CN108629524A - A kind of tunnels and underground engineering risk assessment and management method - Google Patents

A kind of tunnels and underground engineering risk assessment and management method Download PDF

Info

Publication number
CN108629524A
CN108629524A CN201810454897.3A CN201810454897A CN108629524A CN 108629524 A CN108629524 A CN 108629524A CN 201810454897 A CN201810454897 A CN 201810454897A CN 108629524 A CN108629524 A CN 108629524A
Authority
CN
China
Prior art keywords
risk
management
target
coefficient value
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810454897.3A
Other languages
Chinese (zh)
Inventor
康仕彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Road and Bridge Corp
Original Assignee
China Road and Bridge Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Road and Bridge Corp filed Critical China Road and Bridge Corp
Priority to CN201810454897.3A priority Critical patent/CN108629524A/en
Publication of CN108629524A publication Critical patent/CN108629524A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of tunnels and underground engineering risk assessment and management methods,Determine risk target and monitoring index content,Panel of expert is set up to investigate risk target,Obtain the survey data of risk target,The data of investigation are handled,Obtain a series of set of research and appraisal indexs,Determine methods of risk assessment,The effect of being calculated according to appraisal procedure and assessing risk target coefficient value,Calculated total efficiency coefficient value is classified by rule,Management and prevention so as to administrative staff to risk,Determine risk management layer,Formulate risk management target,Formulate risk management contents,It checks and whether hard objectives risk solves and release,Total efficiency coefficient value can be easily calculated using efficiency coefficient method,Administrative staff can be faster,Scheme of controlling risk and the measure solved the problems, such as are formulated more in time,Quadratic risk function assessment is carried out to risk target after managing risk target,The safety of construction personnel is ensured,Construction speed and construction property safety.

Description

A kind of tunnels and underground engineering risk assessment and management method
Technical field
The present invention relates to risk analysis of tunnel and management domain, specially a kind of tunnels and underground engineering risk assessment and pipe Reason method.
Background technology
The risk assessment in tunnel is to investigate thoroughly risk factors from construction source, rationally determines risk class, abandons or change and is residual The engineering proposal that risk is high is stayed, risk processing and surveillance and control measure is proposed, carries out the risk management of system, improve the management water of risk It is flat, it is intended to ensure safety, environmental protection, ensure the duration, controlled investment, improve benefit.
Risk assessment and management should be adjusted dynamically in force, to ensure that risk assessment is smooth.
The risk assessment target in tunnel is:It is worked by risk assessment, identifies all potential risks factors, determine risk Grade proposes risk treatment measures, various risks is dropped to acceptable level, and safety, environmental protection, guarantee work are ensured to reach Phase, controlled investment, the purpose improved benefit.
The risk assessment target in tunnel has:
(1) security risk:Casualties, economic loss, third party's casualties, third party's economic loss, construction delay Deng;
(2) duration risk:Construction delay, economic loss etc.;
(3) investment risk:Economic loss, third party's economic loss etc.;
(4) environment breaks unreal, economic loss, third party's economic loss etc..
The method of risk assessment has:The side such as risk analytic hierarchy process (AHP), matrix method, Fuzzy Comprehensive Evaluation, brainstorming Method.
Risk identification is the basis of risk assessment, also makes the important step in risk analysis, and the purpose is in searching project All possible risk factors.
Risk identification follows scientific, systemic, comprehensive, predictive principle.Risk identification is generated according to risk Root or classification etc. establish the tree-shaped or layer structure for embodying risk factors and event category and hierarchical relationship, form risk and refer to Mark system, in conjunction with engineering practice, the mode for establishing risk tablet menu is identified.
But existing risk analysis of tunnel has the following defects with management method:
(1) method of domestic existing risk assessment has:Risk exponential, Fault Tree Analysis, obscures analytic hierarchy process (AHP) Comprehensive Evaluation and method etc. can be opened up, still, when using above method dynamic evaluation the risk of tunnel construction there is also it is certain not Foot is mainly shown as that personal subjectivity influences big, calculating process complexity etc., to make the time lengthening of risk assessment, is unfavorable for Timely management and risk control to risk factors and place, to increase the uncertain factor of risk, security risk is larger.
(2) management method is that corresponding scheme and measure are taken in the region larger to risk after existing risk assessment, is adopted No longer detect original risk target after taking, in such risk target may also there are residual risk factors, can be to construction personnel Safety threatens, or is adversely affected to construction progress, or causes greater loss to construction property.
Invention content
In order to overcome the shortcomings of that prior art, the present invention provide a kind of tunnels and underground engineering risk assessment and management Method can easily calculate total efficiency coefficient value using efficiency coefficient method, administrative staff can faster, formulate control risk more in time Scheme and the measure solved the problems, such as, so that the risk of constructing tunnel and loss are reduced to minimum, to wind after managing risk target Dangerous target carries out quadratic risk function assessment, to by remaining risk control to tolerance interval, greatly ensure constructor Safety, construction speed and the construction property safety of member, can effectively solve the problem that the problem of background technology proposes.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of tunnels and underground engineering risk assessment and management method, a kind of tunnels and underground engineering methods of risk assessment, Include the following steps:
S100, risk target and monitoring index content are determined, sets up panel of expert and risk target is investigated, obtains wind The survey data of dangerous target;
S200, the data of investigation are handled, obtains a series of set of research and appraisal indexs;
S300, the effect of determining methods of risk assessment, being calculated according to appraisal procedure and assess risk target coefficient value;
S400, calculated total efficiency coefficient value is classified by rule, management and prevention so as to administrative staff to risk.
Further, the monitoring index content in the step S100 includes mainly:Vault (earth's surface) sedimentation, periphery are received Hold back, underground water, face observation, supporting construction observation etc..
Further, the method for the processing survey data in the step S200 is as follows:
A satisfactory value and not permissible value first are determined to each single item risk target, obtain the satisfactory value of evaluation index:Xhi(i =1,2 ..., n) and evaluation goal not permissible value Xsi(i=1,2 ..., n), XhiAnd XsiRespectively i-th evaluation index The not permissible value of satisfactory value and i-th of evaluation index;
Then expert gives a mark to the factual survey result of every risk target, obtains the actual value of evaluation index:Xi (i=1,2 ..., n), Xi are the actual value of i-th of evaluation index.
Further, the methods of risk assessment in the step S300 is " efficiency coefficient method ", obtains efficiency coefficient value Computational methods are as follows:
S301, the effect of a evaluation index coefficient value is calculated:
diFor i-th of evaluation index the effect of coefficient value;
After S302, expert score to every risk target, normalized weight is obtained using analytic hierarchy process (AHP), utilize with Lower formula calculates normalized weight coefficient:
PiAnd wiThe normalized weight coefficient of the flexible strategy and i-th of evaluation index of respectively i-th evaluation index;
S303, the general power coefficient value according to the result Calculation Estimation object of two above formula:
D is general power coefficient value.
Further, total efficiency coefficient value criteria for classification in the step S400 is as follows:
(1) for total efficiency coefficient value within the scope of 60-70, risk class is evaluated as highest, at this moment using red instruction, in advance Alert rank is emergency alarm;
(2) total efficiency coefficient value is within the scope of 70-80, and risk class is evaluated as medium, at this moment uses orange instruction, in advance Alert rank is moderate alarm;
(3) total efficiency coefficient value is within the scope of 80-90, and risk class is evaluated as relatively low, at this moment yellow is used to indicate, in advance Alert rank is slight alarm;
(4) for total efficiency coefficient value within the scope of 90-100, risk class is evaluated as minimum, at this moment use green instruction, Warning level is no alarm.
6. a kind of management method of tunnels and underground engineering risk, includes the following steps:
S500, risk management layer is determined;
S600, risk management target is formulated;
S700, risk management contents are formulated;
S800, it checks simultaneously whether hard objectives risk solves and release, if not releasing, reappraises simultaneously managing risk mesh Mark.
Further, the risk management layer in the step S500 includes:
Owner's layer:First manager, responsible person, risk management functional department and the relevant departments for being responsible for risk management;
Subject of implementation layer:Designing unit, unit in charge of construction, supervisor etc., each subject of implementation should establish risk management respectively Group.
Further, the step of risk management target is formulated in the step S600 is as follows:
S601, by the way that risk analysis and preliminary assessment, ratio is selected into row line and tunnel multi-scheme, propose that each scheme exists Risk, specify risk class, be fabricated to Risk Assessment Report;
S602, evade material risk, prevent smaller risk, reduce the preliminary measure of risk, the decision for that can study provides Foundation.
Further, the step of risk management contents are formulated in the step S700 is as follows:
S701, owner's layer first examine unit mass guarantee system and counting accountability at different levels;
S702, designing unit are according to risk assessment and management on last stage as a result, real-time update risk information and risk The corresponding control measure of target, the risk management specific implementation mode and detailed rules and regulations in this stage are write in design, to cope at any time i.e. By the risk situation of arrival;
S702, risk management report is write, and indicates the various points for attention proposed in risk management.
The prior art is compared, the beneficial effects of the invention are as follows:
(1) efficiency coefficient method of the present invention can easily calculate total efficiency coefficient value, can determine whether according to risk assessment hierarchical table With the risk class for determining target, and provided with " red, orange, yellow, green " etc. " four color alerts ", be more advantageous to corresponding risk into The hand-manipulating of needle is to operation, to evade risk;
(2) general power Y-factor method Y of the invention calculates power value-at-risk and is easily understood, and calculating process is simple, can be easily quick Ground obtains the risk class of monitoring objective, and to make, administrative staff formulate scheme of controlling risk faster, more in time and solution is asked The measure of topic, to which the risk of constructing tunnel and loss are reduced to minimum;
(3) Each performs its own functions with designing unit for owner's layer, and the division of labor is clear, and cooperating with each other makes the management process Jing Jing of risk have Item greatly can control risk factors or be solved to dynamics, and ensure the stability of construction safety and construction progress, and manage Reason personnel carry out quadratic risk function assessment to risk target, to by remaining risk control to tolerance interval, greatly protect The safety for having hindered construction personnel has ensured construction speed and construction property safety.
Description of the drawings
Fig. 1 is the risk assessment of the present invention and the flow diagram of management method.
Figure label:
1- quadrupods;2- semicircles are open;3- shaft mounting plates;4- limit rotary shaft columns;5- limiting slots;The single ladders of 6-;7- Idler wheel;8- brake plates;9- pneumatic cylinders;10- piston rods;11- regulates and controls plate;12- limiting plates;13- hemispherical hollow caps;
301- fixed mounting plates;302- movable installation boards;303- inserted blocks;304- slots;305- hinges;401- spindle posts;
402- rotates jack-post;403- gangboard mounting grooves.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1, the present invention provides a kind of tunnels and underground engineering risk assessment and management method, a kind of tunnel and Underground engineering methods of risk assessment, includes the following steps:
S100, risk target and monitoring index content, a certain area inside risk target, that is, tunnel or underground engineering are determined The need detection region in domain and object are set up panel of expert and are investigated risk target, preferably carry out profession using multiple experts Property detection, obtain the survey data of risk target, after the survey data got, first integrate the data of all experts, Cast out and differ maximum two data with median, is then averaged, the average value obtained in this way is more convincing, wind The result nearly assessed is also just relatively reliable.
Monitoring index content in the step S100 includes mainly:Vault (earth's surface) sedimentation, perimeter convergence, underground water, Face observation, supporting construction observation etc..
The judgment method of vault (earth's surface):Vault (earth's surface) sedimentation value is compared with monitoring criteria value, and to vault (earth's surface) settling data is further processed, and can obtain vault (earth's surface) rate of settling, if sedimentation value is more than monitoring criteria value, Then using the rate of settling as leading indicator.
It need to remark additionally, the scoring criterion of every monitoring index content is as follows:
(1) ground settlement satisfactory value XhiFor 30mm, not permissible value XsiFor 100mm, and the satisfactory value X of ground settlement ratehiFor 0.2mm/d, not permissible value XsiFor 5mm/d;
(2) judgement of perimeter convergence is similar to the sedimentation of vault, the satisfactory value X of perimeter convergencehiFor 16mm, not permissible value XsiFor 80mm, the satisfactory value X of perimeter convergence ratehiFor 0.2mm/d, not permissible value XsiFor 5mm/d;
(3) according to underground water, there are the case where volume to give a mark, and is divided into anhydrous (100 points), infiltration (70 points), water clock (40 points) shove (20 points), spray (0 point);
(4) evaluation index of face is determined by expert estimation, is divided into five kinds of situations according to the degree of stability of face, is beaten Divide situation as follows:Excellent stability (100 points), stability good (75 points), stability general (50 points), stability poor (25 points) and Stability is very poor (0 point);
(5) free from flaw (100 points), a little crack (75 points), small area are divided into according to the variation degree of Tunnel Five kinds of situations such as (0 point) that cracking (50 points), supporting wall peel off (25 points), supporting is caved in.
(5) the satisfactory value X of underground water, face and supporting constructionhiIt is 100 points, not permissible value XsiIt is 0 point.
S200, the data of investigation are handled, obtains a series of set of research and appraisal indexs, the evaluation index of investigation Actual value (X including evaluation index1, X2... Xi... Xn), i.e., the marking numerical value that expert carries out according to the actual result of investigation. And expert can obtain the not permissible value (X of evaluation index according to standard as defined in data or national projects1, Xs2... Xsi... Xsn) With the satisfactory value (X of evaluation indexh1, Xh2... Xhi... Xhn), facilitate the calculating of follow-up efficiency coefficient value.
The method of processing survey data in the step S200 is as follows:
A satisfactory value and not permissible value first are determined to each single item risk target, obtain the satisfactory value of evaluation index:Xhi(i =1,2 ..., n) and evaluation goal not permissible value Xsi(i=1,2 ..., n), XhiAnd XsiRespectively i-th evaluation index The not permissible value of satisfactory value and i-th of evaluation index;
Then expert gives a mark to the factual survey result of every risk target, obtains the actual value of evaluation index:Xi (i=1,2 ..., n), Xi are the actual value of i-th of evaluation index.
Methods of risk assessment in the step S300 is " efficiency coefficient method ", obtains the computational methods of efficiency coefficient value such as Under:
S300, the effect of determining methods of risk assessment, being calculated according to appraisal procedure and assess risk target coefficient value; S301, the effect of a evaluation index coefficient value is calculated:
diFor i-th of evaluation index the effect of coefficient value;
After S302, expert score to every risk target, normalized weight is obtained using analytic hierarchy process (AHP), utilize with Lower formula calculates normalized weight coefficient:
PiAnd wiThe normalized weight coefficient of the flexible strategy and i-th of evaluation index of respectively i-th evaluation index;
S303, the general power coefficient value according to the result Calculation Estimation object of two above formula:
D is general power coefficient value.
S400, calculated total efficiency coefficient value is classified by rule, management and prevention so as to administrative staff to risk.
Preferably, risk factor calculation formula is easily understood, and calculating process is not cumbersome, is obtained to risk evaluation result Provide a convenient, risk factor made quickly to obtain, to enable administrative staff faster, control tunnel and underground work more in time Risk in journey, and specify corresponding measure in time and implement to solve safety problem and risk in construction, it is construction personnel Good, safety a construction environment is provided with neighbouring resident, has evaded risk, has reduced the security risk of construction, reduced The loss of engineering property.
Total efficiency coefficient value criteria for classification in the step S400 is as follows:
(1) for total efficiency coefficient value within the scope of 60-70, risk class is evaluated as highest, at this moment using red instruction, in advance Alert rank is emergency alarm;
(2) total efficiency coefficient value is within the scope of 70-80, and risk class is evaluated as medium, at this moment uses orange instruction, in advance Alert rank is moderate alarm;
(3) total efficiency coefficient value is within the scope of 80-90, and risk class is evaluated as relatively low, at this moment yellow is used to indicate, in advance Alert rank is slight alarm;
(4) for total efficiency coefficient value within the scope of 90-100, risk class is evaluated as minimum, at this moment use green instruction, Warning level is no alarm.
To the observation of risk class and corresponding measure is worked out for convenience of appraiser, facilitates administrative staff and appraiser It is as follows to have made risk assessment hierarchical table for the conclusion for compareing and obtaining risk class size:
Total work rate coefficient D Risk class Early warning color indicates Warning level or degree
60-70 Highest It is red Emergency alarm
70-80 It is medium Orange Moderate is alarmed
80-90 It is relatively low It is yellow Slight alarm
90-100 It is minimum It is green Without alarm
After monitoring and evaluating tunnel and the risk factor and risk class of underground engineering, need to corresponding risk target It is controlled, risk factors is avoided to cause the loss of larger security risk and property.
Preferably, after easily calculating total efficiency coefficient value according to efficiency coefficient method, according to risk assessment hierarchical table Judge and determine the risk class of target, and provided with " four color alerts " such as " red, orange, yellow, green ", is more advantageous to corresponding wind Danger is carried out for operation, to evade risk.
When the risk class of risk assessment prediction slight alarm and it is following when, that is, yellow, green alert when, can press Former scheme construction, but the moment is wanted to detect the variation of slight alarm region in constructing, one have the case where Alert Level rising immediately on Report and determining Managed Solution;
When the risk class that risk assessment goes out is middle rank or highest, illustrate that tunnel landform deforms big, risk factor At this moment height should be reinforced monitoring and observing dynamics, in time, correctly adjust arrangement and method for construction, and controlled accordingly to risk target System, takes appropriate measures, prevents the generation of large deformation disaster.
A kind of management method of tunnels and underground engineering risk, includes the following steps:
S500, risk management layer is determined, the personnel of the participation tunnel risk management in risk management layer are pre-job necessary Training is participated in, the compromise of risk control status, the solution of security risk, property loss minimum is understood and learn how to formulate Scheme etc..Risk management layer in the step S500 includes:
Owner's layer:First manager, responsible person, risk management functional department and the relevant departments for being responsible for risk management, industry Main layer can also invite expert group to carry out assistance management if necessary, to keep risk control relatively reliable, more professional.It is real Apply body layer:Designing unit, unit in charge of construction, supervisor etc., each subject of implementation should establish risk management group respectively.
S600, the step of formulating risk management target, risk management target is formulated in the step S600 is as follows:
S601, by risk analysis and preliminary assessment, ratio being selected into row line and tunnel multi-scheme, to avoid in risk Big region carries out the construction of tunnels and underground engineering, avoids possible property loss and safety problem, proposes that each scheme is deposited Risk, specify risk class, be fabricated to Risk Assessment Report.
S602, evade material risk, can be realized by explosion or modification arrangement and method for construction or route, prevent smaller risk, it will Risk control reduces the preliminary measure of risk, the decision for that can study provides foundation in the acceptable range of minimum.
S700, the step of formulating risk management contents, risk management contents are formulated in the step S700 is as follows:
S701, owner's layer first examine unit mass guarantee system and counting accountability at different levels, to ensure to construct The safety of quality, stability, ensure the safety of construction equipment, the reasonability of equipment placement location and apply under high temperature environment The safety prevention measure of work, to reducing risk as much as possible, reducing the security risk of construction and reducing the property of construction Loss.
S702, designing unit are according to risk assessment and management on last stage as a result, real-time update risk information and risk The corresponding control measure of target, the risk management specific implementation mode and detailed rules and regulations in this stage are write in design, to cope at any time i.e. By the risk situation of arrival, after risk management embodiment and detailed rules and regulations make, operating personnel's implement general plan control should be allowed in time System and issue-resolution, to reduce or thoroughly solve security risk and greater risk.
S702, risk management report is write, and indicates the various points for attention proposed in risk management.
Each performs its own functions with designing unit for owner's layer, and the division of labor is clear, and cooperating with each other keeps the management process of risk in perfect order, energy Very big dynamics risk factors are controlled or are solved, have ensured the stability of construction safety and construction progress.
S800, it after implementing corresponding risk control operation, checks and whether hard objectives risk solves and release, that is, carry out Quadratic risk function is assessed, and judges risk whether in tolerance interval, if residual risk is larger, reappraises simultaneously managing risk mesh Mark, finishes when the residual risk in risk target no longer threatens to engineering or worker.This process continues to The construction stage of tunnel or underground engineering terminates, and ensures the safety of construction personnel and resident.After the completion of later stage Tunnel Engineering, need Periodic maintenance is carried out to tunnel and detects its stability, safety.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Profit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.

Claims (9)

1. a kind of tunnels and underground engineering methods of risk assessment, it is characterised in that:Include the following steps:
S100, risk target and monitoring index content are determined, sets up panel of expert and risk target is investigated, obtains risk mesh Target survey data;
S200, the data of investigation are handled, obtains a series of set of research and appraisal indexs;
S300, the effect of determining methods of risk assessment, being calculated according to appraisal procedure and assess risk target coefficient value;
S400, calculated total efficiency coefficient value is classified by rule, management and prevention so as to administrative staff to risk.
2. a kind of tunnels and underground engineering methods of risk assessment according to claim 1, it is characterised in that:The step Monitoring index content in S100 includes mainly:Vault (earth's surface) sedimentation, perimeter convergence, underground water, face observation, supporting knot Structure observation etc..
3. a kind of tunnels and underground engineering methods of risk assessment according to claim 1, it is characterised in that:The step The method of processing survey data in S200 is as follows:
A satisfactory value and not permissible value first are determined to each single item risk target, obtain the satisfactory value of evaluation index:Xhi(i=1, 2 ..., n) and evaluation goal not permissible value Xsi(i=1,2 ..., n), XhiAnd XsiThe satisfaction of respectively i-th evaluation index The not permissible value of value and i-th of evaluation index;
Then expert gives a mark to the factual survey result of every risk target, obtains the actual value of evaluation index:Xi(i=1, 2 ..., n), Xi is the actual value of i-th of evaluation index.
4. a kind of tunnels and underground engineering methods of risk assessment according to claim 1, it is characterised in that:The step Methods of risk assessment in S300 is " efficiency coefficient method ", show that the computational methods of efficiency coefficient value are as follows:
S301, the effect of a evaluation index coefficient value is calculated:
diFor i-th of evaluation index the effect of coefficient value;
After S302, expert score to every risk target, normalized weight is obtained using analytic hierarchy process (AHP), utilizes following public affairs Formula calculates normalized weight coefficient:
PiAnd wiThe normalized weight coefficient of the flexible strategy and i-th of evaluation index of respectively i-th evaluation index;
S303, the general power coefficient value according to the result Calculation Estimation object of two above formula:
D is general power coefficient value.
5. a kind of tunnels and underground engineering methods of risk assessment according to claim 1, it is characterised in that:The step Total efficiency coefficient value criteria for classification in S400 is as follows:
(1) for total efficiency coefficient value within the scope of 60-70, risk class is evaluated as highest, at this moment using red instruction, early warning grade It Wei not emergency alarm;
(2) total efficiency coefficient value is within the scope of 70-80, and risk class is evaluated as medium, at this moment uses orange instruction, early warning grade It Wei not moderate alarm;
(3) total efficiency coefficient value is within the scope of 80-90, and risk class is evaluated as relatively low, at this moment yellow is used to indicate, early warning grade It Wei not slight alarm;
(4) for total efficiency coefficient value within the scope of 90-100, risk class is evaluated as minimum, at this moment use green instruction, early warning Rank is no alarm.
6. a kind of management method of tunnels and underground engineering risk, it is characterised in that:Include the following steps:
S500, risk management layer is determined;
S600, risk management target is formulated;
S700, risk management contents are formulated;
S800, it checks simultaneously whether hard objectives risk solves and release, if not releasing, reappraises simultaneously managing risk target.
7. a kind of management method of tunnels and underground engineering risk according to claim 6, it is characterised in that:The step Risk management layer in S500 includes:
Owner's layer:First manager, responsible person, risk management functional department and the relevant departments for being responsible for risk management;
Subject of implementation layer:Designing unit, unit in charge of construction, supervisor etc., each subject of implementation should establish risk management group respectively.
8. a kind of management method of tunnels and underground engineering risk according to claim 6, it is characterised in that:The step The step of risk management target is formulated in S600 is as follows:
S601, by risk analysis and preliminary assessment, selecting ratio into row line and tunnel multi-scheme, proposing wind existing for each scheme Danger, specifies risk class, is fabricated to Risk Assessment Report;
S602, evade material risk, prevent smaller risk, reduce the preliminary measure of risk, the decision for that can study provides foundation.
9. a kind of management method of tunnels and underground engineering risk according to claim 6, it is characterised in that:The step The step of risk management contents are formulated in S700 is as follows:
S701, owner's layer first examine unit mass guarantee system and counting accountability at different levels;
S702, designing unit are according to risk assessment and management on last stage as a result, real-time update risk information and risk target Corresponding control measure, design are write the risk management specific implementation mode and detailed rules and regulations in this stage, will be arrived with coping at any time The risk situation come;
S702, risk management report is write, and indicates the various points for attention proposed in risk management.
CN201810454897.3A 2018-05-14 2018-05-14 A kind of tunnels and underground engineering risk assessment and management method Pending CN108629524A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810454897.3A CN108629524A (en) 2018-05-14 2018-05-14 A kind of tunnels and underground engineering risk assessment and management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810454897.3A CN108629524A (en) 2018-05-14 2018-05-14 A kind of tunnels and underground engineering risk assessment and management method

Publications (1)

Publication Number Publication Date
CN108629524A true CN108629524A (en) 2018-10-09

Family

ID=63693040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810454897.3A Pending CN108629524A (en) 2018-05-14 2018-05-14 A kind of tunnels and underground engineering risk assessment and management method

Country Status (1)

Country Link
CN (1) CN108629524A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113837664A (en) * 2021-11-03 2021-12-24 天津电力工程监理有限公司 Project risk analysis system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104133985A (en) * 2014-07-02 2014-11-05 山东大学 Evaluation method of geological disaster risk attribute interval of tunnel and underground construction

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104133985A (en) * 2014-07-02 2014-11-05 山东大学 Evaluation method of geological disaster risk attribute interval of tunnel and underground construction

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
谢全敏 等: "基于功效系数法的滑坡灾害风险评估研究", 《水利水电技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113837664A (en) * 2021-11-03 2021-12-24 天津电力工程监理有限公司 Project risk analysis system

Similar Documents

Publication Publication Date Title
CN110852577B (en) Urban flood assessment method based on urban toughness and urban watershed hydrologic model
CN109000158B (en) Pipeline leakage early warning system and method based on Internet of things and BIM and application thereof
CN107332698A (en) A kind of Security Situation Awareness Systems and method towards bright Great Wall intelligent perception system
CN104281920A (en) Tailing pond layered index safety assessment and early-warning method and system
CN103426137B (en) A kind of drainage pipeline defect quantitative comprehensive estimation method
CN106779320A (en) A kind of gas pipeline damage from third-party methods of risk assessment based on fuzzy mathematics
CN110490432B (en) Bidirectional reference characteristic fire-fighting risk assessment method and system based on Hausdorff distance
CN110675038A (en) Urban underground comprehensive pipe gallery risk assessment method based on control force
CN113515720B (en) Method for identifying and evaluating major safety risk of dangerous chemical enterprise
CN112071032A (en) Dangerous chemical major hazard source alarm hierarchical management system
Li et al. [Retracted] Construction of Urban Flood Disaster Emergency Management System Using Scenario Construction Technology
CN109118039B (en) Inland water area oriented ship self-sinking important risk identification, prevention and control device and method
Meng et al. Risk assessment of deep foundation pit construction based on analytic hierarchy process and fuzzy mathematics
CN113506001A (en) Intelligent management and control auxiliary decision method for lean safety risk of operation site
CN108629524A (en) A kind of tunnels and underground engineering risk assessment and management method
Sadeghi et al. Identification and prioritization of seismic risks in urban worn-out textures using fuzzy delphi method
Han et al. An Online safety monitoring system of hydropower station based on expert system
CN101882294A (en) urban fire risk assessment method based on criterion
Junjia et al. Identification and analysis of hoisting safety risk factors for IBS construction based on the AcciMap and cases study
JP2004164591A (en) Flood prevention supporting apparatus, flood prevention supporting program and flood prevention support method
CN105590034A (en) Flood prevention and disaster reduction capability evaluation model
CN113077170A (en) Emergency capacity quantitative evaluation method based on scene construction
CN116957322A (en) Method and device for risk assessment of drainage pipe network
CN115860415A (en) Emergency auxiliary model for accident of oil and gas conveying pipeline
Xie et al. Notice of retraction: The fuzzy comprehensive evaluation of the highway emergency plan based on G1 method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB02 Change of applicant information

Address after: 100011 No. 88, Anding outside street, Dongcheng District, Beijing No. 1008

Applicant after: CHINA ROAD & BRIDGE Corp.

Address before: 100011 No. 88, Anding outside street, Dongcheng District, Beijing.

Applicant before: CHINA ROAD & BRIDGE Corp.

CB02 Change of applicant information
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181009

RJ01 Rejection of invention patent application after publication