CN108824211A - A kind of bridge pier foundation in construction duration method in the river of bridge - Google Patents

A kind of bridge pier foundation in construction duration method in the river of bridge Download PDF

Info

Publication number
CN108824211A
CN108824211A CN201810805942.5A CN201810805942A CN108824211A CN 108824211 A CN108824211 A CN 108824211A CN 201810805942 A CN201810805942 A CN 201810805942A CN 108824211 A CN108824211 A CN 108824211A
Authority
CN
China
Prior art keywords
cofferdam
layer
construction
river
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810805942.5A
Other languages
Chinese (zh)
Inventor
李敬
黄大昌
黄生效
彭洪国
陈宏仙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Rui Tong Engineering Construction Group Co Ltd
Original Assignee
Sichuan Rui Tong Engineering Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Rui Tong Engineering Construction Group Co Ltd filed Critical Sichuan Rui Tong Engineering Construction Group Co Ltd
Priority to CN201810805942.5A priority Critical patent/CN108824211A/en
Publication of CN108824211A publication Critical patent/CN108824211A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Abstract

The invention discloses bridge pier foundation in construction duration methods in a kind of river of bridge, including steps are as follows:Trestle is set up from river two sides are synchronous, it extends in river, set up platform in trestle end, stayed among platform set it is multiple for construct pile foundations cavity, by pile foundation casing inserting piling into bottom of river channel soil layer, the pore-forming operation in pile foundation casing, in cast-in-situ bored pile is poured in pile foundation casing in stake holes, removes trestle and platform, cast-in-situ bored pile after the completion of construction carries out cofferdam construction, pours cushion cap concrete, sets up temporary rest pier bracket, connection support portion is poured from cushion cap to two sides;The twice battered leg that support portion is V-type setting is connected, is embedded with the horizontally disposed prestressing tendon of multiple tracks on battered leg.The present invention is by above-mentioned setting, and quality can obtain good guarantee to the pier footing of bridge in the construction process, and the connection support portion being arranged on cushion cap also can be good at providing support force structure for bridge, is conducive to the stability of bridge entirety.

Description

A kind of bridge pier foundation in construction duration method in the river of bridge
Technical field
The present invention relates to bridge construction field, in particular to bridge pier foundation in construction duration method in a kind of river of bridge.
Background technique
Bridge is essential architectural engineering in town road, major function be also no longer limited to " Whening happen upon streams, bridge them " this One traditional application places, more have the more powerful and complicated bridge of the functions such as railway bridge, urban viaduct, viaduct Beam.
The technique of any one bridge therein is all more complex, and body of a bridge quality requirement is high, not only needs to meet normal logical Row demand will also can adapt to gravity, frictional force, centrifugal force and the effect of vibration of current train, while often multispan bridge Across the normal navigation for also needing to meet river, therefore water pressure when the body of a bridge there is a need for being able to resist navigation and water is floating Power.
Multispan bridge is required to build pier footing in river, and the stability of pier footing is for the steady of bridge entirety It is qualitative particularly important.Therefore how to reinforce the stability of pier footing, and particularly important part during bridge construction.
Summary of the invention
The object of the present invention is to provide bridge pier foundation in construction duration methods in a kind of river of bridge, have reinforcement pier footing steady Fixed effect.
Above-mentioned technical purpose of the invention technical scheme is that, bridge pier in a kind of river of bridge Foundation construction method, including steps are as follows:
S1, trestle construction set up trestle from river two sides are synchronous, extend in river;
S2, platform construction set up platform in trestle end, stay among platform and set multiple cavitys for pile foundation of constructing;
S3, cast-in-situ bored pile pour, by inserting piling in pile foundation casing cavity reserved among platform into bottom of river channel soil layer, Pore-forming operation in pile foundation casing, in pouring cast-in-situ bored pile in stake holes in pile foundation casing;
S4, bearing platform construction remove trestle and platform, and the cast-in-situ bored pile after the completion of construction carries out cofferdam construction, and cofferdam is complete It draws water after, cofferdam inner support is installed, pours cushion cap concrete again;
S5, connection support portion construction, sets up temporary rest pier bracket, connection support portion is poured from cushion cap to two sides;
Wherein, the twice battered leg that support portion is V-type setting, when setting up temporary rest pier bracket, the edge centered on cushion cap are connected in S5 To the multiple rows of prefabricated pile of two sides inserting piling, the top of prefabricated pile has poured multiple interim cushion caps in bridge length direction, takes on interim cushion cap If more steel-pipe piles, steel-pipe pile top absolute altitude is matched with the bottom surface absolute altitude for connecting support portion, and steel-pipe pile top is successively laid with vertical Beam, distribution beam and the bottom surface template for connecting support portion;Bottom surface template carries out internal reinforcing bar binding after being installed, then is attached The concrete pouring construction of support portion, while the horizontally disposed prestressing tendon of multiple tracks is embedded on twice battered leg.
By using above-mentioned technical proposal, cast-in-situ bored pile is capable of providing good stress posting body, can by top by Power is timely transmitted in supporting course, and pile foundation stability is also higher, is conducive to the stability of pier footing;In bearing platform construction, To the dismounting sequence of cofferdam inner support when processing method and reinforcement means and casting concrete to cofferdam, can be good at tieing up The whole stress balance for holding cofferdam reduces the whole deformation in cofferdam, keeps cofferdam to internal holding effect, is conducive to ensure and hold The construction quality and finished size of platform, it is particularly important for the stability under loading of cushion cap;The connection support portion being arranged on cushion cap Also it can be good at providing support force structure for bridge, be conducive to the stability of bridge entirety, meanwhile, cushion cap stress itself is equal It is even reliable, further enhance the global reliability of bridge itself.
The further setting of the present invention is:Cushion cap includes upper layer and lower layer in the S4, and lower layer is cuboid and is connected to brill On hole pouring pile, upper layer is taper type and is fixedly connected with twice battered leg;When cofferdam construction, continuously applied using single layer steel sheet pile Work after the completion of cofferdam, to operation of drawing water is carried out in cofferdam, when moisture takes out 1/3 in cofferdam, sets up the cofferdam inner support of first layer, When moisture is evacuated to 2/3 in cofferdam, sets up the cofferdam inner support of the second layer and set up in the cofferdam of third layer in cofferdam after moisture pump Support.
By using above-mentioned technical proposal, is constructed, kept to list by moisture and interlocking for cofferdam inner support when setting up cofferdam Layer steel sheet pile continuous action has abutting force, to offset the pressure of external water pressure, keeps the force stability of single layer steel sheet pile.
The further setting of the present invention is:After the completion of the cofferdam inner support of third layer is set up, cofferdam inner base soil layer is flattened, The first layer of blinding layer, the underclad portion for pouring cushion cap again is poured, first layer is removed after the completion of pouring in the cofferdam of third layer Support, then the second layer of the underclad portion of cushion cap is poured, the second layer removes the cofferdam inner support of the second layer after the completion of pouring, then pours and hold The third layer of the underclad portion of platform, third layer remove the cofferdam inner support of third layer after the completion of pouring.
By using above-mentioned technical proposal, pouring for cushion cap also successively substitutes between the inner support of cofferdam, to further tie up The withstanding effect power to single layer steel sheet pile is held, reduces external water pressure to the pressure of single layer steel sheet pile, while being also advantageous to The stability of cofferdam internal structure.
The further setting of the present invention is:Three layers of cofferdam inner support structures setting are identical, include angle brace, binder support and Landing support;The angle brace includes at least two supporting rods disposed in parallel, and is equipped with and hangs down between two adjacent supporting rods Straight connecting rod;The binder support is arranged along the cofferdam width direction, including two main brace binders disposed in parallel, and two It is arranged between the main brace binder for truss;The bottom end of landing support is inserted in the basic soil layer of cofferdam bottom, lands the top of support The fixed bottom surface for being connected to angle brace and binder support in end, and when the underclad portion of cushion cap pours, landing support directly pours in cushion cap Portion.
By using above-mentioned technical proposal, angle brace, the combination that binder supports and landing support is mutual, which can significantly increase, encloses The structural stability on weir, at the same land support do not need remove directly pour to cushion cap, also further strengthen cofferdam with Connectivity between cushion cap is able to ascend the overall stability in cofferdam within the construction stage of cofferdam effect.
The further setting of the present invention is:In S3 when bored pile construction, a point multiple batches carry out simultaneously, and each batch The position of secondary while construction cast-in-situ bored pile is staggered in plum blossom.
By using above-mentioned technical proposal, divides multiple batches and be conducive to accelerate construction progress, and each batch is applied simultaneously The position of the cast-in-situ bored pile of work is staggered in plum blossom, on the one hand provides certain construction space to each lots, separately On the one hand influencing each other between each stake holes is also reduced.
The further setting of the present invention is:In S2 when platform construction, from bank to the inserting piling multirow steel tubes stake of korneforos elder generation, steel pipe The top of stake is equipped with crossbeam, is laid with stringer on crossbeam, distribution beam is laid on stringer, is equipped with panel in distribution beam.
The further setting of the present invention is:K font supporting element is welded on the crossbeam to reinforcing crossmember and steel-pipe pile, The long side of the K font supporting element is parallel with crossbeam.
The further setting of the present invention is:The trestle construct when, from bank into river more steel-pipe piles of inserting piling, steel pipe The top of stake is equipped with crossbeam, is laid with stringer on crossbeam, distribution beam is laid on stringer, is equipped with panel in distribution beam.
By using above-mentioned technical proposal, trestle and platform temporary facility important when being all foundation construction, by above-mentioned Structure, so that trestle and platform stable structure, bearing capacity is high, can adapt to most of construction requirement.
In conclusion the invention has the advantages that:Pier footing stable structure of the railway bridge in river, by Power is uniform, and since sequence of construction is proper, quality can obtain good guarantee;Connection support portion is additionally provided on pier footing, Convenient for connecting with superstructure, different loading angle and size are adapted to.
Detailed description of the invention
Fig. 1 is the side view of cushion cap and connection support portion;
Fig. 2 is the top view in cofferdam;
Fig. 3 is the sequence of construction distribution map of cast-in-situ bored pile.
In figure:1, cushion cap;2, underclad portion;3, top section;4, support portion is connected;5, cofferdam;6, angle brace;7, binder Support;8, first batch;9, second lot;10, third batch.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art It can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as in this hair All by the protection of Patent Law in bright scope of the claims.
Embodiment, a kind of bridge pier foundation in construction duration method in the river of bridge, includes the following steps:
S1, trestle construction.Synchronous to five row's steel-pipe pile of river center inserting piling, every row two from bank both sides, four meters of horizontal spacing, Eight meters of longitudinal span, amounts to Ha Noi and extends 40 meters.Steel pipe stake top erector's word steel welds K word as crossbeam on crossbeam The long side of the supporting element of shape, K font supporting element is parallel with crossbeam, to reach the connection of reinforcing crossmember and two steel-pipe piles with row Intensity.
After crossbeam installation is reinforced, from bank, into river, segmental hoisting Bailey beam is laid with as stringer in Bailey beam I-steel is fixedly connected by welding as distribution beam, distribution beam with stringer, and panel is re-layed in distribution beam, i.e. completion trestle Construction.
S2, platform construction.After the completion of trestle construction, by trestle from bank to 6 row's steel-pipe pile of river center inserting piling, steel pipe Need to stay the spacing set for basic pile foundation construction between stake, steel pipe stake top erector's word steel is used as crossbeam, welding K font on crossbeam Supporting element, the long side of K font supporting element is parallel with crossbeam, with reach reinforcing crossmember and with row two steel-pipe piles connection it is strong Degree.After crossbeam installation is reinforced, from bank, into river, segmental hoisting Bailey beam is laid with I-steel in Bailey beam as stringer As distribution beam, distribution beam is fixedly connected by welding with stringer, and panel is re-layed in distribution beam, that is, completes applying for platform Work.Meanwhile according to the diameter of foundation pile, the cavity of respective numbers and diameter is installed in platform interior.
S3, bored pile construction.After the completion of platform construction, 12 pile base casing inserting pilings are entered in the river soil body, Impact holing method pore-forming is used in pile foundation casing, as shown in figure 3, being divided into first batch 8, second lot 9 and third when pore-forming The stake point of totally 3 batches and each cast-in-situ bored pile for carrying out, and carrying out simultaneously simultaneously is distributed batch 10 in plum blossom, then to pore-forming The interior concreting for carrying out basic pile foundation, completes the pouring construction of cast-in-situ bored pile.
S4, cushion cap 1 are constructed.After the completion of cast-in-situ bored pile pours, first trestle and platform are all removed, as shown in Fig. 2, edge 12 pile base casings, which circumferentially enclose, sets cofferdam 5, and cofferdam 5 is enclosed using single layer steel sheet pile to be set, and encloses and is set as rectangle, and in first inserting piling Close up at downstream after trip.
After the completion of cofferdam 5 is constructed, pumping operation is carried out.When moisture takes out 1/3 in cofferdam 5, set up in the cofferdam 5 of first layer It supports, when moisture is evacuated to 2/3 in cofferdam 5, sets up 5 inner support of cofferdam of the second layer and set up third layer in cofferdam 5 after moisture pump 5 inner support of cofferdam.Three layers of 5 inner support structure of cofferdam setting are identical, include angle brace 6, binder support 7 and landing support;Angle brace 6 includes at least Two supporting rods disposed in parallel, and vertical connecting rod is equipped between two adjacent supporting rods;It encloses on 7 edge of binder support 5 width direction of weir is arranged, including two main brace binders disposed in parallel, is arranged between two main brace binders for truss.
After the completion of three layers of 5 inner support of cofferdam in cofferdam 5 are reinforced, soil layer basic in cofferdam 5 is flattened, basis is poured Bed course, binding 1 reinforcing bar of cushion cap, installation template, as shown in Figure 1, cushion cap 1 includes upper layer and lower layer, lower layer is cuboid and is connected to On cast-in-situ bored pile, upper layer is taper type and is fixedly connected with twice battered leg.
When pouring 2 structure of underclad portion of cushion cap 1, part multilayer is carried out, and first pours the first layer of the underclad portion 2 of cushion cap 1, First layer removes 5 inner support of cofferdam of third layer after the completion of pouring, when the concrete structural strength of first layer reaches 75%, then pour The second layer of the underclad portion 2 of cushion cap 1 is built, the second layer removes 5 inner support of cofferdam of the second layer after the completion of pouring, when mixing for the second layer When Xtah Crude Clay structure intensity reaches 75%, then the third layer of the underclad portion 2 of cushion cap 1 is poured, third layer removes third after the completion of pouring 5 inner support of cofferdam of layer.Wherein, the bottom end for landing support is inserted in the basic soil layer of 5 bottom of cofferdam, and the top fixation for landing support is supported It is connected to the bottom surface of angle brace 6 and binder support 7, and in placement layer by layer cushion cap 1, landing support is not needed to remove and directly be poured into cushion cap 1 It is internal.
After the completion of the underclad portion 2 of cushion cap 1 pours, 3 reinforcing bar of top section, installation template are bound, casting concrete simultaneously stays Reinforcing bar is connected out.
S5, connection support portion 4 are constructed.The twice battered leg that support portion 4 is V-type setting is connected, when construction, first sets up interim branch Pier bracket, it is concrete prefabricated to 3 row of two sides inserting piling along bridge length direction centered on cushion cap 1 when setting up temporary rest pier bracket Stake, the top of concrete precast pile pours the interim cushion cap 1 of multiple levels, sets up more steel-pipe piles, steel pipe on interim cushion cap 1 The top absolute altitude of stake is matched with the bottom surface absolute altitude for connecting support portion 4.
I-steel is successively laid with as stringer and distribution beam on the top of steel-pipe pile, re-lays the bottom surface of connection support portion 4 Template, bottom surface template carry out internal reinforcing bar binding after being installed, reinforced slab is pre- between the reinforcing bar of twice battered leg after the completion of pricking 2 horizontally disposed prestressing tendons are embedded with, are finally attached the concrete pouring construction of support portion 4 again.Connection support portion 4 pours After the completion of building, temporary rest pier bracket, i.e. bridge pier foundation in construction duration in the river of completion railway bridge are removed.

Claims (8)

1. a kind of bridge pier foundation in construction duration method in river of bridge, which is characterized in that including steps are as follows:
S1, trestle construction set up trestle from river two sides are synchronous, extend in river;
S2, platform construction set up platform in trestle end, stay among platform and set multiple cavitys for pile foundation of constructing;
S3, cast-in-situ bored pile pour, by inserting piling in pile foundation casing cavity reserved among platform into bottom of river channel soil layer, Pore-forming operation in pile foundation casing, in pouring cast-in-situ bored pile in stake holes in pile foundation casing;
S4, cushion cap (1) construction, removes trestle and platform, and the cast-in-situ bored pile after the completion of construction carries out cofferdam (5) construction, It draws water after the completion of cofferdam (5), cofferdam (5) inner support is installed, pours cushion cap (1) concrete again;
S5, connection support portion (4) construction, sets up temporary rest pier bracket, and connection support portion (4) is poured from cushion cap (1) to two sides;
Wherein, the twice battered leg that support portion (4) are V-type setting is connected in S5, when setting up temporary rest pier bracket, is with cushion cap (1) Center is along bridge length direction to the multiple rows of prefabricated pile of two sides inserting piling, and the top of prefabricated pile has poured multiple interim cushion caps (1), temporarily More steel-pipe piles are set up on cushion cap (1), steel-pipe pile top absolute altitude is matched with the bottom surface absolute altitude for connecting support portion (4), steel-pipe pile Top is successively laid with the bottom surface template of stringer, distribution beam and connection support portion (4);Bottom surface template carries out internal steel after being installed Muscle binding, then it is attached the concrete pouring construction of support portion (4), while being embedded with multiple tracks on twice battered leg and being horizontally disposed with Prestressing tendon.
2. bridge pier foundation in construction duration method in a kind of river of bridge according to claim 1, it is characterised in that:In the S4 Cushion cap (1) includes upper layer and lower layer, and lower layer is cuboid and is connected on cast-in-situ bored pile, upper layer be taper type and with twice battered leg It is fixedly connected;When cofferdam (5) is constructed, continuously constructed using single layer steel sheet pile, it is interior to cofferdam (5) to take out after the completion of cofferdam (5) Water operation when cofferdam (5) interior moisture takes out 1/3, sets up cofferdam (5) inner support of first layer, when cofferdam (5) interior moisture is evacuated to 2/3, It sets up cofferdam (5) inner support of the second layer, after cofferdam (5) interior moisture pump, sets up cofferdam (5) inner support of third layer.
3. bridge pier foundation in construction duration method in a kind of river of bridge according to claim 2, it is characterised in that:Third layer After the completion of cofferdam (5) inner support is set up, cofferdam (5) inner base soil layer is flattened, blinding layer is poured, is poured under cushion cap (1) again The first layer of layer part (2), first layer removes cofferdam (5) inner support of third layer after the completion of pouring, then pours the lower layer of cushion cap (1) The partially second layer of (2), the second layer removes cofferdam (5) inner support of the second layer after the completion of pouring, then pours the lower layer part of cushion cap (1) Cofferdam (5) inner support of third layer is removed after the completion of dividing the third layer of (2), third layer to pour.
4. bridge pier foundation in construction duration method in a kind of river of bridge according to claim 3, it is characterised in that:Described in three layers (5) inner support structure setting in cofferdam is identical, includes angle brace (6), binder support (7) and landing support;The angle brace (6) includes at least two Root supporting rod disposed in parallel, and vertical connecting rod is equipped between two adjacent supporting rods;The binder supports (7) It is arranged along the cofferdam (5) width direction, including two main brace binders disposed in parallel, is purlin between two main brace binders Frame setting;The bottom end of landing support is inserted in the basic soil layer of cofferdam (5) bottom, and the top fixation for landing support is connected to angle brace (6) and the bottom surface of binder support (7), and when the underclad portion (2) of cushion cap (1) pours, landing support directly pours interior into cushion cap (1) Portion.
5. bridge pier foundation in construction duration method in a kind of river of bridge according to claim 1, it is characterised in that:It drills in S3 When filling pile construction, a point multiple batches carry out simultaneously, and the position of each batch while the cast-in-situ bored pile constructed is handed in plum blossom Mistake setting.
6. bridge pier foundation in construction duration method in a kind of river of bridge according to claim 1, it is characterised in that:Platform in S2 When construction, from bank to the inserting piling multirow steel tubes stake of korneforos elder generation, the top of steel-pipe pile is equipped with crossbeam, is laid with stringer, stringer on crossbeam Upper laying distribution beam is equipped with panel in distribution beam.
7. bridge pier foundation in construction duration method in a kind of river of bridge according to claim 6, it is characterised in that:The crossbeam On be welded with K font supporting element to reinforcing crossmember and steel-pipe pile, the long side of the K font supporting element is parallel with crossbeam.
8. bridge pier foundation in construction duration method in a kind of river of bridge according to claim 7, it is characterised in that:The trestle When construction, from bank, into river, more steel-pipe piles of inserting piling, the top of steel-pipe pile are equipped with crossbeam, are laid with stringer, stringer on crossbeam Upper laying distribution beam is equipped with panel in distribution beam.
CN201810805942.5A 2018-07-20 2018-07-20 A kind of bridge pier foundation in construction duration method in the river of bridge Pending CN108824211A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810805942.5A CN108824211A (en) 2018-07-20 2018-07-20 A kind of bridge pier foundation in construction duration method in the river of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810805942.5A CN108824211A (en) 2018-07-20 2018-07-20 A kind of bridge pier foundation in construction duration method in the river of bridge

Publications (1)

Publication Number Publication Date
CN108824211A true CN108824211A (en) 2018-11-16

Family

ID=64140149

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810805942.5A Pending CN108824211A (en) 2018-07-20 2018-07-20 A kind of bridge pier foundation in construction duration method in the river of bridge

Country Status (1)

Country Link
CN (1) CN108824211A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344335A (en) * 2019-07-31 2019-10-18 中铁十五局集团第四工程有限公司 A kind of method of steel trestle, initial platform and cofferdam construction in bridge construction process
CN111042144A (en) * 2019-12-27 2020-04-21 中冶天工集团有限公司 Excavation method for foundation pit of underground beam under condition of continuous flow of riverway in cold region

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006207124A (en) * 2005-01-25 2006-08-10 Nippon Sharyo Seizo Kaisha Ltd Steel-made pier structural body and its construction method
CN101838993A (en) * 2010-05-17 2010-09-22 中铁二十局集团有限公司 Construction technology of steel sheet pile cofferdam for Yellow River Channel internal support table construction
CN106049281A (en) * 2016-06-01 2016-10-26 中国铁建大桥工程局集团有限公司 Deep-water construction method of bridge at water pebble soil and argillaceous sandstone areas and auxiliary working platform
CN108005094A (en) * 2017-12-07 2018-05-08 中铁二十局集团第工程有限公司 Pier and pier top beam section construction method in naked rock river bed water

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006207124A (en) * 2005-01-25 2006-08-10 Nippon Sharyo Seizo Kaisha Ltd Steel-made pier structural body and its construction method
CN101838993A (en) * 2010-05-17 2010-09-22 中铁二十局集团有限公司 Construction technology of steel sheet pile cofferdam for Yellow River Channel internal support table construction
CN101838993B (en) * 2010-05-17 2012-04-18 中铁二十局集团有限公司 Construction technology of steel sheet pile cofferdam for Yellow River Channel internal support table construction
CN106049281A (en) * 2016-06-01 2016-10-26 中国铁建大桥工程局集团有限公司 Deep-water construction method of bridge at water pebble soil and argillaceous sandstone areas and auxiliary working platform
CN108005094A (en) * 2017-12-07 2018-05-08 中铁二十局集团第工程有限公司 Pier and pier top beam section construction method in naked rock river bed water

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刘宝龙: "水中大体积V型墩斜腿组合式支撑体系下施工技术研究", 《铁道工程学报》 *
李清: "小榄水道特大桥群桩基础深水施工技术", 《科技资讯》 *
王涛: "小榄水道特大桥主桥大直径桩基施工探析", 《贵州工业大学学报(自然科学版)》 *
高松等: "水中承台钢板桩围堰施工技术研究", 《山西建筑》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344335A (en) * 2019-07-31 2019-10-18 中铁十五局集团第四工程有限公司 A kind of method of steel trestle, initial platform and cofferdam construction in bridge construction process
CN110344335B (en) * 2019-07-31 2021-08-10 中铁十五局集团有限公司 Method for constructing steel trestle, initial platform and cofferdam in bridge construction process
CN111042144A (en) * 2019-12-27 2020-04-21 中冶天工集团有限公司 Excavation method for foundation pit of underground beam under condition of continuous flow of riverway in cold region

Similar Documents

Publication Publication Date Title
CN106223360B (en) Using the open cut cast in place and precast construction subway station construction method of stake supporting system
CN101424073A (en) Bridge deck and steel girder second combination method for whole arch precasted steel-concrete composite continuous box girder
CN102286924B (en) Bridge construction method with inverted procedures
CN108442237B (en) Structure for rapid splicing of prefabricated bridge pier and prefabricated bearing platform and construction method of structure
CN108103926A (en) Assembled hollow pier and its construction method based on end plate welding
JP2004278148A (en) Construction method of bridge
CN112411362A (en) Bridge pier, construction method thereof and bridge
CN112575670A (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN112554077A (en) Steel pipe concrete assembled truss composite beam construction system and construction method
CN114457668B (en) Large-span space special-shaped arch rib delphinium type basket steel box arch bridge and rapid construction method
CN210238260U (en) Full-prefabricated assembled structural bridge suitable for grassland wetland
CN206090275U (en) Assembled rectangular concrete -filled steel tube makes up truss bridge
CN108824211A (en) A kind of bridge pier foundation in construction duration method in the river of bridge
CN210049103U (en) High-grade high-speed highway bracket spanned by large-span cast-in-place box girder
Ingebrigtsen Stolma bridge, norway
CN103510458A (en) Pile type continuous rigid frame bridge and construction method thereof
CN110219235A (en) A kind of full precast assembly structural bridge and its construction method suitable for grassland wetland
CN211872669U (en) Uneven jacking system of current bridge superstructure
CN109898540B (en) Wet joint structure among bridge pier, bearing platform and pile foundation and construction process thereof
CN112627002A (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN111706128A (en) Prefabricated inspection pit stand column and construction method thereof
CN215104688U (en) Viaduct strides parallel bridge buttress full assembled support in ground
CN220767747U (en) Railway basket arch bridge construction structure with large inclined span longitudinal slope underground double parallel structure
CN114045855B (en) Soft soil foundation large-span reinforced concrete beam construction method
CN108755669A (en) Across tunnel steel reinforced concrete bored concrete pile, conversion beam construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181116