CN108442384A - A kind of concrete support pile layout in foundation pit - Google Patents
A kind of concrete support pile layout in foundation pit Download PDFInfo
- Publication number
- CN108442384A CN108442384A CN201810351922.5A CN201810351922A CN108442384A CN 108442384 A CN108442384 A CN 108442384A CN 201810351922 A CN201810351922 A CN 201810351922A CN 108442384 A CN108442384 A CN 108442384A
- Authority
- CN
- China
- Prior art keywords
- support pile
- concrete support
- foundation pit
- concrete
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
Abstract
The invention discloses the concrete support pile layouts in a kind of foundation pit, include the concrete support pile of various shapes, the adjacent two sides structure of foundation pit at an acute angle or a right angle when, it is circular first concrete support pile that horizontal cross-section is provided on the outside of this angle;When the adjacent two sides of foundation pit constitute obtuse angle, the second concrete support pile that horizontal cross-section is polygon is provided on the outside of this angle, the angle of foundation pit and the side of polygon are oppositely arranged;Foundation pit is that third concrete support pile is arranged in smooth place, and width of the third concrete support pile close to soil layer side is not less than the side far from foundation pit.The advantages of invention, is:The concrete support pile of different cross section figure is arranged by the shape of margin of foundation pit by the present invention, can obtain preferably protection using less material in this way.
Description
Technical field
The present invention relates to building field, the concrete support pile layout in especially a kind of foundation pit.
Background technology
In order to ensure the safety or safe construction of the building in foundation pit, need that concrete branch is arranged at the madial wall of foundation pit
Fender pile, due to the pressure of the madial wall by foundation pit, since foundation pit is largely the loop configuration for having corner, the different position of foundation pit
It sets and the pressure of concrete support pile is different, and the structure of concrete support pile is consistent in the prior art.
The structure of concrete support pile must be stablized, and under some particular surroundings, concrete support pile is also easy to crack, and drops significantly in this way
The safety of low construction.Existing concrete support pile is round or rectangular, the contact area of circular concrete support pile and foundation pit
Small, such foundation pit is easy to tilt, although rectangular concrete support pile and the foundation area of foundation pit is big, but waste of resource.Cause
This, a kind of new concrete support pile of urgent need is laid out to solve the above problems.
Invention content
In order to overcome the above-mentioned prior art, for this purpose, the present invention provides the concrete support pile layout in a kind of foundation pit.
To achieve the above object, the present invention uses following technical scheme:
A kind of concrete support pile layout in foundation pit, includes the concrete support pile of various shapes, and the adjacent two sides of foundation pit are constituted
When acute angle or right angle, it is circular first concrete support pile that horizontal cross-section is provided on the outside of this angle;Foundation pit it is adjacent two
Be provided with the second concrete support pile that horizontal cross-section is polygon when side constitutes obtuse angle, on the outside of this angle, the angle of foundation pit with
The side of polygon is oppositely arranged;Foundation pit is that third concrete support pile, width of the third concrete support pile close to soil layer side is arranged in smooth place
Degree is not less than the side far from foundation pit.
Further, the outer edge of the second concrete support pile and third concrete support pile is smooth shape.
Further, the third concrete support pile upper surface be trapezoidal portion and curved portion combination, the trapezoidal portion it is upper
Bottom edge is replaced with the tangent curved portion in two sides, and bottom is close to soil layer.
Further, the density of the foundation pit corner concrete support pile is more than the density for the concrete support pile smoothly located.
Further, in the height direction, top is Basalt fiber concrete to the concrete support pile, and lower part is mixed for cement
Solidifying soil.
Further, the altitude range of the Basalt fiber concrete is 0.8-1.2m.
Further, concrete support pile includes basalt fibre arrangement of reinforcement, and the concrete support pile outer edge shape changes place
It is both provided with basalt fibre arrangement of reinforcement.
Further, the density of basalt fibre arrangement of reinforcement of the concrete support pile at soil layer is more than appointing far from soil layer
The concentration of meaning position.
Further, concrete support pile further includes steel arrangement of reinforcement, and the basalt fibre arrangement of reinforcement and steel arrangement of reinforcement are arranged alternately, arc
Place is respectively provided with basalt fibre arrangement of reinforcement.
The advantage of the invention is that:
(1) the concrete support pile of different cross section figure is arranged by the shape of margin of foundation pit by the present invention, can make in this way
With obtaining preferably protection in the case of less material.
The outer edge of (2) second concrete support piles and third concrete support pile is smooth shape, ensures that concrete support pile stress is more uniform.
(3) supporting that third concrete support pile can be improved in the case of reduction material is placed in the setting of third concrete support pile
Ability.
(4) density of the concrete support pile of foundation pit corner is more than the density for the concrete support pile smoothly located, and may insure in this way
The support capacity of entire foundation pit.
(5) concrete support pile of the present invention top Basalt fiber concrete, lower part are cement concrete, and use basalt
Fiber arrangement of reinforcement increases the intensity of concrete support pile in this way.
(6) concentration by basalt fibre arrangement of reinforcement in different location is arranged, and further includes steel arrangement of reinforcement, is ensureing in this way
Cost can be saved in the case of intensity.
Description of the drawings
Fig. 1 is the vertical view of the concrete support pile layout in a kind of foundation pit of the present invention.
Fig. 2 is the vertical view of concrete support pile in the embodiment of the present invention 1.
Fig. 3 is the front view of concrete support pile in Example 1 and Example 2 of the present invention.
Fig. 4 is the vertical view of concrete support pile in the embodiment of the present invention 2.
The meaning of label symbol is as follows in figure:
The trapezoidal portion 12- curved portions 13- rectangular portions of 1- concrete support piles 11-
14- 15-cement concretes of Basalt fiber concrete
2- basalt fibre arrangement of reinforcement 3- steel arrangements of reinforcement
4- foundation pits 101- the first concrete support pile 102- the second concrete support pile 103- third concrete support piles
Specific implementation mode
Embodiment 1
As shown in Figure 1, the concrete support pile layout in a kind of foundation pit, includes the concrete support pile 1 of various shapes, in 4 phase of foundation pit
Adjacent two sides structure at an acute angle or a right angle when, it is circular first concrete support pile that horizontal cross-section is provided on the outside of this angle
101;When the adjacent two sides of foundation pit 4 constitute obtuse angle, second that horizontal cross-section is polygon is provided on the outside of this angle
Concrete support pile 102, the angle of foundation pit 4 and the side of polygon are oppositely arranged;It is that third concrete support pile is arranged in smooth place in foundation pit 4
103, width of the third concrete support pile 103 close to soil layer side is not less than the side far from foundation pit 4.The outer edge of concrete support pile 1
It is smooth shape.The density of 4 corner's concrete support pile 1 of the foundation pit is more than the density for the concrete support pile 1 smoothly located.
Wherein the first concrete support pile 101, the second concrete support pile 102, third concrete support pile 103 are column structure, concrete branch
Fender pile 1 includes basalt fibre arrangement of reinforcement 2 and steel arrangement of reinforcement 3.The density of basalt fibre arrangement of reinforcement 2 of the concrete support pile 1 at soil layer
More than the concentration of any position far from soil layer, basalt fibre arrangement of reinforcement 2 and steel arrangement of reinforcement 3 are arranged alternately, are respectively provided at arc profound
Military rock fiber arrangement of reinforcement 2 ensures the anti-crack ability of concrete support pile 1 in the case where saving resource.
As Figure 2-3, third concrete support pile 103 is not less than close to the sectional area of soil layer side vertical direction far from soil layer
Any position vertical direction sectional area, in this embodiment third concrete support pile 103 from close to soil layer to far from soil layer
On direction, the vertical sectional area of concrete supporting 1 is gradually reduced, and specifically, 103 upper surface of third concrete support pile is trapezoidal portion 11
It is replaced with the tangent arc in two sides with the upper bottom edge of the combination of curved portion 12, trapezoidal portion 11, bottom is close to soil layer.It is trapezoidal
The bottom in portion 11 and the angle of two sides are inscribed circle.103 outer edge shape of second concrete support pile 102 and third concrete support pile
The shape Chu Ji corners that change are both provided with basalt fibre arrangement of reinforcement 2.
In the height direction, top Basalt fiber concrete 14, lower part is cement concrete 15 to concrete support pile 1.The reality
The height for applying Basalt fiber concrete 14 in example is 0.8m.Basalt fiber concrete 14 includes basalt fibre, basalt
The weight of fiber accounts for the 1% of entire weight.Since the top pile crown connection top Guan Liang of concrete support pile 1 forms the foundation pit 4 being closed
Support system, top pile crown uses Basalt fiber concrete 14 so that pile crown intensity is reinforced, conducive to whole stress.
Embodiment 2
Difference from Example 1 is the structure of third concrete support pile 103, as shown in figure 4, third concrete support pile 103
Upper surface is the combination of rectangular portion 13 and curved portion 12, and rectangular portion 13 is far from soil layer and the side parallel with soil layer face is as arc
The diameter in portion 12, curved portion 12 is semicircle in this embodiment.Curved portion 12 is respectively provided with basalt fibre arrangement of reinforcement 2, is saving
Ensure the anti-crack ability of concrete support pile 1 in the case of resource.
In the height direction, top Basalt fiber concrete 14, lower part is cement concrete 15 to concrete support pile 1.The reality
The height for applying Basalt fiber concrete 14 in example is 1.2m.Basalt fiber concrete 14 includes basalt fibre, basalt
The weight of fiber accounts for the 2% of entire weight.Since the top pile crown connection top Guan Liang of concrete support pile 1 forms the foundation pit 4 being closed
Support system, top pile crown uses Basalt fiber concrete 14 so that pile crown intensity is reinforced, conducive to whole stress.
Embodiment 3
Different from documents 1 is, the height of Basalt fiber concrete 14 is 1m, Basalt fiber concrete 14
In the weight of basalt fibre account for the 3% of entire basalt weight concrete.
Embodiment 4
Different from documents 2 is, the height of Basalt fiber concrete 14 is 1m, Basalt fiber concrete 14
In the weight of basalt fibre account for the 3% of entire basalt weight concrete.
The preferred embodiment that these are only the invention is not intended to limit the invention creation, all in the present invention
All any modification, equivalent and improvement etc., should be included in the guarantor of the invention made by within the spirit and principle of creation
Within the scope of shield.The preferred embodiment that these are only the invention is not intended to limit the invention creation, all in this hair
All any modification, equivalent and improvement etc., should be included in the invention made by within the spirit and principle of bright creation
Within protection domain.
Claims (9)
1. the concrete support pile layout in a kind of foundation pit, which is characterized in that the concrete support pile (1) including various shapes, foundation pit (4) phase
Adjacent two sides structure at an acute angle or a right angle when, it is circular first concrete support pile that horizontal cross-section is provided on the outside of this angle
(101);When the adjacent two sides of foundation pit (4) constitute obtuse angle, that horizontal cross-section is polygon is provided on the outside of this angle
Two concrete support piles (102), the angle of foundation pit (4) and the side of polygon are oppositely arranged;Foundation pit is that third concrete supporting is arranged in smooth place
Stake (103), width of the third concrete support pile (103) close to soil layer side are not less than the side far from foundation pit.
2. the concrete support pile layout in a kind of foundation pit according to claim 1, which is characterized in that the second concrete support pile
(102) and the outer edge of third concrete support pile (103) is smooth shape.
3. the concrete support pile layout in a kind of foundation pit according to claim 1, which is characterized in that the third concrete support pile
(103) upper surface is the combination of trapezoidal portion (11) and curved portion (12), the upper bottom edge of the trapezoidal portion (11) with two sides phase
The curved portion (12) cut is replaced, and bottom is close to soil layer.
4. the concrete support pile layout in a kind of foundation pit according to claim 1, which is characterized in that foundation pit (4) turning
The density of place's concrete support pile (1) is more than the density for the concrete support pile (1) smoothly located.
5. the concrete support pile layout in a kind of foundation pit according to claim 1, which is characterized in that the concrete support pile (1)
In the height direction, top is Basalt fiber concrete (14), and lower part is cement concrete (15).
6. the concrete support pile layout in a kind of foundation pit according to claim 5, which is characterized in that the basalt fibre is mixed
The altitude range of solidifying soil (14) is 0.8-1.2m.
7. the concrete support pile layout in a kind of foundation pit according to claim 5, which is characterized in that concrete support pile includes the Black Warrior
Rock fiber arrangement of reinforcement (2), concrete support pile (1) the outer edge shape place of changing are both provided with basalt fibre arrangement of reinforcement (2).
8. the concrete support pile layout in a kind of foundation pit according to claim 7, which is characterized in that the concrete support pile (1)
The density of basalt fibre arrangement of reinforcement (2) at soil layer is more than the concentration of any position far from soil layer.
9. the concrete support pile layout in a kind of foundation pit according to claim 7, which is characterized in that concrete support pile further includes steel
Arrangement of reinforcement (3), the basalt fibre arrangement of reinforcement (3) and steel arrangement of reinforcement (4) are arranged alternately, and basalt fibre arrangement of reinforcement is respectively provided at arc
(3)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810351922.5A CN108442384A (en) | 2018-04-19 | 2018-04-19 | A kind of concrete support pile layout in foundation pit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810351922.5A CN108442384A (en) | 2018-04-19 | 2018-04-19 | A kind of concrete support pile layout in foundation pit |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108442384A true CN108442384A (en) | 2018-08-24 |
Family
ID=63200200
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810351922.5A Pending CN108442384A (en) | 2018-04-19 | 2018-04-19 | A kind of concrete support pile layout in foundation pit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108442384A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826205A (en) * | 2019-03-29 | 2019-05-31 | 深圳宏业基岩土科技股份有限公司 | Double supporting pile structure |
CN110130359A (en) * | 2019-05-10 | 2019-08-16 | 中国建筑西南勘察设计研究院有限公司 | A kind of BFRP tendons material hybrid reinforcement support pile and its construction method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2298285Y (en) * | 1997-03-26 | 1998-11-25 | 福建建专基础工程公司 | Deformed sectional bored concrete pile |
JP2011202373A (en) * | 2010-03-24 | 2011-10-13 | Taisei Corp | Earth retaining structure and construction method of the same |
CN103046543A (en) * | 2013-01-09 | 2013-04-17 | 中国地质大学(武汉) | Antiskid pile with hollow outer isosceles trapezoid cross section and in unequal interval arrangement |
CN204530675U (en) * | 2015-02-09 | 2015-08-05 | 上海三凯建设管理咨询有限公司 | A kind of hexagonal bore castinplace pile |
CN106193026A (en) * | 2016-07-25 | 2016-12-07 | 合肥工业大学 | A kind of fiber reinforced precast concrete tubular stake and processing method thereof |
CN206279545U (en) * | 2016-12-08 | 2017-06-27 | 四川农业大学 | A kind of mini pile and Antiskid pile combination retaining structure of arc arrangement |
CN107130589A (en) * | 2017-06-07 | 2017-09-05 | 安徽省建筑科学研究设计院 | A kind of asymmetric compound armored concrete poured support stake |
CN206693244U (en) * | 2017-04-07 | 2017-12-01 | 中国建筑西南勘察设计研究院有限公司 | A kind of basalt composite reinforcing material foundation pit supporting pile |
CN206768834U (en) * | 2017-04-20 | 2017-12-19 | 中南勘察设计院(湖北)有限责任公司 | A kind of deep basal pit combined support structure |
CN208777315U (en) * | 2018-04-19 | 2019-04-23 | 安徽省建筑科学研究设计院 | A kind of concrete support pile system in foundation pit |
-
2018
- 2018-04-19 CN CN201810351922.5A patent/CN108442384A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2298285Y (en) * | 1997-03-26 | 1998-11-25 | 福建建专基础工程公司 | Deformed sectional bored concrete pile |
JP2011202373A (en) * | 2010-03-24 | 2011-10-13 | Taisei Corp | Earth retaining structure and construction method of the same |
CN103046543A (en) * | 2013-01-09 | 2013-04-17 | 中国地质大学(武汉) | Antiskid pile with hollow outer isosceles trapezoid cross section and in unequal interval arrangement |
CN204530675U (en) * | 2015-02-09 | 2015-08-05 | 上海三凯建设管理咨询有限公司 | A kind of hexagonal bore castinplace pile |
CN106193026A (en) * | 2016-07-25 | 2016-12-07 | 合肥工业大学 | A kind of fiber reinforced precast concrete tubular stake and processing method thereof |
CN206279545U (en) * | 2016-12-08 | 2017-06-27 | 四川农业大学 | A kind of mini pile and Antiskid pile combination retaining structure of arc arrangement |
CN206693244U (en) * | 2017-04-07 | 2017-12-01 | 中国建筑西南勘察设计研究院有限公司 | A kind of basalt composite reinforcing material foundation pit supporting pile |
CN206768834U (en) * | 2017-04-20 | 2017-12-19 | 中南勘察设计院(湖北)有限责任公司 | A kind of deep basal pit combined support structure |
CN107130589A (en) * | 2017-06-07 | 2017-09-05 | 安徽省建筑科学研究设计院 | A kind of asymmetric compound armored concrete poured support stake |
CN208777315U (en) * | 2018-04-19 | 2019-04-23 | 安徽省建筑科学研究设计院 | A kind of concrete support pile system in foundation pit |
Non-Patent Citations (1)
Title |
---|
中航勘察设计研究院等, 地震出版社 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826205A (en) * | 2019-03-29 | 2019-05-31 | 深圳宏业基岩土科技股份有限公司 | Double supporting pile structure |
CN109826205B (en) * | 2019-03-29 | 2024-02-09 | 深圳宏业基岩土科技股份有限公司 | Double-row support pile structure |
CN110130359A (en) * | 2019-05-10 | 2019-08-16 | 中国建筑西南勘察设计研究院有限公司 | A kind of BFRP tendons material hybrid reinforcement support pile and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104110012A (en) | Low-permeability rock-fill material concrete panel rock-fill dam | |
CN205224363U (en) | Connection structure of floor and girder steel | |
CN108442384A (en) | A kind of concrete support pile layout in foundation pit | |
CN208777315U (en) | A kind of concrete support pile system in foundation pit | |
CN102653945A (en) | Foundation reinforcing and replacing structure and construction method thereof | |
CN103452132B (en) | A kind of barricade | |
CN206396615U (en) | Suitable for the bridge structure of bridge pier differential settlement | |
CN206157508U (en) | Light soil roadbed structure | |
CN208685678U (en) | A kind of float Structure of subway station | |
CN209277207U (en) | A kind of post-cast strip waterproof construction | |
CN209483375U (en) | A kind of roadway support structure | |
CN205062817U (en) | Landing stage with combination of excavation supporting system | |
CN208777301U (en) | A kind of concrete support pile including basalt fibre arrangement of reinforcement | |
CN105239584B (en) | Multi-arch type sheet pile supporting construction carries out the construction technology of pattern foundation pit supporting structure | |
CN110387889A (en) | A kind of multi-arch type foundation pit supporting method for strip deep basal pit | |
CN208763020U (en) | A kind of concrete support pile system using carbon fiber arrangement of reinforcement in foundation pit | |
CN208777298U (en) | A kind of concrete support pile including carbon fiber arrangement of reinforcement | |
CN209779666U (en) | Bridge foundation space protection structure on rock cone slope | |
CN204456131U (en) | A kind of structural floor that utilizes is as the structural system of horizontal support | |
CN108330813B (en) | A kind of novel bridge | |
CN108411903B (en) | Concrete support pile comprising basalt fiber reinforced bars | |
CN108396748A (en) | A kind of concrete support pile using carbon fiber arrangement of reinforcement in foundation pit is laid out | |
CN205955008U (en) | Basement roof arch without beam pile cap node that is all -trans | |
CN107620301A (en) | A kind of geology bracing means | |
CN108442360A (en) | A kind of concrete support pile including carbon fiber arrangement of reinforcement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |