The mounting tool and installation method of a kind of D type ceiling in corridor
Technical field
The invention belongs to accommodation outfitting technology fields, and in particular to the mounting tool and installation of a kind of D type ceiling in corridor
Method.
Background technique
D type ceiling is a kind of current widely used ceiling type, deep to be liked by numerous shipowners owner, but
D type ceiling construction is relatively complicated, needs to weld, fixed a large amount of screw rod M8, ears hanging beam, and construction while will also avoid
With the interference of other professions, the common installation of D type ceiling needs then to be welded on screw rod M8 first by screw rod M8 and sleeve combination
On deck, then elastic lifting tip cutting seat and screw rod M8 are tightened, finally ears hanging beam is stuck on elastic lifting tip cutting seat, ears
Hanging beam installs D type ceiling again after the installation is completed, and the spacing of ears hanging beam is 1000-1200mm under normal circumstances, and big
Most non-passenger ship project corridor spacing are in 1000mm or so, that is to say, that the plate of D type ceiling is grown in 1000mm or so, then is made
It is installed with the installation method of screw rod M8, ears hanging beam, construction is complicated, higher cost.
Summary of the invention
Mounting tool and installation method the purpose of the present invention is to provide a kind of D type ceiling in corridor, to simplify
Construction, cost efficiency.
In order to solve the above technical problems, the technical solution adopted by the present invention is that:A kind of erector of D type ceiling in corridor
It fills, the angle steel including enclosing installation connection elasticity h firmware at arm on deck or steel, elastic h fixing piece connects comprising L fixing piece, elasticity
Fitting, U-shaped card slot;L fixing piece angle cleat, flexible connector top is connected with L fixing piece, lower section is connected with U-shaped card slot, U
Type card slot is connected with unilateral top-type material, and tooling further includes corridor hanging beam, and corridor hanging beam is fixed on list by tapping screw one
On the top-type material of side, D type ceiling is fixed on the hanging beam of corridor by tapping screw two.
Preferably, wherein corridor hanging beam is " L " type, a length of 10-100mm in one side, a length of 50-150mm in another side, material
Matter is the galvanized steel plain sheet of thickness 1.2mm, and unilateral top-type material uses the galvanized steel plain sheet of 1.2mm thickness.
A kind of installation method of the mounting tool of D type ceiling in corridor, includes the following steps:
Step S1:The angle steel of installation connection elasticity h fixing piece at deck or steel wall;
Step S2:Elastic h fixing piece is welded on angle steel;
Step S3:By unilateral top-type material and elasticity h fixing piece spot welding;
Step S4:Corridor hanging beam is fixed on unilateral top-type material by tapping screw one;
Step S5:D type ceiling is fixed on the hanging beam of corridor finally by tapping screw two.
Preferably, tapping screw uses cross recess coiled hair self drilling tapping screw, it is this referring to GB/T15856.12002
Tapping screw is made of drill bit and screw two parts, and first from thread Pilot hole is drilled out when assembly, then tapping internal screw thread, when installation can
To realize drilling, tapping, fixation, the disposable completion of locking, and it is easy to disassemble, and material is stainless steel, due to unilateral top-type material
It is the galvanized steel plain sheet of thick 1.2mm with corridor hanging beam material, therefore screw length is 3-4mm.
Compared with prior art, mounting means of the invention reduces a large amount of welding, paints patch work, model
Interference checking work, while material has been saved, alleviate weight;Installation for D type ceiling in corridor provides a kind of convenience, fast
Prompt installation method, and play the effect of cost efficiency.
Detailed description of the invention
Fig. 1 is flow chart of the invention;
Fig. 2 is the scheme of installation of present invention installation D type ceiling;
Fig. 3 is the partial enlarged view of Fig. 2.
Wherein:1, deck;2, D type ceiling;3, steel wall;4, angle steel;5, unilateral top-type material;6-1, tapping screw one;
6-2, tapping screw two;7, corridor hanging beam;8, liner plate;9, elasticity h fixing piece;9-1, L fixing piece;9-2, flexible connector;
9-3, U-shaped card slot.
Specific embodiment
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end
Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached
The embodiment of figure description is exemplary, and for explaining only the invention, and is not considered as limiting the invention.
In the description of the present invention, unless otherwise specified and limited, it should be noted that term " installation ", " connected ",
" connection " shall be understood in a broad sense, for example, it may be mechanical connection or electrical connection, the connection being also possible to inside two elements can
It, can also be indirectly connected through an intermediary to be to be connected directly.It for the ordinary skill in the art, can basis
Concrete condition understands the concrete meaning of above-mentioned term.
As shown in Figure 1-3, a kind of installation method of D type ceiling, a kind of mounting tool of D type ceiling in corridor, packet
The angle steel 4 of the installation connection elasticity h fixing piece 9 at deck 1 or steel wall 3 is included, elastic h fixing piece 9 includes L fixing piece 9-1, bullet
Property connector 9-2, U-shaped card slot 9-3;L fixing piece 9-1 angle cleat 4, be connected above flexible connector 9-2 with L fixing piece 9-1,
Lower section is connected with U-shaped card slot 9-3, and U-shaped card slot 9-3 is connected with unilateral top-type material 5, and tooling further includes corridor hanging beam 7, and corridor is hung
Drop in beam 7 is fixed on unilateral top-type material 5 by one 6-1 of tapping screw, is fixed to D type ceiling by two 6-2 of tapping screw
On corridor hanging beam 7, unilateral top-type material 5 uses the galvanized steel plain sheet of 1.2mm thickness.
Preferably, wherein corridor hanging beam 7 is " L " type, a length of 10-100mm, a length of 50-150mm in another side on one side,
Material is the galvanized steel plain sheet of thickness 1.2mm.
A kind of installation method of the mounting tool of D type ceiling in corridor, includes the following steps:
Step S1:The angle steel 4 of installation connection elasticity h fixing piece 9 at deck 1 or steel wall 3;
Step S2:Elastic h fixing piece 9 is welded on angle steel 4;
Step S3:By unilateral top-type material 5 and 9 spot welding of elasticity h fixing piece;
Step S4:Corridor hanging beam 7 is fixed on unilateral top-type material 5 by one 6-1 of tapping screw;
Step S5:D type ceiling 2 is fixed on corridor hanging beam 7 finally by two 6-2 of tapping screw.
Preferably, tapping screw uses cross recess coiled hair self drilling tapping screw, it is this referring to GB/T15856.12002
Tapping screw is made of drill bit and screw two parts, and first from thread Pilot hole is drilled out when assembly, then tapping internal screw thread, when installation can
To realize drilling, tapping, fixation, the disposable completion of locking, and it is easy to disassemble, and material is stainless steel, due to unilateral top-type material 5
It is the galvanized steel plain sheet of thick 1.2mm with 7 material of corridor hanging beam, therefore screw length is 3-4mm.
Mounting means of the invention reduces a large amount of welding, paints patch work, and model interference checking works, together
Shi Jieyue material, alleviates weight;Installation for D type ceiling in corridor provides a kind of easily and efficiently installation method, and
And play the effect of cost efficiency.
In the description of this specification, the description meaning of reference term " one embodiment ", " example " or " some examples " etc.
Refer to that particular features, structures, materials, or characteristics described in conjunction with this embodiment or example are contained at least one reality of the invention
It applies in example or example.In the present specification, schematic expression of the above terms are not necessarily referring to identical embodiment or show
Example.Moreover, particular features, structures, materials, or characteristics described can be in any one or more of the embodiments or examples
It can be combined in any suitable manner.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that:Not
A variety of change, modification, replacement and modification can be carried out to these embodiments in the case where being detached from the principle of the present invention and objective, this
The range of invention is defined by the claims and their equivalents.