CN108561137A - A kind of rectangular top tube top iron construction to retract and application method - Google Patents
A kind of rectangular top tube top iron construction to retract and application method Download PDFInfo
- Publication number
- CN108561137A CN108561137A CN201810263090.1A CN201810263090A CN108561137A CN 108561137 A CN108561137 A CN 108561137A CN 201810263090 A CN201810263090 A CN 201810263090A CN 108561137 A CN108561137 A CN 108561137A
- Authority
- CN
- China
- Prior art keywords
- iron
- top iron
- oil cylinder
- rectangular
- jacking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title claims abstract description 420
- 229910052742 iron Inorganic materials 0.000 title claims abstract description 210
- 238000010276 construction Methods 0.000 title claims abstract description 53
- 238000000034 method Methods 0.000 title claims abstract description 14
- 238000003466 welding Methods 0.000 claims description 24
- 239000002699 waste material Substances 0.000 abstract description 3
- 238000005516 engineering process Methods 0.000 description 3
- 230000008878 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reaction Methods 0.000 description 2
- NJFMNPFATSYWHB-UHFFFAOYSA-N ac1l9hgr Chemical compound [Fe].[Fe] NJFMNPFATSYWHB-UHFFFAOYSA-N 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/03—Driving non-circular tunnels
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention relates to a kind of rectangular top tube top iron construction to retract and application methods, it is characterized in that, rectangular top iron and the end face of U-shaped top iron are welded as entirety using several iron blocks, the other end of U-shaped top iron is connected by screw bolts with jacking oil cylinder as entirety, realize rectangular top iron, U-shaped top iron and jacking oil cylinder three linkage, rectangular top iron and U-shaped top iron are connected as entirety on ground, lifted on the guide rail of active well;In rollback jacking oil cylinder, drive rectangular top iron and U-shaped top iron whole along guide rail rollback.The present invention avoid in existing rectangular top pipe construction process every section tube top into after, repeatedly lifting and lower caving iron will waste a large amount of construction time.And the top iron construction that can be retracted considers rectangular top iron, U-shaped top iron and jacking oil cylinder to be connected as entirety, whole rollback rectangular top iron, U-shaped top iron and jacking oil cylinder, to improve construction efficiency.
Description
Technical field
The invention belongs to no-dig technique underground engineering field, the rectangular top tube top iron for being related to retract is to be used for high efficiency push pipe
The auxiliary construction technology of jacking.
Background technology
Rectangular top pipe as a kind of important trenchless technology be widely used in Urban Underground Passage, subway entrance,
The underground engineering constructions such as pipe gallery field, since its excavation area is small, overall cost is low, construction efficiency is high, rectangular cross section is sharp
With the high advantage of rate, there is vast potential for future development in urban underground engineering construction field.
But since rectangular top pipe jacking construction is that each section of prefabricated tube coupling one saves land jacking forward, on the fixed top in rear end
Into oil cylinder per one stroke of jacking forward after, it is necessary to retract oil cylinder, and bulky rectangular top iron and U-shaped is sling and transferred again with crane
Iron is pushed up, is provided for next section section of jurisdiction and places space.This will occupy a large amount of construction time, reduce jacking construction efficiency, cause
Construction cost increases.
Invention content
The purpose of the present invention is to provide a kind of rectangular top tube top iron construction to retract and application methods;It avoids existing
Rectangular top pipe engineering construction every section tube top into after, repeatedly lifting and lower caving iron will waste a large amount of construction time.
And the top iron construction that can be retracted considers rectangular top iron, U-shaped top iron and jacking oil cylinder to be connected as entirety, whole rollback rectangular top
Iron, U-shaped top iron and jacking oil cylinder, to improve construction efficiency.
To achieve the above object, a kind of rectangular top tube top iron construction to retract is designed, which is characterized in that by iron block 1, square
Shape top iron 2, U-shaped top iron 3, the jacking oil cylinder 4 with spherical hinge and guide rail 10 form, the end face of rectangular top iron 2 and U-shaped top iron 3
It is welded as entirety using several iron blocks 1, the other end of U-shaped top iron 3 is connected as entirety using bolt 8 with jacking oil cylinder 4, realizes
Rectangular top iron 2, U-shaped top iron 3 and 4 three of jacking oil cylinder linkage, are connected as rectangular top iron 2 and U-shaped top iron 3 on ground whole
Body lifts on the guide rail 10 of active well 6;In rollback jacking oil cylinder 4, rectangular top iron 2 and the whole edge of U-shaped top iron 3 is driven to lead
Rail 10 retracts.
Lifting jacking oil cylinder 4 and cylinder rack 5 are placed in 7 front end of rear parados.
Jacking oil cylinder 4 needs rollback oil cylinder vacating space to place next section section of jurisdiction when jacking reaches a stroke forward
9。
Welding position of the iron block 1 on two top iron is each two of top iron both sides welding, welding two above iron is pushed up, if top
Iron weight is little, and rectangular top iron 2 and U-shaped top iron 3 can be used and directly carries out spot welding company within each one week in contact interface outer ring and inner ring
The mode connect.
U-shaped top iron 3 is connect using direct welding manner in active well 6 with jacking oil cylinder 4 or bolt 8 connects, 8 specification of bolt
For Φ 20,4 end of jacking oil cylinder is arranged symmetrically 4 bolts 8 up and down.
The end of jacking oil cylinder 4 is a spherical hinge, ensures that there are certain degree of freedom at this in rollback oil cylinder;With it is U-shaped
It pushes up the jacking oil cylinder 4 that iron 3 connects to ensure to arrange with jacking axis longitudinal direction vertical guide symmetry principle, and is arranged since least significant end;
When rectangular top iron is smaller with U-shaped top iron weight, it respectively can arrange one on jacking axis longitudinal direction vertical guide both sides and be connect with U-shaped top iron
Jacking oil cylinder, when rectangular top iron and U-shaped top iron weight are larger, can jacking axis longitudinal direction vertical guide both sides respectively arrangement two and
The jacking oil cylinder of U-shaped top iron connection.
The rectangular top tube top iron construction application method that can be retracted, lifting jacking oil cylinder 4 and cylinder rack 5 are placed in rear parados 7
Front end.Rectangular top iron 2 and U-shaped top iron 3 are connected as entirety on ground, lifted on the guide rail 10 of active well 6.U-shaped top iron with
Band spherical hinge jacking oil cylinder 4 uses bolt 8 to connect, and jacking cylinder movement drives rectangular top iron 2 and the whole front and back shifting of U-shaped top iron 3
It is dynamic, to realize the rectangular top tube top iron construction that can be retracted.
Underground engineering construction is carried out in city, surrounding traffic and trip will unavoidably be impacted, so underground
Engineering construction is very high to construction period, and the reduction of duration will directly or indirectly reduce the cost of engineering.Existing rectangular top pipe
Engineering construction every section tube top into after, lift by crane rectangular top iron and U-shaped top iron, rollback jacking oil cylinder, for next section tube coupling
Transfer vacating space.Lifting and lower caving iron will waste a large amount of construction time repeatedly, the construction period be increased, to improve
Construction cost.And the top iron construction that can be retracted considers rectangular top iron, U-shaped top iron and jacking oil cylinder to be connected as entirety, reduces every
Secondary lifting and two class top iron the time it takes of decentralization.
Compared with prior art, the present invention mainly there is following advantage:
1. construction efficiency is high.It has saved each lifting and has transferred bulky rectangular top iron and U-shaped top iron the time it takes, to
Improve construction efficiency.
2. simple in structure.Only with simple iron block and the modes such as it is bolted and makes rectangular top iron, U-shaped top iron and jacking
Oil cylinder forms an entirety, so the structure and construction method are simple.
3. cost-effective.The labor and time cost that furred ceiling iron is spent has been reduced, efficiency is improved, to be construction
Unit and society reduce cost.
4. wide adaptability.Suitable for rectangular top pipe jacking construction under all operating modes.
Description of the drawings
The rectangular top tube top iron construction figure that Fig. 1 can retract(Jacking oil cylinder reaches one stroke).
The rectangular top tube top iron construction figure that Fig. 2 can retract(Jacking oil cylinder drives top iron to retract).
The U-shaped top iron of Fig. 3 is bolted front view with rectangular top iron iron plate.
The U-shaped top iron of Fig. 4 connect partial enlarged view with spherical hinge jacking oil cylinder.
Description of symbols in figure
After 1 iron block, 2 rectangular top iron, 3 U-shaped top iron 4 is with 5 cylinder rack of spherical hinge jacking oil cylinder, 6 active well 7
8 bolt of parados, 9 section of jurisdiction, 10 guide rail 11 connects bolt.
Specific implementation mode
It is clear to make the object of the invention, principle and construction become apparent from, make below in conjunction with drawings and the specific embodiments further
It illustrates.
As shown in Figure 1, Figure 2, Fig. 3, Fig. 4, the top iron construction that can retract is by iron block 1, rectangular top iron 2, U-shaped top iron 3, band spherical hinge
Jacking oil cylinder 4, connection bolt 8 and guide rail 10, connection bolt 11 form.
As Fig. 1 needs rollback oil cylinder vacating space to place down when jacking reaches a stroke to jacking oil cylinder 4 forward
One section section of jurisdiction 9.This can retract top iron construction be:Rectangular top iron 2 and U-shaped top iron 3 use iron block 1 are welded as entirety, and U-shaped top iron
3 are connected by screw bolts with jacking oil cylinder 4 as entirety.Then, in rollback jacking oil cylinder 4, rectangular top iron 2 and U-shaped top iron 3 are driven
It is whole to retract along guide rail 10, such as Fig. 2.To be next 9 vacating space of section section of jurisdiction, avoid lifting rectangular top iron 2 and U-shaped top repeatedly
3 the time it takes of iron.
Embodiment one:The rectangular top tube top iron construction application method that can be retracted.
1, rectangular top iron 2 and U-shaped top iron 3 are welded as entirety on ground.Iron block 1 and rectangular top iron 2, iron block 1 and U-shaped top
3 welding method of iron is arc welding, and 1 size of iron block is 20cm × 10cm, and the iron block on two top iron is connected using bolt 11, bolt 11
Specification is Φ 50.As shown in figure 3, welding position of the iron block 1 on two top iron is each two of top iron both sides welding, weldering above the iron of top
Connect two.If top iron weight it is little, can rectangular top iron 2 and it is U-shaped top iron 3 welding manner can be directly in contact interface outer ring
It is connected using spot welding within each one week with inner ring.
2, top iron and the connection with spherical hinge jacking oil cylinder 4.First, band spherical hinge jacking oil cylinder 4 is hung in and is placed in
In cylinder rack 5,3 entirety of rectangular top iron 2 and U-shaped top iron being welded is hung on the guide rail 10 of active well 6.If rectangular top iron
2 and U-shaped top iron 3 it is whole weight it is little, U-shaped top iron 3 also can be in active well 6 using direct welding manner company with jacking oil cylinder 4
It connects;If the weight of rectangular top iron 2 and U-shaped 3 entirety of top iron is larger, U-shaped top iron 3 is adopted with jacking oil cylinder 4 in active well 6
It is connected with bolt 8,8 specification of bolt is Φ 20, and 4 end of jacking oil cylinder is arranged symmetrically 4 bolts 8 up and down.
3, the end of jacking oil cylinder 4 is a spherical hinge, ensures that there are certain degree of freedom at this in rollback oil cylinder.With U
The jacking oil cylinder 4 that type top iron 3 connects ensures to arrange with jacking axis longitudinal direction vertical guide symmetry principle, and the cloth since least significant end
It sets.When rectangular top iron 2 is smaller with 3 weight of U-shaped top iron, one and U-shaped top can be respectively arranged on jacking axis longitudinal direction vertical guide both sides
The jacking oil cylinder 4 that iron 3 connects can be each on jacking axis longitudinal direction vertical guide both sides when rectangular top iron 2 is larger with 3 weight of U-shaped top iron
Two jacking oil cylinders 4 being connect with U-shaped top iron 3 of arrangement.
Claims (10)
1. a kind of rectangular top tube top iron construction to retract, which is characterized in that by iron block(1), rectangular top iron(2), U-shaped top iron
(3), jacking oil cylinder with spherical hinge(4)And guide rail(10)Composition, rectangular top iron(2)With U-shaped top iron(3)End face use
Several iron blocks(1)It is welded as entirety, U-shaped top iron(3)Other end and jacking oil cylinder(4)Using bolt(8)Entirety is connected as,
Realize rectangular top iron(2), U-shaped top iron(3)And jacking oil cylinder(4)Three links, on ground rectangular top iron(2)And U-shaped top
Iron(3)It is connected as entirety, is lifted into active well(6)Guide rail(10)On;In rollback jacking oil cylinder(4)When, drive rectangular top iron
(2)And U-shaped top iron(3)Entirety is along guide rail(10)It retracts.
2. a kind of rectangular top tube top iron construction to retract as described in claim 1, which is characterized in that lifting jacking oil cylinder
(4)And cylinder rack(5)It is placed in rear parados(7)Front end.
3. a kind of rectangular top tube top iron construction to retract as described in claim 1, which is characterized in that jacking oil cylinder 4 is forward
When jacking reaches a stroke, rollback oil cylinder vacating space is needed to place next section section of jurisdiction(9).
4. a kind of rectangular top tube top iron construction to retract as described in claim 1, which is characterized in that iron block(1)In Liang Ding
Welding position on iron is each two of top iron both sides welding, pushes up welding two above iron, if top iron weight is little, rectangular top iron
(2)And U-shaped top iron(3)The mode for directly carrying out spot welding with inner ring in contact interface outer ring and connecting for each one week can be used.
5. a kind of rectangular top tube top iron construction to retract as described in claim 1, which is characterized in that U-shaped top iron(3)With top
Into oil cylinder(4)In active well(6)Using the connection of direct welding manner or bolt(8)Connection, bolt(8)Specification is Φ 20, jacking
Oil cylinder(4)End is arranged symmetrically 4 bolts up and down(8).
6. a kind of rectangular top tube top iron construction to retract as described in claim 1, which is characterized in that jacking oil cylinder(4)'s
End is a spherical hinge, ensures that there are certain degree of freedom at this in rollback oil cylinder;With U-shaped top iron(3)The jacking oil of connection
Cylinder(4)Ensure to arrange with jacking axis longitudinal direction vertical guide symmetry principle, and is arranged since least significant end;Rectangular top iron and U-shaped top
When iron weight is smaller, a jacking oil cylinder being connect with U-shaped top iron, rectangle can be respectively arranged on jacking axis longitudinal direction vertical guide both sides
It, can be on the jacking axis longitudinal direction vertical guide both sides tops that respectively arrangement two and U-shaped top iron are connect when pushing up iron and larger U-shaped top iron weight
Into oil cylinder.
7. a kind of application method of the rectangular top tube top iron construction to retract, which is characterized in that lifting jacking oil cylinder(4)And oil cylinder
Frame(5)It is placed in rear parados(7)Front end;On ground rectangular top iron(2)And U-shaped top iron(3)It is connected as entirety, is lifted into work
Well(6)Guide rail(10)On;U-shaped top iron with spherical hinge jacking oil cylinder(4)Using bolt(8)Connection, jacking cylinder movement band
Dynamic rectangular top iron(2)And U-shaped top iron(3)It is whole to be moved forward and backward, it is next to realize the rectangular top tube top iron construction that can be retracted
Save section of jurisdiction(9)Vacating space avoids lifting rectangular top iron repeatedly(2)And U-shaped top iron(3)The time it takes.
8. a kind of application method of the rectangular top tube top iron construction to retract as claimed in claim 7, which is characterized in that on ground
Rectangular top iron and U-shaped top iron are welded as entirety;Iron block is arc welding, iron with rectangular top iron, iron block and U-shaped top iron welding method
Block size is 20cm × 10cm, and the iron block on two top iron is connected by screw bolts, and bolt specification is Φ 50;Iron block is on two top iron
Welding position is each two of top iron both sides welding, top iron top welding two;If top iron weight is little, rectangular top iron and U-shaped
The mode for directly carrying out spot welding with inner ring in contact interface outer ring and connecting for each one week can be used in top iron.
9. a kind of application method of the rectangular top tube top iron construction to retract as claimed in claim 7, which is characterized in that top iron with
Connection Step with spherical hinge jacking oil cylinder;First, band spherical hinge jacking oil cylinder is hung in and is placed in cylinder rack, welding
Good rectangular top iron and U-shaped top iron is integrally hung on the guide rail of active well;If the weight of rectangular top iron and U-shaped top iron entirety is not
Greatly, U-shaped top iron can also be connect in active well using direct welding manner with jacking oil cylinder;If rectangular top iron and U-shaped top iron are whole
When the weight of body is larger, U-shaped top iron is connected by screw bolts with jacking oil cylinder in active well, bolt specification is Φ 20, jacking
Oil cylinder end is arranged symmetrically 4 bolts up and down.
10. a kind of application method of the rectangular top tube top iron construction to retract as claimed in claim 7, which is characterized in that jacking
The end of oil cylinder is a spherical hinge, ensures that there are certain degree of freedom at this in rollback oil cylinder;The jacking being connect with U-shaped top iron
Oil cylinder ensures to arrange with jacking axis longitudinal direction vertical guide symmetry principle, and is arranged since least significant end;Rectangular top iron and U-shaped top iron
When weight is smaller, a jacking oil cylinder being connect with U-shaped top iron, rectangular top can be respectively arranged on jacking axis longitudinal direction vertical guide both sides
It, can be in respectively two jackings being connect with U-shaped top iron of arrangement of jacking axis longitudinal direction vertical guide both sides when iron is larger with U-shaped top iron weight
Oil cylinder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810263090.1A CN108561137A (en) | 2018-03-28 | 2018-03-28 | A kind of rectangular top tube top iron construction to retract and application method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810263090.1A CN108561137A (en) | 2018-03-28 | 2018-03-28 | A kind of rectangular top tube top iron construction to retract and application method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108561137A true CN108561137A (en) | 2018-09-21 |
Family
ID=63533552
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810263090.1A Pending CN108561137A (en) | 2018-03-28 | 2018-03-28 | A kind of rectangular top tube top iron construction to retract and application method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108561137A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109339813A (en) * | 2018-11-27 | 2019-02-15 | 中国水利水电第四工程局有限公司 | A kind of pipe jacking tunnelling machine |
CN109630151A (en) * | 2018-11-07 | 2019-04-16 | 中衡设计集团工程咨询有限公司 | Rectangular top pipe tunneling construction method |
CN110761807A (en) * | 2019-12-11 | 2020-02-07 | 北京中岩智泊科技有限公司 | Assembling system and assembling method for prefabricated assembled jacking pipe |
CN111795207A (en) * | 2020-07-17 | 2020-10-20 | 中铁十二局集团有限公司 | Construction method for oversized starting well top pipe |
CN113357437A (en) * | 2021-07-14 | 2021-09-07 | 中国建筑第八工程局有限公司 | Prefabricated back wall with adjustable pipe jacking construction |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101285387A (en) * | 2008-05-22 | 2008-10-15 | 清华大学 | Propelling plant for earth pressure balancing shield |
CN202195160U (en) * | 2011-09-05 | 2012-04-18 | 天津第六市政公路工程有限公司 | Assembled jacking iron for large-caliber pipe jacking construction |
CN102568293A (en) * | 2010-12-14 | 2012-07-11 | 上海市机械施工有限公司 | Rectangular tunnel boring machine teaching system |
CN202531174U (en) * | 2012-02-13 | 2012-11-14 | 盾建重工制造有限公司 | Compound double actively hinging devices of shield machine |
CN103046638A (en) * | 2011-04-28 | 2013-04-17 | 朱奎 | Pipe jacking construction method |
CN105465481A (en) * | 2016-01-25 | 2016-04-06 | 杭州江润科技有限公司 | Construction method for jacking structure of pipe jacking work well |
CN105545317A (en) * | 2015-12-31 | 2016-05-04 | 成都泽翰科技有限公司 | Urban underground pipe gallery drilling and laying machine |
CN105570534A (en) * | 2016-02-22 | 2016-05-11 | 中国水利水电第十一工程局有限公司 | Shallow-burial-depth pipe-jacking equipment capable of controlling ground structural deformation and construction method |
CN205479706U (en) * | 2016-01-25 | 2016-08-17 | 浙江宝田环境建设有限公司 | Push pipe work jing ding advances structure |
CN206111189U (en) * | 2016-10-30 | 2017-04-19 | 成都建工路桥建设有限公司 | Rectangular shield digs jacking force delivery system in top |
CN206368709U (en) * | 2016-12-29 | 2017-08-01 | 中船重型装备有限公司 | Rectangular pipe jacking machine inwall shockproof structure |
CN208587160U (en) * | 2018-03-28 | 2019-03-08 | 中铁上海工程局集团有限公司 | A kind of rectangular top tube top iron construction to retract |
-
2018
- 2018-03-28 CN CN201810263090.1A patent/CN108561137A/en active Pending
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101285387A (en) * | 2008-05-22 | 2008-10-15 | 清华大学 | Propelling plant for earth pressure balancing shield |
CN102568293A (en) * | 2010-12-14 | 2012-07-11 | 上海市机械施工有限公司 | Rectangular tunnel boring machine teaching system |
CN103046638A (en) * | 2011-04-28 | 2013-04-17 | 朱奎 | Pipe jacking construction method |
CN202195160U (en) * | 2011-09-05 | 2012-04-18 | 天津第六市政公路工程有限公司 | Assembled jacking iron for large-caliber pipe jacking construction |
CN202531174U (en) * | 2012-02-13 | 2012-11-14 | 盾建重工制造有限公司 | Compound double actively hinging devices of shield machine |
CN105545317A (en) * | 2015-12-31 | 2016-05-04 | 成都泽翰科技有限公司 | Urban underground pipe gallery drilling and laying machine |
CN105465481A (en) * | 2016-01-25 | 2016-04-06 | 杭州江润科技有限公司 | Construction method for jacking structure of pipe jacking work well |
CN205479706U (en) * | 2016-01-25 | 2016-08-17 | 浙江宝田环境建设有限公司 | Push pipe work jing ding advances structure |
CN105570534A (en) * | 2016-02-22 | 2016-05-11 | 中国水利水电第十一工程局有限公司 | Shallow-burial-depth pipe-jacking equipment capable of controlling ground structural deformation and construction method |
CN206111189U (en) * | 2016-10-30 | 2017-04-19 | 成都建工路桥建设有限公司 | Rectangular shield digs jacking force delivery system in top |
CN206368709U (en) * | 2016-12-29 | 2017-08-01 | 中船重型装备有限公司 | Rectangular pipe jacking machine inwall shockproof structure |
CN208587160U (en) * | 2018-03-28 | 2019-03-08 | 中铁上海工程局集团有限公司 | A kind of rectangular top tube top iron construction to retract |
Non-Patent Citations (1)
Title |
---|
吴圣贤;: "某地铁过街通道大断面矩形顶管工程设计", no. 03 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109630151A (en) * | 2018-11-07 | 2019-04-16 | 中衡设计集团工程咨询有限公司 | Rectangular top pipe tunneling construction method |
CN109339813A (en) * | 2018-11-27 | 2019-02-15 | 中国水利水电第四工程局有限公司 | A kind of pipe jacking tunnelling machine |
CN110761807A (en) * | 2019-12-11 | 2020-02-07 | 北京中岩智泊科技有限公司 | Assembling system and assembling method for prefabricated assembled jacking pipe |
CN111795207A (en) * | 2020-07-17 | 2020-10-20 | 中铁十二局集团有限公司 | Construction method for oversized starting well top pipe |
CN113357437A (en) * | 2021-07-14 | 2021-09-07 | 中国建筑第八工程局有限公司 | Prefabricated back wall with adjustable pipe jacking construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108561137A (en) | A kind of rectangular top tube top iron construction to retract and application method | |
CN201647947U (en) | Tunnel overhaul work extension platform | |
CN203145950U (en) | Support for monolithic horizontal movement station-crossing of shield tunneling machine | |
CN104499416A (en) | Full-hydraulic crawler-type self-moving trestle | |
CN110552709A (en) | self-propelled integral station-crossing method and device suitable for large-diameter shield machine | |
CN203213092U (en) | Self-moving crawler-type hydraulic high-speed rammer compactor | |
CN208587160U (en) | A kind of rectangular top tube top iron construction to retract | |
CN101864976A (en) | Airborne hydraulic multifunctional temporary support machine | |
CN110158973B (en) | Pipe erecting equipment and synchronous operation type pipe erecting construction method | |
CN204371384U (en) | Anchor Agent boost motor | |
CN210563476U (en) | Pipe erecting equipment | |
CN202466543U (en) | Hydraulic movable ingot locking device for plane gate | |
CN215444095U (en) | Subway tunnel inner supporting structure | |
CN207632432U (en) | A kind of underground moving hydraulic support to supporting point device | |
CN216072862U (en) | Heavy jack translation device for narrow space operation | |
CN201932887U (en) | Crawler-typed moving lifting platform special for greenhouse | |
CN211549698U (en) | Jacking working pit | |
CN209040849U (en) | A kind of negative endless tube sheet connecting apparatus of shield tunnel construction | |
CN215826857U (en) | Climbing mechanism for pipeline transportation and installation robot | |
CN203668940U (en) | Shoring mechanism for preventing row piles in foundation pit from deforming | |
CN208650890U (en) | Can Fast Installation heavy section steel support it is hydraulic from move support platform | |
CN203558470U (en) | Intermittence push-pull moving device of hydraulic clamping rail | |
CN208203273U (en) | Multifunctional shield machine originating station | |
CN206397502U (en) | The mechanism that misses the stop is walked in the straight trip of shield machine main unit hydraulic walking | |
CN201874596U (en) | Roadheader-borne hydraulic multifunctional temporary supporting machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||