CN108661410A - A kind of fixed structure of cement shaft tower - Google Patents
A kind of fixed structure of cement shaft tower Download PDFInfo
- Publication number
- CN108661410A CN108661410A CN201810357545.6A CN201810357545A CN108661410A CN 108661410 A CN108661410 A CN 108661410A CN 201810357545 A CN201810357545 A CN 201810357545A CN 108661410 A CN108661410 A CN 108661410A
- Authority
- CN
- China
- Prior art keywords
- fixed
- shaft tower
- arc
- cement shaft
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2253—Mounting poles or posts to the holder
- E04H12/2276—Clamping poles or posts on a stub
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/12—Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The invention discloses a kind of fixed structures of cement shaft tower, including firm banking, lock stud, cable wire, cement shaft tower and Hook, the outside at cement pole bottom of tower end is equipped with firm banking, the inside of the threaded hole is all threaded with locking stud, firm banking top on the outside of the cement shaft tower is fixed with support plate, the side on the adjustable plate top is all equipped with arc fixed plate, the adjustable plate top of arc fixed plate side is all equipped with equidistant positioning pin, the both ends of the arc fixed plate side are all fixed with hinged seat, both ends of the arc fixed plate far from hinged seat side are all fixed with strip buckle, cement pole tower side wall above the arc fixed plate is equipped with arc anti-shake set, the bottom end of the Hook is all fixed with cable wire.The present invention not only increases stability when fixed structure is fixed, and improves convenience degree when fixed structure uses, and realize the fixed function of different cement shaft towers.
Description
Technical field
The present invention relates to cement pole tower technology field, specially a kind of fixed structure of cement shaft tower.
Background technology
Cement shaft tower is mainly made of reinforcing bar and concrete, therefore also referred to as armored concrete cement electric pole tower, main
It is used as stringing pillar in the industries such as electric power, communication, railway, oil, cement shaft tower is broadly divided into prestressing force and non-prestressed two
Kind, however in the fixation procedure of cement shaft tower, general fixed structure use it is relatively complicated, to greatly increase
The set time of cement shaft tower, and the serious labor intensity for increasing operating personnel, the also fixed knot of some cement pole towers
Structure cannot achieve the fixed function of different cement shaft towers, to greatly affect cement shaft tower use scope in addition some
The phenomenon that cement shaft tower easily causes shaking when fixed, to greatly affect stability when cement shaft tower uses,
Prodigious trouble is brought to the use of people.
Invention content
It is mentioned above in the background art to solve the purpose of the present invention is to provide a kind of fixed structure of cement shaft tower
Problem.
To achieve the above object, the present invention provides the following technical solutions:A kind of fixed structure of cement shaft tower, including fixation
The outside of pedestal, locking stud, cable wire, cement shaft tower and Hook, cement pole bottom of tower end is equipped with firm banking, fixed bottom
Three groups of threaded holes are equipped at the marginal position on seat top, and the angle between adjacent screw holes is 120 degree, the screw thread
The inside in hole is all threaded with locking stud, and the firm banking top on the outside of the cement shaft tower is fixed with support plate, support
The top of plate is equipped with three groups of adjustable plates, and the angle between adjacent adjustable plate is 120 degree, and the one of the adjustable plate top
Side is all equipped with arc fixed plate, and the adjustable plate top of arc fixed plate side is all equipped with equidistant positioning pin, the positioning
The support plate top of pin lower section is equipped with equidistant pin hole, and pin hole cooperates with positioning pin, the arc fixed plate side
Both ends be all fixed with hinged seat, and strip clip is hinged on the madial wall of hinged seat, the arc fixed plate is far from hinged
The both ends of seat side are all fixed with strip buckle, and strip buckle cooperates with the one end of strip clip far from hinged seat, institute
It states the cement pole tower side wall above arc fixed plate and is equipped with arc anti-shake set, and pass through Hook between adjacent arc anti-shake set
The bottom end of connection, the Hook is all fixed with cable wire, and the bottom end of cable wire is wrapped in the surface of locking stud.
Preferably, the cement pole tower side wall above the arc fixed plate is equipped with three groups of arc anti-shake sets, and adjacent arcs
Angle between shape anti-shake set is 120 degree.
Preferably, the center position of the locking screw top end is equipped with rotating handle.
Preferably, the surface of the Hook is equipped with anti-drop rod.
Preferably, the center line between the central axes of the locking stud are covered with adjacent arc anti-shake overlaps.
Compared with prior art, the beneficial effects of the invention are as follows:By setting adjustable plate, adjustable plate top on the top of support plate
Arc fixed plate is installed in the side at end, and sets positioning pin, alignment pin position by the adjustable plate top in arc fixed plate side
The support plate top at place sets pin hole, realizes the fixed function of different cement shaft towers, to improve the use model of fixed structure
It encloses, by the fixation hinged seat at the both ends in arc fixed plate side, hinged strip clip on the madial wall of hinged seat, and pass through
Strip buckle is fixed at both ends of the arc fixed plate far from hinged seat side, the set time of fixed structure is shortened, to carry
Convenience degree when high fixed structure uses, while by setting threaded hole, screw thread at the marginal position on firm banking top
The internal whorl connection locking stud in hole, and by setting arc anti-shake set on the cement pole tower side wall above arc fixed plate,
The bottom end fixing tightwire of Hook, avoids the shaking of cement shaft tower, stability when fixation to improve fixed structure,
The present invention not only increases stability when fixed structure is fixed, and improves convenience degree when fixed structure uses, Er Qieshi
The fixed function of different cement shaft towers is showed.
Description of the drawings
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the partial sectional view of the present invention;
Fig. 3 is the partial top view of the present invention.
In figure:1, firm banking;2, stud is locked;3, cable wire;4, arc fixed plate;5, strip clip;6, cement shaft tower;
7, arc anti-shake set;8, Hook;9, hinged seat;10, strip buckles;11, positioning pin;12, threaded hole;13, support plate;14、
Adjustable plate;15, pin hole.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, a kind of embodiment provided by the invention:A kind of fixed structure of cement shaft tower, including fixed bottom
The outside of seat 1, locking stud 2, cable wire 3, cement shaft tower 6 and Hook 8,6 bottom end of cement shaft tower is equipped with firm banking 1, fixed
Three groups of threaded holes 12 are equipped at the marginal position on 1 top of pedestal, and the angle between adjacent screw holes 12 is 120 degree, spiral shell
The inside of pit 12 is all threaded with locking stud 2, and the center position on 2 top of locking stud is equipped with rotating handle, convenient for lock
1 top of firm banking of the rotation process of tight stud 2,6 outside of cement shaft tower is fixed with support plate 13, and the top of support plate 13 is set
There are three groups of adjustable plates 14, and the angle between adjacent adjustable plate 14 is 120 degree, the side on 14 top of adjustable plate is all installed
There is an arc fixed plate 4,14 top of adjustable plate of 4 side of arc fixed plate is all equipped with equidistant positioning pin 11, under positioning pin 11
13 top of support plate of side is equipped with equidistant pin hole 15, and pin hole 15 cooperates with positioning pin 11,4 side of arc fixed plate
Both ends be all fixed with hinged seat 9, and strip clip 5 is hinged on the madial wall of hinged seat 9, arc fixed plate 4 is far from hinged
The both ends of 9 sides of seat are all fixed with strip buckle 10, and strip buckle 10 is mutual with the one end of strip clip 5 far from hinged seat 9
Cooperation, 6 side wall of cement shaft tower of the top of arc fixed plate 4 are equipped with three groups of arc anti-shakes and cover 7, and adjacent arc anti-shake set 7 it
Between angle be 120 degree, lock stud 2 central axes and adjacent arc anti-shake set 7 between center line overlap, be convenient for
Fastening function, avoid the shaking of cement shaft tower 6, and connected by Hook 8 between adjacent arc anti-shake set 7, Hook 8
Bottom end is all fixed with cable wire 3, and the bottom end of cable wire 3 is wrapped in the surface of locking stud 2, and the surface of Hook 8 is equipped with anti-drop rod,
Avoid the disengaging of arc anti-shake set 7.
Operation principle:When fixed structure needs that cement shaft tower is fixed, cement shaft tower 6 is placed on fixation first
The inside of pedestal 1 and support plate 13 makes adjustable plate 14 that arc be driven to fix by the adjustable plate 14 on 13 top of movable joint support plate
Plate 4 is moved to be in close contact with cement shaft tower 6, by 4 side adjustable plate of arc fixed plate, 14 top positioning pin 11 with it is fixed
The mutual cooperation of pin hole 15 on 13 top of support plate is fixed at 11 position of pin of position, passes through 4 side of rotating curved fixed plate later
Strip clip 5 on 9 madial wall of both ends hinged seat makes strip clip 5 with arc fixed plate 4 far from 9 side both ends of hinged seat
Strip buckle 10, which cooperates, to be fixed, and finally arc anti-shake set 7 is sleeved on the side wall of cement shaft tower 6, and utilize extension
Adjacent arc anti-shake set 7 is connected by coupler body 8, the cable wire 3 of 8 bottom end of Hook is being wrapped in 2 surface of locking stud, later
Rotation locking stud 2 makes it be moved down inside the threaded hole 12 at 1 tip edge position of firm banking, and cable wire 3 is tensed, is completed
The fixation work of cement shaft tower.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie
In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter
From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power
Profit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims
Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
Claims (5)
1. a kind of fixed structure of cement shaft tower, including firm banking(1), locking stud(2), cable wire(3), cement shaft tower(6)
And Hook(8), it is characterised in that:The cement shaft tower(6)The outside of bottom end is equipped with firm banking(1), firm banking(1)Top
Three groups of threaded holes are equipped at the marginal position at end(12), and adjacent screw holes(12)Between angle be 120 degree, it is described
Threaded hole(12)Inside be all threaded with locking stud(2), the cement shaft tower(6)The firm banking in outside(1)Top
It is fixed with support plate(13), support plate(13)Top be equipped with three groups of adjustable plates(14), and adjacent adjustable plate(14)Between folder
Angle is 120 degree, the adjustable plate(14)The side on top is all equipped with arc fixed plate(4), arc fixed plate(4)One
The adjustable plate of side(14)Top is all equipped with equidistant positioning pin(11), the positioning pin(11)The support plate of lower section(13)Top
Equipped with equidistant pin hole(15), and pin hole(15)With positioning pin(11)It cooperates, the arc fixed plate(4)The two of side
End is all fixed with hinged seat(9), and hinged seat(9)Madial wall on be hinged with strip clip(5), the arc fixed plate(4)
Far from hinged seat(9)The both ends of side are all fixed with strip buckle(10), and strip buckles(10)With strip clip(5)Far from hinge
Joint chair(9)One end cooperate, the arc fixed plate(4)The cement shaft tower of top(6)Side wall is equipped with arc anti-shake set
(7), and adjacent arc anti-shake set(7)Between pass through Hook(8)Connection, the Hook(8)Bottom end be all fixed with cable wire
(3), and cable wire(3)Bottom end be wrapped in locking stud(2)Surface.
2. a kind of fixed structure of cement shaft tower according to claim 1, it is characterised in that:The arc fixed plate(4)
The cement shaft tower of top(6)Side wall is equipped with three groups of arc anti-shake sets(7), and adjacent arc anti-shake set(7)Between angle be
120 degree.
3. a kind of fixed structure of cement shaft tower according to claim 1, it is characterised in that:The locking stud(2)Top
The center position at end is equipped with rotating handle.
4. a kind of fixed structure of cement shaft tower according to claim 1, it is characterised in that:The Hook(8)Table
Face is equipped with anti-drop rod.
5. a kind of fixed structure of cement shaft tower according to claim 1, it is characterised in that:The locking stud(2)'s
Central axes and adjacent arc anti-shake set(7)Between center line overlap.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810357545.6A CN108661410A (en) | 2018-04-20 | 2018-04-20 | A kind of fixed structure of cement shaft tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810357545.6A CN108661410A (en) | 2018-04-20 | 2018-04-20 | A kind of fixed structure of cement shaft tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108661410A true CN108661410A (en) | 2018-10-16 |
Family
ID=63780138
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810357545.6A Pending CN108661410A (en) | 2018-04-20 | 2018-04-20 | A kind of fixed structure of cement shaft tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108661410A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111720269A (en) * | 2019-03-20 | 2020-09-29 | 新疆金风科技股份有限公司 | Anchoring device and tower |
CN112012890A (en) * | 2019-05-29 | 2020-12-01 | 北京金风科创风电设备有限公司 | Connecting assembly, stay cable type tower and wind generating set |
CN112160643A (en) * | 2020-09-24 | 2021-01-01 | 安吉鼎兴水泥制品有限公司 | Wire pole convenient to replace |
CN115324413A (en) * | 2022-07-25 | 2022-11-11 | 云南永达电力实业有限公司 | Cladding of high strength cement shaft tower encircles reinforcing system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5060435A (en) * | 1990-02-15 | 1991-10-29 | Bogdanow Anatol L | Bracket for support of vertical pole |
CN203891550U (en) * | 2014-05-15 | 2014-10-22 | 国网山东齐河县供电公司 | Electric rod with anti-tilting device |
CN205743224U (en) * | 2016-06-20 | 2016-11-30 | 江苏健德铁塔有限公司 | Moveable counter weight formula base pole |
CN206143794U (en) * | 2016-08-23 | 2017-05-03 | 金宇州 | A column foot structure for communicating by letter tower |
DE102016217793A1 (en) * | 2016-06-17 | 2017-12-21 | Heicon Service Gesellschaft mbH | Device for connecting a pile pile foundation with a supporting structure and method for producing such a connection |
-
2018
- 2018-04-20 CN CN201810357545.6A patent/CN108661410A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5060435A (en) * | 1990-02-15 | 1991-10-29 | Bogdanow Anatol L | Bracket for support of vertical pole |
CN203891550U (en) * | 2014-05-15 | 2014-10-22 | 国网山东齐河县供电公司 | Electric rod with anti-tilting device |
DE102016217793A1 (en) * | 2016-06-17 | 2017-12-21 | Heicon Service Gesellschaft mbH | Device for connecting a pile pile foundation with a supporting structure and method for producing such a connection |
CN205743224U (en) * | 2016-06-20 | 2016-11-30 | 江苏健德铁塔有限公司 | Moveable counter weight formula base pole |
CN206143794U (en) * | 2016-08-23 | 2017-05-03 | 金宇州 | A column foot structure for communicating by letter tower |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111720269A (en) * | 2019-03-20 | 2020-09-29 | 新疆金风科技股份有限公司 | Anchoring device and tower |
CN111720269B (en) * | 2019-03-20 | 2022-07-05 | 新疆金风科技股份有限公司 | Anchoring device and tower |
CN112012890A (en) * | 2019-05-29 | 2020-12-01 | 北京金风科创风电设备有限公司 | Connecting assembly, stay cable type tower and wind generating set |
CN112012890B (en) * | 2019-05-29 | 2022-07-05 | 北京金风科创风电设备有限公司 | Connecting assembly, stay cable type tower and wind generating set |
CN112160643A (en) * | 2020-09-24 | 2021-01-01 | 安吉鼎兴水泥制品有限公司 | Wire pole convenient to replace |
CN115324413A (en) * | 2022-07-25 | 2022-11-11 | 云南永达电力实业有限公司 | Cladding of high strength cement shaft tower encircles reinforcing system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108661410A (en) | A kind of fixed structure of cement shaft tower | |
CN206832123U (en) | A kind of laminated bow with gamut tension | |
CN209339655U (en) | Telescoping tripod | |
CN203870942U (en) | Device for adjusting display angle of advertisement board | |
CN207830945U (en) | A kind of television set that can arbitrarily adjust spatial attitude | |
CN207500997U (en) | A kind of LED street lamp connection structure | |
CN207527241U (en) | A kind of pivoted arm structure | |
CN108678385A (en) | A kind of construction reinforcing bar binding device | |
CN205604449U (en) | Novel adjustable angle steel structure | |
CN209145390U (en) | A kind of durable power transmission rod for facilitating adjusting tension | |
CN209838273U (en) | Insulating folding ladder | |
CN208309931U (en) | Grip device | |
CN208297795U (en) | A kind of overhead cable binding rod and overhead cable binder suit | |
CN208236010U (en) | Diagonal brace drawing device for in-situ concrete wall shuttering supporting | |
CN207700646U (en) | A kind of full hall supporting rack | |
CN206992648U (en) | A kind of portable wire tensioning device | |
CN206454992U (en) | A kind of leader pass pass structure for rolling finish rolling deformed bar | |
CN207596346U (en) | A kind of wind-proof pull rod of crane | |
CN205604578U (en) | Adjustable I -steel structure of strenghthened type | |
CN204767147U (en) | Training ware handrail height quick adjustment mechanism | |
CN207739222U (en) | A kind of anchor point that harbour is berthed | |
CN109393828A (en) | A kind of mattress sheet flareout device using elastic element | |
CN207590710U (en) | A kind of retractor for operation on neck | |
CN209145396U (en) | One kind can be received quickly and be pitched a tent | |
CN203398635U (en) | Bracing frame for replacing vibration damper |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |