CN108678398A - A kind of high-rise building enhancement layer steel structure truss pre-assembly method - Google Patents

A kind of high-rise building enhancement layer steel structure truss pre-assembly method Download PDF

Info

Publication number
CN108678398A
CN108678398A CN201810792200.3A CN201810792200A CN108678398A CN 108678398 A CN108678398 A CN 108678398A CN 201810792200 A CN201810792200 A CN 201810792200A CN 108678398 A CN108678398 A CN 108678398A
Authority
CN
China
Prior art keywords
truss
landing slab
plate
semi
preassembling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810792200.3A
Other languages
Chinese (zh)
Other versions
CN108678398B (en
Inventor
徐国友
宋林
吴晓波
刘波
余海林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201810792200.3A priority Critical patent/CN108678398B/en
Publication of CN108678398A publication Critical patent/CN108678398A/en
Application granted granted Critical
Publication of CN108678398B publication Critical patent/CN108678398B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of high-rise building enhancement layer steel structure truss pre-assembly methods, include the following steps:1)Pre-splicing assembling platform is set up on ground in factory;2) enhancement layer truss is divided into three parts by structural plane:Semi-girder truss portion and outer shroud truss portion are chosen outside Core Walls Structure inner ring truss portion, Core Walls Structure, each part is then divided into multiple components using BIM technology;3)Core Walls Structure inner ring truss portion preassembling;4)Semi-girder truss portion preassembling is chosen outside Core Walls Structure;5)Outer shroud truss portion preassembling.The present invention is that preassembling is more convenient using the scheme for spelling system one, accuracy and reliability higher, and can effectively improve assembled efficiency;And then it is more convenient to make to build the construction of truss enhancement layer, can reduce construction cost.

Description

A kind of high-rise building enhancement layer steel structure truss pre-assembly method
Technical field
The present invention relates to construction articles for use field more particularly to a kind of high-rise building enhancement layer steel structure truss are pre-splicing Dress method.
Background technology
With flourishing for China's steel building, high-rise building is gradually sent out to functional diversities, complicatedization Exhibition, more and more skyscrapers need to be tied with the lateral resisting structure system of outer framework+Core Walls Structure+enhancement layer semi-girder truss etc. to meet Structure design requirement.Enhancement layer is set in skyscraper, the requirement of architectural plane function can be met and meets the strong of structure Degree is stablized, the requirement of displacement and ductility.Wherein, contilever structure connects external frame and Core Walls Structure, enhances structure Globality gives full play to space mass action, to further enhance the whole anti-side rigidity of structure.Meanwhile as building is high Degree gradually increases, and enhancement layer structure also tends to node complication, diversification of forms, the development of component enlargement feature.
High-rise building enhancement layer suffers from that complicated, special-shaped, the scale of construction is big, quality requirement is high, and the number of components is more, size Greatly, the big feature of steel plate thickness welding capacity.When carrying out entity preassembling, it is big often to be faced with the usual scale of construction of enhancement layer structure, work Work amount is big, and the duration is nervous, and scene is no longer assembled, and the case where require component to dispatch from the factory by schedule requirement sequence.Enhancement layer entirety ruler Very little big, preassembling need to occupy larger place, and place is limited, can not provide the field of large-scale truss integral assembling in usual processing factory Ground can only select to carry out preassembling in open area.But this needs special preparation preassembling place, adds special preassembling tire Frame, and open area usually lacks large-tonnage bridge crane equipment.The limitation of these internal, external many factors, increases work It measures, increases processing cost, increase the pressure for ensureing quality and progress, be the pre- of high-rise building enhancement layer semi-girder truss Assembly causes adverse effect.
Invention content
For deficiencies of the prior art, it is an object of the invention to solve the construction of skyscraper truss enhancement layer Trouble, heavy workload, preassembling are inconvenient, low construction efficiency, and accuracy is low, poor reliability, and the problem that construction cost is high, A kind of high-rise building enhancement layer steel structure truss pre-assembly method is provided, preassembling is more convenient, and accuracy and reliability is more Height, and assembled efficiency can be effectively improved;And then it is more convenient to make to build the construction of truss enhancement layer, can reduce construction cost.
In order to solve the above-mentioned technical problem, the technical solution adopted by the present invention is such:A kind of high-rise building reinforcement Layer steel structure truss pre-assembly method, it is characterised in that:Include the following steps:
1)Pre-splicing assembling platform is set up on ground in factory:The pre-splicing assembling platform includes several first H profile steels and landing slab, described First H profile steel is mutually parallel, and the top flange plate of all first H profile steels is located in same level, adjacent two first H profile steels it Between spacing be 0.5-1m;The landing slab be layed on the top flange plate of the first H profile steel and with the top flange of the first H profile steel Plate is fixedly connected, and the length direction of landing slab is vertical with the length direction of the first H profile steel;Wherein, the landing slab is by several Steel plate welds to be formed;
2) enhancement layer truss is divided into three parts by structural plane:Semi-girder truss is chosen outside Core Walls Structure inner ring truss portion, Core Walls Structure Part and outer shroud truss portion, are then divided into multiple components using BIM technology by each part;
3)Core Walls Structure inner ring truss portion preassembling:
A, according to preassembling scheme, line-transect, described ground line-transect include core with drawing Core Walls Structure inner ring truss portion on landing slab The corresponding axis of heart cylinder inner ring truss portion and elevation line, and indicate projection line of the core inner cylinder truss portion on landing slab And layout point;
B, on landing slab, the position of corresponding corner post is laid with one group of corner post supporting rack respectively, and the corner post supporting rack includes along flat Three second H profile steels of platen width direction distribution, the length direction of second H profile steel is consistent with the length direction of landing slab, And second H profile steel is detachably connected with landing slab;It is equipped with the first female vertically on the top flange plate of the second H profile steel Plate, plane where first concave template cross the center line of the top flange plate of the second H profile steel, and detachable with the second H profile steel Connection;First concave template has a locating slot through side thereon, the preassembling of corner post can be made to connect by the locating slot Side is located at vertical plane;Interior truss support frame is equipped between two groups of corner post supporting racks, the interior truss support frame includes at least Three third H profile steels along the distribution of landing slab length direction, the length direction of the third H profile steel and the width direction one of landing slab It causes, and is detachably connected with landing slab;
C, Core Walls Structure corner post is individually placed in the first concave template of two groups of corner post supporting racks, and two corner posts is made to be connected with truss Side it is opposite;Wherein, the Core Walls Structure corner post is divided into upper prop and lower prop, adjusts the position of Core Walls Structure corner post, makes Core Walls Structure angle Layout point on column coincides with the layout point on ground line-transect, then carries out temperature pier to the junction of upper prop and lower prop;So The preassembling box bracket on two corner posts afterwards, and adjust to after being overlapped with the projection line on landing slab, then box bracket is interim It is fixed;
D, truss plate in lower layer is lifted on truss support frame by driving a vehicle, wherein truss plate includes winding up in the lower layer Beam lower plywood, lower-cord beam lower plywood and diagonal web member lower plywood;In hoisting process, lifting successively is winded up under beam lower plywood, lower-cord beam Laminate and diagonal web member lower plywood, then adjust to the projection line on landing slab and overlap, then be fixed temporarily;
E, the position line that truss inner prop, truss inner beam and truss connecting plate are drawn on lower layer's truss plate, is then sequentially placed purlin Frame inner prop, truss inner beam and truss connecting plate;Upper layer truss plate is lifted into truss inner prop, truss inner beam and purlin by driving a vehicle again Above frame connecting plate, the upper layer truss plate includes wind up beam top plate, lower-cord beam top plate and diagonal web member top plate;It lifted Cheng Zhong lifts wind up beam top plate, lower-cord beam top plate and diagonal web member top plate successively, after then adjusting position to qualification, then It is fixed temporarily;
F, the gap between each parts of detection, levelness, complete preassembling;
G, according to using BIM technology divide component, carry out the welding of parts, make each component be respectively formed one it is independent whole Body;
H, step A-H is repeated, until entire Core Walls Structure inner ring truss portion preassembling is completed;
4)Semi-girder truss portion preassembling is chosen outside Core Walls Structure:
A, by landing slab truss support frame and one of which corner post supporting rack remove, while wiping the ground sample on landing slab Line, projection line and layout point;
B, it based on remaining one group of corner post supporting rack, is drawn on landing slab outside Core Walls Structure and chooses semi-girder partly line-transect, and It indicates and chooses projection line and layout point of the semi-girder part on landing slab outside Core Walls Structure;
C, on landing slab, one group of exterior frame column supporting rack is arranged in the position of corresponding exterior frame column, and the exterior frame column supporting rack includes extremely Few three the 4th H profile steels along the distribution of landing slab width direction, the length direction of the length direction and landing slab of the 4th H profile steel Unanimously, and the 4th H profile steel is detachably connected with landing slab;The second female is equipped on the top flange plate of the 4th H profile steel Plate, plane where second concave template cross the center line of the top flange plate of the 4th H profile steel, and detachable with the 4th H profile steel Connection;Between corner post supporting rack and exterior frame column supporting rack, the position of corresponding wind up beam, lower-cord beam and diagonal web member is provided with outer choose Semi-girder truss support frame;It includes at least two the 5th H being distributed along landing slab length direction to choose semi-girder truss support frame outside described The length direction of shaped steel, the 5th H profile steel is consistent with the width direction of landing slab;
D, corner post and exterior frame column are put into corresponding concave template, and make to choose the one of semi-girder truss outside corner post and exterior frame column installation Side is opposite, and then the preassembling box bracket on corner post and exterior frame column, then adjusts to the projection line on landing slab and overlap, then Box bracket is fixed temporarily;
E, semi-girder truss plate will be chosen by driving outside lower layer and be lifted into outer choose on semi-girder supporting rack, wherein choose and stretch outside the lower layer Arm truss plate includes wind up beam lower plywood, lower-cord beam lower plywood and oblique web grider lower plywood;In hoisting process, the beam that winds up is lifted successively Lower plywood, lower-cord beam lower plywood and oblique web grider lower plywood, then adjust to the projection line on landing slab and overlap, then carry out interim It is fixed;Then placement semi-girder connecting plate on semi-girder truss plate is chosen outside lower layer;Again semi-girder truss plate will be chosen by driving outside upper layer It is lifted into above semi-girder connecting plate, it includes wind up beam top plate, lower-cord beam top plate and oblique that semi-girder truss plate is chosen outside the upper layer Web grider top plate after then adjusting position to qualification, then is fixed temporarily;
F, the gap between each parts of detection, levelness, complete preassembling;
G, according to using BIM technology divide component, carry out the welding of parts, make each component be respectively formed one it is independent whole Body;
H, step A-H is repeated, is completed until choosing semi-girder part preassembling outside all Core Walls Structures;
5)Outer shroud truss portion preassembling:
A, outer on landing slab is chosen into semi-girder supporting rack and corner post supporting rack is removed, while wiped the ground line-transect on landing slab, throwing Hachure and layout point;
B, the position for adjusting exterior frame column supporting rack on landing slab is painted then based on the exterior frame column supporting rack on landing slab Outer shroud truss portion processed ground line-transect, and indicate projection line and layout point of the outer shroud truss portion on landing slab;
C, on landing slab, one group of exterior frame column supporting rack is arranged in the position of corresponding another exterior frame column again;It is supported in two groups of exterior frame columns Outer shroud truss element supporting rack is set between frame;The outer shroud truss element supporting rack includes at least two along landing slab length side To the 6th H profile steel of distribution, the length direction of the 6th H profile steel is consistent with the width direction of landing slab, and removable with landing slab Unload connection;
D, another exterior frame column is put into corresponding second concave template, and the side phase that two exterior frame columns are connected with ring truss To then box bracket, is then fixed temporarily by the pre- bottled box bracket on corner post and exterior frame column;
E, lower layer's outer shroud truss element plate is lifted on outer shroud truss element supporting rack by driving a vehicle, wherein outside the lower layer Ring truss element plate includes upper beam lower plywood, underbeam lower plywood and the oblique web grider lower plywood of X-shaped;In hoisting process, successively in lifting Beam lower plywood, underbeam lower plywood and the oblique web grider lower plywood of X-shaped, then adjust to the projection line on landing slab and overlap, then carry out It is fixed temporarily;Then connecting plate is placed on lower layer's outer shroud truss element plate;Again by driving a vehicle upper layer outer shroud truss element plate It is lifted into above semi-girder connecting plate, the upper layer outer shroud truss element plate includes upper beam top plate, underbeam top plate and the oblique abdomen of X-shaped Beam top plate after then adjusting position to qualification, then is fixed temporarily;
F, the gap between each parts of detection, levelness, complete preassembling;
G, according to using BIM technology divide component, carry out the welding of parts, make each component be respectively formed one it is independent whole Body;
H, step A-H is repeated, until all Core Walls Structure outer shroud truss portion preassemblings are completed.
Further, semi-girder truss portion is chosen outside Core Walls Structure inner ring truss portion, Core Walls Structure and outer shroud truss portion is pre- During assembly, when repeating A-H steps, it is both needed to the placement status according to corner post and/or exterior frame column, replaces corresponding female Plate, to ensure corner post and/or exterior frame column and interior truss or outer choose semi-girder truss or ring truss is located at same level.
Further, in the placement process of corner post and exterior frame column, according to layout point, using level meter and sash weight to steel column Position test.
Further, it detects gap between each parts, during levelness, examined by steel tape, level meter It surveys.
Further, in detection process, the mismatch between each parts closes requirement, is indicated and is remembered Record forms preassembling original position parameter and checks table.
Compared with prior art, the invention has the advantages that:
1, it is directed to element structure complexity feature, using the thought of " system spells one ", the welding processing link of partial component is incorporated During preassembling, workload is reduced, cost is reduced, realizes energy saving green processing.
2, big for the component scale of construction in enhancement layer, complicated, the similar feature of structure composition has formulated small lot dress Technological process with formula production is split component by class, classification processing, and the parts unification of same type is processed, is finally spelled Dress is processed into integral component;Simultaneously, it is possible to reduce process intersects, increases utilization of area rate, reduces cost, is also convenient for component Processing quality carries out grading control.
3, by the way of horizontal assembly in factory, factory's internally-fixed assembly platform and supporting rack in bulk are applied in combination, Can in Same Site alternately component assembly work and preassembling work, workload is reduced in a manner of relatively inexpensive; Suitable for the preassembling of enhancement layer truss that is continuous in processing factory, quickly carrying out large span, the big scale of construction, duration anxiety, it is not necessarily to Special preassembling place.
4, it is limited to be directed to place in processing factory, process time urgent feature, by Core Walls Structure inner ring truss portion, Core Walls Structure It chooses semi-girder truss portion outside and outer shroud truss portion is respectively classified into several preassembling components, it is pre- to carry out continuous coupling by manufacture requirement Assembly reduces place and occupies, reduces high-rise working.
5, for the component welded again after preassembling, the parameter check table in situ recorded when using preassembling is to the component Preassembling postwelding check is carried out, ensures component processing quality.
Description of the drawings
Fig. 1 is the structural schematic diagram of pre-splicing assembling platform.
Fig. 2 is Core Walls Structure inner ring truss preassembling jig structure schematic diagram.
Fig. 3 is the side view of Fig. 2.
Fig. 4 is semi-girder truss preassembling jig structure schematic diagram.
Fig. 5 is outer shroud truss preassembling jig structure schematic diagram.
Fig. 6 is the partition structure schematic diagram of Core Walls Structure inner ring truss portion.
Fig. 7 is the partition structure schematic diagram that semi-girder truss portion is chosen outside Core Walls Structure.
Fig. 8 is the partition structure schematic diagram of outer shroud truss portion.
In figure:1-the first H profile steel, 2-landing slabs, the 3-the second H profile steel, 4-third H profile steels, the 5-the first female Plate, the 6-the four H profile steel, the 7-the five H profile steel, the 8-the second concave template, the 9-the six H profile steel.
In Fig. 6-Fig. 8, dotted line frame is the schematic diagram of each component divided.
Specific implementation mode
Present invention will be further explained below with reference to the attached drawings and examples.
Embodiment:Referring to Fig. 1 to Fig. 8, a kind of high-rise building enhancement layer steel structure truss pre-assembly method, including it is as follows Step:
1)Pre-splicing assembling platform is set up on ground in factory:The pre-splicing assembling platform includes several first H profile steels 1 and landing slab 2, institute It states the first H profile steel 1 to be mutually parallel, and the top flange plate of all first H profile steels 1 is located in same level, adjacent two first H-types Spacing between steel 1 is 0.5-1m;The landing slab 2 be layed on the top flange plate of the first H profile steel 1 and with the first H profile steel 1 Top flange plate be fixedly connected, and the length direction of landing slab 2 is vertical with the length direction of the first H profile steel 1;Wherein, described flat Platen 2 is welded by several steel plates and is formed.During assembly, first of first H profile steels 1 are placed at higher position, use level Instrument ensures that its upper level is consistent, on the basis of the upper level of first of first H profile steels 1, often places the first H-type together Steel 1 just examines its upper level using level meter, and a test point is arranged every 1.5m on length direction, highly inconsistent When, it is adjusted by gasket;Bracing wire method is utilized simultaneously, examines all overall surface flatness for having spread the first H profile steel 1, it is ensured that 1 surface of the first H profile steel is spread in same level.Wherein, landing slab 2 is tiled by 30mm steel plates;When laying, ensure steel Plate length direction and the length direction of the first H profile steel 1 are orthogonal, and the gap of 5mm is reserved between adjacent two steel plates, and pass through Electric welding mode makes steel plate be connected with each other;Meanwhile it is levelling using level meter and the progress of bracing wire method, ensure entire workbench flatness In 3mm, every steel plate is uniformly arranged 9 monitoring points, using level meter detection surface level thereon, to undesirable place into Row finishing.
2) enhancement layer truss is divided into three parts by structural plane:Semi-girder is chosen outside Core Walls Structure inner ring truss portion, Core Walls Structure Then each part is divided into multiple components by truss portion and outer shroud truss portion using BIM technology;Specific implementation process In, various pieces are divided into multiple components in one direction using BIM technology.
3)Core Walls Structure inner ring truss portion preassembling:
A, according to preassembling scheme, line-transect, described ground line-transect include core with drawing Core Walls Structure inner ring truss portion on landing slab 2 The corresponding axis of heart cylinder inner ring truss portion and elevation line, and indicate projection of the core inner cylinder truss portion on landing slab 2 Line and layout point.
B, on landing slab 2, the position of corresponding corner post is laid with one group of corner post supporting rack respectively, and the corner post supporting rack includes At least three the second H profile steels 3 along the distribution of 2 width direction of landing slab, the length of the length direction and landing slab 2 of second H profile steel 3 It is consistent to spend direction, and second H profile steel 3 is detachably connected with landing slab 2;It is set vertically on the top flange plate of the second H profile steel 3 There is the first concave template 5, first concave template, 5 place plane crosses the center line of the top flange plate of the second H profile steel 3, and with Second H profile steel 3 is detachably connected;First concave template 5 has a locating slot through side thereon, can be made by the locating slot The preassembling connection side of corner post is located at vertical plane;Interior truss support frame, the interior purlin are equipped between two groups of corner post supporting racks Frame supporting rack includes at least three third H profile steels 4 being distributed along 2 length direction of landing slab, the length direction of the third H profile steel 4 It is consistent with the width direction of landing slab 2, and be detachably connected with landing slab 2.
C, Core Walls Structure corner post is individually placed in the first concave template 5 of two groups of corner post supporting racks, and makes two corner posts and purlin The connected side of frame is opposite;Wherein, the Core Walls Structure corner post is divided into upper prop and lower prop, adjusts the position of Core Walls Structure corner post, makes core Layout point on heart cylinder corner post coincides with the layout point on ground line-transect, then to the junction of upper prop and lower prop temporarily add Gu;Then the preassembling box bracket on two corner posts is adjusted to after being overlapped with the projection line on landing slab 2, then by box bracket It is fixed temporarily.
D, truss plate in lower layer is lifted on truss support frame by driving a vehicle, wherein truss plate includes in the lower layer Wind up beam lower plywood, lower-cord beam lower plywood and diagonal web member lower plywood;In hoisting process, wind up beam lower plywood, lower edge are lifted successively Beam lower plywood and diagonal web member lower plywood, then adjust to the projection line on landing slab 2 and overlap, then be fixed temporarily.
E, the position line that truss inner prop, truss inner beam and truss connecting plate are drawn on lower layer's truss plate, then puts successively Set truss inner prop, truss inner beam and truss connecting plate;Upper layer truss plate is lifted into truss inner prop, truss inner beam by driving a vehicle again Above truss connecting plate, the upper layer truss plate includes wind up beam top plate, lower-cord beam top plate and diagonal web member top plate;It hangs During dress, wind up beam top plate, lower-cord beam top plate and diagonal web member top plate are lifted successively, then adjust position to qualification Afterwards, it then is fixed temporarily.
F, the gap between each parts of detection, levelness, complete preassembling.
G, according to the component divided using BIM technology, the welding of parts is carried out, each component is made to be respectively formed an independence Entirety.
H, step A-H is repeated, until entire Core Walls Structure inner ring truss portion preassembling is completed.In specific implementation process, by It in the adjacent both sides of each corner post is both needed to that interior truss is installed, therefore, in the process, a wherein corner post need to only be removed, then Another corner post is moved on the corner post supporting rack for removing corner post, and turns to another installation side, then replaces corresponding the One concave template 5 is fixed;The corner post adjacent with the corner post side is lifted again carries out installation positioning;Then step C-H is repeated; So as to further save pre-splicing ETL estimated time of loading, preassembling efficiency is improved.
4)Semi-girder truss portion preassembling is chosen outside Core Walls Structure:
A, by landing slab 2 truss support frame and one of which corner post supporting rack remove, while wiping the ground sample on landing slab 2 Line, projection line and layout point.
B, it based on remaining one group of corner post supporting rack, is drawn on landing slab 2 outside Core Walls Structure and chooses semi-girder partly sample Line, and indicate and choose projection line and layout point of the semi-girder part on landing slab 2 outside Core Walls Structure.
C, on landing slab 2, one group of exterior frame column supporting rack, the exterior frame column supporting rack packet is arranged in the position of corresponding exterior frame column Include at least three the 4th H profile steels 6 being distributed along 2 width direction of landing slab, length direction and the landing slab 2 of the 4th H profile steel 6 Length direction is consistent, and the 4th H profile steel 6 is detachably connected with landing slab 2;It is equipped on the top flange plate of the 4th H profile steel 6 Second concave template 8, second concave template, 8 place plane cross the center line of the top flange plate of the 4th H profile steel 6, and with Four H profile steels 6 are detachably connected;Between corner post supporting rack and exterior frame column supporting rack, corresponding wind up beam, lower-cord beam and diagonal web member Semi-girder truss support frame is chosen outside being provided in position.Semi-girder truss support frame is chosen outside described including at least two along 2 length of landing slab The length direction of 5th H profile steel 7 of directional spreding, the 5th H profile steel 7 is consistent with the width direction of landing slab 2;
D, corner post and exterior frame column are put into corresponding concave template, and make to choose the one of semi-girder truss outside corner post and exterior frame column installation Side is opposite, and then the preassembling box bracket on corner post and exterior frame column, then adjusts to the projection line on landing slab 2 and overlap, Box bracket is fixed temporarily again.
E, semi-girder truss plate will be chosen by driving outside lower layer and be lifted into outer choose on semi-girder supporting rack, wherein outside the lower layer It includes wind up beam lower plywood, lower-cord beam lower plywood and oblique web grider lower plywood to choose semi-girder truss plate;In hoisting process, successively in lifting String beam lower plywood, lower-cord beam lower plywood and oblique web grider lower plywood, then adjust to the projection line on landing slab 2 and overlap, then into Row is fixed temporarily;Then placement semi-girder connecting plate on semi-girder truss plate is chosen outside lower layer;Again semi-girder will be chosen by driving outside upper layer Truss plate is lifted into above semi-girder connecting plate, and it includes wind up beam top plate, lower-cord beam upper layer that semi-girder truss plate is chosen outside the upper layer Plate and oblique web grider top plate after then adjusting position to qualification, then are fixed temporarily.
F, the gap between each parts of detection, levelness, complete preassembling.
G, according to the component divided using BIM technology, the welding of parts is carried out, each component is made to be respectively formed an independence Entirety.
H, step A-H is repeated, is completed until choosing semi-girder part preassembling outside all Core Walls Structures.During practice of construction, by Outer contilever structure and connection type, the direction of choosing in each position is consistent, therefore can only repeat step D-H, so as to Pre-splicing ETL estimated time of loading is enough further saved, preassembling efficiency is improved.
5)Outer shroud truss portion preassembling:
A, outer on landing slab 2 is chosen into semi-girder supporting rack and corner post supporting rack is removed, at the same wipe the ground line-transect on landing slab 2, Projection line and layout point.
B, the position for adjusting exterior frame column supporting rack on landing slab 2, then based on the exterior frame column supporting rack, in landing slab Outer shroud truss portion is drawn on 2 line-transect, and indicate projection line and layout point of the outer shroud truss portion on landing slab 2.
C, on landing slab 2, one group of exterior frame column supporting rack is arranged in the position of corresponding another exterior frame column again;In two groups of exterior frame columns Ring truss element supporting rack is set between supporting rack;The outer shroud truss element supporting rack includes at least two and is grown along landing slab 2 The 6th H profile steel 9 of directional spreding is spent, the length direction of the 6th H profile steel 9 is consistent with the width direction of landing slab 2, and and platform Plate 2 is detachably connected.
D, another exterior frame column is put into corresponding second concave template 8, and two exterior frame columns be connected with ring truss one Side is opposite, and then box bracket, is then fixed temporarily by the pre- bottled box bracket on corner post and exterior frame column.
E, lower layer's outer shroud truss element plate is lifted on outer shroud truss element supporting rack by driving a vehicle, wherein under described Layer outer shroud truss element plate includes upper beam lower plywood, underbeam lower plywood and the oblique web grider lower plywood of X-shaped;In hoisting process, hang successively Beam lower plywood, underbeam lower plywood and the oblique web grider lower plywood of X-shaped are loaded onto, then adjusts to the projection line on landing slab 2 and overlaps, then It is fixed temporarily;Then connecting plate is placed on lower layer's outer shroud truss element plate;Again by driving a vehicle upper layer outer shroud truss list First plate is lifted into above semi-girder connecting plate, and the upper layer outer shroud truss element plate includes upper beam top plate, underbeam top plate and X-shaped Oblique web grider top plate, after then adjusting position to qualification, then is fixed temporarily.
F, the gap between each parts of detection, levelness, complete preassembling.
G, according to the component divided using BIM technology, the welding of parts is carried out, each component is made to be respectively formed an independence Entirety.
H, step A-H is repeated, until all Core Walls Structure outer shroud truss portion preassemblings are completed.
Wherein, semi-girder truss portion and outer shroud truss portion preassembling are chosen outside Core Walls Structure inner ring truss portion, Core Walls Structure In the process, when repeating A-H steps, it is both needed to the placement status according to corner post and/or exterior frame column, replaces corresponding concave template, with Ensure corner post and/or exterior frame column and interior truss or outer chooses semi-girder truss or ring truss is located at same level.In corner post and outline border In the placement process of column, according to layout point, tested to the position of steel column using level meter and sash weight.
In detection process after each section preassembling, detects gap between each parts, during levelness, passes through Steel tape, level meter are detected.Also, the mismatch between each parts closes requirement, is indicated and is recorded, shape Table is checked at preassembling original position parameter;In this way, for the component welded again after preassembling, the original position recorded when using preassembling Parameter checks table and carries out preassembling postwelding check to the component, ensures component processing quality.
Finally, it should be noted that technical side the above examples are only used to illustrate the technical scheme of the present invention and are not limiting Case, it will be understood by those of ordinary skill in the art that, those are modified or replaced equivalently technical scheme of the present invention, and The objective and range for not departing from the technical program, are intended to be within the scope of the claims of the invention.

Claims (5)

1. a kind of high-rise building enhancement layer steel structure truss pre-assembly method, it is characterised in that:Include the following steps:
1)Pre-splicing assembling platform is set up on ground in factory:The pre-splicing assembling platform includes several first H profile steels and landing slab, described First H profile steel is mutually parallel, and the top flange plate of all first H profile steels is located in same level, adjacent two first H profile steels it Between spacing be 0.5-1m;The landing slab be layed on the top flange plate of the first H profile steel and with the top flange of the first H profile steel Plate is fixedly connected, and the length direction of landing slab is vertical with the length direction of the first H profile steel;Wherein, the landing slab is by several Steel plate welds to be formed;
2) enhancement layer truss is divided into three parts by structural plane:Semi-girder truss is chosen outside Core Walls Structure inner ring truss portion, Core Walls Structure Part and outer shroud truss portion, are then divided into multiple components using BIM technology by each part;
3)Core Walls Structure inner ring truss portion preassembling:
A, according to preassembling scheme, line-transect, described ground line-transect include core with drawing Core Walls Structure inner ring truss portion on landing slab The corresponding axis of heart cylinder inner ring truss portion and elevation line, and indicate projection line of the core inner cylinder truss portion on landing slab And layout point;
B, on landing slab, the position of corresponding corner post is laid with one group of corner post supporting rack respectively, and the corner post supporting rack includes along flat Three second H profile steels of platen width direction distribution, the length direction of second H profile steel is consistent with the length direction of landing slab, And second H profile steel is detachably connected with landing slab;It is equipped with the first female vertically on the top flange plate of the second H profile steel Plate, plane where first concave template cross the center line of the top flange plate of the second H profile steel, and detachable with the second H profile steel Connection;First concave template has a locating slot through side thereon, the preassembling of corner post can be made to connect by the locating slot Side is located at vertical plane;Interior truss support frame is equipped between two groups of corner post supporting racks, the interior truss support frame includes at least Three third H profile steels along the distribution of landing slab length direction, the length direction of the third H profile steel and the width direction one of landing slab It causes, and is detachably connected with landing slab;
C, Core Walls Structure corner post is individually placed in the first concave template of two groups of corner post supporting racks, and two corner posts is made to be connected with truss Side it is opposite;Wherein, the Core Walls Structure corner post is divided into upper prop and lower prop, adjusts the position of Core Walls Structure corner post, makes Core Walls Structure angle Layout point on column coincides with the layout point on ground line-transect, then carries out temperature pier to the junction of upper prop and lower prop;So The preassembling box bracket on two corner posts afterwards, and adjust to after being overlapped with the projection line on landing slab, then box bracket is interim It is fixed;
D, truss plate in lower layer is lifted on truss support frame by driving a vehicle, wherein truss plate includes winding up in the lower layer Beam lower plywood, lower-cord beam lower plywood and diagonal web member lower plywood;In hoisting process, lifting successively is winded up under beam lower plywood, lower-cord beam Laminate and diagonal web member lower plywood, then adjust to the projection line on landing slab and overlap, then be fixed temporarily;
E, the position line that truss inner prop, truss inner beam and truss connecting plate are drawn on lower layer's truss plate, is then sequentially placed purlin Frame inner prop, truss inner beam and truss connecting plate;Upper layer truss plate is lifted into truss inner prop, truss inner beam and purlin by driving a vehicle again Above frame connecting plate, the upper layer truss plate includes wind up beam top plate, lower-cord beam top plate and diagonal web member top plate;It lifted Cheng Zhong lifts wind up beam top plate, lower-cord beam top plate and diagonal web member top plate successively, after then adjusting position to qualification, then It is fixed temporarily;
F, the gap between each parts of detection, levelness, complete preassembling;
G, according to using BIM technology divide component, carry out the welding of parts, make each component be respectively formed one it is independent whole Body;
H, step A-H is repeated, until entire Core Walls Structure inner ring truss portion preassembling is completed;
4)Semi-girder truss portion preassembling is chosen outside Core Walls Structure:
A, by landing slab truss support frame and one of which corner post supporting rack remove, while wiping the ground sample on landing slab Line, projection line and layout point;
B, it based on remaining one group of corner post supporting rack, is drawn on landing slab outside Core Walls Structure and chooses semi-girder partly line-transect, and It indicates and chooses projection line and layout point of the semi-girder part on landing slab outside Core Walls Structure;
C, on landing slab, one group of exterior frame column supporting rack is arranged in the position of corresponding exterior frame column, and the exterior frame column supporting rack includes extremely Few three the 4th H profile steels along the distribution of landing slab width direction, the length direction of the length direction and landing slab of the 4th H profile steel Unanimously, and the 4th H profile steel is detachably connected with landing slab;The second female is equipped on the top flange plate of the 4th H profile steel Plate, plane where second concave template cross the center line of the top flange plate of the 4th H profile steel, and detachable with the 4th H profile steel Connection;Between corner post supporting rack and exterior frame column supporting rack, the position of corresponding wind up beam, lower-cord beam and diagonal web member is provided with outer choose Semi-girder truss support frame;It includes at least two the 5th H being distributed along landing slab length direction to choose semi-girder truss support frame outside described The length direction of shaped steel, the 5th H profile steel is consistent with the width direction of landing slab;
D, corner post and exterior frame column are put into corresponding concave template, and make to choose the one of semi-girder truss outside corner post and exterior frame column installation Side is opposite, and then the preassembling box bracket on corner post and exterior frame column, then adjusts to the projection line on landing slab and overlap, then Box bracket is fixed temporarily;
E, semi-girder truss plate will be chosen by driving outside lower layer and be lifted into outer choose on semi-girder supporting rack, wherein choose and stretch outside the lower layer Arm truss plate includes wind up beam lower plywood, lower-cord beam lower plywood and oblique web grider lower plywood;In hoisting process, the beam that winds up is lifted successively Lower plywood, lower-cord beam lower plywood and oblique web grider lower plywood, then adjust to the projection line on landing slab and overlap, then carry out interim It is fixed;Then placement semi-girder connecting plate on semi-girder truss plate is chosen outside lower layer;Again semi-girder truss plate will be chosen by driving outside upper layer It is lifted into above semi-girder connecting plate, it includes wind up beam top plate, lower-cord beam top plate and oblique that semi-girder truss plate is chosen outside the upper layer Web grider top plate after then adjusting position to qualification, then is fixed temporarily;
F, the gap between each parts of detection, levelness, complete preassembling;
G, according to using BIM technology divide component, carry out the welding of parts, make each component be respectively formed one it is independent whole Body;
H, step A-H is repeated, is completed until choosing semi-girder part preassembling outside all Core Walls Structures;
5)Outer shroud truss portion preassembling:
A, outer on landing slab is chosen into semi-girder supporting rack and corner post supporting rack is removed, while wiped the ground line-transect on landing slab, throwing Hachure and layout point;
B, the position for adjusting exterior frame column supporting rack on landing slab is painted then based on the exterior frame column supporting rack on landing slab Outer shroud truss portion processed ground line-transect, and indicate projection line and layout point of the outer shroud truss portion on landing slab;
C, on landing slab, one group of exterior frame column supporting rack is arranged in the position of corresponding another exterior frame column again;It is supported in two groups of exterior frame columns Outer shroud truss element supporting rack is set between frame;The outer shroud truss element supporting rack includes at least two along landing slab length side To the 6th H profile steel of distribution, the length direction of the 6th H profile steel is consistent with the width direction of landing slab, and removable with landing slab Unload connection;
D, another exterior frame column is put into corresponding second concave template, and the side phase that two exterior frame columns are connected with ring truss To then box bracket, is then fixed temporarily by the pre- bottled box bracket on corner post and exterior frame column;
E, lower layer's outer shroud truss element plate is lifted on outer shroud truss element supporting rack by driving a vehicle, wherein outside the lower layer Ring truss element plate includes upper beam lower plywood, underbeam lower plywood and the oblique web grider lower plywood of X-shaped;In hoisting process, successively in lifting Beam lower plywood, underbeam lower plywood and the oblique web grider lower plywood of X-shaped, then adjust to the projection line on landing slab and overlap, then carry out It is fixed temporarily;Then connecting plate is placed on lower layer's outer shroud truss element plate;Again by driving a vehicle upper layer outer shroud truss element plate It is lifted into above semi-girder connecting plate, the upper layer outer shroud truss element plate includes upper beam top plate, underbeam top plate and the oblique abdomen of X-shaped Beam top plate after then adjusting position to qualification, then is fixed temporarily;
F, the gap between each parts of detection, levelness, complete preassembling;
G, according to using BIM technology divide component, carry out the welding of parts, make each component be respectively formed one it is independent whole Body;
H, step A-H is repeated, until all Core Walls Structure outer shroud truss portion preassemblings are completed.
2. a kind of high-rise building enhancement layer steel structure truss pre-assembly method according to claim 1, it is characterised in that: During choosing semi-girder truss portion and outer shroud truss portion preassembling outside Core Walls Structure inner ring truss portion, Core Walls Structure, A-H is repeated When step, it is both needed to the placement status according to corner post and/or exterior frame column, replaces corresponding concave template, to ensure corner post and/or outer Frame column and interior truss outer choose semi-girder truss or ring truss is located at same level.
3. a kind of high-rise building enhancement layer steel structure truss pre-assembly method according to claim 1, it is characterised in that: In the placement process of corner post and exterior frame column, according to layout point, tested to the position of steel column using level meter and sash weight.
4. a kind of high-rise building enhancement layer steel structure truss pre-assembly method according to claim 1, it is characterised in that: It detects gap between each parts, during levelness, be detected by steel tape, level meter.
5. a kind of high-rise building enhancement layer steel structure truss pre-assembly method according to claim 1, it is characterised in that: In detection process, the mismatch between each parts closes requirement, is indicated and is recorded, and forms preassembling and joins in situ Number check table.
CN201810792200.3A 2018-07-18 2018-07-18 Pre-assembly method for steel structure truss of reinforced layer of super high-rise building Active CN108678398B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810792200.3A CN108678398B (en) 2018-07-18 2018-07-18 Pre-assembly method for steel structure truss of reinforced layer of super high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810792200.3A CN108678398B (en) 2018-07-18 2018-07-18 Pre-assembly method for steel structure truss of reinforced layer of super high-rise building

Publications (2)

Publication Number Publication Date
CN108678398A true CN108678398A (en) 2018-10-19
CN108678398B CN108678398B (en) 2020-07-14

Family

ID=63814173

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810792200.3A Active CN108678398B (en) 2018-07-18 2018-07-18 Pre-assembly method for steel structure truss of reinforced layer of super high-rise building

Country Status (1)

Country Link
CN (1) CN108678398B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653517A (en) * 2019-01-31 2019-04-19 济南四建(集团)有限责任公司 A kind of multidirectional Load Relief System and the construction method with the system assembly steel vestibule
CN110424746A (en) * 2019-08-21 2019-11-08 中冶建工集团有限公司 The installation method of roofing truss and riding track in a kind of venue
CN111648606A (en) * 2020-06-10 2020-09-11 深圳市市政工程总公司 Construction method for high-altitude cantilever splicing of steel structure
CN111927111A (en) * 2020-09-22 2020-11-13 上海建工集团股份有限公司 Construction method of ultrahigh special-shaped outer frame steel structure
CN115045560A (en) * 2022-06-23 2022-09-13 中建钢构工程有限公司 Pre-assembly method of special-shaped high-rise steel structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100251660A1 (en) * 2007-11-05 2010-10-07 Mccann David accuspacer-prefabricated multi structural timber alignment fixture
CN106639147A (en) * 2016-12-23 2017-05-10 中建八局第二建设有限公司 Construction method of super high-rise building reinforced layer steel structure outrigger truss
CN106760839A (en) * 2016-11-23 2017-05-31 同济大学建筑设计研究院(集团)有限公司 A kind of superelevation steel megastructure vibration damping integrated system
CN107386461A (en) * 2017-08-25 2017-11-24 中冶建工集团有限公司 The multidirectional handing-over box node weld mould bases of steel truss and node population method
CN107795130A (en) * 2017-11-08 2018-03-13 中建钢构有限公司 The large-scale truss pre-assembly method of steel construction and moulding bed

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100251660A1 (en) * 2007-11-05 2010-10-07 Mccann David accuspacer-prefabricated multi structural timber alignment fixture
CN106760839A (en) * 2016-11-23 2017-05-31 同济大学建筑设计研究院(集团)有限公司 A kind of superelevation steel megastructure vibration damping integrated system
CN106639147A (en) * 2016-12-23 2017-05-10 中建八局第二建设有限公司 Construction method of super high-rise building reinforced layer steel structure outrigger truss
CN107386461A (en) * 2017-08-25 2017-11-24 中冶建工集团有限公司 The multidirectional handing-over box node weld mould bases of steel truss and node population method
CN107795130A (en) * 2017-11-08 2018-03-13 中建钢构有限公司 The large-scale truss pre-assembly method of steel construction and moulding bed

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653517A (en) * 2019-01-31 2019-04-19 济南四建(集团)有限责任公司 A kind of multidirectional Load Relief System and the construction method with the system assembly steel vestibule
CN109653517B (en) * 2019-01-31 2024-02-20 济南四建(集团)有限责任公司 Multidirectional unloading system and construction method for assembling steel corridor by using same
CN110424746A (en) * 2019-08-21 2019-11-08 中冶建工集团有限公司 The installation method of roofing truss and riding track in a kind of venue
CN110424746B (en) * 2019-08-21 2021-02-26 中冶建工集团有限公司 Method for installing roof truss and pavement in venue
CN111648606A (en) * 2020-06-10 2020-09-11 深圳市市政工程总公司 Construction method for high-altitude cantilever splicing of steel structure
CN111927111A (en) * 2020-09-22 2020-11-13 上海建工集团股份有限公司 Construction method of ultrahigh special-shaped outer frame steel structure
CN111927111B (en) * 2020-09-22 2020-12-25 上海建工集团股份有限公司 Construction method of ultrahigh special-shaped outer frame steel structure
CN115045560A (en) * 2022-06-23 2022-09-13 中建钢构工程有限公司 Pre-assembly method of special-shaped high-rise steel structure

Also Published As

Publication number Publication date
CN108678398B (en) 2020-07-14

Similar Documents

Publication Publication Date Title
CN108678398A (en) A kind of high-rise building enhancement layer steel structure truss pre-assembly method
CN107100358B (en) Cantilever bracket and bracket body special for unloading-free industrialized safety protection and construction method of cantilever bracket and bracket body
CN103410322B (en) The parallel Truss Steel corridor construction method of large span
CN114086669B (en) Modularized rapid construction method for large-scale space special-shaped curved surface steel net rack
CN111042539A (en) Single-point support installation construction method for large-span steel structure truss
CN103643800A (en) Lifting installation system for buckling restrained supporting member and construction method thereof
CN114033051A (en) Large-span hyperbolic truss construction process based on steel structure spherical curtain cinema engineering
CN114770706B (en) Light T-beam prefabrication equipment and prefabrication installation construction method
CN108842954A (en) A kind of huge different section Honeycomb Beam structural system construction method of installation of aerofoil profile roofing
CN112663583B (en) Construction method for total assembly and closure of pile stabilizing platform
CN106869479A (en) Bailey bracket sliding formwork system construction method
CN109812021A (en) A kind of installation method of large span welding ball grid
CN109267439B (en) Efficient and stable three-layer viaduct and construction process thereof
CN117145051A (en) High-altitude assembly structure of large-span space broken line truss and construction method
CN114134991B (en) High-rise building construction method with conversion structure
WO2023206851A1 (en) Drum joint installation method, steel reticulated shell, and assembly unit construction method
CN203334692U (en) T-type support slip installation structure of plate-type steel truss
CN106988520B (en) Construction method and support system for high-rise suspension structure
CN114941433A (en) Construction method of heavy-weight ship-shaped daylighting roof steel structure
CN112247390A (en) Indoor inverted construction method for large storage tank
CN114482561A (en) Steel structure roof installation method
CN209556320U (en) Steel structure operation platform for super high-rise building core tube construction
CN109441088B (en) Steel structure operation platform for super high-rise building core tube construction
CN108756254A (en) The installation method of cantilever frame platform and cantilever frame
CN106988293B (en) A kind of ship lift main equipment room steel lattice column construction method and installation accuracy control method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant