CN108560638A CN201810344601.2A CN201810344601A CN108560638A CN 108560638 A CN108560638 A CN 108560638A CN 201810344601 A CN201810344601 A CN 201810344601A CN 108560638 A CN108560638 A CN 108560638A
Authority
CN
China
Prior art keywords
pipeline
water
tap water
peak
peak regulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810344601.2A
Other languages
Chinese (zh)
Inventor
池学聪
谭红全
李海军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Panda Machinery Group Co Ltd
Original Assignee
Shanghai Panda Machinery Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Panda Machinery Group Co Ltd filed Critical Shanghai Panda Machinery Group Co Ltd
Priority to CN201810344601.2A priority Critical patent/CN108560638A/en
Publication of CN108560638A publication Critical patent/CN108560638A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/02Public or like main pipe systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/07Arrangement of devices, e.g. filters, flow controls, measuring devices, siphons, valves, in the pipe systems
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/07Arrangement of devices, e.g. filters, flow controls, measuring devices, siphons, valves, in the pipe systems
    • E03B7/072Arrangement of flowmeters
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B7/00Water main or service pipe systems
    • E03B7/07Arrangement of devices, e.g. filters, flow controls, measuring devices, siphons, valves, in the pipe systems
    • E03B7/075Arrangement of devices for control of pressure or flow rate

Abstract

The present invention relates to a kind of tap water peak period peak regulation system and its peak regulating methods, peak regulation system includes tap water pipeline pipeline, user's water tank, peak regulation pumping plant, check valve, pressure charging valve and central controller, peak regulation pumping plant is in parallel with tap water pipeline pipeline, booster pump and check valve are set in turn in pipeline section in parallel with peak regulation pumping plant on tap water pipeline pipeline along the water (flow) direction of tap water pipeline pipeline, and user's water tank, peak regulation pumping plant and pressure charging valve are connected to central controller and are run by central controller controls.Peak regulating method includes:Original user's water tank is transformed;Peak regulation pumping plant is added in the insufficient region of water supply;Check valve and booster pump are installed with peak regulation pumping plant pipe section in parallel on aqueduct;Water flow data in piecewise acquisition pipeline;Central controller is controlled and is allocated to tap water to user's water tank, peak regulation pumping plant and booster pump.The present invention ensures the water consumption of tap water pipeline terminal temperature difference peak period abundance, and enforcement difficulty is low, at low cost.

Description

Tap water peak period peak regulation system and its peak regulating method
Technical field
The invention belongs to the technical fields of tap water allotment, more particularly to a kind of tap water peak period peak regulation system and Its peak regulating method.
Background technology
Originally the terminal temperature difference in the network of rivers is likely to occur anhydrous available situation in the water use peak period, by investigating Trunk Line Terminal pressure deficiency is to cause the anhydrous available one of the major reasons of terminal temperature difference, reason to include mainly:First, it is responsible for spool Underfed caused by diameter is small;Second, causing water flow with water concentration, supply falls short of demand;Third, water factory's pressure is small, causes pipeline last Hold hydraulic pressure insufficient;4th, the long resistance of pipeline end hydraulic pressure caused greatly is insufficient.
Existing solution generally includes amplification caliber, increases pipeline, add water factory's segmentation water supply, promote water factory's water outlet Pressure etc., but all there are problems that construction work amount is big to some extent, cut off the water and cut off the water supply and cost increases etc..
Invention content
Technical problem to be solved by the invention is to provide a kind of tap water peak period peak regulation system and its peak regulating method, It can not only ensure the water consumption of tap water pipeline terminal temperature difference peak period abundance, and enforcement difficulty is low, it is at low cost.
The technical solution adopted by the present invention to solve the technical problems is to provide a kind of tap water peak period peak regulation system, Including tap water pipeline pipeline and user's water tank, user's water tank is connected to tap water pipeline pipeline, which also wraps Several peak regulation pumping plants, check valve, pressure charging valve and central controller are included, several peak regulation pumping plants and tap water pipeline pipeline are simultaneously Connection, the booster pump and check valve are set in turn on tap water pipeline pipeline and tune along the water (flow) direction of tap water pipeline pipeline The pipeline section of peak pumping plant parallel connection, user's water tank, peak regulation pumping plant and pressure charging valve are connected to central controller and are controlled by center Device control operation.
The check valve is arranged adjacent to the water outlet tie point of peak regulation pumping plant and tap water pipeline pipeline and is located at water outlet connection The upstream of point.
The booster pump is arranged adjacent to check valve and is located at the upstream of check valve.
The entery and delivery port of user's water tank and peak regulation pumping plant carries out switch control, user's water tank by solenoid valve With the level detection sensor that is internally provided with of peak regulation pumping plant, the level detection sensor is connected to central controller, the electricity The keying of magnet valve is controlled by central controller.
Segmentation is equipped with the sensing device of acquisition water flow data in the tap water pipeline pipeline, and the sensing device is connected to Central controller.
The present invention solves another technical solution used by its technical problem and is to provide a kind of tap water peak period peak regulation Method includes the following steps:
A) original user's water tank in tap water pipeline is transformed;
B) add peak regulation pumping plant for the insufficient region of water supply in tap water pipeline, the peak regulation pumping plant with originally Water pipeline pipeline is in parallel;
C) check valve is installed in the upstream that the water outlet tie point of each peak regulation pumping plant is corresponded on tap water pipeline pipeline respectively, and Booster pump is arranged in the upstream of corresponding each check valve;
D) water flow data in piecewise acquisition tap water pipeline pipeline;
E) water flow data of the step d) acquisition is transmitted to central controller, the central controller to water flow data into The tap water in tap water pipeline pipeline is adjusted by controlling user's water tank, peak regulation pumping plant and booster pump after row analysis Match.
User's water tank and peak regulation pumping plant by the control of central controller with water offpeak period carry out water storage, with The moisturizing into tap water pipeline pipeline of water peak period.
The step d) includes being acquired to the flow of tap water and transferring data to central controller.
The step d) includes being detected to pipeline internal pressure and transferring data to central controller.
Advantageous effect
The present invention on the basis of original tap water pipeline by introducing new equipment, and by control system to introducing New equipment is controlled, and can not only improve the water supply capacity of former pipeline, and can be in the water use peak period in pipeline Water flow is supplemented, and is allocated with water to end of line to realize, when ensureing tap water pipeline terminal temperature difference peak The sufficient water consumption of section.
In addition, the implementation of the present invention avoids the big construction of quantities, avoid to cut off the hands and cut off the water, also avoids water factory's water outlet The increase of cost is, it can be achieved that property is strong, and enforcement difficulty is low, and cost is relatively low.
Description of the drawings
Fig. 1 is the structural schematic diagram of existing tap water pipeline.
Fig. 2 is the structural schematic diagram of tap water pipeline system of the present invention.
Specific implementation mode
Present invention will be further explained below with reference to specific examples.It should be understood that these embodiments are merely to illustrate the present invention Rather than it limits the scope of the invention.In addition, it should also be understood that, after reading the content taught by the present invention, people in the art Member can make various changes or modifications the present invention, and such equivalent forms equally fall within the application the appended claims and limited Range.
A kind of tap water peak period peak regulation system as shown in Figure 2, including tap water pipeline pipeline 1, user's water tank, two Seat peak regulation pumping plant 2, check valve 3, pressure charging valve 4 and central controller.
User's water tank to be formed by being transformed to original user's water tank in pipeline, is connected to tap water pipeline pipeline 1. Two peak regulation pumping plants 2 are set to the insufficient terminal region of water supply in pipeline, in parallel with tap water pipeline pipeline 1.Booster pump 4 It is set in turn on tap water pipeline pipeline 1 with peak regulation pumping plant 2 simultaneously along the water (flow) direction of tap water pipeline pipeline 1 with check valve 3 The pipeline section of connection, check valve 3 are arranged adjacent to the water outlet tie point of peak regulation pumping plant 2 and tap water pipeline pipeline 1 and are located at water outlet connection The upstream of point, booster pump 4 are arranged adjacent to check valve 3 and positioned at the upstreams of check valve 3.
The entery and delivery port of user's water tank and peak regulation pumping plant 2 carries out switch control, user's water tank and peak regulation pump by solenoid valve Stand 2 the level detection sensor that is internally provided with, level detection sensor is connected to central controller, during the keying of solenoid valve passes through Centre controller is controlled.Segmentation is equipped with the flow being acquired for the flow to tap water and passes in tap water pipeline pipeline 1 Sensor and pressure sensor for being detected to pipeline internal pressure, flow sensor and pressure sensor are connected to central control Device.
A kind of tap water peak period peak regulating method is provided below, includes the following steps:
A) original user's water tank in tap water pipeline is transformed, the entery and delivery port of user's water tank is by can be automatically controlled The solenoid valve of keying carries out switch control, and level detection sensor is arranged in the inside of user's water tank.
B) add peak regulation pumping plant 2 for the insufficient region of water supply in tap water pipeline, peak regulation pumping plant 2 into and out of The mouth of a river carries out switch control by solenoid valve, and level detection sensor is arranged in the inside of peak regulation pumping plant 2.Peak regulation pumping plant 2 with Tap water pipeline pipeline 1 is in parallel.
C) upstream that the water outlet tie point of each peak regulation pumping plant 2 is corresponded on tap water pipeline pipeline 1 is installed by check valve respectively 3, and booster pump 4 is arranged in the upstream of corresponding each check valve 3.Booster pump 4 and check valve 3 are along the flow side of tap water pipeline pipeline 1 To being set in turn in pipeline section in parallel with peak regulation pumping plant 2 on tap water pipeline pipeline 1.By the setting of check valve 3, can avoid The tap water that tap water pipeline pipeline 1 is flowed into from peak regulation pumping plant 2 flows back, and ensures that tap water is fed forward, and unidirectional Booster pump 4 is arranged in the upstream of valve 3, ensures that the tap water in tap water pipeline pipeline 1 is fed forward by check valve 3, while energy Enough lift line end hydraulic pressure, improves tap water transfer efficiency.
D) water flow data in piecewise acquisition tap water pipeline pipeline 1, by flow sensor to the flow of tap water into Row detection, is detected the pressure in pipeline by pressure sensor.
E) flow sensor and the water flow data of pressure sensor acquisition are transmitted to central controller, center control in step d) Device processed analyzes water flow data, and can be by controlling user's water tank, peak regulation pumping plant 2 and booster pump 4 to tap water pipeline Tap water in pipeline 1 is allocated.
The peak regulating method makes full use of the water supply capacity of existing pipeline first, by pressure sensor to pressure in pipeline Detection, the operation of booster pump 4 for automatically controlling hydraulic pressure deficiency pipeline section boost to pipeline, and original is improved by way of laminating water supply There is the water supply capacity of pipeline.
Underfed part carries out supplement supply after boosting, and by the control system, user's water tank and peak regulation pumping plant 2 can Water storage is carried out opening entering water electromagnetic valve with water offpeak period, closing water solenoid valve, and is detected by level detection sensor Water level forms feedback;It in the water use peak period, is opened by the solenoid valve of central controller controls water outlet, so as to certainly Water flow supplement is carried out in water line tube 1.

Claims (9)

1. a kind of tap water peak period peak regulation system, including tap water pipeline pipeline (1) and user's water tank, user's water tank It is connected to tap water pipeline pipeline (1), it is characterised in that:The peak regulation system further include several peak regulation pumping plants (2), check valve (3), Pressure charging valve (4) and central controller, several peak regulation pumping plants (2) are in parallel with tap water pipeline pipeline (1), the booster pump (4) it is set in turn on tap water pipeline pipeline (1) and tune along the water (flow) direction of tap water pipeline pipeline (1) with check valve (3) The pipeline section of peak pumping plant (2) parallel connection, user's water tank, peak regulation pumping plant (2) and pressure charging valve (4) are connected to central controller and pass through Central controller controls are run.
2. a kind of tap water peak period peak regulation system according to claim 1, it is characterised in that:The check valve (3) The water outlet tie point of neighbouring peak regulation pumping plant (2) and tap water pipeline pipeline (1) is arranged and is located at the upstream of water outlet tie point.
3. a kind of tap water peak period peak regulation system according to claim 2, it is characterised in that:The booster pump (4) Neighbouring check valve (3) is arranged and positioned at the upstream of check valve (3).
4. a kind of tap water peak period peak regulation system according to claim 1, it is characterised in that:User's water tank and The entery and delivery port of peak regulation pumping plant (2) carries out switch control, the inside of user's water tank and peak regulation pumping plant (2) by solenoid valve Equipped with level detection sensor, the level detection sensor is connected to central controller, during the keying of the solenoid valve passes through Centre controller is controlled.
5. a kind of tap water peak period peak regulation system according to claim 1, it is characterised in that:The tap water pipeline Segmentation is equipped with the sensing device of acquisition water flow data in pipeline (1), and the sensing device is connected to central controller.
6. a kind of peak regulating method of the tap water peak period peak regulation system in claim 1-5 described in any one, including with Lower step:
A) original user's water tank in tap water pipeline is transformed;
B) add peak regulation pumping plant (2) for the insufficient region of water supply in tap water pipeline, the peak regulation pumping plant (2) with from Water line tube (1) is in parallel;
C) upstream that the water outlet tie point of each peak regulation pumping plant (2) is corresponded on tap water pipeline pipeline (1) is installed by check valve respectively (3), and booster pump (4) is arranged in the upstream of corresponding each check valve (3);
D) water flow data in piecewise acquisition tap water pipeline pipeline (1);
E) water flow data of the step d) acquisitions is transmitted to central controller, and the central controller divides water flow data By controlling user's water tank, peak regulation pumping plant (2) and booster pump (4) to the tap water in tap water pipeline pipeline (1) after analysis It is allocated.
7. a kind of peak period tap water pipeline end water concocting method according to claim 6, it is characterised in that:Institute It states user's water tank and peak regulation pumping plant (2) and water storage is being carried out, in water use peak with water offpeak period by the control of central controller Period moisturizing into tap water pipeline pipeline (1).
8. a kind of peak period tap water pipeline end water concocting method according to claim 6, it is characterised in that:Institute It includes being acquired to the flow of tap water and transferring data to central controller to state step d).
9. a kind of peak period tap water pipeline end water concocting method according to claim 6, it is characterised in that:Institute It includes being detected to pipeline internal pressure and transferring data to central controller to state step d).
CN201810344601.2A 2018-04-17 2018-04-17 Tap water peak period peak regulation system and its peak regulating method Pending CN108560638A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810344601.2A CN108560638A (en) 2018-04-17 2018-04-17 Tap water peak period peak regulation system and its peak regulating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810344601.2A CN108560638A (en) 2018-04-17 2018-04-17 Tap water peak period peak regulation system and its peak regulating method

Publications (1)

Publication Number Publication Date
CN108560638A true CN108560638A (en) 2018-09-21

Family

ID=63535509

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810344601.2A Pending CN108560638A (en) 2018-04-17 2018-04-17 Tap water peak period peak regulation system and its peak regulating method

Country Status (1)

Country Link
CN (1) CN108560638A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109269589A (en) * 2018-11-10 2019-01-25 薛金山 A kind of water volume in water tank calculating system and its calculation method with liquid level regulation
CN114582113A (en) * 2022-03-08 2022-06-03 山东工业职业学院 Device for automatically selecting wireless transmission frequency for intelligent water affairs

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106480933A (en) * 2015-08-31 2017-03-08 上海熊猫机械(集团)有限公司 Peak regulation pumping plant
CN206956840U (en) * 2017-04-07 2018-02-02 上海熊猫机械(集团)有限公司 Peak regulation system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106480933A (en) * 2015-08-31 2017-03-08 上海熊猫机械(集团)有限公司 Peak regulation pumping plant
CN206956840U (en) * 2017-04-07 2018-02-02 上海熊猫机械(集团)有限公司 Peak regulation system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109269589A (en) * 2018-11-10 2019-01-25 薛金山 A kind of water volume in water tank calculating system and its calculation method with liquid level regulation
CN109269589B (en) * 2018-11-10 2021-01-05 薛金山 Water tank water quantity measuring and calculating system with liquid level regulation and control function and calculating method thereof
CN114582113A (en) * 2022-03-08 2022-06-03 山东工业职业学院 Device for automatically selecting wireless transmission frequency for intelligent water affairs

Similar Documents

Publication Publication Date Title
CN205314168U (en) Pump water supply installation in box no negative pressure silence pipe of intelligent regulation water tank water demand
CN105865059A (en) Energy-consumption-free intelligent water-saving temperature control device and method for water heater
CN108560638A (en) Tap water peak period peak regulation system and its peak regulating method
CN102166449B (en) Water treatment device with constant resistance regulation and control function and water treatment method thereof
CN201190558Y (en) Supercharging water injection device
CN103452167A (en) Intermediate booster pump station
WO2014180189A1 (en) Energy-saving control system, excavator and method
CN207776002U (en) Box type negative-pressure-free supercharging water supply system
CN104074237A (en) Novel water supply device with water quality improving module
CN104514242A (en) Constant-pressure water feeding device based on internet of things
CN202865911U (en) Water supply system
CN206570870U (en) A kind of pressurized watering device
CN207228233U (en) Variable quantity and pressure non-negative pressure water-supply installation
CN210216561U (en) Secondary pressurizing water supply device of circulating water system
CN210288549U (en) Integrated pump room water supply device
CN109914523B (en) Water supply network low pressure improvement method based on blocking and pressure-superposed pressurization
CN208748760U (en) A kind of multi-joint non-negative pressure water-supply device of full frequency conversion intelligent
CN104341050B (en) A kind of seawater desalination system and method
CN208830402U (en) A kind of cell peak regulation pumping plant
CN102776920A (en) Pressure-superposing water feeding device
CN108842866A (en) A kind of multi-joint non-negative pressure water-supply device of full frequency conversion intelligent and its control mode
CN216130234U (en) Pipeline layout design and wisdom centralized water supply system
CN204370505U (en) Based on the constant pressure water supplying device of Internet of Things
CN220378419U (en) Energy-saving normal pressure water injection pump system device for oil field
CN209227687U (en) Pipeline recycles constant-voltage equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180921

RJ01 Rejection of invention patent application after publication