CN108797312A - A kind of bent cap structure and its construction method - Google Patents

A kind of bent cap structure and its construction method Download PDF

Info

Publication number
CN108797312A
CN108797312A CN201810795859.4A CN201810795859A CN108797312A CN 108797312 A CN108797312 A CN 108797312A CN 201810795859 A CN201810795859 A CN 201810795859A CN 108797312 A CN108797312 A CN 108797312A
Authority
CN
China
Prior art keywords
construction
bent cap
steel beam
cap structure
hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810795859.4A
Other languages
Chinese (zh)
Inventor
马骉
黄虹
苏俭
田周松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201810795859.4A priority Critical patent/CN108797312A/en
Publication of CN108797312A publication Critical patent/CN108797312A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to technical field of bridge engineering, more particularly to a kind of bent cap structure, it is characterized in that the bent cap structure includes hollow-core construction and solid construction, the wherein described solid construction is corresponding with the position of bridge pier, hollow-core construction then the position between adjacent bridge pier and bent cap to choose arm position corresponding, the perforation of steel beam is set in bent cap end tensioning external prestressing steel beam, solid construction, to realize that external prestressing steel beam turns to;The solid section of the bent cap structure connect to form entirety with bridge pier, and solid construction connect to form consolidated node with pier column.The bent cap structure of the present invention, the weight of bent cap structure can be mitigated significantly, save column, cushion cap and pile foundation dosage, reduce project cost, prefabrication and assembly construction technique can be widely applied, realizes the standardization, batch production, assembling of bent cap structure, the bridge construction for promoting China is horizontal, with good environmental benefit, Social benefit and economic benefit, it is worthy of promotion and application.

Description

A kind of bent cap structure and its construction method
Technical field
The present invention relates to technical field of bridge engineering, and in particular to a kind of bent cap structure.
Background technology
At present in the bridge construction in China, generally there are two types of types for bent cap structure:
(1)Normal concrete bent cap.Using normal concrete and prestressing with bond is set, also may be used when bent cap structure stress is smaller Cancel prestressing with bond, regular reinforcement is only set.The type bent cap generally uses support cast-in-place technique, as " green is built for country Build " implementation of development strategy, bent cap structure construction more and more uses precast assembly process.However, the type bent cap weight Greatly, although can be by hollowing out loss of weight inside bent cap, due to being limited by the arrangement space of prestressing with bond, concrete material The limitation etc. of performance, when bridge width is larger, when bent cap is larger, the weight after loss of weight is still larger, cannot be satisfied and applies Work requirement is limited by factors such as transporting equipment, hanging device and lifting spaces, is answered when urban architecture compact district There is prodigious difficulty with precast assembly process.
(2)Steel construction bent cap.Bent cap agent structure uses steel, and the type bent cap is light-weight, using precast assembly process Construction, prefabrication, on-site consolidation, mechanization degree are high.However, the type bent cap late maintaining workload is very big, synthesis is made Valence is high, is only used on a small quantity in local specific position at present.
With the continuous development of urban construction, there is an urgent need for a kind of novel cover girder constructions, can mitigate the weight of bent cap structure significantly Amount saves column, cushion cap and pile foundation dosage, reduces project cost, is suitble to component integral prefabricated or the prefabricated transporting and hoisting of segmentation, Prefabrication and assembly construction technique can be widely applied, meet urban architecture compact district, bridge width it is larger when rapid construction It is required that and being convenient for late maintaining.
Invention content
In view of the above-mentioned problems, the present invention proposes a kind of bent cap structure, bent cap weight can be greatly reduced, save column, Cushion cap and pile foundation dosage reduce project cost, prefabrication and assembly construction technique can be widely applied, and be convenient for late maintaining, into one The bridge construction that step promotes China is horizontal.
The realization of the present invention is completed by following technical scheme:A kind of bent cap structure, it is characterised in that the bent cap structure packet Include hollow-core construction and solid construction, wherein the solid construction is corresponding with the position of pier column, hollow-core construction then with it is adjacent Position and bent cap between pier column to choose arm position corresponding, it is solid in bent cap end tensioning external prestressing steel beam The perforation of steel beam is set in structure, to realize that external prestressing steel beam turns to;The solid section and pier column of the bent cap structure Connection forms entirety, and solid construction connect to form consolidated node with pier column.
Further, the hollow-core construction is made of ultra-high performance concrete material;The solid construction uses Ultra-high performance concrete material or common concrete material are made.
Further, the solid construction can also carry out part hollow processing.
Further, it is chosen positioned at bent cap on the outside of the hollow-core construction of arm, that is, chooses arm end and be equipped with steel beam anchor point, the body External prestressed steel beam is anchored in bent cap and chooses steel beam anchor point on the outside of arm hollow-core construction, and bent cap end uses ultra-high performance concrete Material.
Further, reinforcing bar should be arranged in the hollow-core construction and solid construction in its concrete material.
Further, the web of the hollow parts of the bent cap structure uses ultra-high performance concrete, can cancel described Web position in stirrup, web position is arranged single vertical hook muscle, fully reduces web thickness.
Further, the web of the hollow-core construction, top plate and bottom plate wall thickness be 8cm ~ 12cm, also can be according to practical feelings Condition is suitably relaxed.
Further, precast segment assembling process and integral prefabricated assembling process can be used in the bent cap structure construction.
Further, single box single chamber, single box double room and single-box multi-cell may be used in the hollow structural part of the bent cap.
Another object of the present invention is to propose a kind of construction method of bent cap structure, bent cap weight can be greatly reduced Amount saves column, cushion cap and pile foundation dosage, reduces project cost, can be widely applied prefabrication and assembly construction technique, and after being convenient for Phase conserves, and the bridge construction for further promoting China is horizontal.
The realization of the present invention is completed by following technical scheme:A kind of construction method of bent cap structure, it is characterised in that this is applied Work method includes the following steps:
A, integral bent cap structure is poured in pre-fabricated factory, the integral cap girder construction includes solid construction and hollow-core construction, Wherein solid construction position is corresponding with pier column position, hollow-core construction then the position between corresponding pier column and Bent cap to choose arm position corresponding, the perforation of steel beam is set in solid construction, is chosen positioned at bent cap and is equipped with steel beam on the outside of the hollow-core construction of arm Anchor point;
B, prefabricated integral cap girder construction is conserved to design strength, tensioning external prestressing steel beam, positioned at the sky for choosing arm end Tensioning external prestressing steel beam at core structure steel beam anchor point, the steel beam in solid construction are perforated to realize external prestressing steel Beam turns to;
C, by preform lid girder construction whole Transporting to construction site, prefabricated integral cap girder construction is installed to using hanging device Through constructing on the bridge pier finished;
D, finally in solid construction position, pier column and bent cap structure are connected as entirety.
The realization of the present invention can also be completed by following technical scheme:A kind of construction method of bent cap structure, it is characterised in that The construction method includes the following steps:
A, it is poured in pre-fabricated factory and builds up multiple bent cap segments, the bent cap segment includes solid construction and hollow-core construction, wherein Solid construction position is corresponding with pier column position, the hollow-core construction then position between corresponding pier column and bent cap To choose arm position corresponding, the perforation of steel beam is set in solid construction, steel beam anchor point is equipped with positioned at arm end is chosen;
B, preform lid girder segment is conserved to design strength, by preform lid girder segment transported batchwise to construction site;
C, bent cap segment is assembled by integral cap girder construction, installation to the bridge pier finished of having constructed using hanging device and holder On, tensioning external prestressing steel beam, in tensioning external prestressing steel beam, solid construction at the steel beam anchor point for choosing arm end Interior steel beam perforates to realize that external prestressing steel beam turns to;
D, finally in solid construction position, pier column and bent cap structure are connected as entirety.
Further, the hollow-core construction uses ultra-high performance concrete material;The solid construction uses superelevation Performance concrete material or common concrete material.
Further, the solid construction connect to form consolidated node with pier column.
The bent cap structure of the present invention can mitigate the weight of bent cap structure significantly, save column, cushion cap and pile foundation and use Amount reduces project cost, can widely apply prefabrication and assembly construction technique.It is an advantage of the invention that:
1. opposite normal concrete bent cap, can greatly reduce bent cap weight, column, cushion cap and pile foundation dosage are saved, reduces work Journey cost, the thin-wall construction part of the bent cap structure, web, top plate and bottom plate are not provided with prestressed strand, and thickness is not It is controlled by the construction of prestressed strand, and uses ultra-high performance concrete material, therefore thickness can greatly reduce, minimum takes 8cm ~ 12cm thickness.Construction control and concrete material of the minimum plate thickness of conventional hollow structure by prestressed strand The control of energy, control are not less than 20cm ~ 25cm.Therefore the present invention has breakthrough in terms of substructure bent cap loss of weight, can Prefabrication and assembly construction technique is widely applied, realizes the standardization, batch production, assembling of bent cap structure;
2. opposite steel construction bent cap, is convenient for late maintaining, good economy performance;
3. being suitble to component integral prefabricated or the prefabricated transporting and hoisting of segmentation, prefabrication and assembly construction technique can be widely applied.
Description of the drawings
The present invention is described in more detail hereinafter in connection with attached drawing.Wherein:
Fig. 1 is the elevational schematic view of novel cover girder construction in the present invention;
Fig. 2 is the A-A sectional views of Fig. 1 in the present invention;
Fig. 3 is the B-B sectional views of Fig. 1 in the present invention;
In the accompanying drawings, identical component uses identical reference numeral.
Specific implementation mode
Below in conjunction with attached drawing, by the way that a preferable specific embodiment is described in detail, the feature of the present invention is further explained It states, in order to the understanding of technical staff of the same trade:
Such as Fig. 1-Fig. 3, figure acceptance of the bid note is respectively:Hollow-core construction 1, solid construction 2, external prestressing steel beam 3.
Hollow-core construction 1, solid construction 2 in novel cover girder construction pour integral bent cap structure in pre-fabricated factory, empty Core structure 1 uses ultra-high performance concrete material, solid construction 2 to use common concrete material.Integral cap girder construction conserve to After design strength, tensioning external prestressing steel beam 3.It, will by transporting equipment after 3 tensioning of external prestressing steel beam and anchoring Preform lid girder construction is installed to having constructed using hanging device and is finished to construction site by preform lid girder construction whole Transporting On bridge pier, finally in 2 position of solid construction, bridge pier and bent cap structure are connected as entirety.When bent cap stress is smaller, can cancel External prestressing steel beam 3.
As shown, a specific embodiment according to the present invention, the bent cap structure is by the first hollow-core construction, the first reality Core structure, the second hollow-core construction, the second solid construction and third hollow-core construction are connected in sequence integral cap girder construction, wherein One hollow-core construction and third hollow-core construction are symmetrical arranged, and the first solid construction and the second solid construction are symmetrical arranged, and first is hollow The outside of structure and third hollow-core construction is equipped with steel beam anchor point, for anchoring external prestressing steel beam, the first solid construction and It is equipped with steel beam in second solid construction to perforate, the contact for external prestressing steel beam turns to.First hollow-core construction, second Hollow-core construction and third hollow-core construction are body structure, using single box double room form.
Although present disclosure is discussed in detail by above preferred embodiment, but it should be appreciated that above-mentioned Description is not considered as limitation of the present invention, and protection scope of the present invention should be limited to the appended claims.

Claims (9)

1. a kind of bent cap structure, it is characterised in that the bent cap structure includes hollow-core construction and solid construction, wherein described solid Structure is corresponding with the position of pier column, and then the position between corresponding pier column and bent cap choose arm to hollow-core construction Position is corresponding, and the perforation of steel beam is set in bent cap end tensioning external prestressing steel beam, solid construction, is answered in advance in vitro to realize Power steel beam turns to;The solid section of the bent cap structure connect to form entirety with pier column, and solid construction connects with pier column It connects to form consolidated node.
2. bent cap structure according to claim 1, it is characterised in that the hollow-core construction uses ultra-high performance concrete Material;The solid construction uses ultra-high performance concrete material or common concrete material.
3. bent cap structure according to claim 1, it is characterised in that be located on the outside of the hollow-core construction of beam-ends and be equipped with steel beam anchor Solid point, the external prestressing steel beam are anchored in the steel beam anchor point of bent cap end, and bent cap end uses very-high performance coagulation Soil material.
4. bent cap structure according to claim 1, it is characterised in that the hollow-core construction and solid construction, in its coagulation Reinforcing bar should be set in soil material.
5. bent cap structure according to claim 1, it is characterised in that the web position setting of the hollow-core construction is single It is vertical to hook muscle, fully reduce web thickness.
6. bent cap structure according to claim 1, it is characterised in that the web of the hollow-core construction, the wall of top plate and bottom plate Thickness is 8cm ~ 12cm, also can suitably be relaxed according to actual conditions.
7. bent cap structure according to claim 1, it is characterised in that single box single chamber, single case may be used in the hollow-core construction Dual chamber and single-box multi-cell.
8. a kind of construction method of bent cap structure, it is characterised in that the construction method includes the following steps:
A, integral bent cap structure is poured in pre-fabricated factory, the integral cap girder construction includes solid construction and hollow-core construction, Wherein solid construction position is corresponding with pier column position, hollow-core construction then the position between corresponding pier column and Bent cap to choose arm position corresponding, the perforation of steel beam is set in solid construction, arm end is chosen and is equipped with steel beam anchor point;
B, prefabricated integral cap girder construction is conserved to design strength, tensioning external prestressing steel beam, positioned at choosing arm end steel beam Tensioning external prestressing steel beam at anchor point, the steel beam in solid construction perforate to realize that external prestressing steel beam turns to;
C, by preform lid girder construction whole Transporting to construction site, prefabricated integral cap girder construction is installed to using hanging device Through constructing on the bridge pier finished;
D, finally in solid construction position, pier column and bent cap structure are connected as entirety.
9. a kind of construction method of bent cap structure, it is characterised in that the construction method includes the following steps:
A, it is poured in pre-fabricated factory and builds up multiple bent cap segments, the bent cap segment includes solid construction and hollow-core construction, wherein Solid construction position is corresponding with pier column position, the hollow-core construction then position between corresponding pier column and bent cap To choose arm position corresponding, the perforation of steel beam is set in solid construction, arm end is chosen and is equipped with steel beam anchor point;
B, preform lid girder segment is conserved to design strength, by preform lid girder segment transported batchwise to construction site;
C, bent cap segment is assembled by integral cap girder construction, installation to the bridge pier finished of having constructed using hanging device and holder On, tensioning external prestressing steel beam, in tensioning external prestressing steel beam, solid construction at the steel beam anchor point for choosing arm end Interior steel beam perforates to realize that external prestressing steel beam turns to;
D, finally in solid construction position, pier column and bent cap structure are connected as entirety.
CN201810795859.4A 2018-07-19 2018-07-19 A kind of bent cap structure and its construction method Pending CN108797312A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810795859.4A CN108797312A (en) 2018-07-19 2018-07-19 A kind of bent cap structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810795859.4A CN108797312A (en) 2018-07-19 2018-07-19 A kind of bent cap structure and its construction method

Publications (1)

Publication Number Publication Date
CN108797312A true CN108797312A (en) 2018-11-13

Family

ID=64077559

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810795859.4A Pending CN108797312A (en) 2018-07-19 2018-07-19 A kind of bent cap structure and its construction method

Country Status (1)

Country Link
CN (1) CN108797312A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440634A (en) * 2018-12-11 2019-03-08 上海市城市建设设计研究总院(集团)有限公司 The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off
CN109881575A (en) * 2019-04-18 2019-06-14 上海市城市建设设计研究总院(集团)有限公司 Using the prefabricated bent cap in π type cross section and its method for prefabricating of prestressing with bond muscle
CN109881574A (en) * 2019-04-18 2019-06-14 上海市城市建设设计研究总院(集团)有限公司 Using the prefabricated bent cap in π type cross section and its method for prefabricating of external prestressing steels
CN110847044A (en) * 2019-11-15 2020-02-28 中交第二航务工程局有限公司 Semi-prefabricated assembled bent cap construction method
CN113605246A (en) * 2021-08-24 2021-11-05 湖南大学 Prestressed UHPC shell-concrete inner core combined bent cap structure and construction method thereof
CN114673077A (en) * 2022-03-21 2022-06-28 中铁第四勘察设计院集团有限公司 Ultra-high performance concrete gate-type pier structure and construction method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440634A (en) * 2018-12-11 2019-03-08 上海市城市建设设计研究总院(集团)有限公司 The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off
CN109440634B (en) * 2018-12-11 2024-02-06 上海市城市建设设计研究总院(集团)有限公司 Prefabricated high-strength concrete hollow bent cap structure with removable internal mold
CN109881575A (en) * 2019-04-18 2019-06-14 上海市城市建设设计研究总院(集团)有限公司 Using the prefabricated bent cap in π type cross section and its method for prefabricating of prestressing with bond muscle
CN109881574A (en) * 2019-04-18 2019-06-14 上海市城市建设设计研究总院(集团)有限公司 Using the prefabricated bent cap in π type cross section and its method for prefabricating of external prestressing steels
CN109881575B (en) * 2019-04-18 2024-03-12 上海市城市建设设计研究总院(集团)有限公司 Pi-shaped cross section prefabricated bent cap adopting internal prestressed tendons and prefabricating method thereof
CN109881574B (en) * 2019-04-18 2024-04-09 上海市城市建设设计研究总院(集团)有限公司 Pi-shaped cross section prefabricated bent cap adopting external prestressed tendons and prefabricating method thereof
CN110847044A (en) * 2019-11-15 2020-02-28 中交第二航务工程局有限公司 Semi-prefabricated assembled bent cap construction method
CN110847044B (en) * 2019-11-15 2021-09-14 中交二航局第一工程有限公司 Semi-prefabricated assembled bent cap construction method
CN113605246A (en) * 2021-08-24 2021-11-05 湖南大学 Prestressed UHPC shell-concrete inner core combined bent cap structure and construction method thereof
CN114673077A (en) * 2022-03-21 2022-06-28 中铁第四勘察设计院集团有限公司 Ultra-high performance concrete gate-type pier structure and construction method

Similar Documents

Publication Publication Date Title
CN108797312A (en) A kind of bent cap structure and its construction method
CN214939292U (en) Cover beam disassembly-free template
CN106958259B (en) A kind of concrete towers column foundation and its construction method
CN106150119B (en) It is a kind of to industrialize high ductility space constraint reinforced masonry wall system and its construction method
CN100516404C (en) Reinforcing-bar concrete building roof with tree-dimensional bearing structure
CN109267489B (en) Construction method for cable-stayed bridge cable tower anchoring area
CN216689076U (en) A prefabricated apron that is used for hollow mound top to pour construction
CN207469438U (en) A kind of prefabricated open tubular column
CN208857669U (en) A kind of bent cap structure
CN113026985A (en) Vertical seam dislocation mutual anchor connection structure of prefabricated shear wall edge member department
CN218786946U (en) Steel bar truss is used in production of two skin walls
CN110005221A (en) A kind of fully assembled overall perfusion whitewashing compound house and its method of construction
CN216340451U (en) Thin-bottom prestressed concrete composite beam
CN214833903U (en) Novel prefabricated coincide beam slab system of formwork exempts from
CN220225782U (en) Structure heat preservation integrated double-sided superposed outer wall
CN214220274U (en) Partially prefabricated truss type steel reinforced concrete Z-shaped column
CN214658137U (en) Assembled prestressed concrete superimposed sheet connected node structure
CN215053872U (en) Assembled frame system
CN217150765U (en) Novel heat preservation wall
CN216999269U (en) Semi-fabricated ultra-high performance concrete constraint steel reinforced concrete pier column
CN218668025U (en) Prefabricated coincide wall of underground garage H type
CN214658263U (en) High-strength concrete superposed column with crossed double-spiral hoop steel
CN219808583U (en) Precast prestressed concrete composite beam
CN214246323U (en) High-strength steel concrete cross-shaped column partially prefabricated and assembled
CN211285689U (en) Semi-assembled retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination