CN108632297A - A kind of high safety network architecture of electric power scheduling automatization system - Google Patents
A kind of high safety network architecture of electric power scheduling automatization system Download PDFInfo
- Publication number
- CN108632297A CN108632297A CN201810485146.8A CN201810485146A CN108632297A CN 108632297 A CN108632297 A CN 108632297A CN 201810485146 A CN201810485146 A CN 201810485146A CN 108632297 A CN108632297 A CN 108632297A
- Authority
- CN
- China
- Prior art keywords
- module
- areas
- operation system
- electric power
- data acquisition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L63/00—Network architectures or network communication protocols for network security
- H04L63/02—Network architectures or network communication protocols for network security for separating internal from external traffic, e.g. firewalls
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/14—Network analysis or design
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L43/00—Arrangements for monitoring or testing data switching networks
- H04L43/08—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters
- H04L43/0805—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability
- H04L43/0811—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability by checking connectivity
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L43/00—Arrangements for monitoring or testing data switching networks
- H04L43/08—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters
- H04L43/0805—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability
- H04L43/0817—Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters by checking availability by checking functioning
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L63/00—Network architectures or network communication protocols for network security
- H04L63/20—Network architectures or network communication protocols for network security for managing network security; network security policies in general
Landscapes
- Engineering & Computer Science (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Computer Security & Cryptography (AREA)
- Environmental & Geological Engineering (AREA)
- Computer Hardware Design (AREA)
- Computing Systems (AREA)
- General Engineering & Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The invention discloses a kind of high safety network architectures of electric power scheduling automatization system,Including analysing terminal and data acquisition module,The data acquisition module is connected with real-time database and timing sequence library,The data acquisition module arrives data transmission to analysing terminal by data transmission module by what real-time database and timing sequence library acquired,The analysing terminal includes central processing unit and Wiring port,Connected graph drafting module draws network-in-dialing figure according to the areas I operation system and the areas II operation system and according to the connectivity in the areas I operation system and the areas II operation system,Data acquisition module is used to acquire the acquisition information of real-time database and timing sequence library,The server end of survival host detection module in the data acquisition module is mounted in each network segment separated by fire wall on an optional computer,The server end is responsible for receiving the probe instructions of console,Viability detection is carried out to the computer in the network segment,Then result is sent to data transmission module.
Description
Technical field
The present invention relates to power system security administrative skill field, specially a kind of Gao An of electric power scheduling automatization system
Whole network framework.
Background technology
Currently, the scheduling station end of China's power grid only net, province's two-stage have just built sorts of systems sets up to up to a hundred, plant stand end
The deployment of secondary device and system is because different application demands is also very complicated.These are widely distributed in main station side and plant stand end
Electrical secondary system functionally can tentatively meet current electric grid operation basic demand, but due to technology development stage,
The problem of factors such as the unicity of system function target and professional division, system Construction, operation and maintenance and management, is also gradually sudden and violent
To expose, it may appear that various failures, most common failure are exactly the failure of the connectivity of network, by the analysis to safety,
From failure, with network diagnostic tool, so that it may quickly and accurately to determine that electricity is restored in the fault point of electric power, debugging
Power scheduling often operation, now lacks a kind of high safety network architecture of electric power scheduling automatization system, traditional security network infrastructure,
Operating personnel are needed to investigate analysis one by one, working efficiency is low, needs to be optimized and perfect, this has the development of network
Very important meaning.
Invention content
It is above-mentioned to solve the purpose of the present invention is to provide a kind of high safety network architecture of electric power scheduling automatization system
The problem of being proposed in background technology.
To achieve the above object, the present invention provides the following technical solutions:A kind of high safety network of electric power scheduling automatization system
Framework, including analysing terminal and data acquisition module, the data acquisition module are connected with real-time database and timing sequence library, the data
Acquisition module arrives data transmission to analysing terminal by data transmission module by what real-time database and timing sequence library acquired, and the analysis is eventually
End includes central processing unit and Wiring port, and the analysing terminal is connected with electrically connected analysis module, safety analysis module, net
Close analysis module, secure data access interface, data traffic analysis module, connected graph drafting module and man-machine interface, the electricity
Whether power linking parsing module electrically connected normal for checking, the safety analysis module for detect it is electrically connected whether just
Often, the gateway analysis module is for testing and analyzing whether terminal default gateway is normal, and the data traffic analysis module is used for
Electric power data flow is detected, the connected graph drafting module connects for drawing electric power networks connected graph, the secure data access
Mouth is connected with the first lateral internet firewall and the second internet firewall, and the described first lateral internet firewall is connected with
The areas I operation system, second internet firewall are connected with the areas II operation system.
Preferably, the analysing terminal is also connected with print module by Wiring port, and the print module includes printer.
Preferably, the man-machine interface includes mouse module, Keysheet module and display apparatus module, and the display apparatus module is LED
Display apparatus module.
Preferably, the connected graph drafting module according to the areas I operation system and the areas II operation system and according to the areas I operation system and
Connectivity in the areas II operation system draws network-in-dialing figure.
Preferably, the data acquisition module is used to acquire the acquisition information of real-time database and timing sequence library, the data acquisition module
In the server end of survival host detection module be mounted in each network segment for being separated by fire wall on an optional computer,
The server end is responsible for receiving the probe instructions of console, and viability detection is carried out to the computer in the network segment, then will knot
Fruit is sent to data transmission module.
Preferably, it is separated respectively with fire wall between the areas I operation system and the areas II operation system.
Compared with prior art, the beneficial effects of the invention are as follows:A kind of high safety net of electric power scheduling automatization system of the present invention
Network framework, data acquisition module are used to acquire the acquisition information of real-time database and timing sequence library, will be real-time by data transmission module
What library and timing sequence library acquired arrives data transmission to analysing terminal, and analysing terminal is connected with electrically connected analysis module, safety analysis
Module, gateway analysis module, secure data access interface, data traffic analysis module, connected graph drafting module and man-machine interface,
Whether electrically connected analysis module electrically connected normal for checking, safety analysis module for detect it is electrically connected whether just
Often, whether gateway analysis module is normal for testing and analyzing terminal default gateway, and data traffic analysis module is for detecting electric power
Data traffic, connected graph drafting module draw network company according to network management database and according to the connectivity in network management database
Logical figure, and by impression block printer mimeograph documents in the block, connected graph drafting module is according to the areas I operation system and the areas II business
System simultaneously draws network-in-dialing figure, data acquisition module according to the connectivity in the areas I operation system and the areas II operation system
Acquisition information for acquiring real-time database and timing sequence library, the server of the survival host detection module in the data acquisition module
End is mounted in each network segment separated by fire wall on an optional computer, which is responsible for receiving the spy of console
Instruction is surveyed, viability detection is carried out to the computer in the network segment, result is then sent to data transmission module, is had very high
Practicability, greatly improve a kind of high safety network architecture of electric power scheduling automatization system using functional, ensure
Its using effect and utilization benefit are suitble to be widely popularized.
Description of the drawings
Fig. 1 is a kind of system block diagram of the high safety network architecture of electric power scheduling automatization system of the present invention.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, the present invention provides a kind of technical solution:A kind of high safety network architecture of electric power scheduling automatization system,
Including analysing terminal and data acquisition module, the data acquisition module is connected with real-time database and timing sequence library, the data acquisition
Module arrives data transmission to analysing terminal, the analysing terminal packet by data transmission module by what real-time database and timing sequence library acquired
Central processing unit and Wiring port are included, the analysing terminal is connected with electrically connected analysis module, safety analysis module, gateway point
Module, secure data access interface, data traffic analysis module, connected graph drafting module and man-machine interface are analysed, the electric power connects
It is electrically connected whether normal for checking to connect analysis module, whether the safety analysis module is electrically connected normal for detecting,
Whether the gateway analysis module is normal for testing and analyzing terminal default gateway, and the data traffic analysis module is for detecting
Electric power data flow, the connected graph drafting module connect for drawing electric power networks connected graph, the secure data access interface
It is connected to the first lateral internet firewall and the second internet firewall, the described first lateral internet firewall is connected with the areas I
Operation system, second internet firewall are connected with the areas II operation system.
Specifically, the analysing terminal is also connected with print module by Wiring port, the print module includes printer.
Specifically, the man-machine interface includes mouse module, Keysheet module and display apparatus module, the display apparatus module is LED
Display apparatus module.
Specifically, the connected graph drafting module according to the areas I operation system and the areas II operation system and according to the areas I operation system and
Connectivity in the areas II operation system draws network-in-dialing figure.
Specifically, the data acquisition module is used to acquire the acquisition information of real-time database and timing sequence library, the data acquisition module
In the server end of survival host detection module be mounted in each network segment for being separated by fire wall on an optional computer,
The server end is responsible for receiving the probe instructions of console, and viability detection is carried out to the computer in the network segment, then will knot
Fruit is sent to data transmission module.
Specifically, being separated respectively with fire wall between the areas I operation system and the areas II operation system.
Operation principle:A kind of high safety network architecture of electric power scheduling automatization system of the present invention, in use, data acquisition module
Acquisition information for acquiring real-time database and timing sequence library will be counted real-time database and arriving for timing sequence library acquisition by data transmission module
According to analysing terminal is transmitted to, analysing terminal is connected with electrically connected analysis module, safety analysis module, gateway analysis module, peace
Full data access interface, data traffic analysis module, connected graph drafting module and man-machine interface, electrically connected analysis module are used for
Check electrically connected whether normal, whether safety analysis module is electrically connected normal for detecting, and gateway analysis module is for examining
Whether normal survey analysing terminal default gateway, data traffic analysis module draws mould for detecting electric power data flow, connected graph
Root tuber draws network-in-dialing figure according to network management database and according to the connectivity in network management database, and by print module
Printer mimeograph documents, connected graph drafting module is according to the areas I operation system and the areas II operation system and according to the areas I operation system
Network-in-dialing figure is drawn with the connectivity in the areas II operation system, data acquisition module is for acquiring real-time database and timing sequence library
Acquisition information, the server end of the survival host detection module in the data acquisition module is mounted on to be separated by fire wall
Each network segment on an optional computer, which is responsible for receiving the probe instructions of console, to the meter in the network segment
Calculation machine carries out viability detection, and result is then sent to data transmission module.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, it is possible to understand that
Can these embodiments be carried out with a variety of variations without departing from the principles and spirit of the present invention, modification, replace and become
Type, the scope of the present invention is defined by the appended.
Claims (6)
1. a kind of high safety network architecture of electric power scheduling automatization system, including analysing terminal and data acquisition module, special
Sign is:The data acquisition module is connected with real-time database and timing sequence library, and the data acquisition module passes through data transmission module
Data transmission is arrived to analysing terminal by what real-time database and timing sequence library acquired, and the analysing terminal includes central processing unit and terminals
Mouthful, the analysing terminal is connected with electrically connected analysis module, safety analysis module, gateway analysis module, secure data and accesses
Interface, data traffic analysis module, connected graph drafting module and man-machine interface, the electrically connected analysis module is for checking electricity
Whether power connection is normal, and whether the safety analysis module is electrically connected normal for detecting, and the gateway analysis module is used for
Whether normal test and analyze terminal default gateway, the data traffic analysis module is for detecting electric power data flow, the company
For logical figure drafting module for drawing electric power networks connected graph, it is anti-that the secure data access interface is connected with the first lateral internet
Wall with flues and the second internet firewall, the described first lateral internet firewall are connected with the areas I operation system, second interconnection
Net fire wall is connected with the areas II operation system.
2. a kind of high safety network architecture of electric power scheduling automatization system according to claim 1, it is characterised in that:Institute
It states analysing terminal and print module is also connected with by Wiring port, the print module includes printer.
3. a kind of high safety network architecture of electric power scheduling automatization system according to claim 1, it is characterised in that:Institute
It includes mouse module, Keysheet module and display apparatus module to state man-machine interface, and the display apparatus module is light-emitting diode display module.
4. a kind of high safety network architecture of electric power scheduling automatization system according to claim 1, it is characterised in that:Institute
Connected graph drafting module is stated according to the areas I operation system and the areas II operation system and according to the areas I operation system and the areas II operation system
In connectivity draw network-in-dialing figure.
5. a kind of high safety network architecture of electric power scheduling automatization system according to claim 1, it is characterised in that:Institute
Acquisition information of the data acquisition module for acquiring real-time database and timing sequence library is stated, the survival host in the data acquisition module is visited
The server end for surveying module is mounted in each network segment separated by fire wall on an optional computer, which is responsible for
The probe instructions for receiving console carry out viability detection to the computer in the network segment, and result, which is then sent to data, passes
Defeated module.
6. a kind of high safety network architecture of electric power scheduling automatization system according to claim 1, it is characterised in that:Institute
It states and is separated respectively with fire wall between the areas I operation system and the areas II operation system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810485146.8A CN108632297A (en) | 2018-05-21 | 2018-05-21 | A kind of high safety network architecture of electric power scheduling automatization system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810485146.8A CN108632297A (en) | 2018-05-21 | 2018-05-21 | A kind of high safety network architecture of electric power scheduling automatization system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108632297A true CN108632297A (en) | 2018-10-09 |
Family
ID=63693844
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810485146.8A Pending CN108632297A (en) | 2018-05-21 | 2018-05-21 | A kind of high safety network architecture of electric power scheduling automatization system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108632297A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114697112A (en) * | 2022-03-31 | 2022-07-01 | 华能澜沧江水电股份有限公司 | Hydropower production real-time data acquisition, transmission, calculation, storage and optimization system |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103067366A (en) * | 2012-12-21 | 2013-04-24 | 广东电网公司电力调度控制中心 | Partition network architecture of electric power dispatching automation system |
CN103177642A (en) * | 2013-03-26 | 2013-06-26 | 广东电网公司佛山供电局 | Method for improving reality of power grid dispatcher training simulation system |
CN103457791A (en) * | 2013-08-19 | 2013-12-18 | 国家电网公司 | Self-diagnosis method of network sampling and control link of intelligent substation |
CN105847021A (en) * | 2015-01-13 | 2016-08-10 | 国家电网公司 | Concentrated operation and maintenance safety audit system in intelligent power grid dispatching control system |
CN206533399U (en) * | 2017-01-12 | 2017-09-29 | 国网安徽省电力公司阜阳供电公司 | A kind of electric power scheduling automatization system |
CN107426062A (en) * | 2017-09-05 | 2017-12-01 | 合肥丹朋科技有限公司 | Computer network connectedness automatic analysis system |
-
2018
- 2018-05-21 CN CN201810485146.8A patent/CN108632297A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103067366A (en) * | 2012-12-21 | 2013-04-24 | 广东电网公司电力调度控制中心 | Partition network architecture of electric power dispatching automation system |
CN103177642A (en) * | 2013-03-26 | 2013-06-26 | 广东电网公司佛山供电局 | Method for improving reality of power grid dispatcher training simulation system |
CN103457791A (en) * | 2013-08-19 | 2013-12-18 | 国家电网公司 | Self-diagnosis method of network sampling and control link of intelligent substation |
CN105847021A (en) * | 2015-01-13 | 2016-08-10 | 国家电网公司 | Concentrated operation and maintenance safety audit system in intelligent power grid dispatching control system |
CN206533399U (en) * | 2017-01-12 | 2017-09-29 | 国网安徽省电力公司阜阳供电公司 | A kind of electric power scheduling automatization system |
CN107426062A (en) * | 2017-09-05 | 2017-12-01 | 合肥丹朋科技有限公司 | Computer network connectedness automatic analysis system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114697112A (en) * | 2022-03-31 | 2022-07-01 | 华能澜沧江水电股份有限公司 | Hydropower production real-time data acquisition, transmission, calculation, storage and optimization system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103532940B (en) | network security detection method and device | |
CN108712433A (en) | A kind of network security detection method and system | |
CN102393738A (en) | Diagnostic device and test method of automobile electronic control unit (ECU) | |
CN103019141B (en) | Control module, control method and electric power dynamic recording device and implementation method thereof | |
CN106713074A (en) | Data network quality piecewise detection method and system based on service content | |
CN108173701B (en) | Intelligent substation network parameter configuration verification method | |
CN112994972B (en) | Distributed probe monitoring platform | |
CN110174564A (en) | The filed detection system and its detection method of equipment for monitoring power quality access main website | |
CN109063008A (en) | A kind of shallow layer ground-temperature energy comprehensive monitoring management system | |
CN107404416A (en) | A kind of visualizing monitor method of power information acquisition system | |
CN105446197B (en) | A kind of column control ground critical data detection device | |
CN106530653B (en) | Power information acquisition method | |
CN207096357U (en) | A kind of high-tension cable operating state monitoring system | |
CN107122532A (en) | The emulation mode and system of intelligence equipment integrating are closed by dispatching formula transformer station | |
CN105807251B (en) | A kind of outdoor electrical energy meter fault self-verifying method | |
CN108632297A (en) | A kind of high safety network architecture of electric power scheduling automatization system | |
CN102170368B (en) | Intelligent fault locating method of distributed measuring system facing heavy gauge member | |
CN110430085B (en) | Intelligent detection device for centralized meter reading communication faults | |
CN107229499A (en) | The main website simulation system and detection method detected for power collection systems failed terminals | |
CN105162653B (en) | A kind of fault detection means of communication data | |
CN109443395B (en) | Method and system for judging whether energy consumption intensity multipoint measurement difference value exceeds limit value | |
CN210899204U (en) | Intelligent detection device for centralized meter reading communication faults | |
CN1324850C (en) | Testing method for nucleus plate of digital user inserting into module | |
CN104584515B (en) | Analyzing communication configuration in Process Control System | |
CN112231157B (en) | AI server HCA card performance test method and system based on hardware topology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181009 |