CN108797870A - Method for connecting floor slab to steel beam of wooden building - Google Patents

Method for connecting floor slab to steel beam of wooden building Download PDF

Info

Publication number
CN108797870A
CN108797870A CN201810358795.1A CN201810358795A CN108797870A CN 108797870 A CN108797870 A CN 108797870A CN 201810358795 A CN201810358795 A CN 201810358795A CN 108797870 A CN108797870 A CN 108797870A
Authority
CN
China
Prior art keywords
floor
steel beam
wooden
shape steel
wooden floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810358795.1A
Other languages
Chinese (zh)
Inventor
焦培峻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuzai Co ltd
Original Assignee
Yuzai Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuzai Co ltd filed Critical Yuzai Co ltd
Publication of CN108797870A publication Critical patent/CN108797870A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/023Separate connecting devices for prefabricated floor-slabs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/10Load-carrying floor structures formed substantially of prefabricated units with metal beams or girders, e.g. with steel lattice girders
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/12Load-carrying floor structures formed substantially of prefabricated units with wooden beams

Abstract

A method for connecting a floor slab to a steel beam of a wooden building comprises the following steps: assembling an I-shaped steel beam on a plane, assembling a wood floor on the inner side of the I-shaped steel beam, locking the wood floor close to the inner side of the I-shaped steel beam by more than one group of combining bolts from the outer side of the I-shaped steel beam to the inner side, installing angle materials for adjusting the flatness of the wood floor and the decorative floor at two ends of the inner side of the decorative floor, attaching the angle materials to the wood floor and protruding out of the I-shaped steel beam, locking the decorative floor and the wood floor by more than one group of combining bolts, and forcing the decorative floor to cover the outer sides of the I-shaped steel beam and the wood floor, thereby quickly building the wood building and shortening the construction period by the combining mode of the invention.

Description

Connection method of the floor of Wood construction to girder steel
Technical field
A kind of connection method the present invention relates to floor of Wood construction to girder steel, more particularly to it is a kind of by one group or more I-shape steel beam group connects multiple wooden floors, reaches Rapid Combination and can shorten the building engineering method of construction time.
Background technology
Wood construction have the advantages that it is a variety of, for example:The raw material of Wood construction is mainly based on timber, and with part concrete And supplemented by metal, thus compared to armored concrete (RC buildings) for, more environmental protection and time for putting up a house is shorter.And timber Temperature is built with adjusting cool in summer and warm in winter, is increasingly liked in recent years by masses.
The mode that the existing carpentery workshop floor applied more than second floor is combined with beam be frame in exterior wall skeleton and compartment skeleton it Between, foundation needs the load-carrying for selecting the wooden frame of appropriate span to bear floor;However, making concessionaire or the foreman's Chang Yin professions of log cabin Knowledge is insufficient or to save cost and ambiguous band mistake, but thus cause log cabin in the future after the completion of, floor when use occurs to walk It crosses at soft, storing furniture and sink, and then seriously affect structure and sound insulation.In addition, existing wooden frame processes relatively complicated, constructor Member is other than needing by design drawing construction, and when having interference between wooden frame and the wooden building materials, construction personnel needs through equipment again Wooden frame is processed again.
Invention content
The main object of the present invention is the connection method for being to provide a kind of floor of Wood construction to girder steel, mainly passes through I-shaped Section steel beam is as girder, sealed wooden floor and the floor of modification on girder, and accordingly, i-shape steel beam provides preferable Support force, and can quickly assemble, reach Rapid Combination and the building engineering method of construction time can be shortened.
The building engineering method of above-mentioned purpose can be reached, including:One i-shape steel beam, which is assembled in one, to be had in plane, by one Wooden floor is assembled on the inside of the i-shape steel beam, then with one group or more of Combining bolt by the outside of the i-shape steel beam inwards Locking so that the wooden floor is fitted tightly on the inside of the i-shape steel beam, both ends installation of the modification floor on the inside of it It is useful for the angle section for adjusting the wooden floor and the modification floor level degree, the wooden floor is fitted in and convexedly stretches in this At i-shape steel beam, modification floor and the wooden floor are locked by one group or more of Combining bolt, force the modification building Plate is covered on the outside of the i-shape steel beam and the wooden floor, accordingly, combination energy fast construction wood through the invention Building shortens the construction time.
In construction, in order to enable the wooden floor to be flattened on the i-shape steel beam, the wooden floor is I-shaped with this The side that girder steel is connected cuts off the wooden floor lower edge angle, in order to install.
Construction when, if encounter between i-shape steel beam and wooden floor generate can not horizontal screw lock the case where when, the work Shaped girder steel can define an interconnecting piece and two planar portions, which can define a horizontal connection portion and one vertically Interconnecting piece is threaded into the vertical joints so that the wood by one group or more of Combining bolt by the interconnecting piece of the i-shape steel beam Matter floor integrally combines with the i-shape steel beam.
In construction, if the i-shape steel beam needs to accept the wooden floor of larger area, or when wanting loading capacity larger, It is further provided with an auxiliary support block on rear side of the wooden floor, by one group or more of Combining bolt by the auxiliary support block side The wooden floor is locked, by auxiliary support block increase and the i-shape steel beam contact area, providing the wooden floor has Larger load stress.
If have in construction construction area it is smaller in the case of, also can by the wooden floor by Combining bolt by the I-shaped The inside facing outward side chain of section steel beam is fixed in the modification floor.
The present invention also can be assembled in a timber beam, the timber beam other than it can wooden floor be installed on i-shape steel beam It is arranged in parallel in the i-shape steel beam side, is locked in the timber beam by the wooden floor by one group or more of Combining bolt.
Description of the drawings
Fig. 1 is first embodiment of the invention assembling figure (one).
Fig. 2 is first embodiment of the invention assembling figure (two).
Fig. 3 is second embodiment of the invention schematic diagram.
Fig. 4 is third embodiment of the invention schematic diagram.
Fig. 5 is four embodiment of the invention schematic diagram.
Fig. 6 is fifth embodiment of the invention schematic diagram.
Fig. 7, Fig. 8 are other embodiment schematic diagram of the present invention.
Reference sign
10 interconnecting piece of i-shape steel beam, 11 planar portions 12
Timber beam 13
20 lower edge angle of wooden floor, 21 vertical joints 23
24 auxiliary support block 25 of horizontal connection portion
Modification 30 angle section of floor, 31 collision mat 32
Combining bolt 40.
Specific implementation mode
It please refers to Fig.1, Fig. 2, the connection method of the floor of Wood construction of the present invention to girder steel comprising:By an i shaped steel Beam 10, which is assembled in one, to be had in plane (such as the ground of Wood construction either Wood construction exterior wall skeleton), by 20 groups of a wooden floor Loaded on inwards being locked by i-shape steel beam outside on the inside of the i-shape steel beam, then with one group or more of Combining bolt 40, make It obtains the wooden floor 20 and is fitted tightly over 10 inside of i-shape steel beam, take a modification manufactured with timber with floor 30 in it The both ends of side are equipped with the angle section 31 for adjusting the wooden floor 20 and 30 flatness of modification floor, are fitted in The wooden floor 20 convexedly stretches at the i-shape steel beam 10, by one group or more of Combining bolt 40 by modification floor 30 and the wood Matter floor 20 locks, and the modification floor 30 is forced to be covered on the outside of the i-shape steel beam 10 and the wooden floor 20, accordingly, Combination energy fast construction Wood construction through the invention shortens the construction time.Further such as Fig. 8, if modification floor 30 It is contacted with the external world, then must be laid with more than one collision mat 32,32 energy of collision mat in the outside of the modification floor 30 The situation that water-sprinkling effect prevents aqueous vapor to be attached to the wooden floor 20 or modification floor 30 and is deformed or rots is generated to send out It is raw.Combined method through the invention, which can exempt, to be commonly used wooden frame repeatedly processing is needed to form trip or bonding pad, and is constructed Personnel can rapid construction, in addition the i-shape steel beam 10 have good intensity, can be to avoid floor caused by construction wrong The problem of recess, noise, generates.
Referring to Fig. 3, in construction, in order to enable the wooden floor 20 to be flattened on the i-shape steel beam 10, this is wooden The side that floor 20 is connected with the i-shape steel beam 10, cuts off 20 lower edge angle 21 of wooden floor, and excision lower edge angle 21 can carry With horizontal connection portion 24 inner face of the i-shape steel beam 10 is fitted in order to installing for the vertical joints 23 of wooden floor 20 When can fit closely.If in addition the i-shape steel beam 10 need accept larger area wooden floor 20, or want loading capacity compared with When big, which is further provided with an auxiliary support block 25, auxiliary by this by one group or more of Combining bolt 40 It helps 25 side of supporting block to lock the wooden floor 20, is increased and 10 contact surface of i-shape steel beam by the auxiliary support block 25 Product, providing the wooden floor 20 has larger load stress.
Referring to Fig. 4, in construction, if encountering between i-shape steel beam 10 and wooden floor 20, generation can not horizontal screw lock The case where when, which can define an interconnecting piece 11 and two planar portions 12, which can define One horizontal connection portion 24 and a vertical joints 23, by one group or more of Combining bolt 40 by the connection of the i-shape steel beam 10 Portion is threaded into the vertical joints 23 so that the wooden floor 20 integrally combines with the i-shape steel beam 10.
Referring to Fig. 5, the present invention other than it can wooden floor 20 be installed on i-shape steel beam 10, also can be assembled in a wood Matter beam 13, which is arranged in parallel in 10 side of i-shape steel beam, wooden by this by one group or more of Combining bolt 40 Floor 20 is locked in the timber beam 13.Design can mitigate the overall weight of floor whereby.
If referring to Fig. 6, have in construction construction area it is smaller in the case of, also the wooden floor 20 can be passed through combination Bolt 40 is fixed in the wooden floor 20 by the inside facing outward side chain of the i-shape steel beam 10 and is used again by such as timber beam 13 or modification Floor 30 connects.
Referring to Fig. 7, the situation of its first and third embodiment of combination mainly illustrated, first by the i-shape steel beam 10 Interconnecting piece locks several Combining bolts 40, and is fixed on the vertical joints 23 of the wooden floor 20 of the other side, accordingly by side Wooden floor 20 connect with i-shape steel beam 10, the wooden floor 20 of the other side is then if first embodiment is with the side of butt Formula is fixed on 24 inside of horizontal connection portion of the i-shape steel beam 10, then is locked with several Combining bolts 40, therefore, by this hair It is bright that suitable form of construction work can be selected according to field conditions, the efficiency of assembling and building can be improved.
By above description, advantages of the present invention is as follows:
(1) characteristic of wooden floor 20 of the invention is formed with the structure of multiple wood tissue texture different directions, this is wooden Floor 20 is high with bonding strength, the good advantage of associativity, for comparing existing engineering method in such a way that plank combines one by one, this Invention substantially shortens the construction period and provides the advantages that Wood construction service life is long.
(2) present invention selects i-shape steel beam 10 as beam body, with high intensity, it is not easy to which the characteristics of deforming is compared Existing structure only by the design of wood sawing trip or binding end for, i-shape steel beam 10 has the advantages that higher assembling.
Obviously, described embodiment is only a part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.

Claims (5)

1. a kind of connection method of floor of Wood construction to girder steel, which is characterized in that its step includes:By an i-shape steel beam group Mounted in one have plane on, a wooden floor is assembled on the inside of the i-shape steel beam, then with one group or more of Combining bolt by Inwards lock on the outside of the i-shape steel beam so that the wooden floor is fitted tightly on the inside of the i-shape steel beam, and a modification is used Both ends of the floor on the inside of it are equipped with the angle section for adjusting the wooden floor and the modification floor level degree, are pasted It is convexedly stretched at the i-shape steel beam together in the wooden floor, which can define an interconnecting piece and two planes Portion, which can define a horizontal connection portion and a vertical joints, by one group or more of Combining bolt by the work The interconnecting piece of shaped girder steel is threaded into the vertical joints, forces the modification with floor to be covered on the i-shape steel beam wooden with this The outside of floor.
2. connection method of the floor of Wood construction according to claim 1 to girder steel, which is characterized in that the wooden floor with The side that the i-shape steel beam is connected cuts off the wooden floor lower edge angle, in order to install.
3. connection method of the floor of Wood construction according to claim 1 to girder steel, which is characterized in that after the wooden floor Side is further provided with an auxiliary support block, and the wooden building is locked by the auxiliary support block side by one group or more of Combining bolt Plate is provided the wooden floor and is answered with larger load by auxiliary support block increase and the i-shape steel beam contact area Power.
4. connection method of the floor of Wood construction according to claim 3 to girder steel, which is characterized in that the wooden floor is logical It crosses Combining bolt and the floor is fixed in by the inside facing outward side chain of the i-shape steel beam.
5. connection method of the floor of Wood construction according to claim 1 to girder steel, which is characterized in that the building of the timber structure Plate further includes a timber beam to the connection method of girder steel, and it is wooden by the wooden floor to be locked in this by one group or more of Combining bolt Liang Zhong.
CN201810358795.1A 2017-04-27 2018-04-20 Method for connecting floor slab to steel beam of wooden building Pending CN108797870A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
TW106114057 2017-04-27
TW106114057A TWI687571B (en) 2017-04-27 2017-04-27 Connection method of floor board of wooden building to steel beam

Publications (1)

Publication Number Publication Date
CN108797870A true CN108797870A (en) 2018-11-13

Family

ID=64093395

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810358795.1A Pending CN108797870A (en) 2017-04-27 2018-04-20 Method for connecting floor slab to steel beam of wooden building

Country Status (2)

Country Link
CN (1) CN108797870A (en)
TW (1) TWI687571B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110469022A (en) * 2019-07-03 2019-11-19 扬州工业职业技术学院 The production method of wooden peg welding laminated timber floor assembly
CN114592648A (en) * 2022-03-07 2022-06-07 安徽富煌钢构股份有限公司 Assembled steel construction self-supporting floor system limit portion end restraint structure of encorbelmenting

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI715246B (en) * 2019-10-15 2021-01-01 台灣門框科技有限公司 Fasteners for angle installation

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2455145A1 (en) * 1979-04-26 1980-11-21 Chasson Francois Prefabricated panel for roof construction - is pinned to square section end tubes with T=section support beams build into gable ends
JPH04155046A (en) * 1990-10-19 1992-05-28 Sekisui House Ltd Floor device
JPH05141029A (en) * 1991-11-19 1993-06-08 Sekisui House Ltd Floor frame for building
JP2001214405A (en) * 2000-02-02 2001-08-07 East Japan Railway Co Girder for construction work
CN203729468U (en) * 2014-01-26 2014-07-23 宁波大学 Connecting structure for steel and bamboo combined floor and steel and bamboo combined beam
CN106245837A (en) * 2016-09-06 2016-12-21 南京工业大学 A kind of assembled GFRP drawing and extruding section bar core wood composite floor slab structural system
JP2017014764A (en) * 2015-06-30 2017-01-19 パナホーム株式会社 Floor panel-beam connection structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1724832A (en) * 2004-07-21 2006-01-25 三泽住宅株式会社 Building using wooden shaped board and construction method thereof
CN201236417Y (en) * 2008-07-08 2009-05-13 苏州工艺美术职业技术学院 Steel-wood constructed beam for garret
CN203834694U (en) * 2014-05-19 2014-09-17 江苏宜润建筑改造技术有限公司 Steel and wood connection structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2455145A1 (en) * 1979-04-26 1980-11-21 Chasson Francois Prefabricated panel for roof construction - is pinned to square section end tubes with T=section support beams build into gable ends
JPH04155046A (en) * 1990-10-19 1992-05-28 Sekisui House Ltd Floor device
JPH05141029A (en) * 1991-11-19 1993-06-08 Sekisui House Ltd Floor frame for building
JP2001214405A (en) * 2000-02-02 2001-08-07 East Japan Railway Co Girder for construction work
CN203729468U (en) * 2014-01-26 2014-07-23 宁波大学 Connecting structure for steel and bamboo combined floor and steel and bamboo combined beam
JP2017014764A (en) * 2015-06-30 2017-01-19 パナホーム株式会社 Floor panel-beam connection structure
CN106245837A (en) * 2016-09-06 2016-12-21 南京工业大学 A kind of assembled GFRP drawing and extruding section bar core wood composite floor slab structural system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110469022A (en) * 2019-07-03 2019-11-19 扬州工业职业技术学院 The production method of wooden peg welding laminated timber floor assembly
CN114592648A (en) * 2022-03-07 2022-06-07 安徽富煌钢构股份有限公司 Assembled steel construction self-supporting floor system limit portion end restraint structure of encorbelmenting
CN114592648B (en) * 2022-03-07 2024-01-16 安徽富煌钢构股份有限公司 Edge overhanging end constraint structure of assembled steel structure self-supporting floor slab system

Also Published As

Publication number Publication date
TW201839225A (en) 2018-11-01
TWI687571B (en) 2020-03-11

Similar Documents

Publication Publication Date Title
CN108797870A (en) Method for connecting floor slab to steel beam of wooden building
CN106801473B (en) Aluminum alloy structure house
CN106759954B (en) Buckling structure of aluminum alloy wallboard, floor and corner connecting material
JP2014141842A (en) Solar battery panel installation structure and method of forming the same
CN207363026U (en) A kind of environmental protection wayside pavilion structural beams
CN210263610U (en) Prefabricated wallboard structure keeps warm
CN108035469A (en) The orthogonal laminated wood composite floor system of space box shape rotary-cut plate laminated wood and its manufacture method
CN217028568U (en) Prefabricated component and prefabricated building
CN204326237U (en) A kind of wind resistance building structure frame
CN206887796U (en) A kind of ready-package deck and its assembled helistop
JP5113875B2 (en) Brick masonry structure
CN213806156U (en) Assembled shock attenuation roof beam for building
Ni et al. Effect of overturning restraint on performance of shear walls
CN110409664B (en) Prestressed steel plate concrete shear wall structure
CN211007177U (en) Splicing structure of steel plate shear wall
KR101497272B1 (en) System Support
TWI668352B (en) Floor to floor connection method for wooden buildings
Carradine et al. Utilizing diaphragm action for wind load design of timber frame and structural insulated panel buildings
CN201236417Y (en) Steel-wood constructed beam for garret
CN205604540U (en) Take tempering stone material curtain board of prestressing force
CN218541064U (en) Movable wall structure and container house
CN114045947B (en) Bearing system combining heat-preservation ceiling and light steel roof truss
CN217630466U (en) Connecting joint of light wood structure middle beam and column
CN219060465U (en) Light steel structure outer wall enclosure
CN211949061U (en) Enclosure system for assembly type steel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
AD01 Patent right deemed abandoned

Effective date of abandoning: 20210702

AD01 Patent right deemed abandoned