CN108396895A - The more curved surface overhanging curtain walls of large span and its construction method - Google Patents

The more curved surface overhanging curtain walls of large span and its construction method Download PDF

Info

Publication number
CN108396895A
CN108396895A CN201810191905.XA CN201810191905A CN108396895A CN 108396895 A CN108396895 A CN 108396895A CN 201810191905 A CN201810191905 A CN 201810191905A CN 108396895 A CN108396895 A CN 108396895A
Authority
CN
China
Prior art keywords
curtain wall
pendant
floor beam
fixed
keel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810191905.XA
Other languages
Chinese (zh)
Other versions
CN108396895B (en
Inventor
胡伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Taixing Decoration Engineering Co Ltd
Original Assignee
Sichuan Taixing Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Taixing Decoration Engineering Co Ltd filed Critical Sichuan Taixing Decoration Engineering Co Ltd
Priority to CN201810191905.XA priority Critical patent/CN108396895B/en
Publication of CN108396895A publication Critical patent/CN108396895A/en
Application granted granted Critical
Publication of CN108396895B publication Critical patent/CN108396895B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms

Abstract

The invention discloses a kind of more curved surface overhanging curtain walls of large span and its construction methods, the more curved surface overhanging curtain walls of the large span and its construction method include the concrete floor with floor beam, base keel, main joist truss, secondary joist and curtain wall unit block, the horizontal position of the floor beam of the concrete floor outer end of different height is different, it is respectively connected with inclined base keel between floor beam per levels, it is tilted between the base keel and floor beam and is fixed with support column, the main joist truss is fixed on base keel, the outer end of main joist truss is fixed with lateral secondary joist, multiple first pendants are fixed on the inside of the curtain wall unit block, the second pendant coordinated with the first pendant is detachably and fixedly provided on the secondary joist, with on the basis of ensureing curtain wall installation accuracy and curved surface conjugation grade, the advantages of greatly reducing difficulty of construction.

Description

The more curved surface overhanging curtain walls of large span and its construction method
Technical field
The present invention relates to building field, more particularly to a kind of more curved surfaces of large span overhang curtain wall and its construction method.
Background technology
With the continuous development of China's architectural decoration, more design abroad theories constantly pour in China, make China The construction technology of building trade has also obtained constantly going out new.The more moulded graces of curved surface curtain wall of large area, rich in artistry, but In the construction that more curved surfaces overhang curtain wall, irregular architecture structure form brings larger difficulty to Deepen Design and construction. Large area overhangs there are errors in construction larger, more curved surface curtain wall point position in space positioning measurements and the installation of curved surface steel truss system Difficult feature.
Invention content
The purpose of the present invention one is to provide a kind of more curved surface overhanging curtain walls of large span, solves more curved surface curtain wall point position in space Positioning measurement and it is difficult to install the problem of.
The present invention above-mentioned technical purpose technical scheme is that:
A kind of more curved surfaces of large span overhang curtain walls, include concrete floor with floor beam, base keel, main joist truss, secondary The horizontal position of keel and curtain wall unit block, the floor beam of the concrete floor outer end of different height is different, per up and down Inclined base keel are respectively connected between the floor beam of layer, is tilted between the base keel and floor beam and is fixed with support column, institute It states main joist truss and is fixed on base keel, the outer end of main joist truss is fixed with lateral secondary joist, the curtain wall unit block Inside is fixed with multiple first pendants, and the second pendant coordinated with the first pendant is detachably and fixedly provided on the secondary joist.
Using the above scheme, the fixation of base keel and floor beam both ensure that the stabilization shape of base keel, also be carried for floor beam Strong support is supplied, and different according to the curvature of the outside of overhanging curtain wall, levels floor beam position can be in advance in water Square offset is generated upwards, also therefore base keel can be presented different degrees of inclination, and incline structure is equivalent to for overhanging The curvature of curtain wall carries out prebuckling adjustment so that steel truss system can be with easier determining point position in space, and carries out pre-bending The bending of truss itself will be reduced after tune is whole, be increased the serious forgiveness of truss installa-tion, be conducive to the accurate installation of curtain wall;And Curtain wall is fixed to by the cooperation of the first pendant and the second pendant on the secondary joist on truss, and the second pendant is matched as replaceable Part can carry out selection adjustment, further realize the fine tuning of curtain wall unit block according to demand;It is realized with this and is ensureing curtain wall peace On the basis of filling precision and curved surface conjugation grade, difficulty of construction is greatly reduced.
Further preferably:The outer end face of the floor beam is fixed with crossbeam, be fixed on the crossbeam respectively with building The false keel of the bilevel base keel connection of face beam.
Using the above scheme, by crossbeam and false keel that the bilevel all base keel of floor beam are linked as stress is whole Body improves the stability and stress-bearing capability of base keel.
Further preferably:The base keel include the end bracket positioned at base keel upper and lower end face, the end bracket and building Face beam abuts, and the chemical anchor bolts being fixedly connected with floor beam are equipped on the end bracket.
Using the above scheme, end bracket is plane, increases the contact area with floor beam, reduces the situation of stress concentration; General end bracket and base keel welding fabrication, chemical anchor bolts preferably can keep end bracket to be fixedly connected with floor beam.
Further preferably:Two support columns, two branch are respectively and fixedly provided on the upper and lower part inner surface of the base keel Dagger is mutually V-shaped and is fixedly connected with floor beam with the other end.
Using the above scheme, each support column can be actually base keel according to tension or the two different situations of resistance to compression It is both direction to provide a direction resistant to lodging, and two V-shaped support columns are then four direction, and base dragon can be improved with this Bone it is each to ability resistant to lodging.
Further preferably:The secondary joist be include two parallel tablets and it is vertical be set to two tablets it Between web, multiple perforation are provided on the web, the web forms two grooves with tablet;Second pendant includes The embedding head being embedded in groove is embedded with by way of wearing bolt in the groove of the secondary joist other side and the second pendant The cushion block of connection.
Using the above scheme, secondary joist is in I-shaped, and the embedding head in secondary joist can be by the abutting branch of two tablets Support, cushion block then ensure that the uniform force on secondary joist both sides, and make each plate face of secondary joist that can provide holding power; And the second pendant can be fixed to different hole position positions according to different locational requirements.
Further preferably:Second pendant further includes being connected to the carrier of plate outer surface and rabbeting for tablet Access slot, the carrier it is L-shaped with it is embedding first body formed, the access slot is surrounded by carrier and embedding head and is molded.
Using the above scheme, carrier is connected to the outer wall of tablet, increases contact area, increases the stress-bearing capability of tablet, Tablet stress is prevented to be bent.
Further preferably:Indent is provided with limiting slot, the interior table of the tablet on the cell wall and slot bottom of the access slot Face is provided with the place-limited edge coordinated with limiting slot.
Using the above scheme, place-limited edge can prevent the second pendant from being detached with secondary joist, when installation, the second pendant It can be slid into groove from the end of secondary joist, then pass through screw bolt reinforcing.
Further preferably:The both sides of the embedding head are each provided with a carrier.
Using the above scheme, upper and lower two parts can be supported, and keep preferable stress performance.
Further preferably:Second pendant further includes upper trailing arm and lower trailing arm, wherein above between trailing arm and carrier It is provided with groove, the end set of the lower trailing arm has lower hook portion;First pendant connects arm including above connecing arm under, wherein On connect arm and abut and the upper surface of upper trailing arm and have the upper hook portion coordinated with upper groove in end set, connect arm and subiculum under described The upper surface of arm abuts and is simultaneously provided with the lower groove coordinated with lower hook portion in tail portion, it is described on connect arm, upper trailing arm, under connect arm and Fastening bolt is provided through on lower trailing arm, the end of fastening bolt is fixed with fastening nut.
Using the above scheme, the curtain wall curved surface opposed vertical plane of building does not exceed 60 ° generally, in this way, upper and lower trailing arm Main support is provided with the cooperation for connecing arm above and below, the cooperation of upper and lower groove and upper and lower hook portion prevents slip apart, and on Connect and under connect the end of arm and the abutting of the second pendant can also be for support.
The purpose of the present invention two is to provide a kind of more curved surface overhanging curtain walls of large span, and steps are as follows for work:
Step 1, the curtain wall curved surface of abbreviation as needed builds the position that floor beam has set floor beam in advance;
Step 2, surveying setting-out is installed base keel between outermost floor beam and is fixed with chemical anchor bolts, installs support column Fixed slanting fixed base keel and floor beam;
Step 3, crossbeam is installed in the outer end of floor beam, the two rows false keel on crossbeam respectively with both sides above and below floor beam Base keel fix;
Step 4, by main joist truss installa-tion on base keel, welding main joist truss and base keel after installation is complete;
Step 5, it is transversely mounted secondary joist on main joist, the second pendant is because in preliminary installation to secondary joist when installation;
Step 6, curvature is designed according to curtain wall unit block, adjusts the position of the second pendant, the first pendant on curtain wall should pacify in advance It installs into;The first pendant on curtain wall unit block is docked with the second pendant, and wears fastening bolt and fixes.
In conclusion the invention has the advantages that:
1, prebuckling adjustment is carried out for the curvature of overhanging curtain wall so that steel truss system can be with easier determining spatial point Position, and the bending for carrying out truss itself after prebuckling adjustment will be reduced, and be increased the serious forgiveness of truss installa-tion, be conducive to curtain wall Precisely installation;
2, by pendant dock in a manner of can in advance be finely tuned when curtain wall unit block be installed, ensure curtain wall installation accuracy with On the basis of curved surface conjugation grade, difficulty of construction is greatly reduced.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present embodiment;
Fig. 2 is enlarged drawings of the Fig. 1 of the present embodiment at A;
Fig. 3 is the structural schematic diagram of first pendant and the second pendant of the present embodiment.
In figure, 1, concrete floor;2, base keel;3, main joist truss;4, secondary joist;5, curtain wall unit block;6, crossbeam; 7, the second pendant;8, the first pendant;9, cushion block;11, floor beam;21, support column;22, end bracket;41, tablet;42, web; 43, place-limited edge;61, false keel;71, embedding head;72, carrier;73, access slot;731, limiting slot;74, upper trailing arm;75, upper groove; 76, lower trailing arm;761, lower hook portion;81, matrix;82, arm is connect on;821, upper hook portion;83, arm is connect under;84, lower groove.
Specific implementation mode
Below in conjunction with attached drawing, invention is further described in detail.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, people in the art Member can as needed make the present embodiment the modification of not creative contribution after reading this specification, but as long as at this It is all protected by Patent Law in the protection domain of invention.
The present embodiment:The more curved surfaces of large span overhang curtain wall, as shown in Figure 1, including the concrete floor with floor beam 11 1, base keel 2, main joist truss 3, secondary joist 4 and curtain wall unit block 5;According to the curtain wall curvature of planning, wherein different height 1 outer end of concrete floor floor beam 11 horizontal position it is different;It is respectively connected with inclination between floor beam 11 per levels Base keel 2, main joist truss 3 is fixed on base keel 2, and the outer end of main joist truss 3 is fixed with lateral secondary joist 4, curtain wall The inside of cell block 5 is fixed with multiple first pendants 8(With reference to Fig. 3), it is detachably and fixedly provided with and the first pendant 8 on secondary joist 4 Second pendant 7 of cooperation(With reference to Fig. 3), the installation and adjustment of the current cell block of cooperation completion of two kinds of pendants.
If the upper and lower end face of Fig. 2 institutes, base keel 2 is provided with end bracket 22, end bracket 22 is welded to connect with base keel 2, end Fishplate bar 22 is abutted with floor beam 11, and the chemical anchor bolts being fixedly connected with floor beam 11 are equipped on end bracket 22.Base keel 2 it is upper The support column 21 being mutually in the shape of the letter V there are two fixing, the other end of two support columns 21 are tilted in portion and lower inner surface Chemical anchor bolts of reaching the same goal are fixedly connected with floor beam 11.The outer end face of floor beam 11 is fixed with crossbeam 6, is fixed on crossbeam 6 point The false keel 61 not connect with 11 bilevel base keel 2 of floor beam, false keel 61 weld in succession with base keel 2.
Main joist truss 3 has multiple steel parts to build, and main joist truss 3 is tentatively fixed on base dragon by first passing through bolt On bone 2, then reinforce fixing by welding.
As shown in figure 3, secondary joist 4 is secured by bolts in main joist truss 3, then reinforce fixing by welding.Secondary dragon Bone 4 be include two parallel tablets 41 and the vertical web 42 being set between two tablets 41, be arranged on web 42 There are multiple perforation, web 42 to form two grooves with tablet 41.Multiple second pendants 7, the second pendant 7 are connected on secondary joist 4 Quantity set according to the curtain wall unit block 5 that is fixed on secondary joist 4.
Second pendant 7 includes the first butted part docked with secondary joist 4 and the second docking section for being docked with the first pendant 8 Point;Wherein the first butted part includes the embedding head 71 being embedded in groove, be connected to 41 outer surface of tablet carrier 72 and The access slot 73 rabbeted for tablet 41.It is embedded with by way of wearing bolt in the groove of 4 other side of secondary joist and the second pendant 7 The cushion block 9 of connection.The L-shaped both sides with the integrated molding of embedding head 71 and embedding head 71 of carrier 72 are each provided with a carrier 72. Access slot 73 is surrounded by carrier 72 and embedding head 71 and is molded, and indent is provided with limiting slot 731 on the cell wall and slot bottom of access slot 73, is put down The inner surface of plate 41 is provided with the place-limited edge 43 coordinated with limiting slot 731.Second butted part includes upper trailing arm 74 and lower trailing arm 76, wherein upper be provided with groove 75 between trailing arm 74 and carrier 72, the end set of lower trailing arm 76 has lower hook portion 761.
First pendant 8 include matrix 81, on connect arm 82 and under connect arm 83, wherein on connect arm 82 abut it is upper with upper trailing arm 74 Surface simultaneously has the upper hook portion 821 coordinated with upper groove 75 in end set, under connect arm 83 and abutted simultaneously with the upper surface of lower trailing arm 76 The lower groove 84 coordinated with lower hook portion 761 is provided in tail portion, above connect arm 82, upper trailing arm 74, under connect arm 83 and lower trailing arm 76 On be provided through fastening bolt, the end of fastening bolt is fixed with fastening nut.Matrix 81 is consolidated by way of wearing back of the body bolt Due to the back side of curtain wall unit block 5, according to the of different sizes of curtain wall unit block 5, quantity can be also varied from fact.
Embodiment 2:The construction method of the more curved surface overhanging curtain walls of large span, as shown in Figure 1, its construction procedure is as follows:
Step 1, the curtain wall curved surface of abbreviation as needed builds the position that floor beam 11 has set floor beam 11 in advance;
Step 2, surveying setting-out installs base keel 2 between outermost floor beam 11 and to fix postposition with chemical bolt pre-buried Plate, installation support column 21 fix slanting fixed base keel 2 and floor beam 11;
Step 3, crossbeam 6 is installed in the outer end of floor beam 11, the two rows false keel 61 on crossbeam 6 respectively with floor beam 11 The base keel 2 of upper and lower both sides are fixed;
Step 4, main joist truss 3 is mounted on base keel 2, welding main joist truss 3 and base keel 2 after installation is complete;
Step 5, it is transversely mounted secondary joist 4 on main joist, the second pendant 7 is because tentatively installing to secondary joist 4 when installation;
Step 6, curvature is designed according to curtain wall unit block 5, adjusts the position of the second pendant 7, the first pendant 8 on curtain wall should be prior Installation is complete;The first pendant 8 on curtain wall unit block 5 is docked with the second pendant 7, and wears fastening bolt and fixes.

Claims (10)

1. a kind of more curved surfaces of large span overhang curtain wall, including carry the concrete floor (1), base keel (2), master of floor beam (11) Keel truss (3), secondary joist (4) and curtain wall unit block (5), it is characterized in that:The concrete floor (1) of different height is outside The horizontal position of the floor beam (11) at end is different, and inclined base keel (2) are respectively connected between the floor beam (11) per levels, It is tilted between the base keel (2) and floor beam (11) and is fixed with support column (21), the main joist truss (3) is fixed on base dragon The outer end of bone (2), main joist truss (3) is fixed with lateral secondary joist (4), is fixed on the inside of the curtain wall unit block (5) Multiple first pendants (8) are detachably and fixedly provided with the second pendant (7) coordinated with the first pendant (8) on the secondary joist (4).
2. the more curved surfaces of large span according to claim 1 overhang curtain wall, it is characterized in that:The outer end face of the floor beam (11) It is fixed with crossbeam (6), is fixed on the crossbeam (6) and is respectively connect with the bilevel base keel (2) of floor beam (11) False keel (61).
3. the more curved surfaces of large span according to claim 2 overhang curtain wall, it is characterized in that:The base keel (2) include being located at The end bracket (22) of base keel (2) upper and lower end face, the end bracket (22) abut with floor beam (11), on the end bracket (22) It is equipped with the chemical anchor bolts being fixedly connected with floor beam (11).
4. the more curved surfaces of large span according to claim 2 overhang curtain wall, it is characterized in that:The top of the base keel (2) and Two support columns (21) are respectively and fixedly provided in lower inner surface, two support columns (21) are mutually in the shape of the letter V and with the other end and flooring Beam (11) is fixedly connected.
5. the more curved surfaces of large span according to claim 2 overhang curtain wall, it is characterized in that:The secondary joist (4) be include two A parallel tablet (41) and the vertical web (42) being set between two tablets (41) are arranged on the web (42) There are multiple perforation, the web (42) to form two grooves with tablet (41);Second pendant (7) includes being embedded in groove Embedding head (71), be embedded with by way of wearing bolt in the groove of secondary joist (4) other side with the second pendant (7) even The cushion block (9) connect.
6. the more curved surfaces of large span according to claim 5 overhang curtain wall, it is characterized in that:Second pendant (7) further includes The access slot (73) for being connected to the carrier (72) of tablet (41) outer surface and rabbeting for tablet (41), the carrier (72) are in L-shaped is integrally formed with embedding head (71), and the access slot (73) is surrounded by carrier (72) and embedding head (71) and is molded.
7. the more curved surfaces of large span according to claim 6 overhang curtain wall, it is characterized in that:The cell wall of the access slot (73) and Indent is provided with limiting slot (731) on slot bottom, and the inner surface of the tablet (41) is provided with the limit with limiting slot (731) cooperation Rib (43).
8. the more curved surfaces of large span according to claim 7 overhang curtain wall, it is characterized in that:The both sides of the embedding head (71) are respectively set Carrier (72) there are one setting.
9. the more curved surfaces of large span according to claim 5 overhang curtain wall, it is characterized in that:Second pendant (7) further includes Upper trailing arm (74) and lower trailing arm (76), wherein upper be provided with groove (75) between trailing arm (74) and carrier (72), under described The end set of trailing arm (76) has lower hook portion (761);First pendant (8) include above connect arm (82) and under connect arm (83), In on connect arm (82) and abut and the upper surface of upper trailing arm (74) and have the upper hook portion coordinated with upper groove (75) in end set (821), arm (83) is connect under described and abuts with the upper surface of lower trailing arm (76) and is provided in tail portion coordinates with lower hook portion (761) Lower groove (84), it is described on connect arm (82), upper trailing arm (74), under connect and be provided through fastening on arm (83) and lower trailing arm (76) The end of bolt, fastening bolt is fixed with fastening nut.
10. the construction method of the more curved surface overhanging curtain walls of large span, it is characterised in that construction procedure is as follows:
Step 1, the curtain wall curved surface of abbreviation as needed builds the position that floor beam (11) has set floor beam (11) in advance;
Step 2, surveying setting-out is installed base keel (2) between outermost floor beam (11) and is fixed with chemical anchor bolts, installed The fixed slanting fixed base keel (2) of support column (21) and floor beam (11);
Step 3, in the outer end of floor beam (11) installation crossbeam (6), two rows false keel (61) on crossbeam (6) respectively with The base keel (2) of floor beam (11) both sides up and down are fixed;
Step 4, main joist truss (3) is mounted on base keel (2), welding main joist truss (3) and base dragon after installation is complete Bone (2);
Step 5, it is transversely mounted secondary joist (4) on main joist, the second pendant (7) is because of preliminary installation to secondary joist (4) when installation On;
Step 6, curvature is designed according to curtain wall unit block (5), adjusts the position of the second pendant (7), the first pendant (8) on curtain wall Should in advance installation is complete;The first pendant (8) on curtain wall unit block (5) is docked with the second pendant (7), and wears fastening bolt It is fixed.
CN201810191905.XA 2018-03-08 2018-03-08 The more curved surface overhanging curtain walls of large span and its construction method Expired - Fee Related CN108396895B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810191905.XA CN108396895B (en) 2018-03-08 2018-03-08 The more curved surface overhanging curtain walls of large span and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810191905.XA CN108396895B (en) 2018-03-08 2018-03-08 The more curved surface overhanging curtain walls of large span and its construction method

Publications (2)

Publication Number Publication Date
CN108396895A true CN108396895A (en) 2018-08-14
CN108396895B CN108396895B (en) 2019-11-22

Family

ID=63092617

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810191905.XA Expired - Fee Related CN108396895B (en) 2018-03-08 2018-03-08 The more curved surface overhanging curtain walls of large span and its construction method

Country Status (1)

Country Link
CN (1) CN108396895B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109595242A (en) * 2018-12-18 2019-04-09 四川衡为营造实业有限公司 A kind of novel connecting component
CN112049286A (en) * 2020-07-22 2020-12-08 中建二局装饰工程有限公司 Large-span special-shaped hyperboloid aluminum plate curtain wall system and construction method thereof
CN114086708A (en) * 2021-11-02 2022-02-25 山西五建集团有限公司 Integrated construction system of gradient annular belt curtain wall bearing system and light enclosure structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575889A (en) * 2009-03-27 2009-11-11 北京市建筑工程装饰有限公司 Multi-curved surface overhung copper plate curtain wall and construction method thereof
CN203701355U (en) * 2013-12-04 2014-07-09 上海鼎中建材有限公司 Open curtain wall joint device with full-size inter-grasping structure
JP2016216955A (en) * 2015-05-18 2016-12-22 大成建設株式会社 External facing material installing structure
CN205976156U (en) * 2016-08-15 2017-02-22 杭州臻万建筑装饰工程有限公司 Marble is pendant futilely

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575889A (en) * 2009-03-27 2009-11-11 北京市建筑工程装饰有限公司 Multi-curved surface overhung copper plate curtain wall and construction method thereof
CN203701355U (en) * 2013-12-04 2014-07-09 上海鼎中建材有限公司 Open curtain wall joint device with full-size inter-grasping structure
JP2016216955A (en) * 2015-05-18 2016-12-22 大成建設株式会社 External facing material installing structure
CN205976156U (en) * 2016-08-15 2017-02-22 杭州臻万建筑装饰工程有限公司 Marble is pendant futilely

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109595242A (en) * 2018-12-18 2019-04-09 四川衡为营造实业有限公司 A kind of novel connecting component
CN112049286A (en) * 2020-07-22 2020-12-08 中建二局装饰工程有限公司 Large-span special-shaped hyperboloid aluminum plate curtain wall system and construction method thereof
CN114086708A (en) * 2021-11-02 2022-02-25 山西五建集团有限公司 Integrated construction system of gradient annular belt curtain wall bearing system and light enclosure structure
CN114086708B (en) * 2021-11-02 2023-05-26 山西五建集团有限公司 Gradual change clitellum curtain bearing system and light envelope integral construction system

Also Published As

Publication number Publication date
CN108396895B (en) 2019-11-22

Similar Documents

Publication Publication Date Title
CN108396895B (en) The more curved surface overhanging curtain walls of large span and its construction method
CN204431472U (en) Make precast beam pedestal
CN101487267B (en) Support stiffness-adjustable pile-raft foundation and construction process
CN102425186A (en) Foundation bolt stock and manufacture method thereof
CN211922298U (en) Recyclable tunnel anchor cable strand embedded pipe fine adjustment device
CN105804361A (en) Wall surface aluminum plate system and installing method thereof
CN102493620A (en) Through long folded fastener type wall body connecting piece of heat insulation integrated plate and mounting method thereof
CN214981834U (en) Bridge embedded steel plate angle adjusting device
CN109914792A (en) A kind of underground garage beam form board supporting structure and construction method
CN104499435A (en) Bracket used for mounting self-anchored suspension bridge splay saddle base
CN201770940U (en) Mounting structure for lower load bearing plate of steel box tower with spatial variable cross section
CN112502047A (en) Method for erecting simply supported PC track beam and linear debugging device
CN212271212U (en) Precast concrete frame column
CN211850389U (en) Steel bar protective layer cushion block
CN107841949B (en) A kind of building technology of inverted trapezoidal Bridge beam assembly moulding bed
CN114108499A (en) Suspended casting beam reference section hinged type triangular bracket combined hanging basket integrated device and construction method thereof
CN104947707A (en) Horizontal embedded part installation method
CN102359073A (en) Grouting template structure for support of concrete simple-supported box girder
CN111549657A (en) Rapid installation method of bridge basin-type rubber support
CN220763010U (en) Pedestal for precast beam
CN215296251U (en) Measuring instrument base device for core tube horizontal structure post-construction
CN208088771U (en) Antistatic raised floor
CN209812260U (en) Adjustable precision platform
CN216920043U (en) Bridge anticollision barrier reinforcing bar installation positioning tool
CN213038172U (en) Structure for adjusting gradient of prefabricated T-shaped beam boot

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191122

CF01 Termination of patent right due to non-payment of annual fee