Prior art keywords
template
frame
clamp assembly
screens
trepanning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810619473.8A
Other languages
Chinese (zh)
Inventor
曹立英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810619473.8A priority Critical patent/CN108487628A/en
Publication of CN108487628A publication Critical patent/CN108487628A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/02Forming boards or similar elements
    • E04G9/06Forming boards or similar elements the form surface being of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a kind of alloy building template architectures, fixture including template and for connecting the template, the template is an integral molding structure, the side of the template is the planar structure for contacting concrete, its other side is equipped with fixed frame for fixing, the fixed frame includes the connection frame and screens frame positioned at the template both ends, the screens frame is inverted L structure, the adjacent screens frame is connected by the fixture, and the height of the connection frame is identical as the height of screens frame.Present invention alloy building template architecture using the above structure and its installation method, assembled, dismounting, convenient in carrying improve working efficiency, versatile, at low cost.

Description

Alloy building template architecture and its installation method
Technical field
The present invention relates to construction engineering technical fields, more particularly to a kind of alloy building template architecture and its installation Method.
Background technology
Currently, in the construction of building concrete formwork for placing, spelling formula template construction template generally use wooden model or plastics are dissipated Template, the mode that template back arris is reinforced are nailed and are fixed using the lumps of wood or steel rough ground.But wooden model is easy swollen mould, opens Split, weight is big and the number of turnover is few, cause to waste a large amount of timber.Plastic formwork is easy to expand with heat and contract with cold, weight is big, of high cost, side Angle is fragile;Also, market circulation is 915*1830mm, 1220*2440mm using template specification, since specification is big, is cut out Saw amount is big, and weight is big, and carrying and installation dismounting is inconvenient, takes time and effort.Template tradition reinforcement means is led to after connecting between template It crosses keel and nails and reinforced, be finished rear form removal, draw out a nail, process is complicated, takes time and effort, and causes construction site chaotic. Conventional template construction needs to open keyhole through walls in big-size formwork, not easy to operate, is not easy form removal, is easily destroyed template, causes damages.
Invention content
The object of the present invention is to provide a kind of alloy building template architecture and its installation method, assembled, dismounting is carried It is convenient, working efficiency is improved, it is versatile, it is at low cost.
To achieve the above object, the present invention provides a kind of alloy building template architecture, including template and for connecting The fixture of the template is connect, the template is an integral molding structure, and the side of the template is the plane for contacting concrete Structure, the other side are equipped with fixed frame for fixing, and the fixed frame includes the connection frame and card positioned at the template both ends Position frame, the screens frame are inverted L structure, and the adjacent screens frame connected by the fixture, the height of the connection frame with The height of the screens frame is identical.
Preferably, trepanning template, height and the screens of the trepanning template are equipped between the screens frame of the template The height of frame is identical, and the trepanning template and screens outer frame side are equipped with vertical keel, and the width of the vertical keel is equal to The sum of the width of the width of the trepanning template and two adjacent screens frames.
Preferably, formwork keel is equipped between the screens frame of the template, the formwork keel is the integral structure of convex, And include trepanning template and vertical keel, the trepanning template is between the screens frame, and the height of the trepanning template Degree is identical as the height of screens frame, and the width of the vertical keel is equal to the width of the trepanning template and adjacent two The sum of the width of screens frame.
Preferably, the connection frame is hollow hollow-core construction, is bolted to connection between the connection frame, described The opening for connecting frame upper and lower ends is filled with tamper, and the connection frame madial wall is identical with the thickness of lateral wall, and is more than The thickness of the connection upper frame edge;
The tamper is one or more in glass cement, foamed glue, plastics match or rubber stopper.
Preferably, the connection frame is hollow solid construction, is bolted to connection between the connection frame.
Preferably, the connection frame is inverted L structure, is bolted to connection between the connection frame.
Preferably, the fixture include the first clamp assembly, the second clamp assembly and bolt, first clamp assembly, Second clamp assembly and the bolt are structure as a whole, and the side of the first clamp assembly body of rod is equipped with for described On the centre position of the opening that the second clamp assembly body of rod is inserted into, first clamp assembly and the second clamp assembly body of rod Be equipped with the matched pin clamp of the bolt, the bolt be with handled wedge structure, first clamp assembly and Collet is equipped in the leg lock of second clamp assembly, the collet is and the matched rectangle knot of the screens frame upper groove Structure.
Preferably, the fixture includes the first clamp assembly and the second clamp assembly, first clamp assembly and described Be equipped on second clamp assembly with the matched collet of screens frame upper groove, first clamp assembly be L-type structure, institute It states the second clamp assembly to be equipped with for the perforative through-hole of the first clamp assembly, second clamp assembly is solid by nut It is scheduled on the side of first clamp assembly.
Preferably, the template is equipped with the vertical rib parallel with the connection frame, and the vertical rib is rectangle knot Structure, the vertical rib include pairs of existing first vertical rib and the second vertical rib, the first vertical rib and institute The overall width for stating the second vertical rib is not more than the width of the vertical keel.
Preferably, lateral rib is additionally provided in the template, the transverse direction rib is hollow or solid rectangular configuration, institute State lateral rib and be equipped with the through-hole that connect with U-shaped folder, the U-shaped folder be equipped with the matched plug of the through-hole, it is described to lead to The quantity in hole is 2, and the distance between described through-hole is not less than the width of the vertical keel, the bottom of the U-shaped folder Equipped with the screw hole for fixing the vertical keel.
A kind of installation method of alloy building template architecture, steps are as follows:
(1) trepanning will be carried out on the madial wall and lateral wall of template connection frame, by bolt by two adjacent templates Connection frame is fixedly connected, and template setting is placed on the steel bar spacer tied up, phase between the screens frame of template is made It is adjacent;
(2) trepanning template is placed between the screens frame of template, is inserted into wall pipe from trepanning template, wall bolt is inserted Enter, vertical keel with holes is then passed through into wall bolt, vertical keel pushes down adjacent screens outer frame side, for resisting adjacent two A screens frame and trepanning template, wall bolt nut is tightened;And for the formwork keel of integral structure, it is only necessary to simultaneously will Wall pipe and wall bolt pass through trepanning template and vertical keel, are fastened, you can;
(3) suitable position for selecting vertical keel, card is fixed on by the collet of the first clamp assembly and the second clamp assembly In the groove of position frame, meanwhile, the second clamp assembly is inserted into the first clamp assembly body of rod, is realized after locking and is fixed vertical keel In template;
(4) lateral rib is set in template, and places vertical keel between through-hole, the plug that U types press from both sides then is used to insert Enter in through-hole, U-shaped folder is fixed on vertical keel with screw, for position among template to be fixed;
(5) lateral keel is arranged on the outside of vertical keel to be fixed.
Therefore, present invention alloy building template architecture using the above structure and its installation method, assembled, dismounting, It carries, conveniently, improves working efficiency, it is versatile, it is at low cost.The structure of the present invention has following technical advantage:
(1) the connection frame of template is rectangular configuration, can select hollow hollow structure;Due to when template connects side wall by Power is big, and the thickness of connection frame side wall is more than the thickness of connection upper frame edge, and the secured connection of template may be implemented in the setting of this structure; Meanwhile hollow hollow structure setting can mitigate template weight, reduce cost.
(2) vertical keel is set at existing vertical rib in pairs, is used to support the medium position of template, strengthens simultaneously The intensity of template;Reduce the connection structure between the first vertical rib and the second vertical rib, alleviates template weight.
Below by drawings and examples, technical scheme of the present invention will be described in further detail.
Description of the drawings
Fig. 1 is the cross-sectional view of alloy building template architecture and its installation method embodiment one of the present invention;
Fig. 2 is the cross-sectional view of alloy building template architecture and its installation method embodiment two of the present invention;
Fig. 3 is the master of vertical rib embodiment in template in alloy building template architecture of the present invention and its installation method View;
Fig. 4 is the master of lateral rib embodiment in template in alloy building template architecture of the present invention and its installation method View;
Fig. 5 is the schematic diagram of fixture embodiment one in alloy building template architecture of the present invention and its installation method;
Fig. 6 is the schematic diagram of template embodiment one in alloy building template architecture of the present invention and its installation method;
Fig. 7 is the schematic diagram of U-shaped folder embodiment in alloy building template architecture of the present invention and its installation method;
Fig. 8 is the schematic diagram of U-shaped folder use state in alloy building template architecture of the present invention and its installation method;
Fig. 9 is the schematic diagram of fixture embodiment two in alloy building template architecture of the present invention and its installation method;
Wherein:1, template;2, bolt;3, vertical keel;4, frame is connected;5, screens frame;6, trepanning template;7, the first fixture Component;8, the second clamp assembly;9, bolt;10, pin clamp;11, collet;12, leg lock;13, the first vertical rib;14, second Vertical rib;15, lateral rib;16, U-shaped folder;17, plug;18, screw hole.
Specific implementation mode
Embodiments of the present invention are described further below in conjunction with the accompanying drawings.
Fig. 1 is the cross-sectional view of alloy building template architecture and its installation method embodiment one of the present invention, as schemed institute Show, a kind of alloy building template architecture, including template 1 and the fixture for connecting template 1, template 1 is integrally formed knot Structure, integral strength are high.The side of template 1 is the planar structure for contacting concrete, and the other side is equipped with for fixing solid Determine frame, fixed frame includes the connection frame 4 and screens frame 5 positioned at 1 both ends of template, and screens frame 5 is inverted L structure, connects the height of frame 4 Degree is identical as the height of screens frame 5.Connection is by connecting frame 4 corresponding with connection frame 4, screens frame 5 and card between adjacent template 1 Position frame 5 is correspondingly connected with, and adjacent screens frame 5 is connected by fixture, and adjacent connection frame 4 is connected by bolt 2.
It is the hollow or solid structure of hollow to connect frame 4.The opening filling of connection 4 upper and lower ends of frame of hollow-core construction It is one or more in glass cement, foamed glue, plastics match or rubber stopper to have tamper, tamper, is prevented in the construction process It connects and blocks sundries in frame 4, influence the connection of template 1.
Fig. 2 is the cross-sectional view of alloy building template architecture and its installation method embodiment two of the present invention, as schemed institute Show, as the embodiment of the present invention two, connection frame 4 or inverted L structure, adjacent connection frame 4 are connected by bolt 2.
Formwork keel is equipped between the screens frame 5 of template 1, formwork keel is the integral structure of convex, and includes trepanning mould Plate 6 and vertical keel 3.Trepanning template 6 is between screens frame 5, and the height phase of the height of trepanning template 6 and screens frame 5 Together.The width of vertical keel 3 is equal to the sum of the width of the width and two adjacent screens frames 5 of trepanning template 6.On formwork keel It equipped with hole, is fixed using wall bolt and wall pipe, it is possible to reduce the damage through walls to wide cut template and damage in the prior art It loses.
Fig. 6 is the schematic diagram of template embodiment one in alloy building template architecture of the present invention and its installation method, such as Shown in figure, connection 4 madial wall of frame is identical with the thickness of lateral wall, and more than the thickness of 4 top of connection frame.Connect 4 side wall of frame Thickness is a, and the thickness of 4 top of connection frame is b, and the numerical value of a is more than b so that when adjacent connection frame 4 is attached, connects frame 4 Madial wall and lateral wall support strength it is big, be conducive to it is adjacent connection frame 4 connection.Meanwhile the connection frame 4 of hollow-core construction can To reduce whole weight, cost is reduced.
Trepanning template 6 is equipped between the screens frame 5 of template 1, the height of trepanning template 6 is identical as the height of screens frame 5, Trepanning template 6 and the outside of screens frame 5 are equipped with vertical keel 3, the width of vertical keel 3 be equal to the width of trepanning template 6 with it is adjacent Two screens frames 5 the sum of width, ensure vertical keel 3 securely resist adjacent screens frame 5 and trepanning template 6.
Fig. 5 is the schematic diagram of fixture embodiment one in alloy building template architecture of the present invention and its installation method, such as Shown in figure, fixture includes the first clamp assembly 7, the second clamp assembly 8 and bolt 9, the first clamp assembly 7, the second clamp assembly 8 It is structure as a whole with bolt 9, the side of 7 body of rod of the first clamp assembly is equipped with opens for what 8 body of rod of the second clamp assembly was inserted into Mouthful, be equipped on the centre position of 8 body of rod of the first clamp assembly 7 and the second clamp assembly with 9 matched pin clamp 10 of bolt, insert Pin 9 is to be equipped with collet 11 in the leg lock 12 of the first clamp assembly 7 and the second clamp assembly 8 with handled wedge structure, Collet 11 be and the matched rectangular configuration of 5 upper groove of screens frame.Vertical keel 3 is fixed on the first clamp assembly 7 and by fixture Two clamp assemblies, 8 inside, collet 11 can be connected firmly in the groove of L-type formation of screens frame 4, ensure that adjacent forms 1 are tight Close connection.
Fig. 9 is the schematic diagram of fixture embodiment two in alloy building template architecture of the present invention and its installation method, such as Shown in figure, fixture includes the first clamp assembly 7 and the second clamp assembly 8, on the first clamp assembly 7 and the second clamp assembly 8 It is fixed on card equipped with the collet 11 with the matched collet 11 of 5 upper groove of screens frame, the first clamp assembly 7 and the second clamp assembly 8 On the frame 5 of position.First clamp assembly 7 is L type structures, and the second clamp assembly 8 is equipped with perforative logical for the first clamp assembly 7 Hole, the second clamp assembly 8 are fixed on by nut on the side of the first clamp assembly 7.
Fig. 3 is the master of vertical rib embodiment in template in alloy building template architecture of the present invention and its installation method View, Fig. 4 are the main views of lateral rib embodiment in template in alloy building template architecture of the present invention and its installation method Figure, as shown, can be equipped with the vertical rib parallel with connection frame in template 1, vertical rib is rectangular configuration, vertical rib It can reinforce the integral strength of template 1.Vertical rib includes existing first vertical rib 13 and the second vertical rib 14 in pairs, The overall width of first vertical rib 13 and the second vertical rib 14 is not more than the width of vertical keel 3, it is ensured that vertical keel 3 resist vertical rib.Lateral rib 15 is additionally provided in template 1, lateral rib 15 is hollow or solid rectangular configuration, laterally Rib 15 can reinforce integral strength.In template 1 lateral rib 15 with vertical rib difference when be arranged, setting that can be single is erected To rib or lateral rib 15.Vertical rib, which is arranged, for the template 1 of wide cut can reinforce whole intensity, while using perpendicular Fixed vertical rib is fixed to keel 3.
Fig. 7 is the schematic diagram of U-shaped folder embodiment in alloy building template architecture of the present invention and its installation method, Fig. 8 It is the schematic diagram of U-shaped folder use state in alloy building template architecture of the present invention and its installation method, as shown, laterally Rib 15 is equipped with through-hole, and the quantity of through-hole is 2, and the distance between through-hole is not less than the width of vertical keel 3.Vertically Keel 3 are fixed on by U-shaped folder 16 on lateral rib 15, and U-shaped folder 16 is equipped with will erect with the matched plug 17 of through-hole, when use It is fixed on the inside of U-shaped folder 16 to keel 3, and the addition through-hole of plug 17 is fixed.The bottom of U-shaped folder 16 is equipped with and is used for The screw hole 18 of fixed vertical keel 3, screw pass through the screw hole 18 of 16 bottom of U-shaped folder to fix on vertical keel 3.
A kind of installation method of alloy building template architecture, steps are as follows:
(1) template 1 is connected and carries out trepanning on the madial wall and lateral wall of frame 4, by bolt 2 by two adjacent templates 1 connection frame 4 is fixedly connected, and the setting of template 1 is placed on the steel bar spacer tied up, the screens frame 5 of template is made Between it is adjacent;
(2) trepanning template 6 is placed between the screens frame 5 of template 1, wall pipe is inserted into from trepanning template 6, by wall bolt It is inserted into, vertical keel 3 with holes is then passed through into wall bolt, vertical keel 3 pushes down adjacent 5 outside of screens frame, for resisting phase Adjacent two screens frames 5 and trepanning template 6, wall bolt nut is tightened;And for the formwork keel of integral structure, only need Wall pipe and wall bolt are passed through into trepanning template and vertical keel simultaneously, be fastened, you can;
(3) suitable position is selected, the collet 11 of the first clamp assembly 7 and the second clamp assembly 8 is fixed on screens frame In 5 groove, meanwhile, the second clamp assembly 8 is inserted into the opening of 7 body of rod of the first clamp assembly, and vertical keel 3 is fixed on by realization In template 1;
(4) vertical keel 3 is placed at the lateral rib 15 being arranged in pairs in template 1, for adding among template 1 Gu;Vertical keel 3 is placed between through-hole, is then used the plug 17 of U-shaped folder 16 to be inserted into through-hole, is consolidated U-shaped folder 16 with screw It is scheduled on vertical keel 3, for 1 intermediate position of template to be fixed;
(5) it is fixed in 3 outside setting lateral keel 15 of vertical keel.
Therefore, present invention alloy building template architecture using the above structure and its installation method, assembled, dismounting, Convenient in carrying improves working efficiency, versatile, at low cost.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention rather than is limited, Although the present invention is described in detail with reference to preferred embodiments, it will be understood by those of ordinary skill in the art that:Its according to Technical scheme of the present invention can be so modified or replaced equivalently, and these modifications or equivalent replacement cannot also make to repair Technical solution after changing is detached from the spirit and scope of technical solution of the present invention.

Claims (10)

1. a kind of alloy building template architecture, it is characterised in that:Fixture including template and for connecting the template, institute It states template to be an integral molding structure, the side of the template is the planar structure for contacting concrete, and the other side is equipped with and uses In fixed fixed frame, the fixed frame includes the connection frame and screens frame positioned at the template both ends, and the screens frame is inverted L Structure, the adjacent screens frame are connected by the fixture, and the height of the connection frame is identical as the height of screens frame.
2. a kind of alloy building template architecture according to claim 1, it is characterised in that:The screens frame of the template Between be equipped with trepanning template, the height of the trepanning template is identical as the height of screens frame, the trepanning template and described Screens outer frame side is equipped with vertical keel, and the width of the vertical keel is equal to the width of the trepanning template and two adjacent cards The sum of the width of position frame.
3. a kind of alloy building template architecture according to claim 1, it is characterised in that:The screens frame of the template Between be equipped with formwork keel, the formwork keel is the integral structure of convex, and includes trepanning template and vertical keel, described to open Hole template is between the screens frame, and the height of the trepanning template is identical as the height of screens frame, described perpendicular It is equal to the sum of the width of the width and two adjacent screens frames of the trepanning template to the width of keel.
4. a kind of alloy building template architecture according to claim 2, it is characterised in that:The connection frame is mouth word Type hollow-core construction is bolted to connection between the connection frame, and the opening of the connection frame upper and lower ends is filled with stifled Plug thing, the connection frame madial wall is identical with the thickness of lateral wall, and more than the thickness of the connection upper frame edge;
The tamper is one or more in glass cement, foamed glue, plastics match or rubber stopper.
5. a kind of alloy building template architecture according to claim 2, it is characterised in that:The connection frame is mouth word Type solid construction or inverted L structure are bolted to connection between the connection frame.
6. a kind of alloy building template architecture according to claim 1, it is characterised in that:The fixture includes first Clamp assembly, the second clamp assembly and bolt, first clamp assembly, second clamp assembly and the bolt are one Body structure, the side of the first clamp assembly body of rod is equipped with the opening being inserted into for the second clamp assembly body of rod, described It is equipped on the centre position of first clamp assembly and the second clamp assembly body of rod and the matched pin clamp of the bolt, institute It is to be equipped with folder in the leg lock of first clamp assembly and second clamp assembly with handled wedge structure to state bolt Head, the collet are and the matched rectangular configuration of screens frame upper groove.
7. a kind of alloy building template architecture according to claim 1, it is characterised in that:The fixture includes first It is equipped on clamp assembly and the second clamp assembly, first clamp assembly and second clamp assembly and the screens frame The matched collet of upper groove, first clamp assembly are L-type structure, and second clamp assembly, which is equipped with, is used for described first The perforative through-hole of clamp assembly, second clamp assembly are fixed on by nut on the side of first clamp assembly.
8. a kind of alloy building template architecture according to claim 2, it is characterised in that:The template be equipped with The parallel vertical rib of the connection frame, the vertical rib are rectangular configuration, and the vertical rib includes in pairs existing the The overall width of one vertical rib and the second vertical rib, the first vertical rib and the second vertical rib is no more than described The width of vertical keel.
9. a kind of alloy building template architecture according to claim 1, it is characterised in that:It is additionally provided in the template Lateral rib, the transverse direction rib is hollow or solid rectangular configuration, and the transverse direction rib is logical equipped with what is connect with U-shaped folder Hole, the U-shaped folder are 2 equipped with the quantity with the matched plug of the through-hole, the through-hole, and between the through-hole Distance is not less than the width of the vertical keel, and the bottom of the U-shaped folder is equipped with the screw hole for fixing the vertical keel.
10. a kind of installation method of alloy building template architecture as described in claim 1-9 Arbitrary Terms, feature exist In steps are as follows:
(1) trepanning will be carried out on the madial wall and lateral wall of template connection frame, by bolt by the connection of two adjacent templates Frame is fixedly connected, and template setting is placed on the steel bar spacer tied up, is made adjacent between the screens frame of template;
(2) trepanning template is placed between the screens frame of template, is inserted into wall pipe from trepanning template, wall bolt is inserted into, so Wall bolt, vertical keel is passed through to push down adjacent screens outer frame side vertical keel with holes afterwards, for resisting two adjacent cards Position frame and trepanning template, wall bolt nut is tightened;And for the formwork keel of integral structure, it is only necessary to while will be through walls Pipe and wall bolt pass through trepanning template and vertical keel, are fastened, you can;
(3) suitable position for selecting vertical keel, screens frame is fixed on by the collet of the first clamp assembly and the second clamp assembly Groove in, meanwhile, the second clamp assembly be inserted into the first clamp assembly body of rod in, be fixed, realization vertical keel is fixed In template;
(4) lateral rib is set in template, and places vertical keel between through-hole, vertical keel is fixed on U-shaped folder Inside is used in combination the plug of U-shaped folder to be inserted into through-hole, U-shaped folder is fixed on vertical keel with screw, for template middle part Position is fixed;
(5) lateral keel is arranged on the outside of vertical keel to be fixed.
CN201810619473.8A 2018-06-11 2018-06-11 Alloy building template architecture and its installation method Pending CN108487628A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810619473.8A CN108487628A (en) 2018-06-11 2018-06-11 Alloy building template architecture and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810619473.8A CN108487628A (en) 2018-06-11 2018-06-11 Alloy building template architecture and its installation method

Publications (1)

Publication Number Publication Date
CN108487628A true CN108487628A (en) 2018-09-04

Family

ID=63342741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810619473.8A Pending CN108487628A (en) 2018-06-11 2018-06-11 Alloy building template architecture and its installation method

Country Status (1)

Country Link
CN (1) CN108487628A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203441107U (en) * 2013-07-17 2014-02-19 贵州平川塑业建材科技有限公司 Connection clamp for plastic steel hollow porous ribbed template
CN103938854A (en) * 2014-04-25 2014-07-23 中国建筑第八工程局有限公司 Connection system of steel aluminum frame of steel aluminum frame formwork and keel
CN206438773U (en) * 2017-01-04 2017-08-25 云南建投建材科技有限责任公司 One kind building aluminum wood composite shuttering system selling sheet formula regulation board clamp
CN107476571A (en) * 2017-08-11 2017-12-15 中国化学工程第六建设有限公司 Exempt from the construction method of punching bamboo glue pattern plate
CN206769394U (en) * 2017-05-24 2017-12-19 中建一局华江建设有限公司 It is a kind of to exempt from punching template installation system for concrete exterior wall
CN208415908U (en) * 2018-06-11 2019-01-22 曹立英 Alloy building template architecture

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203441107U (en) * 2013-07-17 2014-02-19 贵州平川塑业建材科技有限公司 Connection clamp for plastic steel hollow porous ribbed template
CN103938854A (en) * 2014-04-25 2014-07-23 中国建筑第八工程局有限公司 Connection system of steel aluminum frame of steel aluminum frame formwork and keel
CN206438773U (en) * 2017-01-04 2017-08-25 云南建投建材科技有限责任公司 One kind building aluminum wood composite shuttering system selling sheet formula regulation board clamp
CN206769394U (en) * 2017-05-24 2017-12-19 中建一局华江建设有限公司 It is a kind of to exempt from punching template installation system for concrete exterior wall
CN107476571A (en) * 2017-08-11 2017-12-15 中国化学工程第六建设有限公司 Exempt from the construction method of punching bamboo glue pattern plate
CN208415908U (en) * 2018-06-11 2019-01-22 曹立英 Alloy building template architecture

Similar Documents

Publication Publication Date Title
CN209384444U (en) A kind of fabricated shear wall vertical connection structure
CN201535064U (en) Template for buildings
CN208415908U (en) Alloy building template architecture
CN209568705U (en) A kind of constructional column regularization template formwork erecting structure
CN109537882A (en) A kind of yin-yang angle constructive system based on universal plate and the yin-yang angle construction method based on universal plate
CN108487628A (en) Alloy building template architecture and its installation method
CN203412112U (en) Easily repaired beam column node of band open strip-type energy dissipation element
CN209556357U (en) A kind of yin-yang angle constructive system based on universal plate
CN209163541U (en) One kind can turnover type reservoir
CN109235946A (en) One kind can turnover type reservoir
KR20120124623A (en) A prefabricated molding panel
CN212670855U (en) Assembly type building node connection structure
CN108005376A (en) Special fastening connector is used in a kind of New Type Architecture Mode support
CN203939237U (en) The one-time formed erecting device of waterproof epirelief concrete component
CN209670338U (en) Bracing means is used in a kind of fixation kit and reinforced concrete column molding
CN202090589U (en) Plastic construction formwork
CN110836006A (en) Pin-connected panel building steel construction moulding board
CN220909108U (en) Floor side template supporting system with floor holes inside
CN201714085U (en) Shear wall door opening side molding plate reinforcing device
CN206016250U (en) A kind of unit assemble type toilet flange erecting device
CN202913689U (en) Solid ribbed construction template
CN220434365U (en) Storing instrument room with waterproof function
CN215107612U (en) Wood roof truss tip node reinforced structure
CN212002264U (en) Detachable reinforcing system of special-shaped steel-concrete combined column template
CN208152073U (en) A kind of streetlamp foundation formwork for placing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180904

RJ01 Rejection of invention patent application after publication