CN108631322A - Electrical load selectivity off-grid system and method - Google Patents

Electrical load selectivity off-grid system and method Download PDF

Info

Publication number
CN108631322A
CN108631322A CN201810502369.0A CN201810502369A CN108631322A CN 108631322 A CN108631322 A CN 108631322A CN 201810502369 A CN201810502369 A CN 201810502369A CN 108631322 A CN108631322 A CN 108631322A
Authority
CN
China
Prior art keywords
load
generating set
selectivity
grid
generated output
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810502369.0A
Other languages
Chinese (zh)
Inventor
王岩
张占萌
李朝晖
王润东
李雨轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinji Australia Steel Co Ltd
Original Assignee
Xinji Australia Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinji Australia Steel Co Ltd filed Critical Xinji Australia Steel Co Ltd
Priority to CN201810502369.0A priority Critical patent/CN108631322A/en
Publication of CN108631322A publication Critical patent/CN108631322A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Abstract

The invention discloses a kind of electrical load selectivity off-grid system and methods, including generating set, off-grid controller, carry calculation device and on-load switch, it is integrated with memory, selection circuit and Comparison Circuit in off-grid controller, the generated output of generating set is stored in memory;The N number of load of sequence successively decreased according to the priority level of power supply is respectively N1Load ... NnLoad, the priority level of the power supply of N number of load are stored in memory;N1Load ... NnLoad passes through S respectively1On-load switch ... SnOn-load switch is electrically connected to generating set.Beneficial effects of the present invention are:When the part generating set in multiple generating sets breaks down, when undercapacity, the sequence successively decreased successively according to power supply priority level powers to corresponding carried selective, makes the load selectivity off-grid that do not power;Current fault generator group and load supplying situation in real time, intuitively show by display device.

Description

Electrical load selectivity off-grid system and method
Technical field
The present invention relates to power supply technique fields, and in particular to a kind of electrical load selectivity off-grid system and method.
Background technology
According to design, the generated outputs of multiple generating sets >=by the load of multiple electric set electric supply, it is each to ensure Load can work normally.However, reality is after the part generating set failure in multiple generating sets there are causing undercapacity, The case where all loads can not be driven, will lead to all equal cisco unity malfunctions of load.
Invention content
The purpose of the present invention is to provide a kind of electrical load selectivity off-grid system and methods, to solve existing part After generating set failure caused by undercapacity the problem of all loads equal cisco unity malfunction.
To achieve the above object, the technical scheme is that
One aspect of the present invention discloses a kind of electrical load selectivity off-grid system comprising generating set, off-grid control Device, carry calculation device and on-load switch, wherein:
It is integrated with memory, selection circuit and Comparison Circuit in the off-grid controller, hair is stored in the memory The generated output of motor group;
Load number in the electrical load selectivity off-grid system is N, and N >=2 are successively decreased according to the priority level of power supply Sequentially N number of load is respectively N1Load ... NnLoad, the priority level of the power supply of N number of load are stored in the memory It is interior;
N1Load ... NnLoad passes through S respectively1On-load switch ... SnOn-load switch is electrically connected to described Generating set, the S1On-load switch ... the SnOn-load switch is connect with the selection circuit signal;
N1Load ... NnLoad passes through C respectively1Carry calculation device ... CnCarry calculation device with it is described Comparison Circuit signal connects, the C1Carry calculation device ... the CnCarry calculation device is respectively used to calculate N1 Load ... NnThe load of load.
Preferably, the generating set is M groups, and M >=2, the electrical load selectivity off-grid system further includes M power generation Operating states of the units detection switch and M generating set generated output computing device, the generating set condition monitoring are opened It closes and the motor group generated output computing device is connect with the off-grid controller signals.
Preferably, the off-grid controller is PLC controller.
Preferably, the comparison circuit is LM339 or LM393.
Preferably, the rotation circuit is data selector.
Another aspect of the present invention discloses a kind of electrical load selectivity offline method comprising:
Calculate the generated output of generating set;
The load respectively loaded on power grid is calculated, and each load is added to obtain the loaded total load of institute;
Load is classified according to the power supply priority level of load, it is negative in the electrical load selectivity off-grid system Load number is N, and N >=2, the N number of load of sequence successively decreased according to the priority level of power supply is respectively N1Load ... NnLoad;
By the load of the generated output of generating set and each load and comparison,
When the generated output of generating set >=total load to all load supplyings;
When the generated output of generating set is less than the total load, it is powered according to the power supply priority level, and And the sum of the load of the load for the generated output of generating set >=be powered.
Preferably, the generating set is M groups, and M >=2, the electrical load selectivity off-grid system further includes M power generation Operating states of the units detection switch and M generating set generated output computing device, the generating set condition monitoring are opened It closes and the motor group generated output computing device is connect with the off-grid controller signals.
The invention has the advantages that:
When the part generating set in multiple generating sets breaks down so that it is loaded total negative that generated output is less than institute When lotus, that is, when leading to undercapacity, the sequence successively decreased successively according to power supply priority level powers to corresponding carried selective, also Even if the load that do not power carries out off-grid, to ensure to power, the high load of priority level can work normally, to realize choosing Selecting property off-grid, to ensure the safety of greater degree load;
By display device, current fault generator group and load supplying situation in real time, intuitively show, are convenient for Administrative staff understand the failure and load supplying situation of generating set, and directive function is played to work such as subsequent maintenance.
Description of the drawings
Fig. 1 is the circuit diagram of electrical load selectivity off-grid system of the present invention;
Fig. 2 is the control figure of electrical load selectivity off-grid system of the present invention.
Specific implementation mode
The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention..
Embodiment 1
One aspect of the present invention discloses a kind of electrical load selectivity off-grid system, referring to Fig. 1 and Fig. 2 comprising power generation Unit, off-grid controller, carry calculation device and on-load switch, wherein:
It is integrated with memory, selection circuit and Comparison Circuit in the off-grid controller, hair is stored in the memory The generated output of motor group;
Load number in the electrical load selectivity off-grid system is N, and N >=2 are successively decreased according to the priority level of power supply Sequentially N number of load is respectively N1Load ... NnLoad, the priority level of the power supply of N number of load are stored in the memory It is interior;
N1Load ... NnLoad passes through S respectively1On-load switch ... SnOn-load switch is electrically connected to described Generating set, the S1On-load switch ... the SnOn-load switch is connect with the selection circuit signal;
N1Load ... NnLoad passes through C respectively1Carry calculation device ... CnCarry calculation device with it is described Comparison Circuit signal connects, the C1Carry calculation device ... the CnCarry calculation device is respectively used to calculate N1 Load ... NnThe load of load.
It should be noted that the formulation of above-mentioned power supply priority level is according to for the shadow after the importance of electric loading, power-off Size etc. is rung to determine, is input in memory by programming after determining.
In addition, C1Carry calculation device ... CnA kind of realization method of carry calculation device is as follows, is born accordingly Series voltage table and ammeter in load, to detect the real-time voltage and real-time current of corresponding load, the voltage signal and electric current Signal transmission obtains the product of real-time voltage and real real-time current, as should to off-grid controller and after off-grid controller operation Locate the real-time load of load, which is dynamic detection, ensures the reliability of system work, it is contemplated that the shadow of supply variation It rings.
Another aspect of the present invention discloses a kind of electrical load selectivity offline method comprising:
Calculate the generated output of generating set;
The load respectively loaded on power grid is calculated, and each load is added to obtain the loaded total load of institute;
Load is classified according to the power supply priority level of load, it is negative in the electrical load selectivity off-grid system Load number is N, and N >=2, the N number of load of sequence successively decreased according to the priority level of power supply is respectively N1Load ... NnLoad;
By the load of the generated output of generating set and each load and comparison,
When the generated output of generating set >=total load to all load supplyings;
When the generated output of generating set is less than the total load, it is powered according to the power supply priority level, and And the sum of the load of the load for the generated output of generating set >=be powered.
When the part generating set in multiple generating sets breaks down so that it is loaded total negative that generated output is less than institute When lotus, that is, when leading to undercapacity, the sequence successively decreased successively according to power supply priority level powers to corresponding carried selective, also Even if the load that do not power carries out off-grid, to ensure to power, the high load of priority level can work normally, to realize choosing Selecting property off-grid, to ensure the safety of greater degree load.
Embodiment 2
On the basis of embodiment 1, the present embodiment further includes such as display screen display device, the display device with it is described Off-grid controller signals connect.By display device, current fault generator group and load supplying situation are carried out in real time, directly Display is seen, the failure and load supplying situation of generating set are understood convenient for administrative staff, finger is played to work such as subsequent maintenance Lead effect.
Embodiment 3
On the basis of embodiment 2, the generating set is M groups, and M >=2, the electrical load selectivity off-grid system is also Including M generating set condition monitoring switch and M generating set generated output computing device, M generating set operation State-detection switch respectively the 1st generating set operation detecting switch ... M generating set operation detecting switches, M power generation Power of the assembling unit computing device is respectively the 1st generating set power computing device and M generating set power computing devices, the hair Motor group condition monitoring switchs and the motor group generated output computing device is connect with the off-grid controller signals.
Generating set condition monitoring switch is selected and the concatenated ammeter of corresponding generating set herein, when there is electric current When flowing through generating set, i.e., there is electric current to pass through in ammeter.
In addition, the selection of generating set power computing device and the concatenated voltmeter of corresponding generating set, to detect power generation Real-time voltage when unit works, the real-time current of corresponding generating set, voltage signal are detected in conjunction with above-mentioned ammeter After passing to off-grid controller with current signal, by off-grid controller operation, the product of voltage and electric current is obtained to get to generator The real-time generated output of group, the testing result are dynamic detection, ensure the reliability of system work, it is contemplated that the shadow of supply variation It rings.
Embodiment 4
On the basis of embodiment 2, the off-grid controller is PLC controller.
Preferably, the comparison circuit is LM339 or LM393.
Preferably, the rotation circuit is data selector.
Although above having used general explanation and specific embodiment, the present invention is described in detail, at this On the basis of invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Therefore, These modifications or improvements without departing from theon the basis of the spirit of the present invention belong to the scope of protection of present invention.

Claims (8)

1. a kind of electrical load selectivity off-grid system, which is characterized in that including generating set, off-grid controller, carry calculation Device and on-load switch, wherein:
It is integrated with memory, selection circuit and Comparison Circuit in the off-grid controller, generator is stored in the memory The generated output of group;
Load number in the electrical load selectivity off-grid system is N, N >=2, the sequence successively decreased according to the priority level of power supply N number of load is respectively N1Load ... NnLoad, the priority level storage of the power supply of N number of load is in the memory;
N1Load ... NnLoad passes through S respectively1On-load switch ... SnOn-load switch is electrically connected to the power generation Unit, the S1On-load switch ... the SnOn-load switch is connect with the selection circuit signal;
N1Load ... NnLoad passes through C respectively1Carry calculation device ... CnCarry calculation device is compared with described Circuit signal connects, the C1Carry calculation device ... the CnCarry calculation device is respectively used to calculate N1It is negative Carry ... NnThe load of load.
2. electrical load selectivity off-grid system according to claim 1, which is characterized in that the generating set is M groups, M >=2, the electrical load selectivity off-grid system further include M generating set condition monitoring switch and M generating set Generated output computing device, generating set condition monitoring switch and the motor group generated output computing device with The off-grid controller signals connection.
3. electrical load selectivity off-grid system according to claim 1 or 2, which is characterized in that the off-grid controller For PLC controller.
4. electrical load selectivity off-grid system according to claim 3, which is characterized in that the comparison circuit is LM339 or LM393.
5. electrical load selectivity off-grid system according to claim 4, which is characterized in that the rotation circuit is data Selector.
6. electric appliance load selectivity off-grid system according to claim 5, which is characterized in that further include display device, institute Display device is stated to connect with the off-grid controller signals.
7. a kind of electrical load selectivity offline method, which is characterized in that including:
Calculate the generated output of generating set;
The load respectively loaded on power grid is calculated, and each load is added to obtain the loaded total load of institute;
Load is classified according to the power supply priority level of load, the load number in the electrical load selectivity off-grid system For N, N >=2, the N number of load of sequence successively decreased according to the priority level of power supply is respectively N1Load ... NnLoad;
By the load of the generated output of generating set and each load and comparison,
When the generated output of generating set >=total load to all load supplyings;
When the generated output of generating set is less than the total load, it is powered according to the power supply priority level, and send out The sum of the load of the load for the generated output of motor group >=be powered.
8. electrical load selectivity offline method according to claim 7, which is characterized in that the generating set is M groups, M >=2, the electrical load selectivity off-grid system further include M generating set condition monitoring switch and M generating set Generated output computing device, generating set condition monitoring switch and the motor group generated output computing device with The off-grid controller signals connection.
CN201810502369.0A 2018-05-23 2018-05-23 Electrical load selectivity off-grid system and method Pending CN108631322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810502369.0A CN108631322A (en) 2018-05-23 2018-05-23 Electrical load selectivity off-grid system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810502369.0A CN108631322A (en) 2018-05-23 2018-05-23 Electrical load selectivity off-grid system and method

Publications (1)

Publication Number Publication Date
CN108631322A true CN108631322A (en) 2018-10-09

Family

ID=63690161

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810502369.0A Pending CN108631322A (en) 2018-05-23 2018-05-23 Electrical load selectivity off-grid system and method

Country Status (1)

Country Link
CN (1) CN108631322A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110011360A (en) * 2019-03-20 2019-07-12 新奥(中国)燃气投资有限公司 Generating set output load method of adjustment and system
CN112350307A (en) * 2020-10-28 2021-02-09 中国华电科工集团有限公司 Control method and control device for regional distribution network and computer readable storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105337287A (en) * 2015-11-16 2016-02-17 上海电机学院 Electrical load part unloading method and electrical load part unloading system
CN105939021A (en) * 2015-12-15 2016-09-14 国电南瑞科技股份有限公司 Power grid frequency control method of considering low voltage ride-through capability of fan
CN107516904A (en) * 2017-08-31 2017-12-26 国电南瑞科技股份有限公司 A kind of reply power supply off-grid impacts and counted and the accurate duty control method of unit regulating power
CN208674875U (en) * 2018-05-23 2019-03-29 辛集市澳森钢铁有限公司 Electrical load selectivity off-grid system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105337287A (en) * 2015-11-16 2016-02-17 上海电机学院 Electrical load part unloading method and electrical load part unloading system
CN105939021A (en) * 2015-12-15 2016-09-14 国电南瑞科技股份有限公司 Power grid frequency control method of considering low voltage ride-through capability of fan
CN107516904A (en) * 2017-08-31 2017-12-26 国电南瑞科技股份有限公司 A kind of reply power supply off-grid impacts and counted and the accurate duty control method of unit regulating power
CN208674875U (en) * 2018-05-23 2019-03-29 辛集市澳森钢铁有限公司 Electrical load selectivity off-grid system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110011360A (en) * 2019-03-20 2019-07-12 新奥(中国)燃气投资有限公司 Generating set output load method of adjustment and system
CN112350307A (en) * 2020-10-28 2021-02-09 中国华电科工集团有限公司 Control method and control device for regional distribution network and computer readable storage medium

Similar Documents

Publication Publication Date Title
Ambusaidi et al. New circuit topology for fault tolerant H-bridge DC–DC converter
US9297862B2 (en) Systems and apparatus for fault detection in DC power sources using AC residual current detection
Liu et al. Review of fault diagnosis and fault-tolerant control for modular multilevel converter of HVDC
US10503126B2 (en) Access control method for parallel direct current power supplies and device thereof
JP6481571B2 (en) Inspection apparatus and inspection method
CN102053211A (en) Fault diagnosis method of wind power generation system converter device
CN105242136A (en) Super capacitor detection method and device for wind turbine generator
CN108631322A (en) Electrical load selectivity off-grid system and method
CN115407189A (en) Combined detection system and method for special low-voltage circuit breaker for distributed photovoltaic grid connection
CN208674875U (en) Electrical load selectivity off-grid system
CN203858310U (en) Large-power energy-storage current transformer testing system
CN112327082B (en) Method, device and system for testing complete set of energy consumption device of flexible direct current engineering
CN103630801A (en) Voltage withstanding test device with positive and negative polarity voltage output
CN112034298A (en) Switch test device
Sheikh et al. Detection of high impedance fault in DC microgrid
Jlassi et al. A single fault diagnostics approach for power switches, speed sensors and current sensors in regenerative PMSM drives
CN105425149B (en) A kind of AC machine drive system detection device
CN114355074A (en) Testing device and testing method of converter valve system
KR101539333B1 (en) Generator test system
JP2015104276A (en) Power conditioner, and storage method
CN104297701B (en) The shut-off test platform and its method of single bridge arm in three level H-bridge inverters
Li et al. Fault diagnosis and fault-tolerant control of photovoltaic micro-inverter
CN207473053U (en) A kind of equipment for detecting gas-filling cabinet
Ajra et al. Fault Diagnosis of Open Switch Failure in Voltage Source Inverter Using Average and RMS Phase Voltages
CN110365033A (en) A kind of energy-accumulating power station subsystem debugging structure, debugging control program and adjustment method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 052360 Nan Zhi Qiu Zhao Ma Cun Dong Cun, Xinji City, Shijiazhuang City, Hebei Province

Applicant after: Xinji Aosen iron and Steel Group Co.,Ltd.

Address before: 052360 Nan Zhi Qiu Zhao Ma Cun Dong Cun, Xinji City, Shijiazhuang City, Hebei Province

Applicant before: XINJI AOSEN IRON & STEEL Co.,Ltd.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20181009

RJ01 Rejection of invention patent application after publication