CN108612318A CN201810540705.0A CN201810540705A CN108612318A CN 108612318 A CN108612318 A CN 108612318A CN 201810540705 A CN201810540705 A CN 201810540705A CN 108612318 A CN108612318 A CN 108612318A
Authority
CN
China
Prior art keywords
prefabricated panel
bolt
flower basket
construction
adjusted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810540705.0A
Other languages
Chinese (zh)
Inventor
周建敏
徐冰
魏尚起
孙剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201810540705.0A priority Critical patent/CN108612318A/en
Publication of CN108612318A publication Critical patent/CN108612318A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)

Abstract

The present invention relates to a kind of installation adjusting methods of prefabricated panel, include the following steps:One:At least two groups bolt hole is reserved on prefabricated panel, every group of number of bolt hole is two;Two:Prefabricated panel is transported to after construction site, is first checked its appearance and size and prepared screw-bolt hole, confirms that errorless rear lifting is in place;Three:It after lifting is in place, is installed on prefabricated panel and flower basket bolt is adjusted, flower basket bolt one end is bolted with prefabricated panel, and the flower basket bolt other end is fixed to ground using chemical bolt;Four:The verticality that prefabricated panel is adjusted by adjusting adjustable flower basket bolt carries out the installation of wallboard and the component being connected after adjustment, after finally reaching some strength, remove and flower basket bolt is adjusted.The present invention effectively solves to solve the construction difficult problem of lifting, the adjustment of prefabricated panel, saves construction cost, reduces construction risk, improves construction efficiency.

Description

The installation adjusting method of prefabricated panel
Technical field
The present invention relates to a kind of installations of prefabricated panel, the specifically installation adjusting method of prefabricated panel.
Background technology
With the continuous improvement of housing industrialization level, prefabricated outer wall panel, precast beam, precast stair etc. are building work Application in journey is more and more extensive.But for PC components, the installation procedures such as lifting adjustment have component certain damage, such as What, which further strengthens work progress, is particularly important the finished product protection of component.
According to fabricated construction technique needs, prefabricated panel mounting and adjusting is the key that construction, but prefabricated components are installed It can not be fixed at once after in place, and verticality can not ensure, this just brings certain risk or difficulty of construction to construction.
Invention content
The present invention is directed to overcome the deficiencies of existing technologies, a kind of installation adjusting method of prefabricated panel is provided, is effectively solved The construction difficult problem of lifting, the adjustment of prefabricated panel is solved, construction cost is saved, reduces construction risk, improves construction efficiency.
In order to solve the above-mentioned technical problem, the invention is realized in this way:
A kind of installation adjusting method of prefabricated panel, it is characterised in that it includes the following steps:
Step 1:At least two groups bolt hole is reserved on prefabricated panel, every group of number of bolt hole is two;
Step 2:Prefabricated panel is transported to after construction site, is first checked its appearance and size and prepared screw-bolt hole, is confirmed Lifting is in place after errorless;
Step 3:It after lifting is in place, is installed on prefabricated panel and flower basket bolt is adjusted, flower basket bolt one end is logical with prefabricated panel It crosses and is bolted, the flower basket bolt other end is fixed to ground using chemical bolt;
Step 4:The verticality that prefabricated panel is adjusted by adjusting adjustable flower basket bolt carries out wallboard and is connected after adjustment The installation of the component connect after finally reaching some strength, removes and flower basket bolt is adjusted.
The installation adjusting method of the prefabricated panel, it is characterised in that:Reserved bolt hole is on the prefabricated panel 3-4 groups.
The installation adjusting method of the prefabricated panel, it is characterised in that:The prefabricated panel both sides are respectively mounted adjustable Flower basket bolt.
The beneficial effects of the invention are as follows:The construction difficult problem for effectively solving the adjustment of prefabricated panel verticality, saves construction Cost reduces construction risk, improves construction efficiency, safety easy for construction;The present invention is versatile, and construction is relatively flexible, adapts to The construction of various specifications prefabricated panel.
Description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the structural schematic diagram of prefabricated panel.
Fig. 2 is prefabricated panel scheme of installation.
Specific implementation mode
As shown in Figure 1, 2:A kind of installation adjusting method of prefabricated panel, it includes the following steps:
According to fabricated construction technique needs, prefabricated panel mounting and adjusting is the key that construction, but prefabricated components are installed in place After can not be fixed at once, and verticality can not ensure, this just brings certain risk or difficulty of construction, this hair to construction Bright new construction method effectively avoids problem above, easy for construction, safety, and construction cost is low.
Specific implementation step:
Before implementation starts:
According to the appearance and size of prefabricated panel 1, the factors such as weight, and require PC components factory on prefabricated panel(On wallboard At lower edge 800mm)Each to reserve two groups of bolts hole 2, every group of number of bolt hole is 2, for middle-size and small-size wallboard, reserves two above Group bolt hole, but for large-scale component, 3-4 group bolts hole, the adjustment after being easily installed can be reserved.
Implementation process:
Prefabricated panel is transported to after construction site, and first to its appearance and size, suspender prepared screw-bolt hole is checked, after confirmation is errorless Lifting is in place.
It after lifting is in place, is installed on prefabricated panel and flower basket bolt 3 is adjusted, flower basket bolt one end passes through bolt with wallboard Connection, the other end are fixed to ground, are fixed using chemical bolt 4, for large-scale or larger weight prefabricated panel, wallboard both sides It is required to mounting and adjusting flower basket bolt, ensures construction safety and conveniently;
The verticality that prefabricated panel is adjusted by adjusting flower basket bolt carries out the peace of wallboard and the component being connected after adjustment Dress after finally reaching some strength, removes adjustment flower basket bolt.

Claims (3)

1. a kind of installation adjusting method of prefabricated panel, it is characterised in that it includes the following steps:
Step 1:At least two groups bolt hole is reserved on prefabricated panel, every group of number of bolt hole is two;
Step 2:Prefabricated panel is transported to after construction site, is first checked its appearance and size and prepared screw-bolt hole, is confirmed Lifting is in place after errorless;
Step 3:It after lifting is in place, is installed on prefabricated panel and flower basket bolt is adjusted, flower basket bolt one end is logical with prefabricated panel It crosses and is bolted, the flower basket bolt other end is fixed to ground using chemical bolt;
Step 4:The verticality that prefabricated panel is adjusted by adjusting adjustable flower basket bolt carries out wallboard and is connected after adjustment The installation of the component connect after finally reaching some strength, removes and flower basket bolt is adjusted.
2. the installation adjusting method of prefabricated panel according to claim 1, it is characterised in that:It is reserved on the prefabricated panel Bolt hole be 3-4 groups.
3. the installation adjusting method of prefabricated panel according to claim 1, it is characterised in that:The prefabricated panel both sides are equal Flower basket bolt is adjusted in installation.
CN201810540705.0A 2018-05-30 2018-05-30 The installation adjusting method of prefabricated panel Pending CN108612318A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810540705.0A CN108612318A (en) 2018-05-30 2018-05-30 The installation adjusting method of prefabricated panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810540705.0A CN108612318A (en) 2018-05-30 2018-05-30 The installation adjusting method of prefabricated panel

Publications (1)

Publication Number Publication Date
CN108612318A true CN108612318A (en) 2018-10-02

Family

ID=63664522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810540705.0A Pending CN108612318A (en) 2018-05-30 2018-05-30 The installation adjusting method of prefabricated panel

Country Status (1)

Country Link
CN (1) CN108612318A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109296914A (en) * 2018-11-23 2019-02-01 邢道坤 Folded suspension type measuring instrument bracket and its application method
CN113944337A (en) * 2021-10-29 2022-01-18 上海宝冶集团有限公司 Prefabricated wall installation elevation control method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2334067C1 (en) * 2006-12-07 2008-09-20 Общество с ограниченной ответственностью "Свой дом" Method of columns assembly and device for columns gripping
CN102230315A (en) * 2011-04-18 2011-11-02 有利华建筑预制件有限公司 Prefabricated part and semi-prefabricated construction method for multistory building
CN104790676A (en) * 2015-04-29 2015-07-22 中国十七冶集团有限公司 Rapid leveling and alignment device and method for installation of prefabricated wallboards
CN107558746A (en) * 2017-11-06 2018-01-09 新疆远大华美建筑工业有限公司 A kind of out-hung panel bearing diagonal fixing means and instrument
CN207332338U (en) * 2017-10-13 2018-05-08 三峡大学 A kind of assembled architecture wallboard adjustment mechanism

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2334067C1 (en) * 2006-12-07 2008-09-20 Общество с ограниченной ответственностью "Свой дом" Method of columns assembly and device for columns gripping
CN102230315A (en) * 2011-04-18 2011-11-02 有利华建筑预制件有限公司 Prefabricated part and semi-prefabricated construction method for multistory building
CN104790676A (en) * 2015-04-29 2015-07-22 中国十七冶集团有限公司 Rapid leveling and alignment device and method for installation of prefabricated wallboards
CN207332338U (en) * 2017-10-13 2018-05-08 三峡大学 A kind of assembled architecture wallboard adjustment mechanism
CN107558746A (en) * 2017-11-06 2018-01-09 新疆远大华美建筑工业有限公司 A kind of out-hung panel bearing diagonal fixing means and instrument

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109296914A (en) * 2018-11-23 2019-02-01 邢道坤 Folded suspension type measuring instrument bracket and its application method
CN113944337A (en) * 2021-10-29 2022-01-18 上海宝冶集团有限公司 Prefabricated wall installation elevation control method

Similar Documents

Publication Publication Date Title
CN108612318A (en) The installation adjusting method of prefabricated panel
CN106869368A (en) A kind of assembling type steel structure external hanging type wallboard base-supporting attachment structure
CN206174138U (en) Joint construction suitable for steel house room externally -hanging wallboard and major structure
CN206054945U (en) A kind of low cost list branch pipe(tube) antidetonation crane system
CN209227877U (en) Hood type ceiling system for steel structure truss roof system
CN204164505U (en) Universal Joining clasp lifting device
CN103526866B (en) Dry-hang stone curtain wall and mounting method thereof
CN103541477B (en) For keel and the mounting method thereof of dry-hang stone curtain wall
CN110566241A (en) Quickly-assembled supporting shed frame
CN206607709U (en) A kind of assembling type steel structure external hanging type wallboard base-supporting attachment structure
CN215443391U (en) Transmission line and 5G communication sharing steel pipe pole
CN205100443U (en) Be used for overlength industry factory building siphon drainage system
CN206575034U (en) A kind of power distribution cabinet
CN106013558B (en) A kind of mounting connection structure and installation method of GRC Side fascias complex region
CN201972271U (en) Novel precast reinforced concrete shear wall
CN102777703A (en) Assembly type light pipeline hanger
CN204476179U (en) Auxiliary frame construction and installation fixture
CN208918008U (en) A kind of assembled wallboard and attachment device
CN108999318B (en) Unit curtain wall side buried single pendant structure, unit body with side buried single pendant and unit curtain wall mounting method
CN206118212U (en) Multi -media case with adjustable civil buildings are three -dimensional
CN107269014B (en) Hydraulic climbing formwork angle-variable protective net system
CN206495378U (en) A kind of curtain wall with rainwater collecting function
CN206545219U (en) Airport roof photovoltaic bracket basis and airport roof photovoltaic support structure
CN206800452U (en) A kind of assembled pipe gallery support of industrialized production
CN210566663U (en) Novel pipeline support device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181002