CN108360496A - A kind of multifunction module formula soil body pressing formation device - Google Patents

A kind of multifunction module formula soil body pressing formation device Download PDF

Info

Publication number
CN108360496A
CN108360496A CN201810447719.8A CN201810447719A CN108360496A CN 108360496 A CN108360496 A CN 108360496A CN 201810447719 A CN201810447719 A CN 201810447719A CN 108360496 A CN108360496 A CN 108360496A
Authority
CN
China
Prior art keywords
pressing formation
soil body
upper frame
module
formula soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810447719.8A
Other languages
Chinese (zh)
Inventor
任再永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jiayuan Construction Engineering Technology Co Ltd
Original Assignee
Zhejiang Jiayuan Construction Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jiayuan Construction Engineering Technology Co Ltd filed Critical Zhejiang Jiayuan Construction Engineering Technology Co Ltd
Priority to CN201810447719.8A priority Critical patent/CN108360496A/en
Publication of CN108360496A publication Critical patent/CN108360496A/en
Priority to PCT/CN2019/086341 priority patent/WO2019214700A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Abstract

The invention discloses a kind of multifunction module formula soil body pressing formation devices, including upper frame, pressing formation module and soil strength detection device, it is characterised in that the upper frame periphery is equipped with baffle;The pressing formation module includes several convex bodys, and soil body part is contacted in module and is additionally provided with filter device, outer layer jacket is equipped with reinforcing body;Module top forms vacuum collecting chamber with the top plate, and conduit pipe is offered in module;It is additionally provided with additional pressure applicator device on the upper frame and/or pressing formation module;The bottom of convex body is additionally provided with vertical pile body.The present invention can carry out Quick drainage, consolidation and molding to the soil body, be suitable for shallow-layer, middle level and deep level of processing, thus applicability is extensive, and construction efficiency is high, and the construction period is short, and construction cost is low.

Description

A kind of multifunction module formula soil body pressing formation device
Technical field
The present invention relates to stiffening basic ground field more particularly to the consolidation process fields of soft soil foundation, specifically A kind of multifunction module formula soil body pressing formation device.
Background technology
Soil structures are usually to be mixed by solids, liquid water and air, and various material mixing ratios are different to be produced The raw bearing capacity not waited is pressurized when exerting pressure more than soil body bearing capacity and generates sidesway and Compression Settlement, need to original state The mixed structure ratio of the soil body carries out artificial change, is affixed by under the action of pressure outside so that in the soil body solids particles it Between compactness improve, the adrainage material being arranged in the soil body changes the mixing of the soil body as the channel that liquid water and air is discharged Structure makes solid contents that ratio be continuously improved, and to improve the compactness between solids particles, so that the soil body is obtained enhancing and adds Gu improvement achievees the purpose that be pressurized again without will produce lateral soil movement and Compression Settlement when soil body bearing capacity is more than the when of exerting pressure, To meet the requirement to soil body pressure-bearing.
Weak soil include mud, silt clay, mucky silt, become silted up knot sludge, riverway sludge, peat, cumulosol, Table rare earth, surface dust etc. are that a kind of natural moisture content is big, compressibility is high, natural void ratio is more than or equal to 1, low thin of shearing strength Grain soil.Common draining concretion method mainly has preloading and Vacuum-loading Pre-pressing Method.Preloading is in ground Middle setting drainage channel and vertical drainage system drain span to reduce soil solidifying, and ground is under railway embankment load action Discharging consolidation makes foundation bearing capacity improve, and settlement after construction reduces.Vacuum-loading Pre-pressing Method is on the basis of preloading On, airtight layer is formed on load, is constantly drawn water by the normal time, is formed negative pressuren zone in ground, it is soft to make Clay discharging consolidation achievees the purpose that improve bearing capacity, reduces sedimentation.Above-mentioned discharging consolidation method, construction period is very long, generally It could be completed at six months to 1 year, thus construction cost is very high, efficiency is very low.
Above-mentioned draining concretion method is suitable only for large-area construction.Also, since the height of preloading is placed restrictions on, the soil body is held Load requires high occasion that can not also be applicable in.
Invention content
The present invention is to solve above-mentioned technical problem of the existing technology, it is desirable to provide a kind of multifunction module formula soil Body pressing formation device.
To solve the above problems, the present invention uses following technical scheme:Including upper frame, pressing formation module and soil strength Detection device, it is characterised in that the upper frame includes top plate and chassis, and upper frame periphery is equipped with baffle;The pressing formation module Including several convex bodys, the top of module is connect with the chassis, and soil body part is contacted in module and is additionally provided with filter device, institute The outer layer jacket for stating filter device is equipped with reinforcing body;The pressing formation module is welded by steel plate or shaped steel, upper part with The top plate forms vacuum collecting chamber, and filter device described in unicom and vacuum collection are further opened in the pressing formation module The conduit pipe of hydroecium;It is additionally provided with additional pressure applicator device on the upper frame and/or pressing formation module;At least one convex body Bottom is additionally provided with vertical pile body.
The present apparatus is placed on the processed soil body, the weight of device itself generates pressure, additional pressure applicator device to the soil body Dynamic clearance active force is applied to the soil body, by the moisture and air extrusion in the soil body.The aqueous vapor being discharged from the soil body is filled through filtering Set, the conduit pipe in module enters vacuum collecting chamber, is concentrated and is discharged by pipeline, make between the solids particles in the soil body Compactness is improved.The convex body of the baffle and pressing formation module bottom plays barrier effect to the soil body, prevents the soil body Sidesway is generated, so that the soil body is concentrated in the space between baffle and convex body, is adequately squeezed, play Quick drainage and is squeezed Close effect, substantially increases construction efficiency, reduces the construction period, reduces construction cost.
Another feature of the present invention is to add vertical pile body on the basis of lateral pressing formation module.Described hangs down Straight pile body forms stake holes in the soil body, after slinging multifunction module formula soil body pressing formation device, is placed in the stake holes Finished product pile pipe or filling filler.This structure, pressing formation module to the soil body carry out lateral shallow-layer or in shallow processing, plumb pile Body carries out deep-layer reinforcing processing to the soil body, thus is applicable not only to the stabilization by drainage processing of shallow-layer or middle-shallow layer soft soil foundation, together When also can be suitably used for the processing of deep foundation base, keep the applicable situation of the present invention more wide in range.
Another feature of the present invention is that the outer layer jacket of the filter device is equipped with reinforcing body.The reinforcing body terminates in construction After stay in the soil body, utilize the mechanical properties such as the high intensity of geosynthetics, high tenacity, spread soil stress, increase the soil body Tensile strength, improve the soil body, constitute reinforced earth and various composite earthwork structures.Geosynthetics also plays anti-simultaneously It filters, the effect of draining and isolated material.
The present invention is applicable not only to the integral construction of large area, is also applied for the part construction of small area.According to construction area The size in domain can design various sizes of device.For the soil stabilization of large area, can also by the way of locally constructing, It constructs subregion.Each region can construct one by one, can also be constructed simultaneously in each region with multiple devices.
According to the present invention, shape, size, the quantity of the convex body are unlimited, can according to the design needs depending on.Each convex body Structure can be identical, can also be different.The convex body is in continuous arrangement or gap arrangement, and top is directly or by connecting plate and institute The upper frame connection stated.
As an improvement of the present invention, the convex body is at array arrangement.A kind of embodiment of optimization, the convex body are in A line multiple row or row multirow arrangement, each convex body penetrate through the pressing formation module in one direction.I.e.:Multiple convex bodys are simultaneously Row or laid out in parallel.
The embodiment of another kind optimization, the convex body are in the array arrangement of multiple lines and multiple rows, and the convex body of adjacent row/column is simultaneously It arranges or is staggered.
Any standard structure may be used in the filter device.A kind of embodiment of optimization, the filter device Multistorey strainer mesh is arrived including one.It is highly preferred that the strainer is metal screen.Metal screen has intensity high, and repeatable makes The characteristics of using.The filter opening of the strainer of each layer can be the same or different.From the point of view of filtering itself, the filter of outer filter Hole aperture should be greater than the filter opening aperture of inner filter screen, in this way, solid soil particle carries out coarse filtration and fine filtering successively.However, From the point of view of strainer intensity, since the intensity of the small strainer in large aperture is usually higher than the intensity of small-bore strainer, to prevent Strainer deforms in pressurized process, can also the filter opening aperture of outer filter should be less than the filter opening aperture of inner filter screen.
As a further improvement on the present invention, geotextile filter mesh layer can be added between two or more layers metal screen, Form sandwich structure.Multiple layer metal strainer and multilayer geotechnique textile mesh can be arranged alternately.
As the further improvement of the present invention, the quantity of the reinforcing body can be corresponded with convex body quantity, i.e.,: One convex body is set with a reinforcing body.Another interchangeable embodiment, designs a total reinforcing body, by all convex bodys All set loads.
For the further improvement of the present invention, the plumb pile volume surrounding also is provided with filter device, is filled in the filtering The outer layer suit reinforcing body set.The reinforcing body that the reinforcing body being set on the vertical pile body can be set with convex body outer layer is set respectively It sets, can also be designed to integral structure.
The reinforcing body can be TGXG, geotextiles, geomembrane, geotechnical grid, geotechnological gauze pad and composite earthwork Material any one or more of combination therein.
Natural drainage may be used in the drainage pattern of the present invention, can also use water pump or vacuum pump forced drainage.When adopting When with vacuum pump drainage, one moisture trap is set in the front end of vacuum pump, to prevent water point from entering vacuum pump with air-flow, is made Decline at vacuum pump performance or damages.Preferably, it is vacuumized using two-way, after moisture trap works a period of time, separation When the moisture water gone out reaches setting water level, vacuum pump is stopped all the way, and moisture trap is drained, and another way is still kept Work.Two-way alternately operating, sustainable pump drainage water.
It is described that the negative pressure of vacuum with control valve is additionally provided in vacuum collecting chamber as the further improvement of the present invention Regulation pipe.The negative pressure of vacuum regulation pipe is catchmented indoor negative pressure for adjusting vacuum, makes vacuum collecting chamber, moisture trap With the negative pressure shape in vacuum pump at vacuum gradient.Surely when the indoor negative pressure of empty set water is less than lower threshold, control valve is closed;When Vacuum catchments indoor negative pressure when reaching the threshold values upper limit, and control valve is opened, vacuum collecting chamber by negative pressure of vacuum regulation pipe with it is big Conductance is logical, and when vacuum catchments indoor negative pressure less than lower threshold, control valve is closed.So move in circles, so that it is guaranteed that Vacuum pump can persistently draw water.
The negative pressure of vacuum regulation pipe can be arranged in top, centre or the bottom of the vacuum collecting chamber.
As the further improvement of the present invention, the additional pressure applicator device includes vibrating device, percussion device and rammer Hit the combination of any one or more of device.Two or more additional pressure applicator device same layers or layering are uniformly arranged on institute On the upper frame and/or pressing formation module stated.
The baffle can close the periphery for being enclosed in the upper frame.The baffle may be multiple, uniformly set It sets on the periphery of the upper frame.
The baffle can be provided only on the lower section of upper frame.Its height can be with the basic phase of height of pressing formation module Together, the height of pressing formation module can also be higher or lower than.
The baffle can also extend upwardly to the top of upper frame below upper frame, can be with protection setting on upper frame Equipment be not infected with mud.
Preferably, the baffle inner wall has pervious bed, is convenient for Quick drainage.
As the further improvement of the present invention, the vertical pile body is up big and down small cone structure, convenient for indentation And dial-out.
The vertical pile body can be pile pipe structure, can also be solid.
As the further improvement of the present invention, the soil strength detection device is one or more, is arranged described In pressing formation module and/or vertical pile body.Multiple soil strength detection devices can be evenly distributed on the pressing formation module Convex body and/or vertical pile body bottom, middle part and top, with complete detection by the soil strength of each position of the construction soil body. The soil strength detection device includes soil body device for detecting density and/or soil shear strength detection device.
The multifunction module formula soil body pressing formation device of the present invention, can also use unit spliced with integral manufacturing Mode make, i.e.,:One upper frame and one unit of a pressing formation module composition connected to it, two to multiple units spell It connects and constitutes a complete multifunction module formula soil body pressing formation device.It can increase as needed on each unit different Functional component.Using the production method of unit spliced, due to the small volume of each unit, thus making is more simple, can drop Low manufacture difficulty and manufacturing cost.Also, unit can be used as standard size, or as series of products, the unit of each series Structure snd size are identical, then spliced according to design or construction requirement, design and use are more flexible.
A kind of multifunction module formula soil body pressing formation device of the present invention, the ground that can be applied to various capital construction fields add Gu processing, including but not limited to:
(1)Marine field:It such as reclaims fields from the sea, embankment is built a dam;
(2)Storage and transportation transfer field:Such as pier storage yard;
(3)Roadbed field:As the embankment of highway, railway is handled;
(4)Aviation field:Such as airport;
(5)Water Resources Domain:Such as river, river levee, riverbed;
(6)Field of garbage disposal:Such as refuse landfill, sludge-tank;
(7)Mining industry field:Such as washup pond;
(8)Urban construction field:Such as town road and other municipal works;
(9)Work China Democratic National Construction Association field:Such as building, structures.
Description of the drawings
Fig. 1 is the structural schematic diagram of multifunction module formula soil body pressing formation device of the present invention.
Fig. 2 is the structural schematic diagram of pressing formation module and top rack unit of the present invention.
Fig. 3 be pressing formation module of the present invention, upper frame and filter assembly structural schematic diagram.
Fig. 4 be pressing formation module of the present invention, upper frame, filter device and reinforcing body component structural schematic diagram.
Fig. 5 is the knot of pressing formation module of the present invention, the another embodiment of upper frame, filter device and reinforcing body component Structure schematic diagram.
Fig. 6 is the structural schematic diagram that embodiment is arranged side by side in pressing formation module convex body of the present invention.
Fig. 7 is that convex body of the present invention is staggered the structural schematic diagram of embodiment.
Fig. 8 is the structural schematic diagram that pressing formation module convex body of the present invention presents mount structure embodiment.
Fig. 9 is the structural schematic diagram that embodiment is arranged side by side in mount structure convex body in pressing formation module of the present invention.
Figure 10 is that mount structure convex body is staggered the structural schematic diagram of embodiment in pressing formation module of the present invention.
Figure 11 is the structural schematic diagram that embodiment is arranged side by side in pressing formation module cylindrical shape convex body of the present invention.
Figure 12 is that multifunction module formula soil body pressing formation device of the present invention splices embodiment using multiple same units Structural schematic diagram.
Figure 13 is that multifunction module formula soil body pressing formation device of the present invention is real using the splicing of multiple identical and different units Apply the structural schematic diagram of mode.
Figure 14 is invention pressing formation module, upper frame, filter device, reinforcing body and additional pressure applicator device assembly Structural schematic diagram, wherein additional pressure applicator device assembly using layering setting impact hammer and vibrating device.
Figure 15 is invention pressing formation module, upper frame, filter device, reinforcing body, additional pressure applicator device and gear The structural schematic diagram of board group part, wherein additional pressure applicator device assembly uses the impact hammer and vibrating device of same layer setting.
Figure 16 is that the baffle of multifunction module formula soil body pressing formation device of the present invention encloses embodiment using closing Structural schematic diagram.
Figure 17 is that the structure of multifunction module formula soil body pressing formation device flapper gap setting embodiment of the present invention is shown It is intended to.
Figure 18-22 is the work progress schematic diagram for the processing method that the present invention is applied to soft soil foundation.
In figure, 1- upper frames, 2- pressing formation modules, 3- soil strength detection devices, 4- filter devices, 5- collecting chambers, 6- Reinforcing body, 7- vacuum pumps, 8- moisture traps, 9- solenoid valves, 10- drinking-water pipes, 11- modular units, 12- connecting plates, 13- are hit Hammer, 14- holders, 15- vibrating devices, 16- baffles, the vertical pile bodies of 17-, 18- loop wheel machines, the 19- multifunction module formula soil bodys pressure at Type device, 20- soil body surfaces, 21- are molded the soil body, 22- pits, 23- fillers, the space between 26- convex bodys, the vertical stake holes of 29-, 39- negative pressure of vacuum regulation pipes;
101- top plates, 102- chassis;
201- convex bodys, 202- lateral walls, 203- conduit pipes.
Specific implementation mode
Structure Figure and specific implementation mode below, the invention will be further described.
Referring to Fig.1, a kind of multifunction module formula soil body pressing formation device of the invention, including upper frame 1, pressing formation mould Block 2, soil strength detection device 3, filter device 4, baffle 16, additional pressure applicator device, reinforcing body 6 and vertical pile body 17.
In conjunction with Fig. 2, the upper frame 1 is rectangle, including top plate 101 and chassis 102.The pressing formation module 2 is wrapped Include several " V " shape convex bodys 201 disposed in parallel.Each " V " shape convex body 20 is penetrated through along the width direction of upper frame 1, adjacent protuberances It is spaced apart between 201.The top of convex body 201 is connect with chassis 102.The connection can be welding, can also be Slot is set on the chassis 102 of upper frame, and 201 top of convex body, which is inserted into the slot, forms detachable connection.
Soil strength detection device 3 can be arranged in the bottom of convex body 201 and/or side wall 202.It can be in each convex body Soil strength detection device 3 is set on 201, it is strong that can also the soil body be set on the 1 selected convex body 201 to multiple specific positions Spend detection device 3.
When construction, the weight of device itself generates pressure to the soil body, and the moisture and air extrusion in the soil body make in the soil body Solids particles between compactness be improved.The lateral wall 202 of " V " shape convex body 201 plays barrier effect, prevents the soil body Sidesway is generated, in the space 26 between making the soil body be concentrated in convex body, is adequately squeezed, to play Quick drainage and squeeze Close effect.
In conjunction with Fig. 3, on this basis, filter device 4, convex body 201 are set on the lateral wall 202 of the convex body 201 On offer the conduit pipes 203 of multiple inside and outside walls.The filter device 4 uses double-level-metal strainer, repeatable to make With, saving cost, while intensity can also be improved.
The convex body 201 is welded by steel plate or shaped steel, and a vacuum collecting chamber 5 is formed on top and top plate 101.
Filter device 4 can quickly export the aqueous vapor squeezed out in the soil body, and aqueous vapor passes through the water guide on " V " shape convex body 201 Enter the collecting chamber 5 on 201 top of " V " shape convex body behind channel 203.
In conjunction with Fig. 4, a drinking-water pipe 10 is inserted into each collecting chamber 5, the top of drinking-water pipe 10 passes through upper frame 1 to outside Draining.
A kind of more preferably embodiment, using 7 forced drainage of vacuum pump.In the front end of vacuum pump 7, one gas is set Separator 8 causes 7 performance of vacuum pump to decline or damage to prevent water point from entering vacuum pump 7 with air-flow.In present embodiment In, it is vacuumized using two-way, after moisture trap works a period of time, when the moisture water isolated reaches setting water level, Vacuum pump is stopped all the way, and moisture trap is drained, and another way still keeps work.Two-way alternately operating, sustainable pumping Draining.Vacuum pump 7 is controlled by solenoid valve 9 and is opened and closed.
Upper frame 1 uses top plate 101 and 102 mode of chassis, 102 all round closure of chassis, top to connect with top plate 101 It connects, the collecting chamber 5 on each 201 top of " V " shape convex body can be made, which to be interconnected, becomes a big closed vacuum collecting chamber, is taking out Negative pressure is formed during water, is conducive to soil body draining.
The negative pressure of vacuum regulation pipe 39 with control valve is additionally provided in the vacuum collecting chamber 5.The negative pressure of vacuum tune Section pipe 39 is used to adjust the negative pressure in vacuum collecting chamber 5, makes the negative pressure in vacuum collecting chamber 5, moisture trap 8 and vacuum pump 7 Form vacuum gradient.Surely when the negative pressure in empty set hydroecium 5 is less than lower threshold, control valve is closed;Surely in empty set hydroecium 5 When negative pressure reaches the threshold values upper limit, control valve is opened, and vacuum collecting chamber 5 is connected by negative pressure of vacuum regulation pipe 39 with air, until When negative pressure in vacuum collecting chamber 5 is less than lower threshold, control valve is closed.It so moves in circles, so that it is guaranteed that vacuum pump 7 can Persistently draw water.
The negative pressure of vacuum regulation pipe 39 can be arranged in top, centre or the bottom of the vacuum collecting chamber 5. In present embodiment, the negative pressure of vacuum regulation pipe 39 is arranged in the top of the vacuum collecting chamber 5, is located at 1st area of upper frame In domain.
In the present embodiment, adjacent protuberances 201 are continuously arranged, and do not stay gap.With the reality of 201 gap of adjacent protuberances arrangement Mode is applied the difference is that the shape of the molding soil body is different, but two kinds of embodiments played have the technical effect that phase With.
On this basis, reinforcing body 6 is equipped on the lateral wall of convex body 201.The reinforcing body 6 be fabricated to it is described convex The external of body 201 forms compatible sleeve-like structure.Each convex body 201 is set with a reinforcing body.The top of reinforcing body 6 and upper frame 1 contact.
With reference to Fig. 5, pressing formation module of the present invention, the another embodiment of upper frame, filter device and reinforcing body component. In the present embodiment, 201 gap of adjacent protuberances is arranged, and is connected by connecting plate 12.The connecting plate 12 is connect with upper frame 1. The reinforcing body 6 is integrated, and all convex bodys 201 are all covered and are loaded.
With reference to Fig. 6, the another embodiment of pressing formation module of the present invention.In the present embodiment, several " V " shapes Convex body 201 is at array arrangement.The convex block 201 of adjacent row and column is arranged side by side.
With reference to Fig. 7, another embodiment of pressing formation module of the present invention.In the present embodiment, several " V " shapes Convex body 201 is at array arrangement.The convex block 201 of adjacent row and column is staggered.
With reference to Fig. 8, another embodiment of pressing formation module of the present invention.In the present embodiment, the convex body 201 be in the frame-shaped construction of opening upwards.Convex body 201 is penetrated through along the width direction of upper frame 1, length of the multiple convex bodys 201 along upper frame 1 Direction is arranged in parallel.
With reference to Fig. 9, another embodiment of pressing formation module of the present invention.In the present embodiment, multiple upper ledge knots The convex body 201 of structure is at array arrangement.The convex block 201 of adjacent row and column is arranged side by side.
Referring to Fig.1 0, another embodiment of pressing formation module of the present invention.In the present embodiment, multiple upper ledge knots The convex body 201 of structure is at array arrangement.The convex block 201 of adjacent row and column is staggered.
Referring to Fig.1 1, another embodiment of pressing formation module of the present invention.In the present embodiment, the convex body 201 cylindrical structures.Multiple convex bodys 201 are at array arrangement.The convex block 201 of adjacent row and column is arranged side by side.
Referring to Fig.1 2, a kind of another embodiment of multifunction module formula soil body pressing formation device of the present invention.At this In embodiment, a upper frame and one unit 11 of a pressing formation module composition connected to it, two arrive multiple units 11 It is spliced to form a complete multifunction module formula soil body pressing formation device.Corresponding functor is added in each unit, such as Baffle, reinforcing body, vertical pile body, additional pressure applicator device etc..
Referring to Fig.1 3, a kind of another embodiment of multifunction module formula soil body pressing formation device of the present invention.It will not Unit 11 with size is fabricated to corresponding unit module 11-1,11-2, according to the needs that design and construct, by various unit modules It is spliced to form a complete multifunction module formula soil body pressing formation device.
Referring to Fig.1 4, pressing formation module of the present invention, upper frame, filter device, reinforcing body and additional pressure applicator device assembly Structural schematic diagram.In the present embodiment, " V " shape convex body 201 is arranged in gap, and upper part is directly connect with chassis 102.It is pushing up It is equipped with impact hammer 13 and vibrating device 15 at the center of 1 top of frame.
The impact hammer 13 and vibrating device 15 can be one or more.In the present embodiment, the impact hammer 13 and vibrating device 15 respectively be one.Vibrating device 15 is set up directly on top plate 101, and impact hammer 13 is arranged by holder 14 The top of vibrating device 15.
Impact hammer 13 and vibrating device 15 apply dynamic intermediate frequency or low frequency contribution power by forming module to the soil body, make the soil body It is fully squeezed, the aqueous vapor in the soil body is accelerated to be detached with soil particle.
Referring to Fig.1 5, pressing formation module, upper frame, filter device, reinforcing body, additional pressure applicator device and baffle group of the present invention The structural schematic diagram of part.The impact hammer 13 is one, is arranged at the center of top plate 101, the vibrating device 15 is It is multiple, it is uniformly arranged on the periphery of impact hammer 13.Preferably, each impact hammer 13 is arranged at the center of corresponding convex body 201.
The vibrating device 15 can also be arranged in the inside of convex body 201, in vacuum collecting chamber 5.Alternatively, in upper frame Top and the inside of convex body 201 are equipped with vibrating device 15.
It is additionally provided with baffle 16 on the periphery of the upper frame 1.The baffle 16 plays barrier effect to the soil body, prevents the soil body Sidesway is generated, so that the soil body is concentrated in the region of pressing formation module, to obtain more adequately squeezing, further speeds up Aqueous vapor in the soil body is detached with soil particle.
In the present embodiment, the baffle 16 uses slab construction, closing to be enclosed in the periphery of the upper frame 1.Gear Plate 11 extends upwardly to the top of upper frame 1 from the lower section of upper frame 1.Stretching out the baffle of 1 upper section of upper frame can be existed with protection setting Equipment on upper frame 1(Such as impact hammer 13 and vibrating device 14)It is not infected with mud, extends the service life of equipment.16 bottom of baffle It is substantially flush with the bottom of pressing formation module 2.
16 bottom of baffle can also be less than the bottom of pressing formation module 2.This structure, baffle 16 can wrap up Firmly more soil bodys.A large amount of soil bodys are limited in the space of the enclosing of baffle 16, under the action of pressing formation device of the present invention, Adequately squeezed.Since the soil body not will produce sidesway, this extruding is continuous and effective.
Preferably, the inner wall of the baffle 16 has pervious bed, is convenient for Quick drainage.
The material of the baffle 16 can select resistant material, such as steel plate, alloy sheets or high molecular material plate.Using When steel plate, the weight of whole device can be increased, bigger pressure is generated to the soil body, be conducive to accelerate draining.Using macromolecule material Flitch, low cost, lightweight, convenient for manufacture, transport and installation.
Referring to Fig.1 6, the another embodiment of baffle of the present invention.With Figure 15 embodiments the difference is that described Baffle 16 uses shaped steel.
Referring to Fig.1 7, the replaceable Figure 21 embodiments another embodiment of the present invention.It is different from Figure 16 embodiments it It is in the baffle 16 of present embodiment is strip structure, is uniformly arranged on the periphery of the upper frame.The baffle 16 uses " work " word steel.
Pressing formation module, filter device, baffle, additional pressure applicator device and the reinforcing body of above-mentioned different structure can combine At the component of different embodiments.Vertical pile body 17 is set on the component of each embodiment, so that it may constitute one completely Multifunction module formula soil body pressing formation device(As shown in Figure 1).
The vertical pile body 17 can be disposed therein the bottom of a convex body 201.Multiple convex bodys can also be arrived two Vertical pile body 17 is arranged in 201 bottom.
The vertical pile body 17 forms stake holes in the soil body, after slinging multifunction module formula soil body pressing formation device, Finished product pile pipe or filling filler are placed in the stake holes.This structure, pressing formation module carry out the shallow of transverse direction to the soil body Layer or in shallow processing, vertical pile body carries out deep-layer reinforcing processing to the soil body, thus with being applicable not only to shallow-layer or middle-shallow layer weak soil The stabilization by drainage of base is handled, while also can be suitably used for the processing of deep foundation base, keeps the applicable situation of the present invention more wide in range.
In the bottom of the vertical pile body 17, soil strength detection device 3 can also be set.Preferably, in vertical pile body 17 Middle part and top be also uniformly arranged multiple soil strength detection devices 3.The soil strength detection device 3 includes that the soil body is close Spend detection device and/or soil shear strength detection device.
In the lateral wall of the vertical pile body 17, filter device 4 can also be set.The filter device 4 and convex body Filter device 4 on 201 forms integral structure.
It can also be set with reinforcing body 6 outside the filter device 4 of the vertical pile body 17.The reinforcing body is after construction It stays in the soil body, continues to drain while playing reinforced action.
Using a kind of multifunction module formula soil body pressing formation device of the present invention described in Fig. 1, according to the following steps to soft Soil base carries out stabilization by drainage processing:
1)Referring to Fig.1 8, the multifunction module formula soil body pressing formation device 19 of the present invention is hung to construction area by loop wheel machine 18.
2)Referring to Fig.1 9, the dead weight of multifunction module formula soil body pressing formation device 19 imposes the soil body longitudinal static pressure Power;Impact hammer 13 imposes the soil body longitudinal impact force;Vibrating device 15 makes device 19 generate vibration, and then imposes height to the soil body The lateral pressure of frequency;Three of the above force action makes the soil body fully be squeezed in the soil body, the aqueous vapor in the soil body through reinforcing body 5, Conduit pipe 203 on filter device 4 and convex body reaches vacuum collecting chamber 5, then is extracted out via drinking-water pipe 10.Pumping system uses Two-way pattern includes a vacuum pump 7 and a preposition moisture trap 8 per road.The work of moisture trap 8 one of the first via After the section time, when the moisture water isolated reaches setting water level, the vacuum pump 7 on the road is stopped, and moisture trap 8 carries out Draining, the second tunnel still keeps work.Two-way alternately operating, sustainable pump drainage water.In this process, the air water in the soil body is by most It is discharged to big degree, the compactness between solid particle is improved.Solenoid valve 19 controls vacuum pump 7 and moisture trap 8 It opens and closes.
3)With reference to Figure 20, multifunction module formula soil body pressing formation device 19 is sling.The processed soil body is in lateral shape Soil structures 21 are molded at corresponding with pressing formation modular shape, it is corresponding with 17 shape of vertical pile body being longitudinally formed Vertical stake holes 29.Reinforcing body 6 remains in the soil body, can bear tension, resistance to compression, shearing resistance effect, to improve foundation bearing capacity, subtracts Few sedimentation and the stability for increasing the soil body.Meanwhile the reinforcing body 6 can also continue to drain.
4)With reference to Figure 21, filler 23 is backfilled in molding pit 22 and vertical stake holes 29.It can once fill up, Huo Zhe It is tamped again after filling up.One layer can also be filled out, is tamped, then fill out last layer, then tamp, until filling up.
5)With reference to Figure 22, multifunction module formula soil body pressing formation device 19 is hung to next construction area with loop wheel machine 18 Domain repeats step 2)-4), until all construction areas all handle completion.
Wherein, step 4)Backfill filler can be with step 5)Progress can be synchronized to the operation in next region.
It is to be understood that:Above-described embodiment is the description of the invention, rather than limiting the invention, any Without departing from the innovation and creation within the scope of true spirit, each fall within protection scope of the present invention.

Claims (15)

1. a kind of multifunction module formula soil body pressing formation device, including upper frame, pressing formation module and soil strength detection dress It sets, it is characterised in that the upper frame includes top plate and chassis, and upper frame periphery is equipped with baffle;If the pressing formation module includes Dry convex body, the top of module are connect with the chassis, and soil body part is contacted in module and is additionally provided with filter device, the filtering The outer layer jacket of device is equipped with reinforcing body;The pressing formation module is welded by steel plate or shaped steel, upper part with it is described Top plate forms vacuum collecting chamber, and filter device described in unicom and vacuum collecting chamber are further opened in the pressing formation module Conduit pipe;It is additionally provided with additional pressure applicator device on the upper frame and/or pressing formation module;The bottom of at least one convex body is also Equipped with vertical pile body.
2. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that the convex body Continuous arrangement or gap arrangement, top is connect directly or by connecting plate with the upper frame.
3. a kind of multifunction module formula soil body pressing formation device as claimed in claim 2, it is characterised in that the convex body At array arrangement, the side-by-side or staggered setting of convex body of adjacent row/column.
4. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that the filtering Device arrives multistorey strainer mesh including one.
5. a kind of multifunction module formula soil body pressing formation device as claimed in claim 4, it is characterised in that the strainer For metal screen and/or geotextile strainer.
6. a kind of multifunction module formula soil body pressing formation device as claimed in claim 5, it is characterised in that the metal Strainer and geotextile strainer are arranged alternately.
7. a kind of multifunction module formula soil body pressing formation device described in claim 1, it is characterised in that the reinforcing body Including TGXG, geotextiles, geomembrane, geotechnical grid, geotechnological gauze pad and composite geotextile material any type therein or more Kind combination.
8. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that the auxiliary Device for exerting include vibrating device, percussion device and ramming device any one or more of combination.
9. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that the auxiliary Device for exerting is arranged on upper frame.
10. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that the auxiliary Device for exerting is arranged in pressing formation module.
11. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that the baffle Closing is enclosed in the periphery of the upper frame.
12. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that the baffle It is multiple, is uniformly arranged on the periphery of the upper frame.
13. a kind of multifunction module formula soil body pressing formation device as described in claim 1, it is characterised in that described is vertical Pile body is up big and down small cone structure.
14. a kind of multifunction module formula soil body pressing formation device as described in claim 1-13 any one, feature exist In being additionally provided with the negative pressure of vacuum regulation pipe with control valve in vacuum collecting chamber.
15. a kind of multifunction module formula soil body pressing formation device as claimed in claim 14, it is characterised in that described is true Idling pressure regulation pipe can be arranged in top, centre or the bottom of the vacuum collecting chamber.
CN201810447719.8A 2018-05-11 2018-05-11 A kind of multifunction module formula soil body pressing formation device Withdrawn CN108360496A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201810447719.8A CN108360496A (en) 2018-05-11 2018-05-11 A kind of multifunction module formula soil body pressing formation device
PCT/CN2019/086341 WO2019214700A1 (en) 2018-05-11 2019-05-10 Soil mass pressure application forming device suitable for shallow or medium-shallow soft soil foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810447719.8A CN108360496A (en) 2018-05-11 2018-05-11 A kind of multifunction module formula soil body pressing formation device

Publications (1)

Publication Number Publication Date
CN108360496A true CN108360496A (en) 2018-08-03

Family

ID=63011767

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810447719.8A Withdrawn CN108360496A (en) 2018-05-11 2018-05-11 A kind of multifunction module formula soil body pressing formation device

Country Status (1)

Country Link
CN (1) CN108360496A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208571A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 A kind of compacted discharging consolidation soil body joint reinforcement enhancing processing method of mechanical compression
CN109208569A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 The compacted discharging consolidation soil body joint reinforcement of mechanical compression enhances processing method
CN109208572A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 Prefabricated block pressure bearing pile bluk recombination foundation structure processing method
CN109208570A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 Reinforcement module pressure bearing pile bluk recombination foundation structure processing method is placed in backfill
CN109403305A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 A kind of compacted modified enhancing processing method of the discharging consolidation soil body joint soil body of mechanical compression
CN109403306A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 The compacted discharging consolidation soil body of mechanical compression enhances processing method
CN109403303A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 A kind of modified enhancing processing method of compacted discharging consolidation soil body joint original soil excavation of mechanical compression
CN109403307A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 A kind of compacted discharging consolidation soil body enhancing processing method of mechanical compression
CN109403302A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 The compacted discharging consolidation soil body joint original soil of mechanical compression excavates modified enhancing processing method
CN109403304A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 The compacted modified enhancing processing method of the discharging consolidation soil body joint soil body of mechanical compression
CN109440756A (en) * 2018-10-19 2019-03-08 杭州永创基建工程科技股份有限公司 Reinforcement module pressure-bearing pile body combination curing interlayer composite foundation structure processing method is placed in backfill
WO2019214701A1 (en) * 2018-05-11 2019-11-14 杭州永创基建工程科技股份有限公司 Modular soil pressure applying and molding device and soft soil foundation treatment method
WO2019214700A1 (en) * 2018-05-11 2019-11-14 浙江佳源基建工程科技有限公司 Soil mass pressure application forming device suitable for shallow or medium-shallow soft soil foundation

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019214701A1 (en) * 2018-05-11 2019-11-14 杭州永创基建工程科技股份有限公司 Modular soil pressure applying and molding device and soft soil foundation treatment method
CN111315932A (en) * 2018-05-11 2020-06-19 杭州永创基建工程科技股份有限公司 Modular soil body pressure-applying forming device and soft soil foundation treatment method
WO2019214700A1 (en) * 2018-05-11 2019-11-14 浙江佳源基建工程科技有限公司 Soil mass pressure application forming device suitable for shallow or medium-shallow soft soil foundation
CN109403303A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 A kind of modified enhancing processing method of compacted discharging consolidation soil body joint original soil excavation of mechanical compression
CN109403305A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 A kind of compacted modified enhancing processing method of the discharging consolidation soil body joint soil body of mechanical compression
CN109403306A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 The compacted discharging consolidation soil body of mechanical compression enhances processing method
CN109208571A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 A kind of compacted discharging consolidation soil body joint reinforcement enhancing processing method of mechanical compression
CN109403307A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 A kind of compacted discharging consolidation soil body enhancing processing method of mechanical compression
CN109403302A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 The compacted discharging consolidation soil body joint original soil of mechanical compression excavates modified enhancing processing method
CN109403304A (en) * 2018-10-19 2019-03-01 杭州永创基建工程科技股份有限公司 The compacted modified enhancing processing method of the discharging consolidation soil body joint soil body of mechanical compression
CN109440756A (en) * 2018-10-19 2019-03-08 杭州永创基建工程科技股份有限公司 Reinforcement module pressure-bearing pile body combination curing interlayer composite foundation structure processing method is placed in backfill
CN109208570A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 Reinforcement module pressure bearing pile bluk recombination foundation structure processing method is placed in backfill
CN109208572A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 Prefabricated block pressure bearing pile bluk recombination foundation structure processing method
CN109208569A (en) * 2018-10-19 2019-01-15 杭州永创基建工程科技股份有限公司 The compacted discharging consolidation soil body joint reinforcement of mechanical compression enhances processing method

Similar Documents

Publication Publication Date Title
CN108360496A (en) A kind of multifunction module formula soil body pressing formation device
CN108330948A (en) Modular soil body pressing formation device suitable for depth layer Soft Ground
CN108532581A (en) A kind of modular soil body pressing formation device with integrated treatment function
CN108385659A (en) A kind of modular soil body pressing formation device of splicing structure
CN101302757A (en) Method for quickly processing heavy layer soft soil foundation
CN101220589B (en) Soil engineering bag and method for dynamically squeezing and synthetically reinforcing soft groundwork
CN101130952A (en) Packingless fast vacuum prepressing dynamic consolidation method
WO2019214701A1 (en) Modular soil pressure applying and molding device and soft soil foundation treatment method
CN103243703A (en) Soft soil consolidation processing method by utilizing hard hollow tubes with pores reserved on side walls
CN101597898B (en) Rigid drainage pile and construction method thereof
CN108330949A (en) A kind of modular soil body pressing formation device with quick water-discharging function
CN101634139B (en) Dynamic compaction method for backfill foundation with drainage layer
CN108677911A (en) A kind of processing method of modular soil body pressing formation device and soft soil foundation
CN201214787Y (en) Rigid water drain pile
CN201436323U (en) Drainage structure of dynamic compaction foundation
CN109208569A (en) The compacted discharging consolidation soil body joint reinforcement of mechanical compression enhances processing method
CN109403306A (en) The compacted discharging consolidation soil body of mechanical compression enhances processing method
CN210238180U (en) Soft roadbed processing device with unit type gravel pile composite foundation combined with overload prepressing
CN209211425U (en) A kind of multifunction module formula soil body pressing formation device
CN109440756A (en) Reinforcement module pressure-bearing pile body combination curing interlayer composite foundation structure processing method is placed in backfill
CN108360497A (en) A kind of modular soil body pressing formation device with earth-retaining function
CN109403304A (en) The compacted modified enhancing processing method of the discharging consolidation soil body joint soil body of mechanical compression
CN209211426U (en) A kind of modular soil body pressing formation device
CN209227508U (en) A kind of modular soil body pressing formation device with earth-retaining function
CN209211431U (en) A kind of modular soil body pressing formation device with quick water-discharging function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180803

WW01 Invention patent application withdrawn after publication