CN108581133A - A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel - Google Patents

A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel Download PDF

Info

Publication number
CN108581133A
CN108581133A CN201810651704.3A CN201810651704A CN108581133A CN 108581133 A CN108581133 A CN 108581133A CN 201810651704 A CN201810651704 A CN 201810651704A CN 108581133 A CN108581133 A CN 108581133A
Authority
CN
China
Prior art keywords
welding
built
steel
plunger
layers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810651704.3A
Other languages
Chinese (zh)
Inventor
戴荣根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Rong Heavy Industry Co Ltd
Original Assignee
Zhejiang Rong Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Rong Heavy Industry Co Ltd filed Critical Zhejiang Rong Heavy Industry Co Ltd
Priority to CN201810651704.3A priority Critical patent/CN108581133A/en
Publication of CN108581133A publication Critical patent/CN108581133A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/04Welding for other purposes than joining, e.g. built-up welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K9/00Arc welding or cutting
    • B23K9/235Preliminary treatment

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Plasma & Fusion (AREA)
  • Mechanical Engineering (AREA)
  • Arc Welding In General (AREA)

Abstract

The invention discloses a kind of production methods of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel, including using No. 35 steel to make piston body, after being derusted, being deoiled and being preheated to piston body, in three layers of piston body surface overlaying 2Cr13,3Cr13 or 4Cr13 stainless steel, again plunger is obtained after expanding hydrogen processing, the plunger processed using this method, it is controlled using stringent built-up welding temperature, three layers of martensitic stain less steel of built-up welding in plunger body, it is effectively prevent cold crack, cost is reduced while ensureing plunger hardness.

Description

A kind of production of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel Method
Technical field
The present invention relates to the production methods of hydraulic test plunger, particularly relate to a kind of heavy hydraulic equipment carbon steel plunger surface The production method of built-up welding martensitic stain less steel.
Background technology
Plunger is the core component of hydraulic test, and the continuous abrasion during use with cylinder body can make gap increase and leak Liquid causes pressure to reduce, can not normal use, therefore hardness to plunger and wearability and recoverability have higher want It asks.General hydraulic test plunger is all made of but in heavy hydraulic equipment, stainless steel to be used to make plunger using stainless steel It is to do piston body with carbon steel that can lead to way with high costs, common, and in carbon steel body outer cladding stainless steel sleeve, Ci Zhongfang Although method can reduce cost, the compactness between stainless steel sleeve and carbon steel body can influence the mechanical property of plunger, therefore should Method nor preferred plan.When making wearing layer on other field workpiece, martensitic stain less steel wearing layer is obtained using built-up welding, But the martensitic structure residual stress generated is big, is also easy to produce cold crack, and as phosphorus content increases, tendency of hardenability increases, cold crack Sensibility increases, therefore its bead-welding technology cannot be applied mechanically directly in plunger production.
Invention content
It is used the purpose of the present invention is to provide a kind of suitable heavy hydraulic equipment, in carbon steel body surface overlaying geneva Body stainless steel, postwelding are not likely to produce cold crack, and overall cost is relatively low, and mechanical property is good while being easy to the plunger producer repaired Method.
To achieve the purpose of the present invention, intend using following technical scheme:
A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel, including following implementation step Suddenly:
1) No. 35 steel are used to make piston body;
2) it derusted, deoiled to piston body;
3) piston body is preheated using preheating furnace, preheating temperature is not less than 200 DEG C, is not higher than 450 DEG C, and in heap It is kept the temperature during weldering;
4) built-up welding is carried out to piston body, specially using 2Cr13,3Cr13 or 4Cr13 stainless steel welding stick, solder flux is SJ107 or HJ260, electric power polarity use DC reverse connection mode, welding current 280-300A, arc voltage 28-30V, weldering Silk wire feed rate is 1.3-1.6m/min, and built-up welding speed is 550-650mm/min;Built-up welding is carried out using 2Cr13 stainless steel welding sticks When, temperature is controlled at 200-350 DEG C, and when carrying out built-up welding using 3Cr13 stainless steel welding sticks, temperature is controlled at 250-400 DEG C, is used When 4Cr13 stainless steel welding sticks carry out built-up welding, temperature is controlled at 300-450 DEG C.Since 2Cr13,3Cr13,4Cr13 martensite are stainless The poor thermal conductivity of steel, postwelding easy to produce larger internal stress, slow this requires paying special attention to postwelding workpiece on bead-welding technology It is cold, Slow cooling in preferably hot sand or preheating furnace.Due to the dilution of alloying element scaling loss and parent metal, deposited metal first The alloying element loss of layer is maximum, and the second layer takes second place, and third layer loss is less.When using automatic submerged arc welding built-up welding, with built-up welding Several increases, alloying element content become closer to the content of the alloying element in welding wire layer by layer.The built-up welding required in order to obtain The ingredient of layer metal, loss of the element in weld deposit process is considered as when selecting alloy welding wire.To make built-up welding when submerged arc overlay welding Layer reaches scheduled performance requirement, necessary three layers of the built-up welding of each plunger or more, specifically, 2000 tons or less hydraulic tests are used Plunger, hardness requirement HRC45-50 degree, built-up welding two layers of 2Cr13, one layer of 3Cr13;2000 tons or more hydraulic test plungers, firmly Degree requires HRC45-50 degree, three layers of 2Cr13 of built-up welding;2000 tons or less hydraulic test plungers, hardness ask HRC50 degree or more , built-up welding two layers of 2Cr13, one layer of 4Cr13;2000 tons or more hydraulic test plungers, hardness ask HRC50 degree or more, built-up welding One layer of 2Cr13, two layers of 3Cr13.
5) post weld heat treatment removes diffusible hydrogen in connector, while can also improve connector to eliminate welding residual stress Tissue and performance;Specifically, for 3 layers of 2Cr13 stainless steels of built-up welding, using technique as shown in Figure 1;
For two layers of built-up welding, mono- layer of 2Cr13 3Cr13 stainless steels, two layers of 2Cr13, mono- layer of 4Cr13 stainless steel or one layer Bis- layers of 3Cr13 stainless steels of 2Cr13, using technique as shown in Figure 2;
6) magnetic powder inspection is done, judges whether defect, if any fewer defects, then uses 2Cr13 stainless steel electrode reparations to polish;Such as Defect is more than surface area 15%, then re-works rear built-up welding.
Preferably, the 2Cr13 stainless steel weld overlays thickness in monolayer is 2-2.5mm;2Cr13 stainless steel weld overlays Transition zone is acted mainly as, only in 2000 tons or more hydraulic test plungers, hardness requirement HRC45-50 degree, 2Cr13 stainless steels Overlay cladding can be used as face layer.
Preferably, the 3Cr13 stainless steel weld overlays thickness in monolayer is 2-2.5mm;3Cr13 stainless steel weld overlays Face layer is acted mainly as, there is excellent wearability and recoverability, meets the requirement of plunger service life.
Preferably, the 4Cr13 stainless steel weld overlays thickness in monolayer is 2-2.5mm;4Cr13 stainless steel weld overlays, With excellent wearability and recoverability, meet the requirement of plunger service life.
The invention has the advantages that make plunger bodies with No. 35 steel, and on straight carbon steel ontology built-up welding 2Cr13, 3Cr13 or 4Cr13 martensitic stain less steels are controlled using stringent built-up welding temperature, and three layers of martensite of built-up welding are not in plunger body Become rusty steel, effectively prevent cold crack, cost is reduced while ensureing plunger hardness.
Description of the drawings
Fig. 1 is the post weld heat treatment artwork of 3 layers of 2Cr13 stainless steels of built-up welding;
Fig. 2 is two layers of built-up welding, mono- layer of 2Cr13 3Cr13 stainless steels, two layers of 2Cr13, mono- layer of 4Cr13 stainless steel or one layer The post weld heat treatment artwork of bis- layers of 3Cr13 stainless steels of 2Cr13.
Specific implementation mode
Embodiment 1
1500 tons of hydraulic tests use, and hardness requirement HRC50 degree is with upper plug.Using following production method:
1) No. 35 steel are used to make piston body;
2) it derusted, deoiled to piston body;
3) piston body is preheated using preheating furnace, preheating temperature is 300 DEG C, and is kept the temperature in weld deposit process;
4) built-up welding is carried out to piston body, using 2 layers, overall thickness 4-4.5mm of 2Cr13 stainless steel welding sticks built-up welding, then made 1 layer of built-up welding, thickness 2.5mm are carried out with 4Cr13 stainless steel welding sticks.Solder flux is HJ260, and electric power polarity uses DC reverse connection side Formula, welding current 280-300A, arc voltage 28V, welding wire feeding speed are 1.3m/min, and built-up welding speed is 550mm/ min;
5) post weld heat treatment removes diffusible hydrogen in connector, while can also improve connector to eliminate welding residual stress Tissue and performance, technique specially as shown in Figure 2;
6) magnetic powder inspection is done, judges whether defect, if any fewer defects, then uses 2Cr13 stainless steel electrode reparations to polish;Such as Defect is more than surface area 15%, then re-works rear built-up welding.
The plunger produced using the production method, the martensitic stain less steel of built-up welding are reached without cold crack, after tested hardness HRC55 degree, overall cost are remarkably decreased, since with good recoverability, service life greatly prolongs.
Embodiment 2
2500 tons of hydraulic tests use, and hardness requirement HRC50 degree is with upper plug.Using following production method:
1) No. 35 steel are used to make piston body;
2) it derusted, deoiled to piston body;
3) piston body is preheated using preheating furnace, preheating temperature is 300 DEG C, and is kept the temperature in weld deposit process;
4) built-up welding is carried out to piston body, using 1 layer of 2Cr13 stainless steel welding sticks built-up welding, thickness 2mm reuses 3Cr13 Stainless steel welding stick carries out 2 layers of built-up welding, and thickness is overall thickness 4.5mm.Solder flux is HJ260, and electric power polarity uses DC reverse connection side Formula, welding current 280-300A, arc voltage 28V, welding wire feeding speed are 1.4m/min, and built-up welding speed is 600mm/ min;
5) post weld heat treatment removes diffusible hydrogen in connector, while can also improve connector to eliminate welding residual stress Tissue and performance, specific technique as shown in Figure 2;
6) magnetic powder inspection is done, judges whether defect, if any fewer defects, then uses 2Cr13 stainless steel electrode reparations to polish;Such as Defect is more than surface area 15%, then re-works rear built-up welding.
The plunger produced using the production method, the martensitic stain less steel of built-up welding are reached without cold crack, after tested hardness HRC56 degree, overall cost are remarkably decreased, since with good recoverability, service life greatly prolongs.
Embodiment 3
1500 tons of hydraulic tests use, the plunger of hardness requirement HRC45 degree.Using following production method:
1) No. 35 steel are used to make piston body;
2) it derusted, deoiled to piston body;
3) piston body is preheated using preheating furnace, preheating temperature is 300 DEG C, and is kept the temperature in weld deposit process;
4) built-up welding is carried out to piston body, using 2 layers, overall thickness 4-4.5mm of 2Cr13 stainless steel welding sticks built-up welding, then made 1 layer of built-up welding, thickness 2.5mm are carried out with 3Cr13 stainless steel welding sticks.Solder flux is HJ260, and electric power polarity uses DC reverse connection side Formula, welding current 280-300A, arc voltage 28V, welding wire feeding speed are 1.5m/min, and built-up welding speed is 550mm/ min;
5) post weld heat treatment removes diffusible hydrogen in connector, while can also improve connector to eliminate welding residual stress Tissue and performance, specific technique as shown in Figure 2;
6) magnetic powder inspection is done, judges whether defect, if any fewer defects, then uses 2Cr13 stainless steel electrode reparations to polish;Such as Defect is more than surface area 15%, then re-works rear built-up welding.
The plunger produced using the production method, without cold crack, hardness reaches after tested wants the martensitic stain less steel of built-up welding It asks, overall cost is remarkably decreased, since with good recoverability, service life greatly prolongs.
Embodiment 4
3000 tons of hydraulic tests use, the plunger of hardness requirement HRC45 degree.Using following production method:
1) No. 35 steel are used to make piston body;
2) it derusted, deoiled to piston body;
3) piston body is preheated using preheating furnace, preheating temperature is 300 DEG C, and is kept the temperature in weld deposit process;
4) built-up welding is carried out to piston body, uses 3 layers, overall thickness 6-6.5mm of 2Cr13 stainless steel welding sticks built-up welding, solder flux For HJ107, electric power polarity uses DC reverse connection mode, welding current 280-300A, arc voltage 28V, welding wire feeding speed Degree is 1.6m/min, and built-up welding speed is 600mm/min;
5) post weld heat treatment removes diffusible hydrogen in connector, while can also improve connector to eliminate welding residual stress Tissue and performance, specific technique as shown in Figure 1;
6) magnetic powder inspection is done, judges whether defect, if any fewer defects, then uses 2Cr13 stainless steel electrode reparations to polish;Such as Defect is more than surface area 15%, then re-works rear built-up welding.
The plunger produced using the production method, without cold crack, hardness reaches after tested wants the martensitic stain less steel of built-up welding It asks, overall cost is remarkably decreased, since with good recoverability, service life greatly prolongs.

Claims (4)

1. a kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel, including following implementation step Suddenly:
1) No. 35 steel are used to make piston body;
2) it derusted, deoiled to piston body;
3) piston body is preheated using preheating furnace, preheating temperature is not less than 200 DEG C, is not higher than 450 DEG C, and in built-up welding It is kept the temperature in journey;
4) to piston body carry out built-up welding, specially use 2Cr13,3Cr13 or 4Cr13 stainless steel welding stick, solder flux be SJ107 or HJ260, electric power polarity use DC reverse connection mode, welding current 280-300A, arc voltage 28-30V, welding wire feeding speed Degree is 1.3-1.6m/min, and built-up welding speed is 550-650mm/min;When carrying out built-up welding using 2Cr13 stainless steel welding sticks, temperature control System is at 200-350 DEG C, and when carrying out built-up welding using 3Cr13 stainless steel welding sticks, temperature is controlled at 250-400 DEG C, stainless using 4Cr13 When steel welding wire carries out built-up welding, temperature is controlled at 300-450 DEG C;Each plunger must three layers of built-up welding or more, specifically, 2000 tons with Lower hydraulic test plunger, hardness requirement HRC45-50 degree, built-up welding two layers of 2Cr13, one layer of 3Cr13;2000 tons or more hydraulic pressure Equipment plunger, hardness requirement HRC45-50 degree, three layers of 2Cr13 of built-up welding;2000 tons or less hydraulic test plungers, hardness are asked HRC50 degree or more, built-up welding two layers of 2Cr13, one layer of 4Cr13;2000 tons or more hydraulic test plungers, hardness seek HRC50 degree Above, built-up welding one layer of 2Cr13, two layers of 3Cr13;
5) post weld heat treatment removes diffusible hydrogen in connector, while can also improve the tissue of connector to eliminate welding residual stress And performance;Specifically, for 3 layers of 2Cr13 stainless steels of built-up welding, using technique as shown in Figure 1;
For two layers of built-up welding, mono- layer of 2Cr13 3Cr13 stainless steels, two layers of 2Cr13, mono- layer of 4Cr13 stainless steel or one layer of 2C,r13 bis- Layer 3Cr13 stainless steels, using technique as shown in Figure 2;
6) magnetic powder inspection is done, judges whether defect, if any fewer defects, then uses 2Cr13 stainless steel electrode reparations to polish;Such as defect More than surface area 15%, then rear built-up welding is re-worked.
2. a kind of producer of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel according to claim 1 Method, it is characterised in that:The 2Cr13 stainless steel weld overlays thickness in monolayer is 2-2.5mm.
3. a kind of producer of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel according to claim 1 Method, it is characterised in that:The 3Cr13 stainless steel weld overlays thickness in monolayer is 2-2.5mm.
4. a kind of producer of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel according to claim 1 Method, it is characterised in that:The 4Cr13 stainless steel weld overlays thickness in monolayer is 2-2.5mm.
CN201810651704.3A 2018-06-22 2018-06-22 A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel Pending CN108581133A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810651704.3A CN108581133A (en) 2018-06-22 2018-06-22 A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810651704.3A CN108581133A (en) 2018-06-22 2018-06-22 A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel

Publications (1)

Publication Number Publication Date
CN108581133A true CN108581133A (en) 2018-09-28

Family

ID=63633957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810651704.3A Pending CN108581133A (en) 2018-06-22 2018-06-22 A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel

Country Status (1)

Country Link
CN (1) CN108581133A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3895209A (en) * 1974-02-06 1975-07-15 Maruma Tractor & Equip Metal build-up apparatus
CN101444881A (en) * 2008-11-11 2009-06-03 大连新重集团有限公司 Technology for repairing surfacing of piston rod of super large marine diesel engine
CN102189316A (en) * 2010-03-11 2011-09-21 上海一钢机电有限公司 Submerged-arc welding overlaying repairing method for stainless steel hot rolled delivery roll
CN105499751A (en) * 2015-12-28 2016-04-20 湖北万安通复合再制造科技有限公司 Hardfacing repair process used for hot continuous rolling pinch roll

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3895209A (en) * 1974-02-06 1975-07-15 Maruma Tractor & Equip Metal build-up apparatus
CN101444881A (en) * 2008-11-11 2009-06-03 大连新重集团有限公司 Technology for repairing surfacing of piston rod of super large marine diesel engine
CN102189316A (en) * 2010-03-11 2011-09-21 上海一钢机电有限公司 Submerged-arc welding overlaying repairing method for stainless steel hot rolled delivery roll
CN105499751A (en) * 2015-12-28 2016-04-20 湖北万安通复合再制造科技有限公司 Hardfacing repair process used for hot continuous rolling pinch roll

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
何树民等: "35000KN水压机主柱塞的埋弧自动焊", 《焊接与切割》 *
李科等: "35钢堆焊不锈钢耐磨层的组织与性能", 《热加工工艺》 *
王明中: "1800吨水压机主缸柱塞表面堆焊不锈钢", 《钢管技术》 *

Similar Documents

Publication Publication Date Title
CN103447672B (en) Submerged-arc welding technology of big-thickness low-temperature steel plate with yield strength of 690MPa grade
CN102189316B (en) Submerged-arc welding overlaying repairing method for stainless steel hot rolled delivery roll
US9957583B2 (en) Method for repairing break of universal connecting rod of universal coupling
CN101574861B (en) Titanium-coated aluminium laminated composite plate and preparation method thereof
CN105290703A (en) Method for repairing abraded hot roll through submerged arc bead welding and laser cladding
CN105127205B (en) Large-scale bushing roll for producing strip and preparation method thereof
CN106884118A (en) Forging Electroslag Cladding high-speed steel roll and its manufacture method
CN102091719A (en) Limiting mandrel for mandrel pipe mill and manufacturing method thereof
CN112281153A (en) Nickel-based alloy powder for high-speed laser cladding and cladding method thereof
CN110834139B (en) Method for resistance spot welding of dissimilar metals
CN102500864A (en) Cobalt-base alloy overlaying method of claw of control rod driving mechanism of nuclear power station
CN110814497A (en) Film insulation core non-conductive electrode cap and annular nugget resistance spot welding method
CN100457354C (en) Pile-up welding method of turbine low pressure heater pipe plate and shell, water chamber junction
CN109868469A (en) A kind of dusty material and its manufacturing method for laser manufacture mill housing and roll chock composite liner
CN108581133A (en) A kind of production method of heavy hydraulic equipment carbon steel plunger surface built-up welding martensitic stain less steel
CN114192943A (en) Welding method for austenitic stainless steel cladding
CN101890609B (en) Method for repairing lining plate-free flat-head cap of spindle of rolling mill
CN109570695A (en) Process method for H3Cr13 surfacing on surface of 45 steel
CN108856972A (en) The welding procedure of built-up welding tin bronze on a kind of stainless steel
CN105156672B (en) Deep-sea oil drilling-production equipment connects sealing ring and processing method with high-performance titanium
CN107413878A (en) A kind of milling method for improving wear-resisting steel composite board composite effect
US20220033948A1 (en) Method For Improved Current Contacting When Welding Using A Current-Carrying Wire Electrode
CN103286426A (en) Novel alloy welding process
CN112593230A (en) Laser repairing method for surface of nodular cast iron
CN105499835A (en) Welding material and welding method for repairing straightening rolls of hot-rolling separators

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928

RJ01 Rejection of invention patent application after publication