
And structure reinforcing bars firm welding, guarantee that pre-buried size meets drawing requirement, reserved opening, and make pipe of concrete and reserved hole
Docking makes wooden frame mould according to design size, and after the installation of frame mould, receiving forms after pouring, and hole surrounding has reinforced reinforcing bar, pours
After, mark warning sign is inserted, quiescing personnel construct in warning alert at least 36 hours;
S7:After C20 molding, cleared up by form removable, and to the basic bottom beam of construction site;
S8:Armored concrete upper surface after molding carries out the construction of Waterproof structural course, Waterproof structural course in the step S7
Coating film waterproof material to apply in hard layer surface is allowed to hardening and forms film waterproof material, and hard layer is made of metal steel plate, non-
One of made of metal rigid plastics or bentonite plate form film waterproof material after hard layer coating film waterproof material, hardening,
Quiescing personnel construct in warning alert at least 24 hours after coating film waterproof material;
S9:Testing staff carries out waterproof performance test and examination.
2. a kind of hydraulic engineering waterproof construction method according to claim 1, it is characterised in that:In the step S2,
It also needs to carry out safety education to site operation personnel, and is rechecked to the raw material rechecked need to be done, qualified rear allows
It uses.
3. a kind of hydraulic engineering waterproof construction method according to claim 1, it is characterised in that:The S6 is poured in C20,
Vibrating head inserts point with quincunx insertion, and spacing 30-50cm when vibrating, " fast to insert ", " pulling out slowly ", to prevent coagulation scholar surface first
Jolt ramming, and layering, segregation phenomenon occur for lower surface concrete, when preventing from pulling out fastly, concrete has little time to supplement, leaving space, and vibrating head is inserted
It should be twitched up and down after entering concrete, amplitude 5-10cm, to exclude air in concrete, when vibration, no longer sinks depending on concrete surface in level,
No longer there is bubble, surface glows grey pulp-water, and vibrating head does not allow to control pre- between vibrating head and template against template when vibrating
It is left to the spacing of few 40cm, avoids vibrating head collision slab.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810930656.1A CN108894187A (en) | 2018-08-15 | 2018-08-15 | A kind of hydraulic engineering waterproof construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810930656.1A CN108894187A (en) | 2018-08-15 | 2018-08-15 | A kind of hydraulic engineering waterproof construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108894187A true CN108894187A (en) | 2018-11-27 |
Family
ID=64354576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810930656.1A Pending CN108894187A (en) | 2018-08-15 | 2018-08-15 | A kind of hydraulic engineering waterproof construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108894187A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111305156A (en) * | 2020-03-30 | 2020-06-19 | 许艳杰 | Waterproof construction method for hydraulic engineering |
CN115113228A (en) * | 2022-05-09 | 2022-09-27 | 江苏省水利科学研究院 | Polder reduction lake engineering test method based on geographic information technology |
CN116177971A (en) * | 2023-01-04 | 2023-05-30 | 中国十九冶集团有限公司 | Preparation method of fluidized solidified soil and foundation trench backfilling construction method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1442593A (en) * | 2002-03-05 | 2003-09-17 | (株)三豪特殊 | Waterproof layer and water proof construction method using said water proof layer |
CN106906829A (en) * | 2017-04-04 | 2017-06-30 | 孝感市奇思妙想文化传媒有限公司 | A kind of horizontal soil body reinforcement means of subway open-cut foundation ditch |
-
2018
- 2018-08-15 CN CN201810930656.1A patent/CN108894187A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1442593A (en) * | 2002-03-05 | 2003-09-17 | (株)三豪特殊 | Waterproof layer and water proof construction method using said water proof layer |
CN106906829A (en) * | 2017-04-04 | 2017-06-30 | 孝感市奇思妙想文化传媒有限公司 | A kind of horizontal soil body reinforcement means of subway open-cut foundation ditch |
Non-Patent Citations (3)
Title |
---|
刘建民 等: "《土木工程施工教程》", 30 June 2016, 西北工业大学出版社 * |
成雷: "浅析胶东调水工程中暗渠施工的质量控制要点", 《水利建设与管理》 * |
赵青: "《土木工程专业毕业设计指导》", 31 October 2013, 武汉大学出版社 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111305156A (en) * | 2020-03-30 | 2020-06-19 | 许艳杰 | Waterproof construction method for hydraulic engineering |
CN115113228A (en) * | 2022-05-09 | 2022-09-27 | 江苏省水利科学研究院 | Polder reduction lake engineering test method based on geographic information technology |
CN115113228B (en) * | 2022-05-09 | 2023-10-24 | 江苏省水利科学研究院 | Method for detecting return-to-polder and lake engineering based on geographic information technology |
CN116177971A (en) * | 2023-01-04 | 2023-05-30 | 中国十九冶集团有限公司 | Preparation method of fluidized solidified soil and foundation trench backfilling construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104500077B (en) | A kind of shallow-depth-excavation tunnel passes through cottage area construction method | |
CN107524138B (en) | Construction method of ultra-deep foundation pit underground diaphragm wall | |
CN106703814B (en) | Tunneling subway station hole pile construction method | |
CN104564128A (en) | Deformation monitoring method for shallow-buried excavation tunnel construction | |
CN103958780B (en) | The method for forming cementing retaining wall | |
CN102425160A (en) | Method for constructing engineering pile by combining rotary drilling rig with manual pile base chambering | |
CN106958256A (en) | A kind of placement layer by layer, the open caisson construction technique repeatedly sunk | |
CN207777770U (en) | A kind of precast spliced pipe fitting jacking system | |
CN101824824A (en) | Construction method of controlling raised deformation of existing buildings under foundation pits through pile slab supporting and protection | |
CN106088127A (en) | Open caisson construction method | |
CN108894187A (en) | A kind of hydraulic engineering waterproof construction method | |
CN106930319A (en) | A kind of high slope framed revetment and its construction method | |
CN109914456A (en) | A kind of bridge and subway tunnel adjoin newly-built or with design and construction method when building | |
CN108103871A (en) | A kind of construction method of the roadbed foam concrete fill placement technique of neighbouring existing Subway Facilities | |
CN102430277B (en) | Coarse grid sunk well for physically processing waste water and construction method thereof | |
CN110219359A (en) | A kind of Submersed type inspection well and its construction method | |
CN106049196B (en) | Flexible pile combines ballastless track roadbed construction method with stake raft with section | |
CN103696784A (en) | Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure | |
CN101597888B (en) | Construction method of municipal drainage culvert sinking trough | |
CN108505529A (en) | A kind of construction method of the bearing platform construction steel cofferdam of Through Steel case arch bridge | |
CN108952766A (en) | The construction method of Tunnel Passing karst location punishment | |
CN104164881A (en) | Piling wall overlapping cantilever foundation pit support construction method and structure | |
CN107489164A (en) | The heightening and consolidation structure and method of a kind of in-service reinforced concrete retaining wall | |
CN109914161A (en) | A kind of construction method of soft clay area high-speed railway filled-up ground | |
CN104895111B (en) | The construction method of integrated pipe canal in weak soil ground |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181127 |