CN108764650A - A kind of processing method and processing device for netting the investment of grade highway maintenance - Google Patents

A kind of processing method and processing device for netting the investment of grade highway maintenance Download PDF

Info

Publication number
CN108764650A
CN108764650A CN201810403147.3A CN201810403147A CN108764650A CN 108764650 A CN108764650 A CN 108764650A CN 201810403147 A CN201810403147 A CN 201810403147A CN 108764650 A CN108764650 A CN 108764650A
Authority
CN
China
Prior art keywords
maintenance
traffic
average daily
pqi
bci
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810403147.3A
Other languages
Chinese (zh)
Other versions
CN108764650B (en
Inventor
侯芸
董元帅
张艳红
田春玲
刘峰
戴建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHECSC HIGHWAY MAINTENANCE DETECTION TECHNOLOGY Co Ltd
CHINA HIGHWAY ENGINEERING CONSULTING GROUP Co Ltd
Department Of Transportation Network Monitoring And Emergency Response Center
Original Assignee
CHECSC HIGHWAY MAINTENANCE DETECTION TECHNOLOGY Co Ltd
CHINA HIGHWAY ENGINEERING CONSULTING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHECSC HIGHWAY MAINTENANCE DETECTION TECHNOLOGY Co Ltd, CHINA HIGHWAY ENGINEERING CONSULTING GROUP Co Ltd filed Critical CHECSC HIGHWAY MAINTENANCE DETECTION TECHNOLOGY Co Ltd
Priority to CN201810403147.3A priority Critical patent/CN108764650B/en
Publication of CN108764650A publication Critical patent/CN108764650A/en
Application granted granted Critical
Publication of CN108764650B publication Critical patent/CN108764650B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • G06Q10/06375Prediction of business process outcome or impact based on a proposed change
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Embodiment of the invention discloses that a kind of processing method and processing device for netting the investment of grade highway maintenance, this method is according to maintenance costs over the years, the average daily volume of traffic and road conditions index pre-establish Cost Prediction Model, and correspond to the average daily volume of traffic of target in prediction time by average daily traffic volume forecast over the years, using each road conditions index of setting and maintenance dollar cap value as constraints, it quickly determines to meet road conditions index request and the prime investment scheme with maintenance dollar cap value, solving current traditional curing capitalized method cannot quickly judge to meet certain fund and the road surface under road conditions goal condition, bridge tunel engineering conserves fund input problem.

Description

A kind of processing method and processing device for netting the investment of grade highway maintenance
Technical field
The present embodiments relate to technical field of highway maintenance technology, more particularly, to a kind of for netting the investment of grade highway maintenance Processing method and processing device.
Background technology
Road surface, the main body subdivisional work that bridge tunel engineering is road, the quality of maintenance quality directly affect entire road Service level, the proportion that maintenance costs input accounts for entire maintenance input substantially exceed 80%.Tradition puts into the following annual maintenance Measuring and calculating have the following problems:On the one hand, content and subject is numerous, the period is longer.Conventional method is needed according to each subdivisional work Historical situation and volume of traffic growth pattern etc., utility is estimated, the means such as triggering maintenance of classifying are judged, needs to collect Dynamic segmentation is huge, the subdivisional work that is related to and maintenance content are various, the maintenance plan of part subdivisional work has no in addition Decision process, plan are improved with uncertainty, causes to formulate maintenance plan and the period of investment decision is longer.On the other hand, Multiobjective decision-making process is complicated, accuracy is insufficient.In the Maintenance Decision making analysis of multiple target condition, due to road conditions target and fund The multiple constraint of target, maintenance plan and investment need to be adjusted back and forth, until meeting constraint demand.And Maintenance Decision making result is spent for many years Accuracy dependent on performance model accumulate and decision-making technique, existing decision-making technique tend to realize simple target constraint, to more The decision of goal constraint must carry out complicated mathematics and logical operation, be unsuitable for carrying out rapid curing decision.Therefore, for road network The management unit of grade, what it is due to management is a series of routes, manages foster unit and is more concerned under certain fund condition, future The level that the road conditions of road network can be made to reach or maintain.
During realizing the embodiment of the present invention, inventor has found the existing processing for netting the investment of grade highway maintenance Method has that the period is longer, process is complicated, operational poor, accuracy deficiency.
Invention content
The technical problem to be solved by the present invention is to how solve the existing processing side for netting the investment of grade highway maintenance Method has that the period is longer, process is complicated, operational poor, accuracy deficiency.
For the above technical problem, the embodiment provides a kind of processing sides for netting the investment of grade highway maintenance Method, including:
It determines the road network for being intended to carry out maintenance investment, obtains each road in road network maintenance costs over the years and the road network The average daily volume of traffic and road conditions index over the years;
According to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment maintenance costs with the average daily volume of traffic and road conditions The functional relation of index variation;
Obtain it is preset in prediction year in one's duty maintenance dollar cap value and road conditions index lower limiting value, and according to over the years Average daily traffic volume forecast correspond to it is described prediction the time the average daily volume of traffic of target;
It is the average daily volume of traffic of the target to find the average daily volume of traffic according to the functional relation, and meets the road conditions index The minimum maintenance costs of lower limiting value and the maintenance dollar cap value, supports the road network according to the minimum maintenance costs Shield investment.
Second aspect, the embodiment provides the processing units for netting the investment of grade highway maintenance, including:
First acquisition module obtains road network maintenance costs over the years for the determining road network for being intended to carry out maintenance investment The average daily volume of traffic over the years and road conditions index with each road in the road network;
Module is established, is used for according to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment maintenance costs with day The functional relation of the equal volume of traffic and the variation of road conditions index;
Second acquisition module, it is preset in prediction year in one's duty maintenance dollar cap value and road conditions index for obtaining Lower limiting value, and the average daily volume of traffic of target for predicting the time is corresponded to according to average daily traffic volume forecast over the years;
Prediction module is the average daily volume of traffic of the target for finding the average daily volume of traffic according to the functional relation, and full The minimum maintenance costs of the foot road conditions index lower limiting value and the maintenance dollar cap value, according to the minimum maintenance costs pair The road network carries out maintenance investment.
The third aspect present embodiments provides a kind of electronic equipment, including:
At least one processor, at least one processor and bus;Wherein,
The processor, memory complete mutual communication by the bus;
The memory is stored with the program instruction that can be executed by the processor, and the processor calls described program to refer to Order is able to carry out the process described above.
Fourth aspect, present embodiments provides a kind of computer program product, and the computer program product includes storage Computer program in non-transient computer readable storage medium, the computer program include program instruction, when the journey When sequence instruction is computer-executed, the computer is made to execute the process described above.
The embodiment provides a kind of processing method and processing device for netting the investment of grade highway maintenance, this method roots Cost Prediction Model is pre-established according to maintenance costs over the years, the average daily volume of traffic and road conditions index, and passes through average daily friendship over the years Flux prediction correspond to prediction the time the average daily volume of traffic of target, using each road conditions index of setting and maintenance dollar cap value as Constraints is quickly determined to meet road conditions index request and the prime investment scheme with maintenance dollar cap value, solves mesh Preceding traditional curing capitalized method cannot quickly judge that meet certain fund conserves with the road surface under road conditions goal condition, bridge tunel engineering Fund input problem.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is this hair Some bright embodiments for those of ordinary skill in the art without creative efforts, can be with root Other attached drawings are obtained according to these attached drawings.
Fig. 1 is the flow signal provided by one embodiment of the present invention for netting the processing method of grade highway maintenance investment Figure;
Fig. 2 is the flow signal for the processing method for netting the investment of grade highway maintenance that another embodiment of the present invention provides Figure;
Fig. 3 is that PQI when corresponding to MQI=90,92,95,97 that another embodiment of the present invention provides and BCI relationships are illustrated Figure;
Fig. 4 is another embodiment of the present invention offer corresponding to PQInPQI and BCI relation schematic diagrams when >=93;
Fig. 5 is the maintenance of surface expense model regression curve that another embodiment of the present invention provides;
Fig. 6 is the bridge maintenance cost model regression curve that another embodiment of the present invention provides;
Fig. 7 is the structural representation for the processing unit for netting the investment of grade highway maintenance that another embodiment of the present invention provides Figure;
Fig. 8 is the entity structure schematic diagram for the electronic equipment that another embodiment of the present invention provides.
Specific implementation mode
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art The every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
Fig. 1 is the flow diagram provided in this embodiment for netting the processing method of grade highway maintenance investment, referring to figure 1, this method includes:
101:It determines the road network for being intended to carry out maintenance investment, obtains each in road network maintenance costs over the years and the road network The road average daily volume of traffic over the years and road conditions index;
102:According to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment maintenance costs with the average daily volume of traffic and The functional relation of road conditions index variation;
103:Obtain it is preset in prediction year in one's duty maintenance dollar cap value and road conditions index lower limiting value, and according to Average daily traffic volume forecast over the years corresponds to the average daily volume of traffic of target in the prediction time;
104:It is the average daily volume of traffic of the target to find the average daily volume of traffic according to the functional relation, and meets the road conditions Index lower limiting value and it is described maintenance dollar cap value minimum maintenance costs, according to the minimum maintenance costs to the road network into Row maintenance investment.
It should be noted that method provided in this embodiment is executed by the equipment for being able to carry out the above method, for example, calculating Machine.This method is used to carry out the investment needs of road network construction, determines to meet road conditions index request, spends minimum investor Case.Maintenance costs, the average daily volume of traffic and road conditions index over the years can start the time conserved to the road surface of the road network certainly Statistics, can also count from forward 5 years or 10 years historical datas of current year, the present embodiment does not do this specific limit System.
A kind of processing method for netting the investment of grade highway maintenance is present embodiments provided, this method is according to maintenance over the years Expense, the average daily volume of traffic and road conditions index pre-establish Cost Prediction Model, and are corresponded to by average daily traffic volume forecast over the years In the average daily volume of traffic of target in prediction time, using each road conditions index of setting and maintenance dollar cap value as constraints, soon Speed is determined to meet road conditions index request and the prime investment scheme with maintenance dollar cap value, solves current traditional curing and throw Capital's method cannot quickly judge that meet certain fund asks with the road surface under road conditions goal condition, bridge tunel engineering maintenance fund input Topic.
Further, on the basis of the above embodiments, the determination is intended to carry out the road network of maintenance investment, described in acquisition Each road average daily volume of traffic over the years and road conditions index in road network maintenance costs over the years and the road network, including:
It determines the road network for being intended to carry out maintenance investment, q route is shared in the road network, the length of kth route is lk(k =1,2 ..., q);
The average daily friendship of road network maintenance of surface expense over the years and maintenance of bridge and tunnel expense, the road network over the years is counted respectively Correspond to road surface the first index PQI over the years, the second index BCI corresponding to bridge tunnel over the years in flux, the road network,;
Simplify the MQI of the road conditions index for characterizing the road network according to the first index PQI and the second index BCI;
Wherein, MQI=w1PQI+w2BCI, w1The weight for being PQI in MQI, w2The weight for being BCI in MQI, w1+w2= 1, and w is determined according to the ratio x of maintenance of surface expense over the years and maintenance of bridge and tunnel expense1=-0.0007x2+0.03x+0.5167。
Wherein, w1Functional relation with x is according to the ratio of maintenance of surface expense over the years and maintenance of bridge and tunnel expense, over the years Weights of the PQI in MQI carries out what fitting of a polynomial obtained.
It should be noted that MQI is highway technology status score, in general, MQI=wPQIPQI+wBCIBCI+wSCISCI+ wTCITCI, wherein SCI be with the relevant index of roadbed, TCI be with the relevant index of equipment along road, the present embodiment in order to It quickly determines prime investment scheme, ignores the subgrade engineering that accounting is less in road maintenance funds, equipment along road engineering, it is right The calculating of this road conditions index of MQI is simplified.Road conditions index includes corresponding to the first index PQI on road surface and corresponding to bridge Second index BCI of tunnel.Highway index is to obtain characterization highway bulking property by what the first index PQI and the second index BCI were calculated The index of energy.
A kind of processing method for netting the investment of grade highway maintenance is present embodiments provided, this method is to control railway network planning Phase annual maintenance expense and for the purpose of meeting road conditions target call, to dominate the road surface of maintenance costs, two large-engineering of bridge tunnel be to cut Access point simplifies MQI, enabling the method provided through this embodiment quickly determines highway investment scheme.
Further, on the basis of the various embodiments described above, basis maintenance costs over the years, the average daily volume of traffic and The functional relation that road conditions Index Establishment maintenance costs changes with the average daily volume of traffic and road conditions index, including:
Determine PQI and the average daily volume of traffic, maintenance of surface expense first function relationship fPQI(i)=f (PQIi,Ai);
Determine the second function relationship f that BCI takes with the average daily volume of traffic, maintenance of bridge and tunnelBCI(i)=f (BCIi,Ai);
Wherein, fPQI(i)For 1 year maintenance of surface expense, PQIiFor 1 year PQI mean value of all routes in road network, Ai For 1 year average daily volume of traffic of all routes in road network, fBCI(i)For 1 year maintenance of bridge and tunnel expense, BCIiTo own in road network 1 year BCI of route.
In general, obtaining first function and second function using linear fitting by historical data.In the present embodiment, road surface Upkeep charges refer to and implement pavement engineering routine maintenance, preventive maintenance, repair the expense needed for maintenance, specialty work.Maintenance of bridge and tunnel Expense refers to and implements bridge tunel engineering routine maintenance, preventive maintenance, repairs the expense needed for maintenance, specialty work.
Present embodiments provide it is a kind of for net grade highway maintenance investment processing method, this method according to historical data into Row linear fitting, is directed to road surface respectively and bridge establishes the functional relation of maintenance costs and the average daily volume of traffic, so as to according to function Relationship accurately calculates maintenance costs.
Further, on the basis of the various embodiments described above, the acquisition is preset in one's duty foster in prediction year Dollar cap value and road conditions index lower limiting value are protected, and corresponds to the mesh in the prediction time according to average daily traffic volume forecast over the years The average daily volume of traffic is marked, including:
Obtain it is preset prediction year in one's duty maintenance dollar cap value, the first index PQI, the second index BCI and The lower limiting value of the MQI of highway index, obtaining constraints is:
PQIn>=a or BCIn≥b、MQIn>=c and Fn≤d;Wherein, PQInFor the PQI, a PQI that the prediction time is 1 year Target lower limiting value, BCInIt is the target lower limiting value of BCI, MQI for the BCI that the prediction time is 1 year, bnIt is n-th for the prediction time The MQI in year, c are the target lower limiting value of MQI, FnFor the maintenance fund that the prediction time is 1 year, c is maintenance dollar cap value;
Determine that average annual traffic volume growth rate γ is according to the average daily volume of traffic of nearly j
According to average annual traffic volume growth rate γ, pass through formula An=At×(1+γ)n-tIt is 1 year to calculate the prediction time The average daily volume of traffic of target;Wherein, AnFor the average daily volume of traffic of 1 year target, AtFor the equal volume of traffic of current t.
In general, when calculating average annual traffic volume growth rate γ, nearly 3 years data are selected to be calculated, the present embodiment is to this It is not particularly limited.Constraints is:PQIn>=a or BCIn≥b、MQIn>=c and Fn≤ d, i.e. constraints are PQIn≥a、 MQIn>=c and Fn≤ d, alternatively, BCIn≥b、MQIn>=c and Fn≤d.During subsequent prediction, in other constraintss On the basis of, only it need to choose PQIn>=a or BCInOne in >=b is used as constraint.Predict that the time is when the year before last second year is not to Carry out certain year, the present embodiment is not particularly limited this.
A kind of processing method for netting the investment of grade highway maintenance is present embodiments provided, how this method is to determine constraint Condition and the calculating for how carrying out the average daily volume of traffic are defined, with by the average daily volume of traffic of constraints and prediction quickly into The determination of the follow-up prime investment scheme of row.
Further, described that the average daily volume of traffic is found according to the functional relation on the basis of the various embodiments described above For the average daily volume of traffic of the target, and meet the minimum upkeep charges of the road conditions index lower limiting value and the maintenance dollar cap value With, maintenance investment is carried out to the road network according to the minimum maintenance costs, including:
Enable w1PQI+w2BCI=e, when meeting e >=c, the collection of e values is combined into A={ c, c+1 ..., 100 }, and e is integer, The variation relation figure of corresponding PQI and BCI when e is each numerical value in set A is drawn respectively;
In the variation relation figure, using PQI=a or BCI=b as target control line, determine to meet PQI >=a and The collection of MQI >=c or BCI >=b and the target areas MQI >=c, (PQI, BCI) in the target area is combined into B= {(PQIm, BCIm), m is the serial number of (PQI, BCI) in the target area };
For each (PQI, the BCI) and the average daily volume of traffic A of the target in set Bn, according to the first function relationship It calculates 1 year maintenance of surface to take, and is taken according to the maintenance of bridge and tunnel of second function relationship calculating 1 year;
The maintenance of surface calculated corresponding to each group (PQI, BCI) takes the total cost taken with maintenance of bridge and tunnel, obtains by total expense With the set C of composition, total cost Q is found out from set Cm≤ d and the corresponding (PQI of minimum maintenance costs when total cost minimumm, BCIm), maintenance investment is carried out to the road network according to the corresponding maintenance of surface expense of the minimum maintenance costs and maintenance of bridge and tunnel expense.
A kind of processing method for netting the investment of grade highway maintenance is present embodiments provided, this method is defined according to constraint Condition and the average daily volume of traffic carry out the process of minimum maintenance costs, are capable of determining that by linear programming and meet institute's Prescribed Properties Minimum capital project.
Further, on the basis of the various embodiments described above, the PQIi、BCIiAnd AiIt is calculated by the following formula:
Wherein, lkFor the length of kth circuit in the road network,It is 1 year, the PQI of kth circuit,It is 1 year, the BCI of kth circuit,It is 1 year, the average daily volume of traffic of kth circuit.In the present embodiment PQI, BCI, MQI are characteristic.
Present embodiments provide a kind of processing method for netting the investment of grade highway maintenance, the first of this method pair 1 year Index and the second index and the computational methods of 1 year average daily volume of traffic are defined, through this embodiment in working hour energy It is enough quickly to determine each parameter, to facilitate subsequent prediction to calculate.
Specifically, Fig. 2 shows the flows provided in this embodiment for netting the processing method of grade highway maintenance investment Schematic diagram, referring to Fig. 2, this method includes:
1, decision road network object is determined
It determines the quasi- road network for carrying out decision, shares q route in road network, the length of each route is respectively lk(k=1, 2,…,q)
2, the history maintenance data (including static data and dynamic data) of road network are collected, and according to road surface over the years, bridge tunnel Input ratio is established and simplifies MQI calculation formula
Road network road surface over the years, bridge tunel engineering maintenance input are counted, according to the input ratio on road surface and bridge tunel engineering, is ignored The less subgrade engineering of accounting, equipment along road engineering in road maintenance funds simplify MQI and calculate.
MQI=w1PQI+w2BCI formulas 1
In formula:w1:Weights of the PQI in MQI;According to road surface over the years/bridge tunnel expense than determining, w1=-0.0007x2+ 0.03x+0.5167, x are road surface/bridge tunnel expense ratio;w2:Weights of the BCI in MQI, w1+w2=1.
3, cost model is established based on historical data
Based on maintenance input over the years, road conditions, the volume of traffic and maintenance costs relationship are established.
1) PQI and the average daily volume of traffic, maintenance of surface expense relationship
fPQI(i)=f (PQIi,Ai) formula 2
In formula:fPQI(i)1 year maintenance of surface expense (ten thousand yuan);PQIi1 year PQI mean value of all routes in road network, The PQI weighted averages for taking each route are calculated by formula 3;Ai--- 1 year average daily volume of traffic () of all routes in road network, The average daily volume of traffic weighted average for taking each route is calculated by formula 4.
2) relationship of BCI and the average daily volume of traffic, maintenance of bridge and tunnel funds
fBCI(i)=f (BCIi,Ai) formula 5
In formula:fBCI(i)1 year bridge maintenance expense (ten thousand yuan);BCIi1 year BCI of all routes in road network takes each The PQI weighted averages of route are calculated by formula 6.
4, good logical average growth rate per annum is predicted
Based on traffic data over the years, the average growth rate per annum of the nearly 3 years average daily volume of traffic of road network is calculated, it is assumed that currently year is t。
In formula:Nearly 3 years average annual traffic volume growth rates (%) of γ;At--- the average daily volume of traffic () of t.
5, the target component critical value and limited fund condition in future plan year are set:
PQIn>=a or BCIn>=b formulas 8
MQIn>=c formulas 9
Fn≤ d formulas 10
In formula:PQInFor 1 year PQI (dimensionless);A is PQI targets lower limiting value (dimensionless);BCInIt is 1 year BCI (dimensionless);B is BCI targets lower limiting value (dimensionless);MQInFor 1 year MQI (dimensionless);C is MQI target lower limits It is worth (dimensionless);FnFor 1 year road surface, maintenance of bridge and tunnel fund (ten thousand yuan);D is maintenance fund (the sum of road surface, bridge tunnel fund) Upper limit value (ten thousand yuan).
6, according to MQI desired values project period of setting
Enable w1PQI+w2BCI=e, the collection for meeting e >=c are combined into A={ c, c+1 ..., 100 }.Draw MQInUnder the conditions of=A, The variation relation figure of PQI and BCI.MQI is drawn respectivelynEqual in set when each numerical value PQI and BCI variation relation figure, As shown in Figure 3.
7, PQI the or BCI target lower limiting values determined according to the 5th step are looked for using PQI=a or BCI=b as target control line The road condition area for going out while meeting 2 road conditions targets (MQI, PQI or MQI, BCI) forms the road conditions set B=met the requirements {(PQIm, BCIm) | m is the sequence met the requirements }.As shown in Figure 4.
8, in set B, to each (PQIm, BCIm) by year n corresponding average daily traffic where the following Expression 11 prediction planning Amount, PQI is calculated by formula 2mCorresponding maintenance of surface expense fPQI(m), BCI is calculated by formula 5nCorresponding maintenance of bridge and tunnel expense fBCI(n)
An=At×(1+γ)n-tFormula 11
In formula:AnFor the average daily volume of traffic () in year n where planning.
9, each (PQI in set of computations Bm, BCIm) the sum of maintenance costs under combination:
Qm=fPQI(m)+fBCI(m)Formula 12
In formula:QmFor correspondence (PQIm, BCIm) maintenance costs (ten thousand yuan) under combination condition;fPQI(m)For corresponding PQImCondition The maintenance of surface expense (ten thousand yuan) of lower prediction;fBCI(m)For corresponding BCImUnder the conditions of the maintenance of bridge and tunnel expense (ten thousand yuan) predicted.
10, it enables the collection being made of the maintenance costs after set B measuring and calculating be combined into C, Q is found out in Cm≤ d and numerical value minimum is right (the PQI answeredm, BCIm), as meet the road conditions combination under the conditions of road network road conditions target, fund limited target.
Wherein, road conditions index includes MQI, PQI, BCI, and numerical intervals are 0~100.Refer to project period and works as the year before last second year extremely The time limit in certain following year.Road conditions target refers to the road conditions index that project period is certain end of year and it is expected the level reached.
Processing method provided in this embodiment for netting the investment of grade highway maintenance, to control railway network planning phase annual maintenance Expense and for the purpose of meeting road conditions target call, to dominate the road surface of maintenance costs, two large-engineering of bridge tunnel as point of penetration, according to two The data such as the maintenance input over the years of large-engineering, the volume of traffic, road conditions index (PQI, BCI), establish MQI simplified mathematical models, expense Prediction model and volume of traffic model of growth, and carry out three ladders of " MQI target controls, the intervention of subitem target, fund object filtering " Degree target is preferred, and the final road conditions horizontal combination obtained while meeting road conditions and fund target, the guiding plan phase conserves fund Orderly input, solving current traditional curing capitalized method cannot quickly judge to meet certain fund and the road under road conditions goal condition Face, bridge tunel engineering conserve fund input problem.
The present embodiment further illustrates the above method by taking 5 highways that certain Speedway Control Broad is administered as an example Carry out the processing procedure and handling result of maintenance investment.The highway route coding be respectively designated as G1, G2, G3, G4 and G5, definition are road network A by the road network that 5 highways form.5 path lengths that road network A includes be respectively 20.5km, 25.3km, 28.7km, 26.4km and 32.1km.Method includes:
(1) it determines road network object, collects historical information
The maintenance of surface expense and maintenance of bridge and tunnel expense of road network A are collected respectively, as shown in table 1.The each of road network A is collected respectively The route volume of traffic over the years and road condition data (the first index and the second index), as shown in table 2
1 road network A of table maintenance costs data over the years
Year Maintenance of surface expense (ten thousand yuan) Maintenance of bridge and tunnel expense (ten thousand yuan)
2013 6843 871
2014 7689 954
2015 8352 1125
2016 10230 1245
2017 11874 1359
2 each routes of table volume of traffic over the years and road condition data
(2) simplify MQI models
Known by conserving input over the years, the ratio between the road surfaces road network A/maintenance of bridge and tunnel expense is 8.05, substitutes into formula and calculates, w1= 0.0007 × 8.05+0.03 × 8.05+0.5167=0.8, being simplified MQI calculation formula is:
MQI=0.8PQI+0.2BCI formulas 13
(3) road conditions and maintenance costs relationship are established
Using SPSS statistical softwares, daily traffic volume A is established in recurrencei、PQIiWith maintenance of surface expense yp(i)Relationship, see formula 14, it is as shown in Figure 5 that the model of maintenance of surface expense returns to curve;Daily traffic volume A is established in recurrencei、BCIiWith bridge maintenance expense yb(i)Relationship, see formula 15, it is as shown in Figure 6 that the model of bridge maintenance expense returns to curve.
yp(i)=0.575Ai+88.906PQIi- 11243.936 formulas 14
yb(i)=0.036Ai-59.761BCIi+ 5988.996 formulas 15
In formula:yp(i)For 1 year maintenance of surface expense (ten thousand yuan);yb(i)For 1 year bridge maintenance expense (ten thousand yuan).
(4) average growth rate per annum is calculated
It is as shown in table 3 to count to obtain nearly 3 years volume of traffic growth patterns by traffic data over the years.It is calculated nearly 3 years Volume of traffic average growth rate per annum be 11.90%.
3 volume of traffic growth pattern of table
Year The average daily volume of traffic () Average growth rate per annum (%)
2015 20099 6.63
2016 22387 11.38
2017 26349 17.70
(5) road conditions target and limited fund target are set
Using the year two thousand twenty as object of planning year, the setting object of planning is as follows:PQI2020>=93, MQI2020>=90, F2020≤ 200000000 yuan.
(6) structure meets MQI2020Point in >=90 set A, set A is as shown in Figure 3
C=90 is known by road conditions target, enables the integer in MQI=90~100, calculates w1=0.8, w2When=0.2 (PQI, BCI it) combines, establishes set A.Table 4 shows full MQI2020>=90 (PQI, BCI) combination.
Table 4 meets MQI2020>=90 (PQI, BCI) combination
(7) structure meets PQI2020≥93、MQI2020Point such as Fig. 4 cathetus PQI=93 in >=90 set B, set B Shown in the point on the right.
C=90, a=93 are known by road conditions target, on the basis of set A, further screening meets PQI2020≥93、 MQI2020>=90 (PQI, BCI) combination, establishes set B={ (PQIm, BCIm) | m is the sequence met the requirements }.
(8) daily traffic volume under prediction sets B each (PQI, BCI) combination, maintenance of surface expense, maintenance of bridge and tunnel expense
First, the average daily volume of traffic of the year two thousand twenty is predicted
A2020=26349 × (1+11.9%)2020-2017=36919 formulas 16
Secondly, maintenance costs is predicted
The average daily volume of traffic after calculating is substituted into formula 14, formula 15, the maintenance in prediction sets B under each (PQI, BCI) combination Expense.
With MQI=90~100 and APQI in table 42020For (PQI, BCI) combination under the conditions of >=93, road is calculated separately Face maintenance costs, maintenance of bridge and tunnel expense such as table 5.
The lower maintenance costs prediction of 5 set B of table each (PQI, BCI) combination
(9) maintenance costs and composition set C in set of computations B under each (PQI, BCI) combination, obtains as shown in table 6 As a result.
The lower maintenance costs of 6 set B of table each (PQI, BCI) combination calculates
(10) (PQI, the BCI) combination for meeting fund target is found out in set C
It is filtered out under set C by table 6, the minimum maintenance costs of the year two thousand twenty is 19714.25 ten thousand yuan, meets fund target “F2020≤ 20,000 ten thousand yuan " requirement.
To sum up, meeting PQI2020>=93, MQI2020>=90, F2020When≤20,000 ten thousand yuan of multiple target condition, prediction (PQI, the BCI) of the year two thousand twenty is combined as (93,98).
Fig. 7 shows a kind of structure for netting the processing unit of grade highway maintenance investment that the embodiment of the present invention provides Block diagram, referring to Fig. 7, the processing unit provided in this embodiment for netting the investment of grade highway maintenance, including the first acquisition module 701, module 702, the second acquisition module 703 and prediction module 704 are established, wherein
First acquisition module 701 obtains road network upkeep charges over the years for the determining road network for being intended to carry out maintenance investment With the average daily volume of traffic and road conditions index over the years with each road in the road network;
Establish module 702, for according to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment maintenance costs with The functional relation of the average daily volume of traffic and the variation of road conditions index;
Second acquisition module 703, it is preset in prediction year in one's duty maintenance dollar cap value and road conditions for obtaining Index lower limiting value, and the average daily volume of traffic of target for predicting the time is corresponded to according to average daily traffic volume forecast over the years;
Prediction module 704 is the average daily volume of traffic of the target for finding the average daily volume of traffic according to the functional relation, and The minimum maintenance costs for meeting the road conditions index lower limiting value and the maintenance dollar cap value, according to the minimum maintenance costs Maintenance investment is carried out to the road network.
What the processing unit provided in this embodiment for netting the investment of grade highway maintenance was provided suitable for above-described embodiment Processing method for netting the investment of grade highway maintenance, details are not described herein.
A kind of processing unit for netting the investment of grade highway maintenance is present embodiments provided, the device is according to maintenance over the years Expense, the average daily volume of traffic and road conditions index pre-establish Cost Prediction Model, and are corresponded to by average daily traffic volume forecast over the years In the average daily volume of traffic of target in prediction time, using each road conditions index of setting and maintenance dollar cap value as constraints, soon Speed is determined to meet road conditions index request and the prime investment scheme with maintenance dollar cap value, solves current traditional curing and throw Capital's method cannot quickly judge that meet certain fund asks with the road surface under road conditions goal condition, bridge tunel engineering maintenance fund input Topic.
Fig. 8 is the entity structure schematic diagram for showing electronic equipment provided in this embodiment.
With reference to Fig. 8, the electronic equipment includes:Processor (processor) 801, memory (memory) 802 and bus 803;
Wherein,
The processor 801, memory 802 complete mutual communication by the bus 803;
The processor 801 is used to call the program instruction in the memory 802, to execute above-mentioned each method embodiment The method provided, such as including:It determines the road network for being intended to carry out maintenance investment, obtains road network maintenance costs over the years and institute State the average daily volume of traffic and road conditions index that each road is over the years in road network;According to maintenance costs over the years, the average daily volume of traffic and road conditions The functional relation that Index Establishment maintenance costs changes with the average daily volume of traffic and road conditions index;It obtains preset in the prediction time Interior maintenance dollar cap value and road conditions index lower limiting value, and the prediction year is corresponded to according to average daily traffic volume forecast over the years The average daily volume of traffic of target of part;It is the average daily volume of traffic of the target to find the average daily volume of traffic according to the functional relation, and is met The minimum maintenance costs of the road conditions index lower limiting value and the maintenance dollar cap value, according to the minimum maintenance costs to institute It states road network and carries out maintenance investment.
The present embodiment provides a kind of non-transient computer readable storage medium, the non-transient computer readable storage medium Computer instruction is stored, the computer instruction makes the computer execute the method that above-mentioned each method embodiment is provided, example Such as include:It determines the road network for being intended to carry out maintenance investment, obtains each road in road network maintenance costs over the years and the road network The average daily volume of traffic and road conditions index over the years;According to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment upkeep charges With the functional relation with the average daily volume of traffic and the variation of road conditions index;It obtains preset on predicting year in one's duty maintenance fund Limit value and road conditions index lower limiting value, and the target in the prediction time is corresponded to according to average daily traffic volume forecast over the years and is daily handed over Flux;It is the average daily volume of traffic of the target to find the average daily volume of traffic according to the functional relation, and is met under the road conditions index The minimum maintenance costs of limit value and the maintenance dollar cap value, conserves the road network according to the minimum maintenance costs Investment.
The present embodiment discloses a kind of computer program product, and the computer program product includes being stored in non-transient calculating Computer program on machine readable storage medium storing program for executing, the computer program include program instruction, when described program instruction is calculated When machine executes, computer is able to carry out the method that above-mentioned each method embodiment is provided, it may for example comprise:Determination is intended to be conserved The road network of investment obtains each road is over the years in road network maintenance costs over the years and the road network the average daily volume of traffic and road conditions Index;Referred to the average daily volume of traffic and road conditions according to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment maintenance costs Mark the functional relation of variation;Obtain it is preset in prediction year in one's duty maintenance dollar cap value and road conditions index lower limiting value, And correspond to the average daily volume of traffic of target in the prediction time according to average daily traffic volume forecast over the years;According to the functional relation It is the average daily volume of traffic of the target to find the average daily volume of traffic, and meets the road conditions index lower limiting value and the maintenance fund upper limit The minimum maintenance costs of value, maintenance investment is carried out according to the minimum maintenance costs to the road network.
One of ordinary skill in the art will appreciate that:Realize that all or part of step of above method embodiment can pass through The relevant hardware of program instruction is completed, and program above-mentioned can be stored in a computer read/write memory medium, the program When being executed, step including the steps of the foregoing method embodiments is executed;And storage medium above-mentioned includes:ROM, RAM, magnetic disc or light The various media that can store program code such as disk.
The embodiments such as the entity structure of terminal or base station described above are only schematical, wherein the conduct The unit that separating component illustrates may or may not be physically separated, the component shown as unit can be or Person may not be physical unit, you can be located at a place, or may be distributed over multiple network units.It can root According to actual need that some or all of module therein is selected to achieve the purpose of the solution of this embodiment.Ordinary skill Personnel are not in the case where paying performing creative labour, you can to understand and implement.
Through the above description of the embodiments, those skilled in the art can be understood that each embodiment can It is realized by the mode of software plus required general hardware platform, naturally it is also possible to pass through hardware.Based on this understanding, on Stating technical solution, substantially the part that contributes to existing technology can be expressed in the form of software products in other words, should Computer software product can store in a computer-readable storage medium, such as ROM/RAM, magnetic disc, CD, including several fingers It enables and using so that a computer equipment (can be personal computer, server or the network equipment etc.) executes each implementation Method described in certain parts of example or embodiment.
Finally it should be noted that:The above various embodiments is only to illustrate the technical solution of the embodiment of the present invention rather than right It is limited;Although the embodiment of the present invention is described in detail with reference to foregoing embodiments, the ordinary skill of this field Personnel should understand that:It still can be with technical scheme described in the above embodiments is modified, or to which part Or all technical features carries out equivalent replacement;And these modifications or replacements, it does not separate the essence of the corresponding technical solution The range of various embodiments of the present invention technical solution.

Claims (9)

1. a kind of processing method for netting the investment of grade highway maintenance, which is characterized in that including:
It determines the road network for being intended to carry out maintenance investment, it is over the years to obtain each road in road network maintenance costs over the years and the road network The average daily volume of traffic and road conditions index;
According to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment maintenance costs with the average daily volume of traffic and road conditions index The functional relation of variation;
Obtain it is preset in prediction year in one's duty maintenance dollar cap value and road conditions index lower limiting value, and according to day over the years Equal traffic volume forecast corresponds to the average daily volume of traffic of target in the prediction time;
It is the average daily volume of traffic of the target to find the average daily volume of traffic according to the functional relation, and meets the road conditions index lower limit The minimum maintenance costs of value and the maintenance dollar cap value, maintenance throwing is carried out according to the minimum maintenance costs to the road network Money.
2. according to the method described in claim 1, it is characterized in that, the determination is intended to carry out the road network of maintenance investment, acquisition institute The average daily volume of traffic and road conditions index that each road is over the years in road network maintenance costs over the years and the road network are stated, including:
It determines the road network for being intended to carry out maintenance investment, q route is shared in the road network, the length of kth route is lk(k=1, 2,…,q);
The average daily traffic of road network maintenance of surface expense over the years and maintenance of bridge and tunnel expense, the road network over the years is counted respectively Correspond to road surface the first index PQI over the years, the second index BCI corresponding to bridge tunnel over the years in amount, the road network,;
Simplify the highway index MQI of the highway function for characterizing the road network according to the first index PQI and the second index BCI;
Wherein, MQI=w1PQI+w2BCI, w1The weight for being PQI in MQI, w2The weight for being BCI in MQI, w1+w2=1, and W is determined according to the ratio between maintenance of surface expense over the years and maintenance of bridge and tunnel expense x1=-0.0007x2+0.03x+0.5167。
3. according to the method described in claim 2, it is characterized in that, basis maintenance costs over the years, the average daily volume of traffic and The functional relation that road conditions Index Establishment maintenance costs changes with the average daily volume of traffic and road conditions index, including:
Determine PQI and the average daily volume of traffic, maintenance of surface expense first function relationship fPQI(i)=f (PQIi,Ai);
Determine the second function relationship f that BCI takes with the average daily volume of traffic, maintenance of bridge and tunnelBCI(i)=f (BCIi,Ai);
Wherein, fPQI(i) maintenance of surface expense for being 1 year, PQIiFor 1 year PQI mean value of all routes in road network, AiFor road 1 year average daily volume of traffic of all routes, f in netBCI(i) the maintenance of bridge and tunnel expense for being 1 year, BCIiFor all roads in road network 1 year BCI of line.
4. according to the method described in claim 3, it is characterized in that, the acquisition is preset in prediction year in one's duty maintenance Dollar cap value and road conditions index lower limiting value, and the target for predicting the time is corresponded to according to average daily traffic volume forecast over the years The average daily volume of traffic, including:
Obtain it is preset prediction year in one's duty maintenance dollar cap value, the first index PQI, the second index BCI and highway The lower limiting value of the MQI of index, obtaining constraints is:
PQIn>=a or BCIn≥b、MQIn>=c and Fn≤d;Wherein, PQInIt is the mesh of PQI for the PQI that the prediction time is 1 year, a Mark lower limiting value, BCInIt is the target lower limiting value of BCI, MQI for the BCI that the prediction time is 1 year, bnIt it is 1 year for the prediction time MQI, c are the target lower limiting value of MQI, FnFor the maintenance fund that the prediction time is 1 year, c is maintenance dollar cap value;
Determine that average annual traffic volume growth rate γ is according to the average daily volume of traffic of nearly j
According to average annual traffic volume growth rate γ, pass through formula An=At×(1+γ)n-tCalculate the target that the prediction time is 1 year The average daily volume of traffic;Wherein, AnFor the average daily volume of traffic of 1 year target, AtFor the average daily volume of traffic of current t.
5. according to the method described in claim 4, it is characterized in that, described find the average daily volume of traffic according to the functional relation and be The average daily volume of traffic of target, and meet the minimum upkeep charges of the road conditions index lower limiting value and the maintenance dollar cap value With, maintenance investment is carried out to the road network according to the minimum maintenance costs, including:
Enable w1PQI+w2BCI=e, when meeting e >=c, the collection of e values is combined into A={ c, c+1 ..., 100 }, and e is integer, is painted respectively The variation relation figure of e processed corresponding PQI and BCI when being each numerical value in set A;
In the variation relation figure, using PQI=a or BCI=b as target control line, determine to meet PQI >=a and MQI >= The collection of c or BCI >=b and the target areas MQI >=c, (PQI, BCI) in the target area is combined into B={ (PQIm, BCIm), m is the serial number of (PQI, BCI) in the target area };
For each (PQI, the BCI) and the average daily volume of traffic A of the target in set Bn, calculated according to the first function relationship 1 year maintenance of surface takes, and is taken according to the maintenance of bridge and tunnel of second function relationship calculating 1 year;
The maintenance of surface calculated corresponding to each group (PQI, BCI) takes the total cost taken with maintenance of bridge and tunnel, obtains by total cost group At set C, total cost Q is found out from set Cm≤ d and the corresponding (PQI of minimum maintenance costs when total cost minimumm, BCIm), maintenance investment is carried out to the road network according to the corresponding maintenance of surface expense of the minimum maintenance costs and maintenance of bridge and tunnel expense.
6. according to the method described in claim 3, it is characterized in that, the PQIi、BCIiAnd AiIt is calculated by the following formula:
Wherein, lkFor the length of kth circuit in the road network,It is 1 year, the PQI of kth circuit,For 1 year, the BCI of kth circuit,It is 1 year, the average daily volume of traffic of kth circuit.
7. a kind of processing unit for netting the investment of grade highway maintenance, which is characterized in that including:
First acquisition module obtains road network maintenance costs over the years and institute for the determining road network for being intended to carry out maintenance investment State the average daily volume of traffic and road conditions index that each road is over the years in road network;
Module is established, for being handed over average daily according to maintenance costs over the years, the average daily volume of traffic and road conditions Index Establishment maintenance costs The functional relation of flux and the variation of road conditions index;
Second acquisition module, it is preset in prediction year in one's duty maintenance dollar cap value and road conditions index lower limit for obtaining Value, and the average daily volume of traffic of target for predicting the time is corresponded to according to average daily traffic volume forecast over the years;
Prediction module is the average daily volume of traffic of the target for finding the average daily volume of traffic according to the functional relation, and meets institute The minimum maintenance costs for stating road conditions index lower limiting value and the maintenance dollar cap value, according to the minimum maintenance costs to described Road network carries out maintenance investment.
8. a kind of electronic equipment, which is characterized in that including:
At least one processor, at least one processor and bus;Wherein,
The processor, memory complete mutual communication by the bus;
The memory is stored with the program instruction that can be executed by the processor, and the processor calls described program to instruct energy It is enough to execute such as method according to any one of claims 1 to 6.
9. a kind of computer program product, which is characterized in that the computer program product includes being stored in non-transient computer Computer program on readable storage medium storing program for executing, the computer program include program instruction, when described program is instructed by computer When execution, the computer is made to execute the method as described in claim 1 to 6 is any.
CN201810403147.3A 2018-04-28 2018-04-28 Method and device for processing network-level highway maintenance investment Active CN108764650B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810403147.3A CN108764650B (en) 2018-04-28 2018-04-28 Method and device for processing network-level highway maintenance investment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810403147.3A CN108764650B (en) 2018-04-28 2018-04-28 Method and device for processing network-level highway maintenance investment

Publications (2)

Publication Number Publication Date
CN108764650A true CN108764650A (en) 2018-11-06
CN108764650B CN108764650B (en) 2021-01-15

Family

ID=64008757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810403147.3A Active CN108764650B (en) 2018-04-28 2018-04-28 Method and device for processing network-level highway maintenance investment

Country Status (1)

Country Link
CN (1) CN108764650B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110826779A (en) * 2019-10-24 2020-02-21 交通运输部路网监测与应急处置中心 Road network level bridge tunnel maintenance method, device and storage medium
CN112613681A (en) * 2020-12-29 2021-04-06 上海同陆云交通科技有限公司 Road network low-energy-consumption full-life-cycle maintenance scheme optimization method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104573870A (en) * 2015-01-19 2015-04-29 华南理工大学 Expressway operating cost forecasting method
JP6194282B2 (en) * 2014-06-06 2017-09-06 日本電信電話株式会社 Information processing apparatus, information processing method, and program
CN107153928A (en) * 2017-06-28 2017-09-12 江苏智通交通科技有限公司 Visual highway maintenance decision system
KR20170112107A (en) * 2016-03-30 2017-10-12 백근원 Pedestrian auto detection system of crosswalk and method thereof
CN107563669A (en) * 2017-09-24 2018-01-09 武汉武大卓越科技有限责任公司 A kind of highway maintenance method of decision analysis based on learning model
CN107798177A (en) * 2017-10-13 2018-03-13 东南大学 The optimal maintenance timing in road surface based on Pavement performance model before and after maintenance determines method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6194282B2 (en) * 2014-06-06 2017-09-06 日本電信電話株式会社 Information processing apparatus, information processing method, and program
CN104573870A (en) * 2015-01-19 2015-04-29 华南理工大学 Expressway operating cost forecasting method
KR20170112107A (en) * 2016-03-30 2017-10-12 백근원 Pedestrian auto detection system of crosswalk and method thereof
CN107153928A (en) * 2017-06-28 2017-09-12 江苏智通交通科技有限公司 Visual highway maintenance decision system
CN107563669A (en) * 2017-09-24 2018-01-09 武汉武大卓越科技有限责任公司 A kind of highway maintenance method of decision analysis based on learning model
CN107798177A (en) * 2017-10-13 2018-03-13 东南大学 The optimal maintenance timing in road surface based on Pavement performance model before and after maintenance determines method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
姜晴: "高速公路养护序列规划研究", 《中国博士学位论文全文数据库》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110826779A (en) * 2019-10-24 2020-02-21 交通运输部路网监测与应急处置中心 Road network level bridge tunnel maintenance method, device and storage medium
CN112613681A (en) * 2020-12-29 2021-04-06 上海同陆云交通科技有限公司 Road network low-energy-consumption full-life-cycle maintenance scheme optimization method
CN112613681B (en) * 2020-12-29 2022-03-08 上海同陆云交通科技有限公司 Road network low-energy-consumption full-life-cycle maintenance scheme optimization method

Also Published As

Publication number Publication date
CN108764650B (en) 2021-01-15

Similar Documents

Publication Publication Date Title
CN105389987B (en) A kind of road traffic condition Forecasting Methodology and device
CN103699775B (en) Urban road traffic guidance strategy automatic generation method and system
CN108596396A (en) One kind is based on the modified pavement performance prediction of maintenance history and maintenance process and device
CN109686091B (en) Traffic flow filling algorithm based on multi-source data fusion
CN111652520B (en) Pavement maintenance intelligent decision system and method based on big data
CN105205341B (en) A kind of power matching network transformation demand model construction method based on client's demand
CN108764650A (en) A kind of processing method and processing device for netting the investment of grade highway maintenance
CN107633674A (en) A kind of emphasis commerial vehicle exception tracing point elimination method and system
CN109147329A (en) Regional traffic operating status index based on the traffic capacity calculates and method for visualizing
CN112697197A (en) GIS (geographic information System) and BIM (building information modeling) fusion technology based porous flood gate visual management system and method
CN113516258A (en) Intelligent decision analysis system for highway maintenance
CN108388957A (en) A kind of middle and small river Flood Forecasting Method and its forecast system based on multiple features fusion technology
CN107134136A (en) The method and system that road traffic congestion degree sorts between a kind of city
CN113312398A (en) Intelligent planning method, system, terminal and storage medium for water and soil conservation monitoring points
CN107134133A (en) The method and system that highway traffic congestion degree sorts between area under one's jurisdiction
CN109035775A (en) A kind of method and device of emergency event identification
Baladi et al. Pavement condition index--remaining service life
CN111986480A (en) Method, system and storage medium for evaluating influence of urban road traffic incident
CN114118539A (en) Highway accurate maintenance decision-making method based on microscopic unit performance prediction
CN107273686B (en) Rain flood runoff nutrient output load forecasting method
CN110782279A (en) Asset cost accounting method and system for main equipment of power distribution network
Xie et al. The accessibility of Nanjing urban park based on GIS
CN114582121B (en) Road network level full-life maintenance optimization method considering carbon emission
CN109740774A (en) The modification method and electronic equipment in maintenance of surface measure library
CN111814280B (en) Urban rail transit planning method, server and computer-readable storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Yu Liyun

Inventor after: Hou Yun

Inventor after: Wang Shiwei

Inventor after: Xu Qing

Inventor after: Dong Yuanshuai

Inventor after: Zhang Yanhong

Inventor after: Tian Chunling

Inventor after: Liu Feng

Inventor after: Dai Jianhua

Inventor before: Hou Yun

Inventor before: Dong Yuanshuai

Inventor before: Zhang Yanhong

Inventor before: Tian Chunling

Inventor before: Liu Feng

Inventor before: Dai Jianhua

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200312

Address after: 100005 No. 11, inner main street, Dongcheng District, Beijing, Jianguomen

Applicant after: Department of transportation network monitoring and emergency response center

Applicant after: China Highway Engineering Consulting Group Company Ltd.

Applicant after: CHECSC Highway Maintenance Detection Technology Co., Ltd.

Address before: 100089 Beijing city Haidian District West Sanhuan Zizhuqiao Chang Yun Gong No. 17 Beijing Municipal Services Building 2

Applicant before: China Highway Engineering Consulting Group Company Ltd.

Applicant before: CHECSC Highway Maintenance Detection Technology Co., Ltd.

GR01 Patent grant