CN108755757A - Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery - Google Patents
Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery Download PDFInfo
- Publication number
- CN108755757A CN108755757A CN201810706191.1A CN201810706191A CN108755757A CN 108755757 A CN108755757 A CN 108755757A CN 201810706191 A CN201810706191 A CN 201810706191A CN 108755757 A CN108755757 A CN 108755757A
- Authority
- CN
- China
- Prior art keywords
- construction
- prefabrication
- pipe gallery
- assembly
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Chemical & Material Sciences (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The present invention relates to carry out subregion segmentation based on the quick mixed construction method of prefabrication and assembly construction superposed type underground pipe gallery, including to whole underground pipe gallery;Piping lane excavation of foundation pit and bed course, bottom waterproof construction;Prefabrication and assembly construction section assembling construction, while Cast-in-Situ Segment reinforcing bar and form work engineering construction;Concreting and maintenance;Waterproof construction;Next great Qu constructions:It is sequentially completed other flowing water area piping lane main structure constructions according to above-mentioned steps;Backfill:Pipe rack to having completed checking and accepting backfills, until completing entire piping lane construction.This rapid constructing method is by underground pipe gallery subregion segmental construction, each several continuous productive process areas are divided into greatly, each continuous productive process area is further divided into Cast-in-Situ Segment and prefabrication and assembly construction section, the advantage of abundant combined cast-in-situ and prefabricated assembled construction technology, operation side is efficiently used to reach, the purpose of rapid construction.
Description
Technical field
The present invention relates to the construction fields of underground pipe gallery, and prefabrication and assembly construction superposed type underground is based on more particularly to one kind
The quick mixed construction method of pipe gallery.
Background technology
Now, numerous advantageous characteristics such as Urban Underground pipe gallery is comprehensive with its, long-term effect, maintainability, the feature of environmental protection,
By extensive use more and more.Promotion with people to pipe gallery performance requirement, Pipe rack is increasingly complicated, construction week
Phase is increasingly longer, and traditional construction technology has been difficult to meet new requirement, particularly with long range, multi-section complicated construction condition
Under underground pipe gallery, it is proposed that more harsh construction requirement.
Traditional underground pipe gallery construction method generally use integral cast-in-situ mode is taken prefabricated assembled.Work as use
When integral cast-in-situ mode, it is typically due to live a large amount of reinforcing bar, template and concreting engineering, causes difficulty of construction big, applies
The work period is long, while construction cost is high;When using prefabricated assembled, it is larger to be typically due to prefabricated piping lane segment, causes to transport
Inconvenience, at the same it is more demanding to assembled machinery, cause difficulty of construction larger.
Invention content
The construction period can be effectively shortened technical problem to be solved by the invention is to provide a kind of, and it is difficult to reduce site operation
Degree reduces the quick mixed construction method of lower underground pipe gallery of construction comprehensive cost.
The technical solution adopted by the present invention to solve the technical problems is:It provides and is integrated based on prefabrication and assembly construction superposed type underground
The quick mixed construction method of piping lane, is as follows:
(a) piping lane subregion is several great Qu by comprehensive pipe gallery structure feature and construction site condition under base area;It is each big
In area, according to pipe gallery corridor body section size and piping lane accessory interface design feature, it is divided into several continuous productive process areas, per first-class
Water operation area is further divided into Cast-in-Situ Segment and prefabrication and assembly construction section, and cross construction arrangement is carried out according to subregion striping order;
(b) according to cross construction arrangement, after carrying out the work such as precipitation and pattern foundation pit supporting structure, to the first great Qu of pipe gallery into
Then row excavation of foundation pit carries out smooth cleaning to hole bottom, carries out bed course and bottom waterproof;
(c) it according to cross construction arrangement, constructs to the first flowing water operation area in the first great Qu:First to prefabricated dress
It constructs with section, assembly is carried out to piping lane agent structure according to the mode of construction of prefabrication and assembly construction superposed type piping lane successively merogenesis,
And form stable structural system;It constructs simultaneously, to the continuous productive process area Cast-in-Situ Segment in the first flowing water operation area prefabrication and assembly construction section
The reinforced bar engineering and form work engineering of piping lane are constructed, and after waiting for that Cast-in-Situ Segment is constructed with prefabrication and assembly construction section boundary junction, are poured successively
Continuous productive process area bottom plate, side plate and the concrete roof is built, concrete curing is then carried out;It is sequentially completed according to above-mentioned steps
Remaining continuous productive process area piping lane construction in one great Qu;Simultaneously, excavation of foundation pit is carried out to next great Qu;
(d) waterproof construction is carried out to the first great Qu piping lane main bodys, while right successively according to above-mentioned steps (b)~step (c)
Next great Qu underground pipe galleries are constructed;
(e) Pipe rack for having completed checking and accepting is backfilled, until completing entire piping lane construction.
As a supplement to the technical solution of the present invention, the underground pipe gallery in the step (b) is adopted
It is constructed with cut and cover method.
Further, the great Qu of the underground pipe gallery in the step (a) and its continuous productive process area working sources are answered
Reasonable distribution should not result in the work holdup.
Further, the Cast-in-Situ Segment in the step (a) is the non-standard segment part of underground pipe gallery, prefabrication and assembly construction
Section is the standard paragraphs part of underground pipe gallery corridor body.
Further, in the step (c), along managing since prefabrication and assembly construction section and Cast-in-Situ Segment intersection one end when construction
Corridor is longitudinally assembled, in other end prefabrication and assembly construction section and Cast-in-Situ Segment intersection, after the completion of should waiting for the assembly of prefabrication and assembly construction section piping lane,
The installation of Cast-in-Situ Segment template is carried out again and reinforcing bar is laid with.
Further, the prefabrication and assembly construction section piping lane is using the form for assembling superposed type.
Further, it when Cast-in-Situ Segment is poured with prefabrication and assembly construction section underplate concrete in the step (c), is handed over wall
The place of connecing should be higher by floor level 300mm or more, and steel plate for sealing water is arranged and carries out water-proofing treatment.
Preferably, Cast-in-Situ Segment and prefabrication and assembly construction section intersection are deformation joint type of attachment, then prefabrication and assembly construction section and cast-in-place
Section individually casting concrete.
Preferably, Cast-in-Situ Segment and prefabrication and assembly construction section intersection be it is wet connect type of attachment, then prefabrication and assembly construction section and Cast-in-Situ Segment
Continuous concrete.
Advantageous effect:The present invention is by advance subregion segmented mode, according to Pipe rack feature, sectional dimension and live item
Entire piping lane is divided into several sections of roughly equal great Qu by the factors such as part, each to divide into several continuous productive process areas greatly, each
Continuous productive process area is further divided into Cast-in-Situ Segment and prefabrication and assembly construction section.The non-standard segments such as accessory interface to underground pipe gallery portion
Divide and constructed at the construction field (site) using cast-in-place mode, novel assembly is used to the standard paragraphs part of underground pipe gallery corridor body
Superposed type erection method, the advantages of being effectively combined cast-in-place and prefabricated assembled two kinds of construction technologies.
Due to using novel assembly superposed type erection method, piping lane main body to be split as the bases such as bottom plate, side plate and top plate
This component greatly facilitates the transport of prefabricated components, requirement when on-site consolidation is greatly reduced to mechanical performance;It is right
It, can compared to full prefabrication system by the way of field cast-in-place in being difficult to the prefabricated non-standard segment interface position of batch production on a small quantity
Effectively to reduce the project cost of the part, while the transporting of such non-standard structural element, assembled and forming difficulty are evaded, have ensured
The overall stiffness and forming accuracy at crucial important interface position.
Compared to current existing construction method, situ wet operation and form erecting operation is greatly reduced, the scene of reducing is applied
The working strength of work difficulty and operating worker, while key position overall stiffness and forming accuracy can be effectively ensured, effectively drop
Low engineering comprehensive cost, substantially accelerates construction progress.
Description of the drawings
Fig. 1 is a preferred embodiment of the present invention big differentiation area's schematic diagram;
Fig. 2 is the areas the ① great sequence of construction figure of embodiment in Fig. 1;
Fig. 3 is the areas the ① great stepwise schematic views of embodiment in Fig. 1;
Fig. 4 is that the prefabrication and assembly construction of embodiment in Fig. 1 overlaps section sequence of construction figure.
Specific implementation mode
Present invention will be further explained below with reference to specific examples.It should be understood that these embodiments are merely to illustrate the present invention
Rather than it limits the scope of the invention.In addition, it should also be understood that, after reading the content taught by the present invention, people in the art
Member can make various changes or modifications the present invention, and such equivalent forms equally fall within the application the appended claims and limited
Range.
As shown in Figs 1-4, embodiments of the present invention are related to based on the quick of prefabrication and assembly construction superposed type underground pipe gallery
Mixed construction method, is as follows:
(a) piping lane subregion is several great Qu by comprehensive pipe gallery structure feature and construction site condition under base area;It is each big
In area, according to pipe gallery corridor body section size and piping lane accessory interface design feature, it is divided into several continuous productive process areas, per first-class
Water operation area is further divided into Cast-in-Situ Segment and prefabrication and assembly construction section, and cross construction arrangement, underground are carried out according to subregion striping order
The subregion segmentation of pipe gallery should be reasonable, should not result in the work holdup;Cast-in-Situ Segment is the non-standard segment part of underground pipe gallery, in advance
Load segment processed is the standard paragraphs part of underground pipe gallery corridor body;
(b) according to cross construction arrangement, after carrying out the work such as precipitation and pattern foundation pit supporting structure, to the first great Qu of pipe gallery into
Then row excavation of foundation pit carries out smooth cleaning to hole bottom, carries out bed course and waterproof, underground pipe gallery is applied using cut and cover method
Work;
(c) it according to cross construction arrangement, constructs to the first flowing water operation area in the first great Qu:First to prefabricated dress
It constructs with section, assembly is carried out to piping lane agent structure according to the mode of construction of prefabrication and assembly construction superposed type piping lane successively merogenesis,
And form stable structural system;It constructs simultaneously, to the continuous productive process area Cast-in-Situ Segment in the first flowing water operation area prefabrication and assembly construction section
The reinforced bar engineering and form work engineering of piping lane are constructed, and after waiting for that Cast-in-Situ Segment is constructed with prefabrication and assembly construction section boundary junction, are poured successively
Continuous productive process area bottom plate, side plate and the concrete roof is built, concrete curing is then carried out;It is sequentially completed according to above-mentioned steps
Remaining continuous productive process area piping lane construction in one great Qu;Simultaneously, excavation of foundation pit is carried out to next great Qu;From prefabricated dress when construction
Start longitudinally to be assembled along piping lane with section and Cast-in-Situ Segment intersection one end, have a common boundary in other end prefabrication and assembly construction section and Cast-in-Situ Segment
Place after the completion of should waiting for the assembly of prefabrication and assembly construction section piping lane, then carries out the installation of Cast-in-Situ Segment template and reinforcing bar laying;Cast-in-Situ Segment and prefabricated dress
When being poured with section underplate concrete, it should be higher by floor level 300mm or more with wall junction, and steel plate for sealing water progress is set
Water-proofing treatment;
(d) waterproof construction is carried out to the first great Qu piping lane main bodys, while right successively according to above-mentioned steps (b)~step (c)
Next great Qu underground pipe galleries are constructed;
(e) Pipe rack for having completed checking and accepting is backfilled, until completing entire piping lane construction.Described is pre-
Load segment piping lane processed is using the form for assembling superposed type.
When Cast-in-Situ Segment and prefabrication and assembly construction section intersection are deformation joint type of attachment, then prefabrication and assembly construction section and Cast-in-Situ Segment are distinguished
Independent casting concrete.
When Cast-in-Situ Segment and prefabrication and assembly construction section intersection be it is wet connect type of attachment when, then prefabrication and assembly construction section and Cast-in-Situ Segment continuously pour
Build concrete.
A kind of embodiment as the present invention:
One Urban Underground pipe gallery, as shown in Figure 1, east-west, 717 meters long, standard section beam overall is 7.3m, total high
Include the non-standard segments such as air inlet, exhaust outlet, escaping exit, hoisting port, line branches mouth, personnel's entrance, standard for 4.3m
Section piping lane top earthing thickness about 3.0m.Piping lane complicated integral structure, site operation narrow field, construction period are tight.
The Urban Underground pipe gallery based on the quick mixed construction method packet of prefabrication and assembly construction superposed type underground pipe gallery
Include following steps:
Piping lane subregion is 3 areas Ge great by comprehensive pipe gallery structure feature and construction site condition under step (a), base area, such as
Shown in Fig. 1:
The 1. big section length be about 251 meters, including end well, comprehensive storehouse draining pump sump, line branches mouth, the air draft of combustion gas cabin
The non-standard segments such as mouth and escaping exit and combustion gas cabin draining pump sump.
The 2. big section length be about 228 meters, including comprehensive cabin air inlet and escaping exit, comprehensive storehouse draining pump sump, pipeline point
Branch mouth, combustion gas cabin hoisting port, the comprehensive non-standard segments such as cabin hoisting port and personnel's entrance.
The 3. big section length be about 238 meters, including divide transformer and distribution power station, combustion gas cabin exhaust outlet and escaping exit, comprehensive cabin air inlet
The non-standard segments such as mouth and escaping exit, comprehensive cabin hoisting port.
Cast-in-Situ Segment is divided into using cast-in-place concrete construction technique to above-mentioned non-standard segment, remaining standard paragraphs is using prefabricated
Assembly method is constructed, and prefabrication and assembly construction section is divided into.
From according to the areas ① great → areas the ② great → areas ③ great sequential deployment construction operation.
Step (b) after carrying out the work such as precipitation and pattern foundation pit supporting structure, carries out excavation of foundation pit, so to the areas pipe gallery ① great
Smooth cleaning is carried out to hole bottom afterwards, carries out bed course;
Step (c), as shown in Fig. 2, 1. dividing into 2 continuous productive process areas greatly by the, specific segmentation is as shown in figure 3, the 1st stream
Water operation area includes 1-1,1-2,2-1,2-2 sections, and wherein 1-1 and 2-1 are Cast-in-Situ Segment, and 1-2 and 2-2 are prefabrication and assembly construction section;2nd stream
Water operation area includes 3-1,3-2,4-1,4-2 sections, and wherein 3-1 and 4-1 are Cast-in-Situ Segment, and 3-2 and 4-2 are prefabrication and assembly construction section.1-1 with
1-2 intersects at J1, is connected by deformation joint form;1-2 intersects with 2-1 at J2, and form connection is connect by wet;2-1 and 2-2
Intersect at J3, is connected by deformation joint form;2-2 intersects with 3-1 at J4, and form connection is connect by wet;3-1 and 3-2 exists
Intersect at J5, is connected by deformation joint form;3-2 intersects with 4-1 at J6, is connected by deformation joint form;4-1 and 4-2 exists
Intersect at J7, is connected by deformation joint form.
Step (c), which implements, is divided into following steps:
Step (c-1):It constructs first to the 1st continuous productive process area.Construction, prefabrication and assembly construction are started simultaneously at from J1 and J3
Section 1-2,2-2 promote from J1, J3 assembled successively from left to right respectively.As shown in figure 4, first carrying out bed course A constructions, then it is laid with
Bottom plate B re-lays wallboard C-1, C-2, C-3, until 1-2,2-2 sections of assembly finish.At the same time, Cast-in-Situ Segment 1-1,2-1 from J1,
Start at J2, promote assembling reinforcement and support shuttering until finishing from right to left, it is first assembled that 1-2 sections of final sections should be controlled at J2
After, re-lay the reinforcing bar and template of the 2-1 sections of ends at J2.
Step (c-2):To 1-1 sections of progress concreting in the 1st continuous productive process area, while 1-2 sections and 2-1 sections are carried out
Underplate concrete pours, as shown in figure 4, wherein in the concreting of wallboard junction at plate top surface 300mm S1.
Wait for that underplate concrete reaches some strength, be laid with 1-2 sections of top plate supportings and top plate, then uniformly pour 1-2 and 2-1 sections of wall and
Concrete roof.At the same time, it constructs to the 2nd continuous productive process area.Construction, prefabrication and assembly construction section are started simultaneously at from J5 and J7
3-2,4-2 promote assembly successively from left to right from J5, J7 respectively, until assembly finishes.Meanwhile Cast-in-Situ Segment 3-1,4-1 from J5,
Start at J7, promotes assembling reinforcement and support shuttering from right to left until finishing.It is first assembled that 3-2 sections of final sections should be controlled at J6
After, re-lay the reinforcing bar and template of the 4-1 sections of ends at J6.
Step (c-3):Underplate concrete is carried out to 2-2 sections and 3-1 sections, 3-2,4-1 and 4-2 sections to pour, wherein in wallboard
Junction concreting is at plate top surface 300mm.Wait for that underplate concrete reaches some strength, be laid with 2-2,3-2 and
Then 4-2 sections of top plate supportings and top plate pour 2-2 and 3-1 sections, 3-2,4-1 and 4-2 sections of walls and concrete roof, directly respectively
It is finished to the 1st continuous productive process area pipe Pipe rack main body construction;At the same time, excavation of foundation pit is carried out to the areas ② great.
Step (d):Waterproof construction is carried out to the areas ① great piping lane main body;
Step (e):It constructs to the areas ② great according to step (b)~step (c), meanwhile, base is carried out to the areas ③ great
It excavates in hole;
Step (f):Region to completing checking and accepting in the areas ① great piping lane backfills, while the areas ② great piping lane master
Body carries out waterproof construction;
Step (g):It constructs to the areas ③ great according to step (b)~step (c).
Step (h):Region to completing checking and accepting in the areas ② great piping lane backfills, while the areas ③ great piping lane master
Body carries out waterproof construction;
Step (i):Region to completing checking and accepting in the areas ③ great piping lane backfills, until entire piping lane main body knot
Structure construction terminates.
The present invention forms effective continuous productive process by advance subregion segmented mode as can be seen from the above embodiments,
So that construction operation resource is effectively used, substantially accelerate construction progress;By great Qu inner tissues cross construction, and distinguish existing
The advantages of pouring section and prefabrication and assembly construction section, being effectively combined cast-in-place and prefabricated assembled two kinds of construction technologies is greatly reduced existing
Field wet construction and form erecting operation, reduce site operation difficulty and the working strength of operating worker, while pass can be effectively ensured
Key position overall stiffness and forming accuracy effectively reduce engineering comprehensive cost.
Claims (9)
1. the quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery, is as follows:
(a) piping lane subregion is several great Qu by comprehensive pipe gallery structure feature and construction site condition under base area;In each great Qu,
According to pipe gallery corridor body section size and piping lane accessory interface design feature, it is divided into several continuous productive process areas, each flowing water is made
Industry area is further divided into Cast-in-Situ Segment and prefabrication and assembly construction section, and cross construction arrangement is carried out according to subregion striping order;
(b) according to cross construction arrangement, after carrying out the work such as precipitation and pattern foundation pit supporting structure, base is carried out to the first great Qu of pipe gallery
Hole is excavated, and is then carried out smooth cleaning to hole bottom, is carried out bed course and bottom waterproof;
(c) it according to cross construction arrangement, constructs to the first flowing water operation area in the first great Qu:First to prefabrication and assembly construction section
It constructs, assembly, and shape is carried out to piping lane agent structure according to the mode of construction of prefabrication and assembly construction superposed type piping lane successively merogenesis
At stable structural system;It constructs simultaneously, to the continuous productive process area Cast-in-Situ Segment piping lane in the first flowing water operation area prefabrication and assembly construction section
Reinforced bar engineering and form work engineering construction pour this successively after waiting for the construction of Cast-in-Situ Segment and prefabrication and assembly construction section boundary junction
Continuous productive process area bottom plate, side plate and concrete roof, then carry out concrete curing;It is big it to be sequentially completed first according to above-mentioned steps
Remaining continuous productive process area piping lane construction in area;Simultaneously, excavation of foundation pit is carried out to next great Qu;
(d) waterproof construction is carried out to the first great Qu piping lane main bodys, while according to above-mentioned steps b~step c successively to next great Qu
Underground pipe gallery is constructed;
(e) Pipe rack for having completed checking and accepting is backfilled, until completing entire piping lane construction.
2. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:Underground pipe gallery in the step (b) is constructed using cut and cover method.
3. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:The great Qu and its continuous productive process area working sources of underground pipe gallery in the step (a) answer reasonable distribution,
It should not result in the work holdup.
4. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:Cast-in-Situ Segment in the step (a) is the non-standard segment part of underground pipe gallery, and prefabrication and assembly construction section is underground
The standard paragraphs part of pipe gallery corridor body.
5. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:In the step (c), when construction since prefabrication and assembly construction section and Cast-in-Situ Segment intersection one end along piping lane it is longitudinal into
Luggage is matched, and in other end prefabrication and assembly construction section and Cast-in-Situ Segment intersection, after the completion of should waiting for the assembly of prefabrication and assembly construction section piping lane, then is showed
It pours section template installation and reinforcing bar is laid with.
6. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:The prefabrication and assembly construction section piping lane is using the form for assembling superposed type.
7. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:When Cast-in-Situ Segment is poured with prefabrication and assembly construction section underplate concrete in the step (c), height is being answered with wall junction
Go out floor level 300mm or more, and steel plate for sealing water is set and carries out water-proofing treatment.
8. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:Cast-in-Situ Segment is that deformation joint type of attachment, then prefabrication and assembly construction section and Cast-in-Situ Segment are single respectively with prefabrication and assembly construction section intersection
Only casting concrete.
9. the quick mixed construction method according to claim 1 based on prefabrication and assembly construction superposed type underground pipe gallery,
It is characterized in that:Cast-in-Situ Segment connects type of attachment with prefabrication and assembly construction section intersection to be wet, then prefabrication and assembly construction section and Cast-in-Situ Segment continuous placing
Concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810706191.1A CN108755757A (en) | 2018-06-29 | 2018-06-29 | Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810706191.1A CN108755757A (en) | 2018-06-29 | 2018-06-29 | Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108755757A true CN108755757A (en) | 2018-11-06 |
Family
ID=63975408
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810706191.1A Pending CN108755757A (en) | 2018-06-29 | 2018-06-29 | Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108755757A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109778865A (en) * | 2018-12-19 | 2019-05-21 | 上海建工集团股份有限公司 | A kind of piping lane subregion excavation method guaranteeing that existing road half range is current |
CN111173029A (en) * | 2020-01-10 | 2020-05-19 | 上海二十冶建设有限公司 | Prefabricated superposed assembly type underground comprehensive pipe gallery sandwich wallboard and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106801436A (en) * | 2017-01-25 | 2017-06-06 | 中冶建工集团有限公司 | A kind of construction method for overlapping assembled underground pipe gallery |
CN106875159A (en) * | 2017-02-17 | 2017-06-20 | 中国十七冶集团有限公司 | The city integrated piping lane construction total management system of cast-in-place structural |
CN106894445A (en) * | 2017-04-11 | 2017-06-27 | 吉林森煌建筑材料集团有限公司 | One kind assembling superposed type pipe gallery and its method of construction |
KR20180016194A (en) * | 2016-08-05 | 2018-02-14 | 최승희 | Precast mountain type rahmen structure and method for constructing this same |
-
2018
- 2018-06-29 CN CN201810706191.1A patent/CN108755757A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20180016194A (en) * | 2016-08-05 | 2018-02-14 | 최승희 | Precast mountain type rahmen structure and method for constructing this same |
CN106801436A (en) * | 2017-01-25 | 2017-06-06 | 中冶建工集团有限公司 | A kind of construction method for overlapping assembled underground pipe gallery |
CN106875159A (en) * | 2017-02-17 | 2017-06-20 | 中国十七冶集团有限公司 | The city integrated piping lane construction total management system of cast-in-place structural |
CN106894445A (en) * | 2017-04-11 | 2017-06-27 | 吉林森煌建筑材料集团有限公司 | One kind assembling superposed type pipe gallery and its method of construction |
Non-Patent Citations (4)
Title |
---|
李慧民: "《全国建造师执业资格考试工程项目管理案例分析》", 31 January 2006 * |
杨洪等: "老城区现有道路综合管廊与高架路建设相结合案例", 《中国给水排水》 * |
蒋瞳瞳: "浅论综合管廊的产业化应用", 《中国房地产业》 * |
黄艳雁等: "《建筑构造》", 30 April 2014 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109778865A (en) * | 2018-12-19 | 2019-05-21 | 上海建工集团股份有限公司 | A kind of piping lane subregion excavation method guaranteeing that existing road half range is current |
CN111173029A (en) * | 2020-01-10 | 2020-05-19 | 上海二十冶建设有限公司 | Prefabricated superposed assembly type underground comprehensive pipe gallery sandwich wallboard and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101864959A (en) | Method for tunneling construction of main structure of underground station | |
CN106245674A (en) | Hollow wallboard mixed prefabricated assembly type comprehensive pipe gallery and construction method thereof | |
CN207348091U (en) | A kind of assembled pipe gallery | |
CN108149706A (en) | Prefabricated assembled comprehensive pipe gallery spliced by cast-in-place hidden beams and laminated slabs and construction method thereof | |
CN106088147A (en) | Hollow wallboard mixed prefabricated assembly type comprehensive pipe gallery and construction method thereof | |
CN103256052A (en) | Construction method for integral straight middle wall type double-arch tunnel | |
CN107842035A (en) | A kind of ultra-high performance concrete precast assembly pipe gallery system and construction method | |
CN108086353A (en) | Hollow wall plate mixed prefabricated assembly type comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof | |
CN110439574B (en) | Tunnel structure for shield lateral translation starting and slag discharging material conveying and construction method | |
CN108086354A (en) | Prefabricated assembled comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof | |
CN106988603A (en) | A kind of Assembled enclosing wall and its construction method | |
CN110424454A (en) | Build together method and the structure of building together of pipe gallery and subway station | |
CN105350581A (en) | Advanced sealing structure for basement top slab settlement post-cast strips | |
CN109972656A (en) | A kind of overlapping fabricated construction pipe gallery and its construction method | |
CN108005118A (en) | Underground pipe gallery main structure integration construction method | |
CN110080287A (en) | A kind of assembled flat-top has the open cutting construction method of column underground structure | |
CN207998860U (en) | A kind of assembled pipe gallery | |
CN108755757A (en) | Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery | |
CN110158656A (en) | A kind of integrated template piping lane and its method of construction | |
CN113250494A (en) | Assembled integrated toilet and construction method | |
CN208415305U (en) | A kind of precast assembly monoblock type pipe gallery and component and unit | |
CN110318427A (en) | A kind of prefabricated pipe gallery construction method of segmentation | |
CN208633847U (en) | A kind of corrugated steel supporting construction suitable for circular arch stalk formula tunnel full-section excavation | |
CN112012763B (en) | Construction method of double-layer primary support multi-arch tunnel structure | |
CN109629664A (en) | Basement construction method based on assembled resin concrete drainage ditch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181106 |