CN108510224A - 一种装配式建筑逆向物流选址方法 - Google Patents

一种装配式建筑逆向物流选址方法 Download PDF

Info

Publication number
CN108510224A
CN108510224A CN201810207948.2A CN201810207948A CN108510224A CN 108510224 A CN108510224 A CN 108510224A CN 201810207948 A CN201810207948 A CN 201810207948A CN 108510224 A CN108510224 A CN 108510224A
Authority
CN
China
Prior art keywords
assembled architecture
bee
recovery point
reverse logistic
algorithm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810207948.2A
Other languages
English (en)
Inventor
李俊青
段培永
段朋
韩玉艳
桑红燕
郑志新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaocheng University
Original Assignee
Liaocheng University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaocheng University filed Critical Liaocheng University
Priority to CN201810207948.2A priority Critical patent/CN108510224A/zh
Publication of CN108510224A publication Critical patent/CN108510224A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06NCOMPUTING ARRANGEMENTS BASED ON SPECIFIC COMPUTATIONAL MODELS
    • G06N3/00Computing arrangements based on biological models
    • G06N3/004Artificial life, i.e. computing arrangements simulating life
    • G06N3/006Artificial life, i.e. computing arrangements simulating life based on simulated virtual individual or collective life forms, e.g. social simulations or particle swarm optimisation [PSO]

Abstract

本发明涉及建筑逆向物流选址技术领域,且公开了一种装配式建筑逆向物流选址方法,包括以下步骤:初始化实验参数,生产初始解集,创建装配式建筑回收点编码向量,循环为每个装配加工点随机选择一个装配式建筑回收点,并记录到该装配式建筑回收点对应的链表下,直到所有装配加工点均已选择完毕。该装配式建筑逆向物流选址方法,通过提出了一种有效的两阶段向量的编码结构,设计了性能良好的邻域结构,构建了新的雇佣蜂、跟随蜂和侦察蜂策略,通过现实生产实例和随机实例的测试,并与当前文献典型算法对比分析,验证了算法的有效性和稳定性,优化提出的混合算法,并应用算法求解装配式建筑逆向物流网络中多目标问题。

Description

一种装配式建筑逆向物流选址方法
技术领域
本发明涉及建筑逆向物流选址技术领域,具体为一种装配式建筑逆向物流选址方法。
背景技术
近年来,分布式生产优化研究已经成为热点领域,随着PC构件厂商的不断升级,加工工厂一般分布在不同地段或地域,也迫切要求开展分布式装配式建筑优化的相关研究,Naderi和Ruiz分析了分布式流水车间调度问题(distributed permutationflow-shopscheduling problem,DPFSP)的模型,并给出了几种启发式规则,之后许多学者针对DPFSP开展相关研究,然而,只针对一般流水车间调度问题开展研究,尚缺乏针对实际约束的装配式建筑生产问题的研究,区别于正向物流,逆向物流通过建立从消费者到各级装配式建筑回收点的物流网络,实现资源回收或处理废弃物品,包括生产中的废品和副产品、缺陷产品或维修退回产品,以及过期和不合格产品等,由于产品回收过程中,顾客需求的不确定性,回收渠道的复杂性,以及回收处理方式的多样性等特点,逆向物流比正向物流更复杂,逆向物流所面对的复杂问题中,选址问题是其核心问题,因而也得到了越来越多的国内外学者的关注和研究,人工蜂群算法是一种新的群体智能优化方法,由Karaboga等于2005年首次提出,主要应用于求解连续函数优化问题,潘全科等针对ABC方法应用到离散问题领域,提出了离散人工蜂群算法,并应用求解流水线调度,李俊青等则把离散ABC方法应用到求解多目标柔性作业车间调度问题、铁水调度问题和带维修约束的柔性调度问题等领域,上述文献表明,ABC算法由于有效平衡了全局搜索和局部搜索能力,可以有效应用于求解复杂调度问题。
但是分布式装配式建筑生产优化存在诸多热点问题,如分布式生产项目调度、分布式配送优化、分布式装配生产工厂选择和分布式装配式建筑逆向物流等问题,有待深入开展研究,本文针对装配式建筑构件生产中的逆向物流问题开展模型建立,结合人工蜂群优化算法,设计一种离散人工蜂群算法,并开展算法性能测试研究。
发明内容
(一)解决的技术问题
针对现有技术的不足,本发明提供了一种装配式建筑逆向物流选址方法,具备有效性和稳定性等优点,解决了算法性能差的问题。
(二)技术方案
为实现上述有效性和稳定性的目的,本发明提供如下技术方案:包括以下步骤:
1)初始化实验参数,生产初始解集;
2)创建装配式建筑回收点编码向量,循环为每个装配加工点随机选择一个装配式建筑回收点,并记录到该装配式建筑回收点对应的链表下,直到所有装配加工点均已选择完毕;
3)创建装配式建筑回收中心编码向量,循环每个有装配加工点记录的装配式建筑回收点,随机为其分配一个装配式建筑回收中心,并记录到该装配式建筑回收中心对应的链表中;
4)若终止条件满足,则结束算法,否则,执行步骤5-8;
5)给当前解集中每个解分派雇佣蜂,执行挖掘搜索工作;
6)分派跟随蜂,进一步挖掘更新后的解集;
7)如果满足派出侦察蜂的条件,则随机选择一种侦察蜂策略,开展进一步强化搜索;
8)返回步骤2。
(三)有益效果
与现有技术相比,本发明提供了一种装配式建筑逆向物流选址方法,具备以下有益效果:该装配式建筑逆向物流选址方法,通过提出了一种有效的两阶段向量的编码结构,设计了性能良好的邻域结构,构建了新的雇佣蜂、跟随蜂和侦察蜂策略,通过现实生产实例和随机实例的测试,并与当前文献典型算法对比分析,验证了算法的有效性和稳定性,优化提出的混合算法,并应用算法求解装配式建筑逆向物流网络中多目标问题。
具体实施方式
下面将结合本发明的实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
一种装配式建筑逆向物流选址方法,包括以下步骤:
1)初始化实验参数,生产初始解集;
2)创建装配式建筑回收点编码向量,循环为每个装配加工点随机选择一个装配式建筑回收点,并记录到该装配式建筑回收点对应的链表下,直到所有装配加工点均已选择完毕;
3)创建装配式建筑回收中心编码向量,循环每个有装配加工点记录的装配式建筑回收点,随机为其分配一个装配式建筑回收中心,并记录到该装配式建筑回收中心对应的链表中;
4)若终止条件满足,则结束算法,否则,执行步骤5-8;
5)给当前解集中每个解分派雇佣蜂,执行挖掘搜索工作;
6)分派跟随蜂,进一步挖掘更新后的解集;
7)如果满足派出侦察蜂的条件,则随机选择一种侦察蜂策略,开展进一步强化搜索;
8)返回步骤2。
实验例:
以VC++6.0为开发环境,采用Intel Core i5 3.3GHZ、4GB RAM的PC机,实现了求解装配式建筑逆向物流网络选址问题的HDABC算法,算法参数设置如下:
1)初始解集大小=5;
2)雇佣蜂数量=5;
3)跟随蜂数量=5;
4)侦查蜂数量=1;
5)侦察蜂派出时机:某个解超过10秒没有更新;
6)局部搜索策略相关参数:雇佣蜂、跟随蜂循环次数Ti=10,侦察蜂循环次数Ti=50,邻域解集大小Tn=10;
结束条件:运行时间超过150秒。
实验结果分析:某企业共有10个装配加工点,5个备选装配式建筑回收点和3个备选装配式建筑回收中心,每个装配式建筑回收点的年运营费用为2万元,每个装配式建筑回收中心的运营费用为30万元,单位产品的日存储费用为10元,年工作日为250天,装配加工点人工费用为单位产品10元,每个装配式建筑回收点服务覆盖半径为12.5km,装配加工区的单位产品惩罚成本为500元,装配式建筑回收中心的最大容量为1000,装配式建筑回收点的最大容量为200,规模效应因子参见文献6,其中参数e=100,增加了装配式建筑回收点容量约束,去掉惩罚成本,回收产品从装配加工点运送到装配式建筑回收中心的运输费用。
本发明的有益效果是:通过提出了一种有效的两阶段向量的编码结构,设计了性能良好的邻域结构,构建了新的雇佣蜂、跟随蜂和侦察蜂策略,通过现实生产实例和随机实例的测试,并与当前文献典型算法对比分析,验证了算法的有效性和稳定性,优化提出的混合算法,并应用算法求解装配式建筑逆向物流网络中多目标问题。
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。

Claims (1)

1.一种装配式建筑逆向物流选址方法,其特征在于,包括以下步骤:
1)初始化实验参数,生产初始解集;
2)创建装配式建筑回收点编码向量,循环为每个装配加工点随机选择一个装配式建筑回收点,并记录到该装配式建筑回收点对应的链表下,直到所有装配加工点均已选择完毕;
3)创建装配式建筑回收中心编码向量,循环每个有装配加工点记录的装配式建筑回收点,随机为其分配一个装配式建筑回收中心,并记录到该装配式建筑回收中心对应的链表中;
4)若终止条件满足,则结束算法,否则,执行步骤5-8;
5)给当前解集中每个解分派雇佣蜂,执行挖掘搜索工作;
6)分派跟随蜂,进一步挖掘更新后的解集;
7)如果满足派出侦察蜂的条件,则随机选择一种侦察蜂策略,开展进一步强化搜索;
8)返回步骤2。
CN201810207948.2A 2018-03-14 2018-03-14 一种装配式建筑逆向物流选址方法 Pending CN108510224A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810207948.2A CN108510224A (zh) 2018-03-14 2018-03-14 一种装配式建筑逆向物流选址方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810207948.2A CN108510224A (zh) 2018-03-14 2018-03-14 一种装配式建筑逆向物流选址方法

Publications (1)

Publication Number Publication Date
CN108510224A true CN108510224A (zh) 2018-09-07

Family

ID=63376560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810207948.2A Pending CN108510224A (zh) 2018-03-14 2018-03-14 一种装配式建筑逆向物流选址方法

Country Status (1)

Country Link
CN (1) CN108510224A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111401655A (zh) * 2020-03-26 2020-07-10 上海第二工业大学 一种医疗废弃物回收设施选址的决策方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103034912A (zh) * 2012-12-20 2013-04-10 诸暨市供电局 一种分布式电源选址定容的优化方法
US20170264095A1 (en) * 2015-07-14 2017-09-14 Restore Nv Self-learning, real-time, data-driven power metering system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103034912A (zh) * 2012-12-20 2013-04-10 诸暨市供电局 一种分布式电源选址定容的优化方法
US20170264095A1 (en) * 2015-07-14 2017-09-14 Restore Nv Self-learning, real-time, data-driven power metering system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李俊青 等: "人工蜂群优化及其在资源管理中的应用", 《聊城大学学报(自然科学版)》 *
黄丽君: "基于离散人工蜂群算法的废弃物逆向物流网络设计", 《福州大学学报(自然科学版)》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111401655A (zh) * 2020-03-26 2020-07-10 上海第二工业大学 一种医疗废弃物回收设施选址的决策方法

Similar Documents

Publication Publication Date Title
Wu et al. Portfolio planning of renewable energy with energy storage technologies for different applications from electricity grid
Yang et al. Multi-objective low-carbon disassembly line balancing for agricultural machinery using MDFOA and fuzzy AHP
Dawei et al. Green supply chain management: A literature review
Bah et al. Evaluation of automotive parts suppliers through ordinal priority approach and TOPSIS
Butturi et al. A model for renewable energy symbiosis networks in eco-industrial parks
Lu et al. Sustainability evaluation of public–private partnership microgrid considering uncertainty and risk preference
Neupane et al. GOFLEX: extracting, aggregating and trading flexibility based on FlexOffers for 500+ prosumers in 3 European cities [operational systems paper]
Zhang et al. Manufacturer's carbon abatement strategy and selection of spent power battery collecting mode based on echelon utilization and cap-and-trade policy
CN108510224A (zh) 一种装配式建筑逆向物流选址方法
Silvestro et al. Review of transmission and distribution investment decision making processes under increasing energy scenario uncertainty
Sichone et al. Electricity load shedding. An econometric analysis of the productivity of firms in the manufacturing sector in Lusaka
Cheng et al. An innovative profit allocation to distributed energy resources integrated into virtual power plant
Siddiquee et al. Demand response in smart grid–A systematic mapping study
Ghinmine et al. Implementation of Green Manufacturing in Industry-A case study
Kaya et al. Evaluation of green and renewable energy system alternatives using a multiple attribute utility model: the case of Turkey
Xu et al. Research on Stackelberg Game Optimization Dispatch of Metamodel of Integrated Energy System Considering Carbon Capture and P2G
Lagzaie et al. Providing a Multiproduct and Multiperiodic Model for Closed-Loop Green Supply Chain under Conditions of Uncertainty Based on a Fuzzy Approach for Solving Problem of Business Market
Salinas-Herrera et al. On the Impacts of Multi-Agent Transactive Energy in Distribution Networks-Part 1: GTSPF Construction and ETSim Integration
Eckhoff et al. Electric mobility integration in energy communities: trending topics and future research directions
Grishkina Application of digital twin technologies for the optimization of the energy consumption for a wood clattering panels manufacturer
Mansour et al. Optimization of permutation no-idle flow shop green scheduling using adequate genetic algorithm
Rohn et al. Sustainable product design and resource management at the Kambium Furniture Workshop
Song et al. DESIGN OF MULTI-OBJECTIVE FLOW SHOP SCHEDULING METHOD BASED ON HYBRID GENETIC ALGORITHM.
Huang et al. A Practical Classification Evaluation Approach for Comprehensive Competitiveness of Distributed Energy Supply Systems
Hu et al. Analysis of Energy Internet Business Model Considering Carbon Trading

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180907

WD01 Invention patent application deemed withdrawn after publication