CN108722162A - A kind of flue gas depth takes off white minimum discharge apparatus and method - Google Patents

A kind of flue gas depth takes off white minimum discharge apparatus and method Download PDF

Info

Publication number
CN108722162A
CN108722162A CN201810942555.6A CN201810942555A CN108722162A CN 108722162 A CN108722162 A CN 108722162A CN 201810942555 A CN201810942555 A CN 201810942555A CN 108722162 A CN108722162 A CN 108722162A
Authority
CN
China
Prior art keywords
flue gas
desulfurizing tower
white
heat pipe
heat exchange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810942555.6A
Other languages
Chinese (zh)
Other versions
CN108722162B (en
Inventor
张殿坤
李坤
张鹏
张晶静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI JINSENYUAN ENVIRONMENTAL PROTECTION ENGINEERING CO LTD
Original Assignee
ANHUI JINSENYUAN ENVIRONMENTAL PROTECTION ENGINEERING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI JINSENYUAN ENVIRONMENTAL PROTECTION ENGINEERING CO LTD filed Critical ANHUI JINSENYUAN ENVIRONMENTAL PROTECTION ENGINEERING CO LTD
Priority to CN201810942555.6A priority Critical patent/CN108722162B/en
Publication of CN108722162A publication Critical patent/CN108722162A/en
Application granted granted Critical
Publication of CN108722162B publication Critical patent/CN108722162B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/34Chemical or biological purification of waste gases
    • B01D53/74General processes for purification of waste gases; Apparatus or devices specially adapted therefor
    • B01D53/77Liquid phase processes
    • B01D53/78Liquid phase processes with gas-liquid contact
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/002Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by condensation
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/34Chemical or biological purification of waste gases
    • B01D53/46Removing components of defined structure
    • B01D53/48Sulfur compounds
    • B01D53/50Sulfur oxides
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D2258/00Sources of waste gases
    • B01D2258/02Other waste gases
    • B01D2258/0283Flue gases

Abstract

The invention discloses a kind of flue gas depth to take off white minimum discharge apparatus and method, is related to flue gas after desulfurization deep treatment field, including desulfurizing tower, heat exchange of heat pipe A, air-introduced machine and Tuo Bai devices;The desulfurizing tower includes that desulfurizing tower carries effect tower tray, and desulfurizing tower spraying layer restrains rapid ball condensing unit, demister and desulfurizing tower outlet;The heat exchange of heat pipe A is connect by the air-introduced machine with the desulfurizing tower;In the inside of the desulfurizing tower, it is sequentially arranged the desulfurizing tower from bottom to top and has carried effect tower tray, the desulfurizing tower spraying layer, the rapid ball condensing unit of the tube bank and the demister;The desulfurizing tower is circumscribed with the de- white device, including liquid drop separator, heat exchange of heat pipe B take off white temperature raising wind turbine and the first electric control valve.The present invention realizes flue gas emission particulate matter and is not higher than 5mg/m3, sulfur dioxide is not higher than 35mg/m3.The substantially visible white cigarette of no visual really realizes the requirement of minimum discharge.

Description

A kind of flue gas depth takes off white minimum discharge apparatus and method
Technical field
The present invention relates to flue gas after desulfurization deep treatment fields more particularly to a kind of flue gas depth to take off white minimum discharge device With method.
Background technology
Former boiler (kiln) flue gas all compares by wet-method desulfurized fume band water, band gypsum rain and sulfate, and dust-laden It is more serious, while flue gas hangover reaches several kilometers, causes atmosphere pollution.By analysis expert, the substance is to cause haze weather One of factor.The content of harmful substances from flue gases is reduced, the important topic in flue gas after desulfurization deep treatment field is just become.
Therefore, those skilled in the art is dedicated to developing a kind of smoke gas treatment tapping equipment and method, is promoted in flue gas Depth dust removing effects.
Invention content
In view of the drawbacks described above of the prior art, the technical problem to be solved by the present invention is to how realize the de- butter depth of water Spend dust removing effects.
To achieve the above object, the present invention provides a kind of flue gas depth to take off white minimum discharge device, including desulfurizing tower, heat Heat exchange of heat pipe A, air-introduced machine and Tuo Bai devices;
The desulfurizing tower includes that desulfurizing tower carries effect tower tray, desulfurizing tower spraying layer, restrains rapid ball condensing unit, demister and Desulfurizing tower exports;
The heat exchange of heat pipe A is connect by the air-introduced machine with the desulfurizing tower;In the inside of the desulfurizing tower, under It has been sequentially arranged the desulfurizing tower on and and has carried effect tower tray, the desulfurizing tower spraying layer, the rapid ball condensing unit of the tube bank and described Demister;Between the demister and desulfurizing tower outlet, the desulfurizing tower is circumscribed with the de- white device, including Liquid drop separator, heat exchange of heat pipe B take off white temperature raising wind turbine and the first electric control valve;The liquid drop separator and the heat pipe One end of heat exchanger B connects, and the other end of the heat exchange of heat pipe B is connected with the de- white temperature raising wind turbine, described to take off white temperature raising Wind turbine is connected with first electric control valve again, after de- white temperature raising flue gas is adjusted in first electric control valve, It is described to take off white temperature raising flue gas into desulfurizing tower outlet, it is discharged after being mixed with main flue gas.
Further, the heat exchange of heat pipe A and heat exchange of heat pipe B is close together;The heat exchange of heat pipe A is height Heat exchange of heat pipe is warmed, is cooled down to flue gas;The heat exchange of heat pipe B is low temperature heat pipe heat exchanger, is heated to flue gas.
Further, the flue gas circulation of the heat exchange of heat pipe A is 37 ten thousand steres/hour, the heat exchange of heat pipe B Flue gas circulation be 12 ten thousand steres/hour.
Further, the desulfurizing tower spraying layer is circumscribed with main desulfurization pump and doctor solution plate heat exchanger;The main desulfurization For the doctor solution of pump discharge after doctor solution plate heat exchanger cooling, the doctor solution enters the institute inside the desulfurizing tower Desulfurizing tower spraying layer is stated, with heat smoke haptoreaction.
Further, the rapid ball condensing unit of the tube bank is connected to condensate water circulatory storage tank, condensate pump, condensate liquid plate successively Formula heat exchanger, is attached by pipeline each other, forms a set of circulation condensation device;It is produced after being condensed to flue gas Flue gas condensing water is flow to described cold by raw condensed water by the liter gas water collector inside the desulfurizing tower by the pipeline Condensate circulating storage groove is stored, the condensed water in the condensate water circulatory storage tank using the condensate pump pressurization and it is described After condensate liquid plate heat exchanger carries out cooling, the rapid ball condensing unit of the tube bank is entered by the pipeline and continues cooled flue gas.
Further, the condensate water circulatory storage tank will produce partly precipitated object after recycling for a long time, through pump Pressurization by the condensate water circulatory storage tank condensed water and sediment be sent to sediment piece-rate system, extra condensed water is by pumping To advanced treatment of wastewater, the extra condensed water is made as system circulating water moisturizing circulation after being handled using film separation system With;Water in the condensate water circulatory storage tank is supplemented by technique moisturizing, and the technique moisturizing comes from technique water tank.
Further, the de- white temperature raising wind turbine pressurizes to flue gas, and the air quantity for taking off white temperature raising wind turbine is 120,000 Cube m/h.
Further, the de- white temperature raising wind turbine is also connect with the second electric control valve, second electric control valve pair It is hot standby that the de- white temperature raising flue gas enters kiln original chimney after being adjusted;The flue gas circulation of first electric control valve Flue gas circulation for 5-6 ten thousand steres/hour, second electric control valve is 6-7 ten thousand steres/hour.
Further, the height of the desulfurizing tower is 70 meters.
The present invention also provides a kind of methods that flue gas depth takes off white minimum discharge, the described method comprises the following steps:
Step 1, main flue gas exchanged heat into the heat exchange of heat pipe A after by the air-introduced machine enter the desulfurization Tower, the main flue gas are the flue gas after boiler or kiln dedusting, are 150 DEG C -180 in the temperature for entering the heat exchange of heat pipe A DEG C, the main flue gas is reduced to 100 DEG C -140 DEG C after heat exchange into the temperature of the desulfurizing tower;
Step 2, the main flue gas pass sequentially through the desulfurizing tower and put forward effect from bottom to top after entering in the desulfurizing tower Tower tray and the desulfurizing tower spraying layer, after by the desulfurizing tower spraying layer temperature of the main flue gas will drop to 55 DEG C- 65℃;
Step 3, main flue gas continuation pass sequentially through the rapid ball condensing unit of the tube bank and demisting dress from below to up It sets, carries out condensation desulfurization and dedusting demisting dehydration, condensed -47 DEG C of discharge flue-gas temperature≤45 DEG C, dust content<10mg/ Nm3
25% to 35% discharge flue gas carries out de- white processing by the de- white device in step 4, the step 3, first The heat exchange of heat pipe B is entered back by the liquid drop separator, between the discharge flue gas is warming up to 130 DEG C -160 DEG C, Then it is divided into two-way under white temperature raising fan action in described take off, wherein be connected with first electric control valve all the way, described the After the de- white temperature raising flue gas is adjusted in one electric control valve, the de- white temperature raising flue gas goes out into the desulfurizing tower Mouthful, it is discharged after being mixed in step 3 65% to the 75% discharge flue gas, mixed flue-gas temperature is 68 ℃-75℃。
The device and method that above-mentioned flue gas depth takes off white minimum discharge are applied in flue gas after desulfurization deep treatment field, hair It is apparent now to take off butter water depth dust removing effects.Again by transformation condensation inside heat-exchange temperature control, desulfurizing tower and flue gas after desulfurization The measures such as heating realize flue gas emission particulate matter and are not higher than 5mg/m3, sulfur dioxide is not higher than 35mg/m3.Summer (the 4-10 months) Condensed smoke temperature reaches 47 DEG C hereinafter, flue gas reduces by 10% or less containing wet;Winter (March next year in November -) condensed smoke temperature Reach 45 DEG C hereinafter, flue gas contains wet 15% or less.Smog discharge temperature reaches certain critical-temperature or more, and substantially no visual is visible " white cigarette " really realizes the requirement of minimum discharge, substantially improves atmosphere pollution environment, build clear water blue sky environment.
The technique effect of the design of the present invention, concrete structure and generation is described further below with reference to attached drawing, with It is fully understood from the purpose of the present invention, feature and effect.
Description of the drawings
Fig. 1 is the overall schematic of the preferred embodiment of the present invention.
Wherein, 1- desulfurizing towers, 101- desulfurizing towers carry effect tower tray, 102- desulfurizing tower spraying layers, the rapid ball condensation dress of 103- tube banks It sets, 104- demisters, 105- desulfurizing towers outlet, 2- heat exchange of heat pipes A, 3- air-introduced machine, 4- takes off white device, 401- drop separations Device, 402- heat exchange of heat pipes B, 403- take off white temperature raising wind turbine, the first electric control valves of 404-, the second electric control valves of 5-, 6- master Desulfurization pumps, 7- doctor solution plate heat exchangers, 8- condensate water circulatory storage tanks, 9- sediment piece-rate systems, 10- advanced treatment of wastewater, 11- technique moisturizings, 12- film separation systems, 13- condensate pumps, 14- condensate liquid plate heat exchangers.
Specific implementation mode
Multiple preferred embodiments that the present invention is introduced below with reference to Figure of description, keep its technology contents more clear and just In understanding.The present invention can be emerged from by many various forms of embodiments, and protection scope of the present invention not only limits The embodiment that Yu Wenzhong is mentioned.
In the accompanying drawings, the identical component of structure is indicated with same numbers label, everywhere the similar component of structure or function with Like numeral label indicates.The size and thickness of each component shown in the drawings are to be arbitrarily shown, and there is no limit by the present invention The size and thickness of each component.In order to keep diagram apparent, some places suitably exaggerate the thickness of component in attached drawing.
As shown in Figure 1, the higher temperatures main flue gas after boiler (kiln) dedusting, temperature is between 150 DEG C -180 DEG C, first Make heat exchange into the part lower temperature flue gas after heat exchange of heat pipe A2 and desulfurization, main flue gas is cooled down 40 DEG C -50 DEG C or so, Main flue gas temperature control enters back into desulfurizing tower 1 at 130 DEG C -140 DEG C or so.Heat exchange of heat pipe A2 passes through air-introduced machine 3 and desulfurization Tower 1 connects.In desulfurizing tower 1, main flue gas carries effect tower tray 101 by desulfurizing tower from bottom to top, desulfurizing tower spraying layer 102 enters pipe Beam rapids ball condensing unit 103 is cooled down, and flue gas after cooling carries out demisting using demister 104.Due to the temperature of flue gas Degree reduces, and the volume of flue gas also accordingly becomes smaller.Into after desulfurizing tower 1, the average upflow velocity of flue gas is also corresponding to become smaller, de- Under conditions of sulphur section height is constant, using effect tower tray new technology is put forward, so that liquid-gas ratio is substantially reduced, flue gas evaporating capacity is reduced, from root The generation of the vapour concentration of flue gas is reduced in sheet.Flue-gas temperature will after flue gas rises to desulfurizing tower spraying layer 102 in desulfurizing tower 1 It is down to 65 DEG C or so.If the temperature that flue gas enters desulfurizing tower 1 is 140 DEG C, flue gas rises to desulfurizing tower spray in desulfurizing tower 1 Flue-gas temperature is 55 DEG C after drenching layer 102, and seriously band water enters back into the tube bank rapids ball condensing unit on top to main flue gas at this time with mist 103 and demister 104, carry out condensation desulfurization and dedusting demisting dehydration, condensed discharge flue-gas temperature is at 45 DEG C or so, dust-laden Concentration<10mg/Nm3, dehydrating demisting reaches industry advanced level.Main flue gas is through the rapid ball condensing unit 103 of tube bank and demister After 104 processing, reach 47 DEG C hereinafter, flue gas reduces by 10% or less containing wet in summer (the 4-10 months) condensed smoke temperature;Winter (11 The March moon-next year) condensation after smoke temperature reach 45 DEG C hereinafter, flue gas contain wet 15% or less.In summer, although temperature≤45 DEG C, also In 45 DEG C of saturated humidity.As direct emission also will present white cigarette when temperature is relatively low.
It is discharged from tower top outlet side duct with 30% or so flue gas, carrying out flue gas by de- white device 4 takes off in vain, first Through flue by liquid drop separator 401, into after heat exchange of heat pipe B402, flue gas is warming up to 145 DEG C or so, and tolerance ratio is about 3:1.Flue gas after heating is divided into two-way after being pressurizeed by de- white temperature raising wind turbine 403, wherein routing the first electric control valve 404 control System is adjusted, and the flue gas by taking off white temperature raising enters desulfurizing tower outlet 105 and mixes discharge with the main flue gas of 75% or so amount, after mixing Flue-gas temperature between 68-75 DEG C, water vapour is far from saturation point.Summer smoke stack emission is substantially without visual white cigarette;? When environment temperature only has -10 DEG C or less, visual white cigarette amount is seldom.Another way is controlled to adjust by the first electric control valve 5, utilizes original Flue send, hot standby direct exhausting when guarantee kiln emergent hot standby to concrete chimney, guarantee kiln safety operation.
Go out the after cooling in the rapid ball condensing unit 103 of tube bank containing the higher mixed flue gas of steam of desulfurizing tower spraying layer 102 Flue gas condensing water flow in condensate water circulatory storage tank 8 and follows by the liter gas water collector inside desulfurizing tower 1 by condensed water certainly Ring cooling uses.Partly precipitated object after long-time recycles is sent to sediment piece-rate system 9 through pump pressurization, and condensed water follows Water in ring storage tank 8 is supplemented by technique moisturizing 11, and technique moisturizing 11 comes from technique water tank.Extra condensate liquid is by being pumped to sewage Advanced treating 10 using film separation system 12 handle after using the extra condensed water in this part as system circulating water moisturizing circulation It uses, condenses water zero discharge, do not constitute secondary pollution.
It is pressurizeed by condensate pump 13, is entered by pipeline through 14 condensation cycle liquid after cooling of subcooling condensate plate heat exchanger and taken off Tube bank rapids ball condensing unit 103 inside sulphur tower 1 continues cycling through the higher containing steam of the cooling outlet of desulfurizing tower spraying layer 102 Mixed flue gas realizes that flue gas cools.
The doctor solution of main 6 outlet of desulfurization pump doctor solution after the cooling of doctor solution plate heat exchanger 7 enters inside desulfurizing tower 1 Desulfurizing tower spraying layer 102, with heat smoke haptoreaction.While desulfuration efficiency raising being reduced due to temperature, the vapour of doctor solution Rate is reduced, and desulfurizing tower internal steam concentration greatly reduces, and prerequisite is provided in vain for flue gas is de-.
During main smoke airflow is through the rapid ball condensing unit 103 of tube bank and demister 104, condensate water circulatory storage tank 8 The condensed liquid pump 13 of interior circulating condensing liquid pressurizes and after the cooling of subcooling condensate plate heat exchanger 14 through pipeline and nozzle, certainly super The grade tube bank rapids bottoms ball dedusting demister A are inversely spraying with flue gas flow direction downwards, and a small amount of water mist is acted in main flue gas upflow velocity Under enter together with main flue gas from the bottoms super tube bank rapids ball dedusting demister A, baffle at bottom effect under make multi-change speed With deflecting campaign, make between the drop and drop of the different-grain diameter in flue gas, between micronic dust and micronic dust, is sent out between drop and micronic dust Raw collision, to coalescence, grain size becomes larger, and in the case where the eddy flow power of flue gas is acted on upward towing force, keeps turbulence sphere " public in tube bank Turn ", so that all turbulence spheres is generated " rotation " in the effect of the lower layer's ball revolution power and frictional force of turbulence sphere.
And flue gas, when impacting turbulence sphere, the water mist in flue gas is attracted on turbulence sphere, and more droplet is adsorbed on On turbulence sphere, then the surface of turbulence sphere forms moisture film, and more drops, which are adsorbed on, makes the moisture film on turbulence sphere thicken on turbulence sphere And water droplet is formed, desorption discharge;Micronic dust is equally adsorbed by liquid film, is desorbed with drop and big drop is discharged, under the effect of gravity The super tube bank rapids ball dedusting demister B that super tube bank rapids ball dedusting demister bottom enters lower part together with spray liquid is discharged, Clean flue gas is discharged from the super tube bank rapids ball dedusting demister on top, what most low temperature spray liquids took off with top Drop containing micro grit is mixed with main flue gas adverse current, to absorb the heat in flue gas, makes flue gas cool-down, at the same absorb with it is molten Enter harmful substance such as SO3, SO2 in flue gas, micronic dust etc., then is removed under the effect of gravity into the super tube bank rapids ball dedusting of lower layer Day with fog B.
It is and inverse on the one hand due to the continuous variation of air velocity after condensate liquid enters super tube bank rapids ball dedusting demister B The impact of flowing liquid makes drop generate more another typical material and increase the contact area with main flue gas;On the other hand, turbulator Surface area it is very big, surface is all that the surface area of liquid film and smoke contacts is also very big, to improve heat of solution absorbing reaction Efficiency, so that flue gas is sufficiently achieved cooling, the harmful substance in flue gas made fully to be taken away by liquid, contain in temperature-fall period Central Plains Due to being cooled down, the strain of water vapour liquid phase is removed the flue gas of saturated vapor at water, is finally all flowed under the influence of gravity into The lower resistance water collector of bottom, then the flow ipe from lower resistance water collector annular groove, be discharged into condensing soln circulating tank after It is continuous to recycle.
Due to the process also absorption with solution to sulfur dioxide cooled down to flue gas, in condensate water circulatory after gradually concentrating Bottom has a small amount of ammonium sulfate precipitation object in storage tank 8, and partly precipitated object is sent to film separation system 12 by pumping.
The preferred embodiment of the present invention has been described in detail above.It should be appreciated that the ordinary skill of this field is without wound The property made labour, which according to the present invention can conceive, makes many modifications and variations.Therefore, all technician in the art Pass through the available technology of logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea Scheme, all should be in the protection domain being defined in the patent claims.

Claims (10)

1. a kind of flue gas depth takes off white minimum discharge device, which is characterized in that including desulfurizing tower, heat exchange of heat pipe A, air-introduced machine and Take off white device;
The desulfurizing tower includes that desulfurizing tower carries effect tower tray, and desulfurizing tower spraying layer restrains rapid ball condensing unit, demister and desulfurization Tower exports;
The heat exchange of heat pipe A is connect by the air-introduced machine with the desulfurizing tower;In the inside of the desulfurizing tower, from bottom to top It has been sequentially arranged the desulfurizing tower and has put forward effect tower tray, the desulfurizing tower spraying layer, the rapid ball condensing unit of the tube bank and the demisting Device;Between the demister and desulfurizing tower outlet, the desulfurizing tower is circumscribed with the de- white device, including drop Separator, heat exchange of heat pipe B take off white temperature raising wind turbine and the first electric control valve;The liquid drop separator and the heat pipe heat exchanging One end of device B connects, and the other end of the heat exchange of heat pipe B is connected with the de- white temperature raising wind turbine, described to take off white temperature raising wind turbine It is connected with first electric control valve again, it is described after de- white temperature raising flue gas is adjusted in first electric control valve It takes off white temperature raising flue gas to export into the desulfurizing tower, be discharged after being mixed with main flue gas.
2. flue gas depth as described in claim 1 takes off white minimum discharge device, which is characterized in that the heat exchange of heat pipe A with The heat exchange of heat pipe B is close together;The heat exchange of heat pipe A is high temperature heat pipe heat exchanger, is cooled down to flue gas;The heat Heat exchange of heat pipe B is low temperature heat pipe heat exchanger, is heated to flue gas.
3. flue gas depth as described in claim 1 takes off white minimum discharge device, which is characterized in that the heat exchange of heat pipe A's Flue gas circulation is 37 ten thousand steres/hour, and the flue gas circulation of the heat exchange of heat pipe B is 12 ten thousand steres/hour.
4. flue gas depth as described in claim 1 takes off white minimum discharge device, which is characterized in that outside the desulfurizing tower spraying layer It is connected to main desulfurization pump and doctor solution plate heat exchanger;The doctor solution of the main desulfurization pump discharge passes through the doctor solution plate-type heat-exchange After device cooling, the doctor solution enters the desulfurizing tower spraying layer inside the desulfurizing tower, with heat smoke haptoreaction.
5. flue gas depth as described in claim 1 takes off white minimum discharge device, which is characterized in that the rapid ball condensation dress of the tube bank It sets and is connected to condensate water circulatory storage tank successively, condensate pump, condensate liquid plate heat exchanger is attached by pipeline each other, Form a set of circulation condensation device;The condensed water generated later is being condensed to flue gas by the liter gas inside the desulfurizing tower Flue gas condensing water is flow to the condensate water circulatory storage tank by the pipeline and stored by water collector, the condensate water circulatory After condensed water in storage tank carries out cooling using condensate pump pressurization and the condensate liquid plate heat exchanger, by the pipe Road enters the rapid ball condensing unit of the tube bank and continues cooled flue gas.
6. flue gas depth as claimed in claim 5 takes off white minimum discharge device, which is characterized in that the condensate water circulatory storage tank Will produce partly precipitated object after recycling for a long time, through pump pressurization by the condensate water circulatory storage tank condensed water and Sediment is sent to sediment piece-rate system, and extra condensed water is handled by being pumped to advanced treatment of wastewater using film separation system The extra condensed water is used as system circulating water moisturizing circulation afterwards;Water in the condensate water circulatory storage tank is mended by technique Water is supplemented, and the technique moisturizing comes from technique water tank.
7. flue gas depth as described in claim 1 takes off white minimum discharge device, which is characterized in that described to take off white temperature raising wind turbine pair Flue gas pressurizes, and the air quantity for taking off white temperature raising wind turbine is 12 ten thousand steres/hour.
8. flue gas depth as described in claim 1 takes off white minimum discharge device, which is characterized in that described to take off white temperature raising wind turbine It is connect with the second electric control valve, second electric control valve enters kiln to described take off after white temperature raising flue gas is adjusted Former chimney is hot standby;The flue gas circulation of first electric control valve is 5-6 ten thousand steres/hour, second motorized adjustment The flue gas circulation of valve is 6-7 ten thousand steres/hour.
9. flue gas depth as described in claim 1 takes off white minimum discharge device, which is characterized in that the height of the desulfurizing tower is 70 meters.
10. a kind of method that flue gas depth takes off white minimum discharge, which is characterized in that the described method comprises the following steps:
Step 1, main flue gas exchanged heat into the heat exchange of heat pipe A after by the air-introduced machine enter the desulfurizing tower, institute It is the flue gas after boiler or kiln dedusting to state main flue gas, is 150 DEG C -180 DEG C in the temperature for entering the heat exchange of heat pipe A, institute It states temperature of the main flue gas into the desulfurizing tower after heat exchange and is reduced to 100 DEG C -140 DEG C;
Step 2, the main flue gas pass sequentially through the desulfurizing tower and carry effect tower tray from bottom to top after entering in the desulfurizing tower With the desulfurizing tower spraying layer, the temperature of the main flue gas will drop to 55 DEG C -65 DEG C after by the desulfurizing tower spraying layer;
Step 3, main flue gas continuation pass sequentially through the rapid ball condensing unit of the tube bank and the demister from below to up, into Row condensation desulfurization and dedusting demisting dehydration, condensed discharge flue-gas temperature is≤45 DEG C -47 DEG C, dust content<10mg/Nm3
25% to 35% discharge flue gas carries out de- white processing by the de- white device in step 4, the step 3, first passes through The liquid drop separator enters back into the heat exchange of heat pipe B, between the discharge flue gas is warming up to 130 DEG C -160 DEG C, then It is divided into two-way under the de- white temperature raising fan action, wherein it is connected with first electric control valve all the way, first electricity After the de- white temperature raising flue gas is adjusted in dynamic regulating valve, the de- white temperature raising flue gas is exported into the desulfurizing tower, with 65% to the 75% discharge flue gas is discharged after being mixed in step 3, and mixed flue-gas temperature is 68 DEG C -75 ℃。
CN201810942555.6A 2018-08-17 2018-08-17 Deep-whitening ultralow-emission device and method for flue gas Active CN108722162B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810942555.6A CN108722162B (en) 2018-08-17 2018-08-17 Deep-whitening ultralow-emission device and method for flue gas

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810942555.6A CN108722162B (en) 2018-08-17 2018-08-17 Deep-whitening ultralow-emission device and method for flue gas

Publications (2)

Publication Number Publication Date
CN108722162A true CN108722162A (en) 2018-11-02
CN108722162B CN108722162B (en) 2023-11-24

Family

ID=63942979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810942555.6A Active CN108722162B (en) 2018-08-17 2018-08-17 Deep-whitening ultralow-emission device and method for flue gas

Country Status (1)

Country Link
CN (1) CN108722162B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109107328A (en) * 2018-11-05 2019-01-01 南京普兰特换热设备有限公司 It solves desulfurization fume and takes off white method and desulphurization system
CN109550382A (en) * 2018-12-04 2019-04-02 北京朗净时代环境科技有限公司 A kind of desulfuration boiler flue gas purification device
CN109569172A (en) * 2018-11-30 2019-04-05 佛山丰汇环保工程有限公司 A kind of self-loopa flue gas takes off white device
CN110180314A (en) * 2019-04-15 2019-08-30 江苏现代路桥有限责任公司 The white processing unit that disappears of station tail gas is mixed in a kind of drip
CN110935277A (en) * 2019-12-25 2020-03-31 河南心连心化学工业集团股份有限公司 Coal chemical industry solid waste drying tail gas treatment device and treatment method
CN114590861A (en) * 2022-03-24 2022-06-07 万华化学集团股份有限公司 Low-energy-consumption deoxygenation device and low-energy-consumption deoxygenation process

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101259364A (en) * 2008-04-16 2008-09-10 中冶华天工程技术有限公司 Wet desulphurization technique for sintered flue gas
JP2015000360A (en) * 2013-06-14 2015-01-05 バブコック日立株式会社 Exhaust gas treatment device and exhaust gas treatment method
CN107019988A (en) * 2017-05-24 2017-08-08 北京化工大学苏州(相城)研究院 The application of flue gas desulphurization system and method and sulfur recovery tail gas incinerator
CN107261699A (en) * 2017-06-15 2017-10-20 上海交通大学 A kind of apparatus and method of the ultra-clean dedusting eliminating white smoke of desulfurization fume
CN107321161A (en) * 2017-08-04 2017-11-07 江苏科行环保科技有限公司 A kind of single column desulfurization cooperates with dedusting minimum discharge device
CN108211748A (en) * 2018-03-27 2018-06-29 陕西大秦环境科技有限公司 A kind of desulfurization white-smoke-removing device and technique
CN108355457A (en) * 2018-04-24 2018-08-03 青岛达能环保设备股份有限公司 Wet desulfurization flue gas disappears white system
CN207708561U (en) * 2017-12-26 2018-08-10 北京盛聚福科技有限公司 A kind of demisting based on flue gas after catalytic cracking and desulfurizing disappears white system
CN209020165U (en) * 2018-08-17 2019-06-25 安徽金森源环保工程有限公司 A kind of flue gas depth takes off white minimum discharge device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101259364A (en) * 2008-04-16 2008-09-10 中冶华天工程技术有限公司 Wet desulphurization technique for sintered flue gas
JP2015000360A (en) * 2013-06-14 2015-01-05 バブコック日立株式会社 Exhaust gas treatment device and exhaust gas treatment method
CN107019988A (en) * 2017-05-24 2017-08-08 北京化工大学苏州(相城)研究院 The application of flue gas desulphurization system and method and sulfur recovery tail gas incinerator
CN107261699A (en) * 2017-06-15 2017-10-20 上海交通大学 A kind of apparatus and method of the ultra-clean dedusting eliminating white smoke of desulfurization fume
CN107321161A (en) * 2017-08-04 2017-11-07 江苏科行环保科技有限公司 A kind of single column desulfurization cooperates with dedusting minimum discharge device
CN207708561U (en) * 2017-12-26 2018-08-10 北京盛聚福科技有限公司 A kind of demisting based on flue gas after catalytic cracking and desulfurizing disappears white system
CN108211748A (en) * 2018-03-27 2018-06-29 陕西大秦环境科技有限公司 A kind of desulfurization white-smoke-removing device and technique
CN108355457A (en) * 2018-04-24 2018-08-03 青岛达能环保设备股份有限公司 Wet desulfurization flue gas disappears white system
CN209020165U (en) * 2018-08-17 2019-06-25 安徽金森源环保工程有限公司 A kind of flue gas depth takes off white minimum discharge device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109107328A (en) * 2018-11-05 2019-01-01 南京普兰特换热设备有限公司 It solves desulfurization fume and takes off white method and desulphurization system
CN109569172A (en) * 2018-11-30 2019-04-05 佛山丰汇环保工程有限公司 A kind of self-loopa flue gas takes off white device
CN109550382A (en) * 2018-12-04 2019-04-02 北京朗净时代环境科技有限公司 A kind of desulfuration boiler flue gas purification device
CN110180314A (en) * 2019-04-15 2019-08-30 江苏现代路桥有限责任公司 The white processing unit that disappears of station tail gas is mixed in a kind of drip
CN110935277A (en) * 2019-12-25 2020-03-31 河南心连心化学工业集团股份有限公司 Coal chemical industry solid waste drying tail gas treatment device and treatment method
CN114590861A (en) * 2022-03-24 2022-06-07 万华化学集团股份有限公司 Low-energy-consumption deoxygenation device and low-energy-consumption deoxygenation process
CN114590861B (en) * 2022-03-24 2023-08-11 万华化学集团股份有限公司 Low-energy-consumption deoxidizing device and low-energy-consumption deoxidizing process

Also Published As

Publication number Publication date
CN108722162B (en) 2023-11-24

Similar Documents

Publication Publication Date Title
CN108722162A (en) A kind of flue gas depth takes off white minimum discharge apparatus and method
CN108434924B (en) System and method for eliminating white smoke from smoke
CN206810050U (en) A kind of flue gas of wet desulphurization disappears white system
CN109289430B (en) Dry-wet coupling integrated smoke whitening and dust removing device
CN107261699A (en) A kind of apparatus and method of the ultra-clean dedusting eliminating white smoke of desulfurization fume
CN107930309B (en) Wet smoke plume eliminating system
CN107008119A (en) A kind of device and method for eliminating the wet misty rain of wet desulphurization
CN108465340B (en) White smoke plume eliminating device and method
CN103868087A (en) Method and device for cooperatively enhancing PM2.5 (Particulate Matter 2.5) removal and smoke afterheat deep utilization
CN110102139B (en) Method for removing white in boiler flue gas through multi-stage heat exchange
CN110124465B (en) Low-energy-consumption wet flue gas water-receiving and white-removing device and method
CN107042048B (en) Gravity heat pipe type demisting method and demisting device
CN109772071A (en) White plume based on upper spray upper air spray column eliminates system
CN106914124A (en) The heat pipe heat exchanging water saving anti-gypsum rain device of demisting in wet desulfuration tower
CN108421399A (en) Collaboration promotes fine particle and the devices and methods therefor of sulfur trioxide acid mist removing in a kind of process of wet desulphurization of single column two-region
CN108926953A (en) One kind condensing again steam-heated white plume governing system based on fluorine plastic-steel
CN108144383A (en) Flue gas pollutant processing system and processing method, chimney
CN109099451A (en) A kind of flue gas energy-saving and emission-reduction disappear Bai Wuchong heat-exchange system
CN209714650U (en) The baffle plate type demisting deduster of built-in cooling
CN107158913A (en) A kind of apparatus and method of the ultra-clean dedusting of desulfurization fume
CN208200434U (en) A kind of Waste water concentrating liquid stream crystallizing and drying system of flue gas direct emission
CN209020165U (en) A kind of flue gas depth takes off white minimum discharge device
CN109663490A (en) Wet desulfurization flue gas condenser system and flue gas condensing method with water balance function
CN108325747B (en) A kind of electrostatic precipitation system of heat pipe and the subregion humidification dry-wet-coupled based on desulfurization wastewater processing
CN111569630B (en) Wet desulfurization system and wet desulfurization method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant