CN108486298A - Hot accumulated slag cleaning device and method for cleaning - Google Patents
Hot accumulated slag cleaning device and method for cleaning Download PDFInfo
- Publication number
- CN108486298A CN108486298A CN201810235768.5A CN201810235768A CN108486298A CN 108486298 A CN108486298 A CN 108486298A CN 201810235768 A CN201810235768 A CN 201810235768A CN 108486298 A CN108486298 A CN 108486298A
- Authority
- CN
- China
- Prior art keywords
- warm sludge
- slag
- chain cable
- convert
- accumulated slag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21B—MANUFACTURE OF IRON OR STEEL
- C21B3/00—General features in the manufacture of pig-iron
- C21B3/04—Recovery of by-products, e.g. slag
- C21B3/06—Treatment of liquid slag
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02W—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
- Y02W30/00—Technologies for solid waste management
- Y02W30/50—Reuse, recycling or recovery technologies
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Manufacturing & Machinery (AREA)
- Materials Engineering (AREA)
- Metallurgy (AREA)
- Organic Chemistry (AREA)
- Cleaning In General (AREA)
Abstract
The present invention relates to a kind of hot accumulated slag cleaning device and a kind of hot accumulated slag method for cleaning, belong to metallurgical technology field.Hot accumulated slag cleaning device, including warm sludge turn over and convert device, and warm sludge, which turns over, to be converted device inner wall bottom surface and be provided with chain cable, and chain cable is turned over along warm sludge converts device length direction arrangement, and chain cable turns over that convert device slag inlet one end be Detachable connection structure in warm sludge.Hot accumulated slag method for cleaning, includes the following steps:Before ploughing under molten state warm sludge, turns over to convert in warm sludge and above-mentioned hot accumulated slag cleaning device is installed on device;Molten state warm sludge is turned over by warm sludge and converts device and ploughs under in slag container;When warm sludge turns over and converts device bottom surface accumulated slag and reach preset thickness, turned in warm sludge and convert device slag inlet one end, chain cable is dragged by boom hoisting, make it is hardened turn over that convert the accumulated slag layer fragmentation of device bottom surface be clinker in warm sludge, and turn over warm sludge and to convert device and detach;Clinker after fragmentation is turned over to convert in device from warm sludge and is cleaned up.The present invention is easy to operate, accumulated slag treating capacity is big, operating efficiency is high.
Description
Technical field
The present invention relates to a kind of hot accumulated slag cleaning device and a kind of hot accumulated slag method for cleaning, belong to metallurgical technology
Field.
Background technology
It is mostly improved from increase mechanical equipment etc. about the method for cleaning of accumulated slag, and the main needle of scarfing cinder operation
Processing to cold conditions accumulated slag.Almost without the report about hot slag method for cleaning.Representative patents skill about clinker removal method
Art mainly has:
(1) a kind of ladles of CN106735159A slag cleaning device (publication date with cover:2017.5.31):
The disclosure of the invention a kind of ladle slag cleaning device with cover, described device include holder, maintenance platform, elevator, inclination
Pedestal, ladle fixed seat, cinder bogie;Inclined base is arranged in the cantilever tip, and elevator is arranged on inclined base, and the elevator is used
In pull-up backpack cover;The cradle top also sets up maintenance platform, and maintenance platform is in same plane with inclined base, is used for elevator
Repair;The ladle fixed seat is for fixing ladle;The cinder bogie is used for scarfing cinder.Which solves steel ladle edge dry slags
After normally cannot be capped or be capped after can not scarfing cinder with cover, the problem of causing ladle to cannot achieve full stroke covering, be mainly used in
In Ferrous Metallurgy on ladle with cover used in converter and refining furnace.
(2) CN206467261U is a kind of for clearing up trough and the hook machine rake (publication date of slag runner:2017.9.5):
The invention provides a kind of hook machine rakes for clearing up trough and slag runner, belong to metallurgical technology field, purpose
It is the cleaning efficiency for improving slag iron, technical solution is that composition includes rectangular base plate, rectangle rear baffle, right angled triangle side
Baffle and lever, the rear baffle is vertical with bottom plate, and the lower end of rear baffle is fixedly connected with the rear end of bottom plate, the side shield
Two pieces of setting, they are arranged symmetrically in the both sides of bottom plate, and a right-angle side of every piece of side shield and the side of bottom plate connect, another
The side of right-angle side and rear baffle connects, and the lever is perpendicular to rear baffle and is fixed on the trailing flank of rear baffle.This
Each rib of utility model is all linear, is both convenient for the slag iron bonded on scraping trough and slag runner side wall, can also
The slag iron for being deposited on trough and slag runner bottom is efficiently collected, can also easily be scooped up the slag iron of accumulation, to carry significantly
The high cleaning efficiency of slag iron.
The prior art (1) clears up the accumulated slag that steel ladle edge with cover sticks together using cinder bogie;The prior art (2) is harrowed using hook machine
Accumulated slag in the trough of sub- cleaning rule shape, slag runner.The structure of two kinds of prior arts is complex, and handles the quantity of slag
It is small, the extensive processing of hot slag can not be applied to.
Invention content
The technical problem to be solved by the present invention is to:A kind of hot accumulated slag cleaning device and a kind of hot accumulated slag are provided
Method for cleaning, turned over applied to warm sludge convert in device hot accumulated slag cleaning, it is easy to operate, can handle a large amount of accumulated slags, operation effect
Rate is high.
The technical solution adopted in the present invention is to solve above-mentioned technical problem:Hot accumulated slag cleaning device, including warm sludge
It turns over and converts device, warm sludge, which turns over, to be converted device inner wall bottom surface and be provided with chain cable, and chain cable is turned over along warm sludge converts device length direction arrangement, chain
Rope turns in warm sludge and converts device slag inlet one end as Detachable connection structure.
It is further:Chain cable is steel chain rope.
It is further:Chain cable is the more than one piece being arranged side by side.
It is further:By bar connecting between more than one piece chain cable, reinforcing bar is along chain cable length direction arranged for interval.
It is further:It is divided into multigroup between more than one piece chain cable, every group of chain cable passes through one group of bar connecting.
It is further:Chain cable turns over that convert the type of attachment of device slag inlet one end be to be buckled by crotch and hang over warm sludge in warm sludge
It turns over and converts device slag inlet breast board outer end.
It is further:Chain cable is turned in warm sludge converts the type of attachment of device slag notch one end freely to hang or being fixed on heat
Slag, which turns over, converts the appropriate position of device slag notch.
Hot accumulated slag method for cleaning, includes the following steps:
Before ploughing under molten state warm sludge, turns over to convert in warm sludge and above-mentioned hot accumulated slag cleaning device is installed on device;
Molten state warm sludge is turned over by warm sludge and converts device and ploughs under in slag container;
When warm sludge turns over and converts device bottom surface accumulated slag and reach preset thickness, is turned in warm sludge and convert device slag inlet one end, passed through
Boom hoisting drags the chain cable that is laid in advance, make it is hardened turn over that convert the accumulated slag layer fragmentation of device bottom surface be clinker in warm sludge, and with heat
Slag, which turns over, converts device separation;
The clinker after fragmentation is turned over to convert in device from warm sludge using the mode for pushing away slag rake, high pressure water or manual cleaning and is cleared up
Fall.
The beneficial effects of the invention are as follows:Using the accumulated slag in non-special steel chain rope processing shaped flow channel, and do not increase substantially
Oil (gas) filling device investment, accumulated slag treating capacity is big, operating efficiency is high;It is suitable for clearing up chute, the warm sludges such as slag runner turn over to convert and cross slag in device and cut
Face is big, the personnel of being not easy to approach the operating environment of operation;The height of runner, defeated slag device inner surface is bonded in suitable for clearing up solidification
Warm accumulated slag layer.
It solves the warm sludge under high rhythm of production using the method for cleaning hot molten slag and clears up problem, both eliminate bore hole
The large scale equipments such as machine, rock drill are invested, and reduce post number of workers, improve scarfing cinder operating environment, and safety coefficient is high.Together
When have many advantages, such as to save place, easily operated.
Description of the drawings
Fig. 1 is the structural schematic diagram of the hot accumulated slag cleaning device of the present invention;
Parts, position and number in figure:1- warm sludges, which turn over, converts device, 2- chain cables, 3- reinforcing bars.
Specific implementation mode
The invention will be further described with reference to the accompanying drawings and embodiments.
As shown in Figure 1, hot accumulated slag cleaning device, including warm sludge turn over and convert device 1, warm sludge, which turns over, converts 1 inner wall bottom surface of device
It is provided with chain cable 2, chain cable 2 is turned over along warm sludge converts 1 length direction of device arrangement, and chain cable 2 turns in warm sludge and converts 1 slag inlet one end of device
For Detachable connection structure.It is chute, slag runner etc. that warm sludge, which turns over and converts 1 generally use mode of device,.
The present invention is suitable for clearing up the high temperature accumulated slag layer that solidification is bonded in runner, defeated slag device inner surface, should select resistance to height
Warm material, considers working environment and cost of manufacture, and chain cable 2 is preferably steel chain rope.
In addition, for better scarfing cinder effect, chain cable 2 is the more than one piece being arranged side by side.
It is connected by reinforcing bar 3 between more than one piece chain cable 2, reinforcing bar 3 is along 2 length direction arranged for interval of chain cable.It can be formed in this way
The discontinuity Hard link of more chain cables 2, to facilitate scarfing cinder.Chain cable 2 is usually connected and fixed by reinforcing bar 3 by welding.
It when being connected using reinforcing bar 3, can will also be divided into multigroup between more than one piece chain cable 2, every group of chain cable 2 is connected by one group of reinforcing bar 3
It connects.
Chain cable 2 turns over that convert the connection structure of 1 slag inlet one end of device be to hang over warm sludge by crotch button and turn over to convert device in warm sludge
1 slag inlet breast board outer end, it is simple in structure, it is easy to implement.And chain cable 2 turns in warm sludge and converts one end of 1 slag notch of device and can freely hang down
It falls, could be secured to warm sludge and turn over and convert the appropriate position of 1 slag notch of device.
Hot accumulated slag method for cleaning, includes the following steps:
Before ploughing under molten state warm sludge, turns over to convert in warm sludge and above-mentioned hot accumulated slag cleaning device is installed on device 1;
Molten state warm sludge is turned over by warm sludge and converts device 1 and ploughs under in slag container;
It when warm sludge turns over and converts 1 bottom surface accumulated slag of device and reach preset thickness, is turned in warm sludge and converts 1 slag inlet one end of device, led to
It crosses boom hoisting and drags the chain cable 2 being laid in advance, hardened turned in warm sludge is made to convert the accumulated slag layer fragmentation of 1 bottom surface of device as clinker, and
It is turned over warm sludge and converts device 1 and detach;Crane, electric hoist etc. can be used in boom hoisting;
The clinker after fragmentation is turned over from warm sludge using the mode for pushing away slag rake, high pressure water or manual cleaning and is converted in device 1 clearly
Reason is fallen.
Embodiment:
The present invention, which is ploughed under in molten state blast furnace slag in the technique in smelting vessel, to be implemented, and is as follows:
Preparation stage:It 2 groups of steel chain ropes is laid in warm sludge turns over and convert in device, 4 steel chain ropes form 1 group, every steel chain rope
Diameter is about 5cm, a length of 10m, and the spacing of adjacent two steel chain ropes is 60cm, and every group of steel chain rope passes through the steel bar welding that spacing is 3m
Connection;Steel chain rope turns over to convert device slag inlet one end and by crotch button hang over warm sludge and turn in warm sludge converts device slag inlet breast board outer end,
Steel chain rope turns in warm sludge and converts device slag notch one end and be fixedly installed, and meets steel chain Suo Jun and be affixed on warm sludge and turn over and convert device bottom surface and put
It sets.
Turn over the slag stage:It is operated according to normal slag work flow of turning over, slag ladle and warm sludge turn over after converting device contraposition, tumble in tank
Molten blast furnace slag (temperature >=1250 DEG C) turns over the quantity of slag >=20t/ times, turns over slag number and is turned over depending on warm sludge and converts device floor space thickness of slag layer
Depending on, to extend the scarfing cinder period, the scarfing cinder operation frequency is reduced, it is to sentence to be turned over warm sludge and convert accumulated slag influence slag stream smooth outflow in device
According to progress scarfing cinder.
The disintegrating slag stage:When needing to carry out scarfing cinder operation, slag input end steel chain rope is hung over into the boom hoistings such as crane, electric hoist
On, dragging steel chain rope (2 groups are simultaneously) makes accumulated slag layer be shaken, and attrition crushing is fritter disintegrating slag and is turned over warm sludge and convert device and detach.
The scarfing cinder stage:It is turned over using high pressure water impact warm sludge and converts disintegrating slag block in device, 1 operative employee uses single high-pressure water pipe
Warm sludge can be turned in 10min and convert disintegrating slag block in device and clean out.Clinker, which with flow leaves warm sludge and turns over, to be converted device and falls into slag bucket
Middle draining, washing slag water enter the use of turbid circulating water system circulation, and the clinker after draining enters Solid state fermentation flow.
From the point of view of embodiment effect, warm sludge turns over the accumulated slag 2.4m for converting and having thickness about 10cm in device3, by pulling steel chain rope
Slag blanket is broken into fritter in 1min and is turned over warm sludge and converted device and be kept completely separate by group, and then 1 operative employee uses single high pressure
Disintegrating slag block is turned over to convert in device and be cleaned up completely by water pipe in 10min from warm sludge.
Present device small investment, characteristics of compact layout, it is easy to operate, be effectively improved operating environment, improve scarfing cinder operation effect
Rate can be applicable in the same industry.
Claims (8)
1. hot accumulated slag cleaning device, including warm sludge turn over and convert device (1), it is characterised in that:Warm sludge, which turns over, converts device (1) inner wall bottom table
Face is provided with chain cable (2), and chain cable (2) is turned over along warm sludge converts device (1) length direction arrangement, and chain cable (2) is turned in warm sludge converts device
(1) slag inlet one end is Detachable connection structure.
2. hot accumulated slag cleaning device as described in claim 1, it is characterised in that:Chain cable (2) is steel chain rope.
3. hot accumulated slag cleaning device as described in claim 1, it is characterised in that:Chain cable (2) is the more than one piece being arranged side by side.
4. hot accumulated slag cleaning device as claimed in claim 3, it is characterised in that:Pass through reinforcing bar (3) between more than one piece chain cable (2)
Connection, reinforcing bar (3) is along chain cable (2) length direction arranged for interval.
5. hot accumulated slag cleaning device as claimed in claim 4, it is characterised in that:Be divided between more than one piece chain cable (2) it is multigroup, often
Group chain cable (2) is connected by one group of reinforcing bar (3).
6. hot accumulated slag cleaning device as described in claim 1, it is characterised in that:Chain cable (2) warm sludge turn over convert device (1) into
The type of attachment of cinder notch one end is by crotch button to hang over warm sludge and turn over to convert device (1) slag inlet breast board outer end.
7. hot accumulated slag cleaning device as described in claim 1, it is characterised in that:Chain cable (2) turns in warm sludge and converts device (1) and go out
The type of attachment of cinder notch one end is freely to hang or be fixed on warm sludge and turn over to convert device (1) appropriate position of slag notch.
8. hot accumulated slag method for cleaning, which is characterized in that include the following steps:
Before ploughing under molten state warm sludge, turns over to convert in warm sludge and heat as claimed in any of claims 1 to 7 in one of claims is installed on device (1)
State accumulated slag cleaning device;
Molten state warm sludge is turned over by warm sludge and converts device (1) and ploughs under in slag container;
It when warm sludge turns over and converts device (1) bottom surface accumulated slag and reach preset thickness, is turned in warm sludge and converts device (1) slag inlet one end, led to
Boom hoisting dragging chain cable (2) is crossed, so that hardened turned in warm sludge is converted the accumulated slag layer fragmentation of device (1) bottom surface as clinker, and and warm sludge
It turns over and converts device (1) separation;
The clinker after fragmentation is turned over from warm sludge using the mode for pushing away slag rake, high pressure water or manual cleaning and converts cleaning in device (1)
Fall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810235768.5A CN108486298A (en) | 2018-03-21 | 2018-03-21 | Hot accumulated slag cleaning device and method for cleaning |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810235768.5A CN108486298A (en) | 2018-03-21 | 2018-03-21 | Hot accumulated slag cleaning device and method for cleaning |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108486298A true CN108486298A (en) | 2018-09-04 |
Family
ID=63318973
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810235768.5A Pending CN108486298A (en) | 2018-03-21 | 2018-03-21 | Hot accumulated slag cleaning device and method for cleaning |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108486298A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU910765A1 (en) * | 1980-08-12 | 1982-03-07 | Предприятие П/Я Г-4781 | Arrangement for knocking-out bears from slag cups |
US5360204A (en) * | 1993-09-20 | 1994-11-01 | Keibler-Thompson Corp. | Boom and lance for removing slag from crucible |
CN101148685A (en) * | 2007-08-16 | 2008-03-26 | 中冶宝钢技术服务有限公司 | Slag removing method |
CN201428147Y (en) * | 2009-06-23 | 2010-03-24 | 鞍山钢铁集团公司 | Special high-temperature resistant shovel |
CN202688334U (en) * | 2012-05-21 | 2013-01-23 | 中冶宝钢技术服务有限公司 | Slag removal device |
CN203440385U (en) * | 2013-07-15 | 2014-02-19 | 马鞍山市双益机械制造有限公司 | Slag loosening device for steel slag |
CN206467261U (en) * | 2017-01-23 | 2017-09-05 | 石家庄钢铁有限责任公司 | Hook machine rake for clearing up trough and slag runner |
-
2018
- 2018-03-21 CN CN201810235768.5A patent/CN108486298A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU910765A1 (en) * | 1980-08-12 | 1982-03-07 | Предприятие П/Я Г-4781 | Arrangement for knocking-out bears from slag cups |
US5360204A (en) * | 1993-09-20 | 1994-11-01 | Keibler-Thompson Corp. | Boom and lance for removing slag from crucible |
CN101148685A (en) * | 2007-08-16 | 2008-03-26 | 中冶宝钢技术服务有限公司 | Slag removing method |
CN201428147Y (en) * | 2009-06-23 | 2010-03-24 | 鞍山钢铁集团公司 | Special high-temperature resistant shovel |
CN202688334U (en) * | 2012-05-21 | 2013-01-23 | 中冶宝钢技术服务有限公司 | Slag removal device |
CN203440385U (en) * | 2013-07-15 | 2014-02-19 | 马鞍山市双益机械制造有限公司 | Slag loosening device for steel slag |
CN206467261U (en) * | 2017-01-23 | 2017-09-05 | 石家庄钢铁有限责任公司 | Hook machine rake for clearing up trough and slag runner |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201913209U (en) | Continuous casting tundish used for improving cleanliness of molten steel | |
CN201087194Y (en) | Slag clearing machine | |
CN108486298A (en) | Hot accumulated slag cleaning device and method for cleaning | |
CN209974856U (en) | Lead liquid slag removing device for lead pot | |
CN101418357B (en) | Overturn type top dust cover | |
CN208960983U (en) | A kind of steel ladle residue cleaning plant | |
CN104611511B (en) | Coreless induction furnace intelligence argon bottom-blowing dusts control system and its control method | |
CN106694835A (en) | Slag flushing chute device | |
CN102051438A (en) | Slag scraping and early warning protection system for oxygen lance | |
CN201960120U (en) | Casting ladle with slag trap device | |
CN205660151U (en) | Grasp of clearance ladle package mouthful long -pending sediment | |
CN205650930U (en) | Flame cutting machine cuts automatic cleaning device of sediment | |
CN210711683U (en) | Aluminum ash separator | |
CN106944608A (en) | Control the device and operating method of molten steel Large Inclusions | |
CN208586316U (en) | A kind of blast furnace residue channel slide cover board | |
CN105855530A (en) | Slag scraping and breaking device for steel ladle and application method thereof | |
CN105817613A (en) | Anchor for cleaning accumulated slag at steel ladle hole | |
CN210030764U (en) | Flue gas trapping device for swing chute of blast furnace | |
CN105798421A (en) | Automatic removing device for cutting residues of flame cutting machine | |
CN207049913U (en) | A kind of slag-tapping tube of boiler anti-block apparatus | |
CN215033556U (en) | Ladle mouth slagging cleaning device | |
CN209021233U (en) | A kind of dross device that can effectively remove steel ladle opening accumulated slag | |
CN203382785U (en) | Double-tooth slag adhering hopper | |
CN204897963U (en) | A scrape sediment ware for clearing up converter mouth and furnace crown amass sediment | |
CN213624209U (en) | Water-retaining and smoke-blocking device for blast furnace slag bin |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180904 |