CN108763186A - The method for building up and device of workday calendar bivariate table and the computational methods and device of working day number of days - Google Patents
The method for building up and device of workday calendar bivariate table and the computational methods and device of working day number of days Download PDFInfo
- Publication number
- CN108763186A CN108763186A CN201810561445.5A CN201810561445A CN108763186A CN 108763186 A CN108763186 A CN 108763186A CN 201810561445 A CN201810561445 A CN 201810561445A CN 108763186 A CN108763186 A CN 108763186A
- Authority
- CN
- China
- Prior art keywords
- date
- serial number
- stamp
- close
- bivariate table
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F40/00—Handling natural language data
- G06F40/10—Text processing
- G06F40/166—Editing, e.g. inserting or deleting
- G06F40/177—Editing, e.g. inserting or deleting of tables; using ruled lines
- G06F40/18—Editing, e.g. inserting or deleting of tables; using ruled lines of spreadsheets
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/109—Time management, e.g. calendars, reminders, meetings or time accounting
Abstract
The present invention provides the computational methods and device of a kind of method for building up of workday calendar bivariate table and device and working day number of days, pass through the workaday number of days of the Modeling Calculation of workday calendar bivariate table, each project that calculates rapidly and efficiently raises the working day number of days that the phase includes, and then calculate whether meet regulatory requirements, achieve the purpose that the real-time high-efficiency supervision whole industry raises whether the phase exceeds the time limit.
Description
Technical field
The present invention relates to Internet technical fields, in particular to a kind of method for building up of workday calendar bivariate table
And the computational methods and device of device and working day number of days.
Background technology
The p2p nets issued according to country borrow regulatory requirements:P2p net credit item mesh raises phase on included working day no more than 22
It.Supervising platform needs to calculate whole industry project data.
Include workaday calculating during fixed function calculated for two days in other Data Analysis Software such as existing Excel
Method has the following disadvantages:
1. usage scenario is limited on software itself platform.
2. these softwares are mostly external creation, festivals or holidays regulation does not include domestic peculiar holiday (such as:National Day, the Dragon Boat Festival
Deng), and change is dumb, inconvenient.
3. the scene that not applicable mass data calculates in real time.
Invention content
For the above-mentioned prior art the problem of, the present invention provides a kind of computational methods of working day number of days.
In a first aspect, an embodiment of the present invention provides a kind of method for building up of workday calendar bivariate table, the method packet
It includes:
Date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
It sorts successively since the default date, before the date serial number sovolin on the date serial number previous date of current date
The date stamp on date, wherein the date serial number on default date presets the date stamp on date;
According to date stamp and date serial number, workday calendar bivariate table is established.
Second aspect, the embodiment of the present invention additionally provide a kind of computational methods of working day number of days, the method includes:
The Start Date and Close Date of acquisition business;
According to the Start Date and Close Date of business, the working day number of days between Start Date and Close Date are calculated.
Further, after the Start Date and Close Date that obtain business, the method further includes:
According to Start Date and Close Date, the Start Date and Close Date are searched in calendar bivariate table on weekdays
Date stamp and date serial number;
According to the Start Date and Close Date of business, the working day number of days between Start Date and Close Date are calculated,
Including:
The date serial number that workaday number of days between Start Date and Close Date is equal to the Close Date subtracts beginning day
The date serial number of phase adds the date stamp of Start Date.
Further, the method for building up of the workday calendar bivariate table includes:
Date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
It sorts successively since the default date, before the date serial number sovolin on the date serial number previous date of current date
The date stamp on date, wherein the date serial number on default date presets the date stamp on date;
According to date stamp and date serial number, workday calendar bivariate table is established.
Further, according to Start Date and Close Date, the Start Date is searched in calendar bivariate table on weekdays
With the date stamp and date serial number of Close Date, including:Workday calendar bivariate table is loaded as distributed computing framework
Variable is broadcasted, is distributed in the memory of each node of Distributed Calculation.It is each in workday calendar bivariate table and distributed storage
The Start Date and Close Date of node storage, obtain the date stamp and date serial number of Start Date and Close Date.
The third aspect, what the embodiment of the present invention additionally provided a kind of workday calendar bivariate table establishes device, described device
Including:
Mark module, for the date to be marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
Sorting module, for sorting successively since the default date, the date serial number previous date of current date
Date serial number adds the date stamp of current date, wherein the date serial number on default date presets the date stamp on date;
Module is established, for according to date stamp and date serial number, establishing workday calendar bivariate table.
Fourth aspect, the embodiment of the present invention additionally provide a kind of computing device of working day number of days, and described device includes:
Acquisition module, Start Date and Close Date for obtaining business;
Computing module is calculated for the Start Date and Close Date according to business between Start Date and Close Date
Working day number of days.
Further, described device further includes:
Searching module, for according to Start Date and Close Date, searching the beginning in calendar bivariate table on weekdays
The date stamp and date serial number on date and Close Date;
Computing module is additionally operable to:
The date serial number that workaday number of days between Start Date and Close Date is equal to the Close Date subtracts beginning day
The date serial number of phase adds the date stamp of Start Date.
Wherein, the method for building up of the workday calendar bivariate table includes:
Date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
It sorts successively since the default date, before the date serial number sovolin on the date serial number previous date of current date
The date stamp on date, wherein the date serial number on default date presets the date stamp on date;
According to date stamp and date serial number, workday calendar bivariate table is established.
Further, searching module is additionally operable to:
Workday calendar bivariate table is loaded as to the broadcast variable of distributed computing framework, it is each to be distributed to Distributed Calculation
In the memory of node.The Start Date and Close Date of workday calendar bivariate table and each node storage in distributed storage,
Obtain the date stamp and date serial number of Start Date and Close Date.
5th aspect, an embodiment of the present invention provides a kind of computer storage media, for being stored as the third aspect and the
The computer software instructions used in device described in four aspects.
The embodiment of the present invention brings following advantageous effect:
An embodiment of the present invention provides a kind of method for building up of workday calendar bivariate table and device and working day number of days
Computational methods and device, by the workaday number of days of the Modeling Calculation of workday calendar bivariate table, calculating rapidly and efficiently is every
A project raises the working day number of days for the phase including, and then calculates whether meet regulatory requirements, reaches the real-time high-efficiency supervision whole industry
The purpose whether the recruitment phase exceeds the time limit.
Other features and advantages of the present invention will illustrate in the following description, also, partly become from specification
It obtains it is clear that understand through the implementation of the invention.The purpose of the present invention and other advantages in specification, claim
Specifically noted structure is realized and is obtained in book and attached drawing.
To enable the above objects, features and advantages of the present invention to be clearer and more comprehensible, preferred embodiment cited below particularly, and coordinate
Appended attached drawing, is described in detail below.
Description of the drawings
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art
Embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, in being described below
Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor
It puts, other drawings may also be obtained based on these drawings.
A kind of flow chart of the method for building up for workday calendar bivariate table that Fig. 1 is provided by first embodiment of the invention;
A kind of flow chart of the computational methods for working day number of days that Fig. 2 is provided by second embodiment of the invention;
A kind of flow chart of the method for building up for workday calendar bivariate table that Fig. 3 is provided by third embodiment of the invention;
A kind of structure diagram of the computing device for working day number of days that Fig. 4 is provided by fourth embodiment of the invention.
Specific implementation mode
To keep destination, technical solution and the advantage of the embodiment of the present invention clearer, below in conjunction with attached drawing to this hair
Bright technical solution is clearly and completely described, it is clear that and described embodiments are some of the embodiments of the present invention, without
It is whole embodiment.The component of embodiments of the present invention, which are generally described and illustrated herein in the accompanying drawings can be with a variety of different
It configures to arrange and design.Therefore, the detailed description of the embodiment of the present invention to providing in the accompanying drawings is not intended to limit below
The range of claimed invention processed, but it is merely representative of the selected embodiment of the present invention.Based on the embodiments of the present invention,
Every other embodiment obtained by those of ordinary skill in the art without making creative efforts, belongs to this hair
The range of bright protection.
Embodiment one
A kind of flow chart of the method for building up of workday calendar bivariate table shown in FIG. 1 is participated in, this method is applied to specific
Include the following steps:
S101. the date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
S102. it sorts successively since the default date, the date serial number on the date serial number previous date of current date
Add the date stamp of current date, wherein the date serial number on default date presets the date stamp on date;
S103. according to date stamp and date serial number, workday calendar bivariate table is established.
An embodiment of the present invention provides the method for building up of workday calendar bivariate table, carry out the number of days of evaluation work day, quickly
It efficiently calculates each project and raises the working day number of days that the phase includes, and then calculate whether meet regulatory requirements, reach real-time
The purpose that efficiently whether the supervision whole industry recruitment phase exceeds the time limit.
Embodiment two
Participate in a kind of calculation flow chart of working day number of days shown in Fig. 2, the work that this method provides in embodiment one
It realizes, specifically comprises the following steps on the basis of the calculating of day number of days:
S201. the Start Date and Close Date of business are obtained;
S202. according to Start Date and Close Date, the Start Date and knot are searched in calendar bivariate table on weekdays
The date stamp and date serial number on beam date;
Workday calendar bivariate table is loaded as to the broadcast variable of distributed computing framework, it is each to be distributed to Distributed Calculation
In the memory of node.The Start Date and Close Date of workday calendar bivariate table and each node storage in distributed storage,
Obtain the date stamp and date serial number of Start Date and Close Date.
S203 calculates the working day day between Start Date and Close Date according to the Start Date and Close Date of business
Number.
In embodiments of the present invention, computational methods are specially the workaday number of days etc. between Start Date and Close Date
The date serial number that Start Date is subtracted in the date serial number of Close Date adds the date stamp of Start Date.
Wherein, the method for building up of the workday calendar bivariate table includes:
S11. the date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
S12. it sorts successively since the default date, the date serial number on the date serial number previous date of current date adds
The date stamp of current date, wherein the date serial number on default date presets the date stamp on date;
S13. according to date stamp and date serial number, workday calendar bivariate table is established.
An embodiment of the present invention provides a kind of computational methods of working day number of days, pass through the foundation of workday calendar bivariate table
Method carrys out the number of days of evaluation work day, and each project that calculates rapidly and efficiently raises the working day number of days that the phase includes, Jin Erji
It is no at last to meet regulatory requirements, achieve the purpose that the real-time high-efficiency supervision whole industry raises whether the phase exceeds the time limit.
Embodiment three
For the method for building up for the workday calendar bivariate table that previous embodiment is provided, an embodiment of the present invention provides one
Kind workday calendar bivariate table establishes device, a kind of knot for establishing device of workday calendar bivariate table shown in Figure 3
Structure block diagram, the device include such as lower part:
Mark module 31, for the date to be marked, workaday date stamp is 1, and the date stamp of inoperative is
0;
Sorting module 32, for sorting successively since the default date, the date serial number previous date of current date
Date serial number add the date stamp of current date, wherein the date serial number on default date presets the date stamp on date;
Module 33 is established, for according to date stamp and date serial number, establishing workday calendar bivariate table.
Example IV
For the computational methods for the working day number of days that previous embodiment is provided, an embodiment of the present invention provides a kind of work
The computing device of day number of days, a kind of structure diagram of the computing device of working day number of days shown in Figure 4, the device include such as
Lower part:
Acquisition module 41, Start Date and Close Date for obtaining business;
Computing module 42, for according to the Start Date and Close Date of business, calculate Start Date and Close Date it
Between working day number of days.
Further, described device further includes:
Searching module 43, for according to Start Date and Close Date, being opened described in lookup in calendar bivariate table on weekdays
The date stamp and date serial number on beginning date and Close Date;
Computing module 42 is additionally operable to:
The date serial number that workaday number of days between Start Date and Close Date is equal to the Close Date subtracts beginning day
The date serial number of phase adds the date stamp of Start Date.
Wherein, the method for building up of the workday calendar bivariate table includes:
Date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
It sorts successively since the default date, before the date serial number sovolin on the date serial number previous date of current date
The date stamp on date, wherein the date serial number on default date presets the date stamp on date;
According to date stamp and date serial number, workday calendar bivariate table is established.
Further, searching module 43 is additionally operable to:
Workday calendar bivariate table is loaded as to the broadcast variable of distributed computing framework, it is each to be distributed to Distributed Calculation
In the memory of node.The Start Date and Close Date of workday calendar bivariate table and each node storage in distributed storage,
Obtain the date stamp and date serial number of Start Date and Close Date.
The embodiment of the present invention additionally provides a kind of computer storage media, the device for being stored as above-described embodiment offer
Computer software instructions used.
In addition, in the description of the embodiment of the present invention unless specifically defined or limited otherwise, term " installation ", " phase
Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can
Can also be electrical connection to be mechanical connection;It can be directly connected, can also indirectly connected through an intermediary, Ke Yishi
Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition
Concrete meaning in invention.
In the description of the present invention, it should be noted that term "center", "upper", "lower", "left", "right", "vertical",
The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to
Convenient for the description present invention and simplify description, do not indicate or imply the indicated device or element must have a particular orientation,
With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.
In addition, term " first ", " second ", " third " are used for description purposes only, it is not understood to indicate or imply phase
To importance.
It should be noted that in embodiment provided by the present invention, it should be understood that disclosed system and method, it can
To realize by another way.The apparatus embodiments described above are merely exemplary, for example, the unit is drawn
Point, only a kind of division of logic function, formula that in actual implementation, there may be another division manner, in another example, multiple units or group
Part can be combined or can be integrated into another system, or some features can be ignored or not executed.It is described to be used as separation unit
The unit that part illustrates may or may not be physically separated, and the component shown as unit can be or also may be used
Not to be physical unit, you can be located at a place, or may be distributed over multiple network units.It can be according to reality
Needs some or all of the units may be selected to achieve the purpose of the solution of this embodiment ground.
In addition, each functional unit in embodiment provided by the invention can be integrated in a processing unit, also may be used
It, can also be during two or more units be integrated in one unit to be that each unit physically exists alone.
It, can be with if the function is realized in the form of SFU software functional unit and when sold or used as an independent product
It is stored in a computer read/write memory medium.Based on this understanding, technical scheme of the present invention is substantially in other words
The part of the part that contributes to existing technology or the technical solution can be expressed in the form of software products, the meter
Calculation machine software product is stored in a storage medium, including some instructions are used so that a computer equipment (can be
People's computer, server or network equipment etc.) it performs all or part of the steps of the method described in the various embodiments of the present invention.
And storage medium above-mentioned includes:USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited
The various media that can store program code such as reservoir (RAM, Random Access Memory), magnetic disc or CD.
In addition, term " first ", " second ", " third " are used for description purposes only, it is not understood to indicate or imply phase
To importance.
Finally it should be noted that:Embodiment described above, only specific implementation mode of the invention, to illustrate the present invention
Technical solution, rather than its limitations, scope of protection of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair
It is bright to be described in detail, it will be understood by those of ordinary skill in the art that:Any one skilled in the art
In the technical scope disclosed by the present invention, it can still modify to the technical solution recorded in previous embodiment or can be light
It is readily conceivable that variation or equivalent replacement of some of the technical features;And these modifications, variation or replacement, do not make
The essence of corresponding technical solution is detached from the spirit and scope of technical solution of the embodiment of the present invention, should all cover the protection in the present invention
Within the scope of.Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.
Claims (10)
1. a kind of method for building up of workday calendar bivariate table, which is characterized in that the method includes:
Date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
It sorts successively since the default date, the date serial number on the date serial number previous date of current date adds current date
Date stamp, wherein the date serial number on default date presets the date stamp on date;
According to date stamp and date serial number, workday calendar bivariate table is established.
2. a kind of computational methods of working day number of days, which is characterized in that the method includes:
The Start Date and Close Date of acquisition business;
According to the Start Date and Close Date of business, the working day number of days between Start Date and Close Date are calculated.
3. according to the method described in claim 2, it is characterized in that, obtain business Start Date and Close Date after, institute
The method of stating further includes:
According to Start Date and Close Date, the day of the Start Date and Close Date are searched in calendar bivariate table on weekdays
Phase marks and date serial number;
According to the Start Date and Close Date of business, the working day number of days between Start Date and Close Date are calculated, including:
Workaday number of days between Start Date and Close Date is equal to the date serial number of Close Date and subtracts Start Date
Date serial number adds the date stamp of Start Date.
4. according to the method described in claim 3, it is characterized in that, the method for building up of the workday calendar bivariate table includes:
Date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
It sorts successively since the default date, the date serial number on the date serial number previous date of current date adds current date
Date stamp, wherein the date serial number on default date presets the date stamp on date;
According to date stamp and date serial number, workday calendar bivariate table is established.
5. according to the method described in claim 4, it is characterized in that, according to Start Date and Close Date, calendar on weekdays
The date stamp and date serial number of the Start Date and Close Date are searched in bivariate table, including:By workday calendar two dimension
Table is loaded as the broadcast variable of distributed computing framework, is distributed in the memory of each node of Distributed Calculation.Workday calendar
The Start Date and Close Date of bivariate table and each node storage in distributed storage, acquisition Start Date and Close Date
Date stamp and date serial number.
6. a kind of workday calendar bivariate table establishes device, which is characterized in that described device includes:
Mark module, for the date to be marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
Sorting module, for sorting successively since the default date, the date on the date serial number previous date of current date
Serial number adds the date stamp of current date, wherein the date serial number on default date presets the date stamp on date;
Module is established, for according to date stamp and date serial number, establishing workday calendar bivariate table.
7. a kind of computing device of working day number of days, which is characterized in that described device includes:
Acquisition module, Start Date and Close Date for obtaining business;
Computing module calculates the work between Start Date and Close Date for the Start Date and Close Date according to business
Make day number of days.
8. according to the method described in claim 2, it is characterized in that, described device further includes:
Searching module, for according to Start Date and Close Date, searching the Start Date in calendar bivariate table on weekdays
With the date stamp and date serial number of Close Date;
Computing module is additionally operable to:
Workaday number of days between Start Date and Close Date is equal to the date serial number of Close Date and subtracts Start Date
Date serial number adds the date stamp of Start Date;
Wherein, the method for building up of the workday calendar bivariate table includes:
Date is marked, workaday date stamp is 1, and the date stamp of inoperative is 0;
It sorts successively since the default date, the date serial number on the date serial number previous date of current date adds current date
Date stamp, wherein the date serial number on default date presets the date stamp on date;
According to date stamp and date serial number, workday calendar bivariate table is established.
9. device according to claim 8, which is characterized in that searching module is additionally operable to:
Workday calendar bivariate table is loaded as to the broadcast variable of distributed computing framework, is distributed to each node of Distributed Calculation
Memory in.It the Start Date and Close Date of workday calendar bivariate table and each node storage in distributed storage, obtains
The date stamp and date serial number of Start Date and Close Date.
10. a kind of computer storage media, which is characterized in that the device for being stored as described in claim 1 to 5 any one
Computer software instructions used.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810561445.5A CN108763186A (en) | 2018-06-01 | 2018-06-01 | The method for building up and device of workday calendar bivariate table and the computational methods and device of working day number of days |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810561445.5A CN108763186A (en) | 2018-06-01 | 2018-06-01 | The method for building up and device of workday calendar bivariate table and the computational methods and device of working day number of days |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108763186A true CN108763186A (en) | 2018-11-06 |
Family
ID=64002389
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810561445.5A Pending CN108763186A (en) | 2018-06-01 | 2018-06-01 | The method for building up and device of workday calendar bivariate table and the computational methods and device of working day number of days |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108763186A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113469651A (en) * | 2021-06-30 | 2021-10-01 | 建信金融科技有限责任公司 | Method and device for determining number of days of working day |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060136241A1 (en) * | 2004-12-20 | 2006-06-22 | Microsoft Corporation | Method and system for work scheduling on calendars |
CN101331507A (en) * | 2005-12-15 | 2008-12-24 | 微软公司 | Providing schedulable calendars electronically |
CN102184483A (en) * | 2011-05-16 | 2011-09-14 | 浪潮集团山东通用软件有限公司 | Flexible and extensible user-defined working calendar based work flow scheduling framework |
CN107679835A (en) * | 2017-10-19 | 2018-02-09 | 山东浪潮通软信息科技有限公司 | A kind of method and device for positioning work calendar |
-
2018
- 2018-06-01 CN CN201810561445.5A patent/CN108763186A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060136241A1 (en) * | 2004-12-20 | 2006-06-22 | Microsoft Corporation | Method and system for work scheduling on calendars |
CN101331507A (en) * | 2005-12-15 | 2008-12-24 | 微软公司 | Providing schedulable calendars electronically |
CN102184483A (en) * | 2011-05-16 | 2011-09-14 | 浪潮集团山东通用软件有限公司 | Flexible and extensible user-defined working calendar based work flow scheduling framework |
CN107679835A (en) * | 2017-10-19 | 2018-02-09 | 山东浪潮通软信息科技有限公司 | A kind of method and device for positioning work calendar |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113469651A (en) * | 2021-06-30 | 2021-10-01 | 建信金融科技有限责任公司 | Method and device for determining number of days of working day |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106156888B (en) | Routing inspection path planning method and device for routing inspection robot | |
CN105682105B (en) | A kind of method and apparatus for planning website evaluation | |
Peraković et al. | Challenges and Issues of ICT in Industry 4.0 | |
CN104717743B (en) | Mobile terminal method for tracing and system based on signalling analysis | |
CN104484233B (en) | A kind of resource allocation methods | |
CN109996202B (en) | Flow charging method and device | |
CN108090643A (en) | Express logistics dispatching method and device | |
CN109919365A (en) | A kind of electric vehicle paths planning method and system based on double decision searches | |
CN105260954A (en) | Construction cost list service system based on Internet-of-things technology | |
CN108259637A (en) | A kind of NAT device recognition methods and device based on decision tree | |
CN105991478A (en) | Server resource distribution method and system | |
CN107103453A (en) | Public emolument computational methods and system | |
CN108596785A (en) | Processing method, device, computer equipment and the storage medium of power equipment data | |
CN111008885A (en) | Method, equipment and medium for managing and sharing charge pal based on block chain | |
CN108763186A (en) | The method for building up and device of workday calendar bivariate table and the computational methods and device of working day number of days | |
CN109710542A (en) | A kind of completely N-ary tree construction method and device | |
CN104486769B (en) | A kind of choosing method and device for being worth cell | |
CN106982126A (en) | A kind of resource-sharing charging method and message accounting, memory bank | |
CN111581187B (en) | Data management method, device, computer equipment and storage medium for intelligent park | |
CN106341498A (en) | Network address based locating method and device and IP segment data storage method and device | |
CN105159881A (en) | Method and device for polymerizing data module in page | |
CN110366122A (en) | A kind of wholesale price method and apparatus | |
CN107943857A (en) | Automatic method, apparatus, terminal device and the storage medium for reading AutoCAD forms | |
CN114399173A (en) | 5G base station site evaluation method and device and electronic equipment | |
CN113905066A (en) | Networking method of Internet of things, networking device of Internet of things and electronic equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181106 |