CN108343062A - A kind of intelligent plant pile construction method - Google Patents

A kind of intelligent plant pile construction method Download PDF

Info

Publication number
CN108343062A
CN108343062A CN201810133432.8A CN201810133432A CN108343062A CN 108343062 A CN108343062 A CN 108343062A CN 201810133432 A CN201810133432 A CN 201810133432A CN 108343062 A CN108343062 A CN 108343062A
Authority
CN
China
Prior art keywords
pile
drilling rod
construction
prefabricated
stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810133432.8A
Other languages
Chinese (zh)
Inventor
刘全林
宋伟民
盛晓幸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Qiangjin Foundation Engineering Co Ltd
Original Assignee
Shanghai Qiangjin Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Qiangjin Foundation Engineering Co Ltd filed Critical Shanghai Qiangjin Foundation Engineering Co Ltd
Priority to CN201810133432.8A priority Critical patent/CN108343062A/en
Publication of CN108343062A publication Critical patent/CN108343062A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/26Placing by using several means simultaneously

Abstract

The present invention provides a kind of intelligent plant pile construction method, includes the following steps:(1) fluidised form solidified earth is formed;(2) it is implanted into prefabricated pile.Step (1) includes:Configure two slurries, construction mixing pile aspects:The soil body aliquot replacement in stake holes, stir in situ are formed by fluidised form solidified earth using the drilling rod with upper and lower mouth spray, lower brill construction when construction mixing pile;In drilling process, slurries that upper mouth spray sprays by the blade on drilling rod further with soil shear failure;It is implanted into during prefabricated pile, is implanted into prefabricated pile body in fluidised form solidified earth, forms composite pile;Cycle construction mixing pile, implantation prefabricated pile successively, form more composite piles.Compared with prior art, equipment consolidation process weak soil basis using the present invention, has uniform intensity, uniform density, higher bearing capacity and preferable water-stagnating effect, construction cost is low, dust pollution is controlled in work progress, and non-environmental-pollution is environmentally protective.

Description

A kind of intelligent plant pile construction method
Technical field
The present invention relates to technical field of civil engineering, are specifically related to a kind of intelligent construction method for planting stake.
Background technology
In field of civil engineering, traditional construction of prefabricated piles mainly has hammering method and static pressure method, both modes are deposited The problems such as penetrating resistance is big, speed is slow, soil compaction is serious, to the building on periphery, pipeline and structure during construction of prefabricated piles It builds object and generates harm.Although taking some stress release measures that can alleviate the harm of soil compaction, this soil compaction facts have proved Harm is difficult to eliminate.In addition, formation resistance is bigger, need the pressure of pile sinking bigger, leads to damage of the pile driving process to pile body just It is bigger.In order to protect pile body without damage in work progress, it is necessary to using the piling compared with high-bearing capacity so that the cost of pile foundation Increase very much.Another method is pilot hole drag reduction, and this not only adds construction costs, although and pilot hole drag reduction, also reduce The side-friction force of foundation soil, leads to the reduction of bearing capacity of pile foundation, to increase project cost.
In mud class soft layer, since the frictional resistance of the soil body is relatively low, cause the side bearing capacity of pile body smaller so that The intensity of pile shaft material does not play effect, cannot fully apply, and generates larger waste.
Prefabricated pile enters decomposed rock and is currently impossible across dense sand stratum, to limit the application range of prefabricated pile.
For the region of surrounding enviroment complexity, it can only use cast-in-situ bored pile, cast-in-situ bored pile in the construction process will production Raw a large amount of slurry coat method and pore-forming pulping will generate pollution to environment.Simultaneously as the quality of concrete placed under water is difficult to Ensure and the mudcake on drill-pouring pile body periphery causes pile body bearing capacity to decline so that the cost of cast-in-situ bored pile is than prefabricated pile Cost is high by 40% or more.
It drills in sandy gravel stratum, borehole cleaning is very difficult, so that the construction time of cast-in-situ bored pile and cost is increased more.
The problem of being haveed the advantages that based on prefabricated pile basis and bored pile foundation and respective, the highly desirable general of engineering circles The advantages of this two kinds of pile foundations, develops, overcome its there are the shortcomings that, need to innovate a kind of pile foundation construction equipment.
Invention content
Technical problem to be solved by the present invention lies in overcome problems of the prior art, provide a kind of intelligence Plant pile construction method.
A kind of intelligent plant pile construction method, includes the following steps:
(1) fluidised form solidified earth is formed
1) slurries are configured:
Slurries parameter is inputted in the pulp feeding system of backstage, carries out River Bank Stability automatically;
2) construction mixing pile:
Construction parameter is inputted in the intellectualizing system of mixing pile construction equipment, using the drilling rod with upper and lower mouth spray, Soil body aliquot replacement in stake holes, stir in situ are formed fluidised form solidified earth by lower brill construction;In drilling process, upper mouth spray spray The slurries gone out by the blade on drilling rod further with soil shear failure;After inputting construction parameter, whole process automated construction;
(2) it is implanted into prefabricated pile:
It is implanted into prefabricated pile body in fluidised form solidified earth, prefabricated pile body is docked by more piece, and it is solid that previous section pile body is inserted into fluidised form Change in soil and reserved banjo fixing butt jointing, later section pile body are lifted by crane and docked with previous section pile body, prefabricated pile is continued into after docking Body forms composite pile until all prefabricated piles are all implanted into;
Cycle construction mixing pile, implantation prefabricated pile successively, form more composite piles.
Lower in step 2) to bore construction, detailed process is as follows:
A) drilling rod stirring is sunk, and is sunk since stake top absolute altitude h1, and lower mouth spray opens whitewashing, lasting whitewashing stirring to stake Bottom h3;
B) drilling rod stirring is promoted to h2 from h3, and mouth spray is descended to whitewash in the process;
C) drilling rod stirs again from h2 and sinks down into a bottom h3, does not whitewash in the process, pure stirring;
D) drilling rod stirring is promoted to h2, in the process upper mouth spray whitewashing;
E) drilling rod stirring is promoted to stake top absolute altitude h1, and upper mouth spray continues to whitewash in the process.
When stake top absolute altitude is ground elevation, h1 0.
When stake top absolute altitude is located at ground elevation or less, need to fetching earth within the scope of stake top to ground elevation, drilling rod Upper corresponding position is provided with helical blade, and helical blade takes out the soil body in stake top h1 to 0 range of ground elevation, and stake top It does not whitewash within the scope of to ground elevation.
E) in step, when drilling rod stirring is promoted to stake top absolute altitude h1,0-3 meters can be shifted to an earlier date and close upper mouth spray whitewashing.
Drilling rod course changing control is as follows:
Drilling rod stirs since stake top absolute altitude h1 and sinks down into a bottom h3, and drilling rod rotates forward;
By being carried in the h3 stirrings of stake bottom to h2, drilling rod inverts drilling rod in the process, then stirs sink down into a bottom again, and drilling rod rotates forward;
Drilling rod is promoted to h1 sections by stake bottom h3 stirrings, and drilling rod first inverts, and when needing progress stake top to fetch earth, drilling rod rotates forward.
Implantation construction of prefabricated piles is immediately begun to after mixing pile construction, the construction time of every prefabricated pile is small less than 1.5 When, it plants pile driving construction overall process and carries out measuring for verticality and adjustment.
In step (2), the connection of prefabricated pile body using mechanical connection or is welded to connect.
In prefabricated pile docking operation, previous section prefabricated pile end is clamped using a pile follower equipment, then later section stake with It is docked, and after docking, is unclamped the end clamping of previous section prefabricated pile, will be docked using prefabricated pile gravity or application pressure Prefabricated pile implantation afterwards.
It configuring in slurry processes, backstage pulp feeding system is weighed stirring automatically according to the slurries total amount of setting, the ratio of mud, and oneself Trend mixing pile construction equipment is for slurry.
Advantageous effect:Compared with prior art, using upper and lower mouth spray combination by the way of whitewash, can make whitewashing with The soil body is adequately stirred, and especially upper mouth spray, when drilling rod above carries, slurries are stirred blade and are stirred, at reinforcing Weak soil basis is managed, uniform intensity, uniform density, higher bearing capacity and preferable water-stagnating effect, construction is made it have and makes Valence is low, and full automatic backstage pulp feeding system so that dust pollution is controlled in work progress, and non-environmental-pollution is environmentally protective.
Description of the drawings
The following describes the present invention in detail with reference to the accompanying drawings and specific embodiments;
Fig. 1 is a kind of structural schematic diagram of intelligent mixing pile construction equipment of the present invention.
Fig. 2 is drilling rod schematic diagram of the present invention.
Fig. 3 is three pulley structures schematic diagram of the present invention.
Fig. 4 is pulp feeding system schematic diagram in backstage of the present invention.
Fig. 5 is intelligence control system schematic diagram of the present invention.
Fig. 6 is plant stake device structure schematic diagram of the present invention.
Fig. 7 is drilling depth h- time t curve graphs during equipment construction of the present invention.
Fig. 8 is that upper and lower whitewashing switchs close corresponding with drilling depth h- time t curves to equipment construction of the present invention in the process System's figure.
Fig. 9 is drilling rod work progress schematic diagram of the present invention.
Specific implementation mode
In order to make the technical means, the creative features, the aims and the efficiencies achieved by the present invention be easy to understand, tie below Conjunction is specifically illustrating, and the present invention is further explained.
Equipment in the present embodiment, for the soil body aliquot replacement in stake holes, stir in situ to be formed the stream plasticity soil body, hole Interior insertion prefabricated pile body, bonds to form composite foundation pile with solidified earth
Referring to Fig. 1 and Fig. 2, intelligent mixing pile construction equipment forms stream plastic clay for cement mixing method of constructing Body.Equipment includes pile frame 1, and drilling rod 2 is arranged on pile frame, and drilling rod 2 is used to form cement mixing method;2 bottom of drilling rod is equipped with The drill bit 5 of pore-forming in rock stratum and hard stratum;Power head 6 is housed on drilling rod, motor is installed in power head 6, motor connects frequency conversion Device changes velocity of rotation by Frequency Converter Control frequency shift, and to control the rotating speed of drilling rod 2, same drilling rod turns to Motor reversal can be realized by exchanging the alternating current phase sequence of frequency converter.Frequency converter is arranged in the power distribution cabinet of pile frame
Power head 6 connects hoist engine 9 by steel wire rope 8, and drilling rod 2 is promoted or declined by hoist engine 8.
Referring to Fig. 2, the bottom setting lower mouth spray 22 of drilling rod 2 is provided with mouth spray 21 in the middle part of drilling rod, in drilling rod 2 It is respectively arranged with the shotcrete pipe being connected with upper mouth spray 21, lower mouth spray 22, is turned in 2 two shotcrete pipes of top of drilling rod and a whitewashing Change valve connection.Whitewashing switching valve can carry out the conversion whitewashing of high-low-position as needed.Whitewashing switching valve is connected by feed pipe for mortar Backstage pulp feeding system.
2 bottom of the drilling rod is additionally provided with puff prot, and corresponding drilling rod is internally provided with the air jet pipe being connect with puff prot, Air jet pipe connects air compressor machine.Air jet pipe is used for the jet into the stirring soil body so that cement grout is further mixed with the soil body.
Stirring blade 7 is provided on the drilling rod.The stirring blade 7 is arranged in drilling rod certain length.In upper mouth spray 41 lower section stirring blade 7, when propose brill whitewashing, cement grout that stirring blade 7 can spray gunniting hole 41 is into one Step is mixed with the soil body.
Helical blade 3 is provided on the drilling rod;Helical blade 3 is located at drilling rod top.Helical-blade 3 is for the top that drills It fetches earth, and the slurries after stirring blade 7 is used to drill stir.
The drilling rod 2 is that can connect drilling rod, by drilling rod connection device, by drilling rod spreading, realizes that stirring drilling depth reaches To 40m or more, control pile frame height is within 30m.
Referring to Fig. 4, the backstage pulp feeding system, including a slurry can 41, the cement that the interior storage of slurry can 41 is stirred Slurries, slurry can 41 connect stock pump 42 by feed pipe for mortar, are provided with flowmeter 43 on stock pump 42, stock pump 42 is connected by feed pipe for mortar Shotcrete pipe on mixing pile construction equipment drilling rod 2, specific feed pipe for mortar are connect with the whitewashing switching valve on drilling rod top, and slurries pass through Whitewashing switching valve is transported to mouth spray or lower mouth spray.It is set on slurry can 41 there are one agitator tank 44, agitator tank is used for will Cement and water are sufficiently stirred according to setting ratio;It is provided with stirring blade in agitator tank 44, paddle is driven by motor Piece, motor are variable-frequency motor, are connect with frequency converter, and FREQUENCY CONTROL motor speed is passed through;It is also equipped with and stirs in the slurry can 41 Mix blade.It is separately connected a cement bucket 45 and a bucket 46 on agitator tank 44, is both provided on cement bucket 45 and bucket 46 Poidometer 47 and corresponding control valve;Bucket 46 connects water tank or external water pipe, and cement bucket 45 connects dry powder cementing tank 48.The slurry can 41 can set up multiple stock pumps separately and be separately connected different mixing pile construction equipment by feed pipe for mortar.
Referring to Fig. 5, mixing pile machine intelligence control system, including foreground stake machine PLC (programmable controller);On power head Variable-frequency motor connect a frequency converter, frequency converter by frequency change further control variable-frequency motor rotating speed, frequency converter with PLC connections;Temperature sensor is additionally provided on variable-frequency motor, temperature sensor is connect with PLC, monitors the work of variable-frequency motor in real time Make temperature;Three pulleys are set on the steel wire rope of hoist engine, and three pulleys are fixed on pile frame by holder, and two, right side pulley is solid Surely steel wire rope is abutted, steel wire rope is pressed on the first two pulley by third pulley, the rotation of rope belt movable pulley, and third is sliding Technology for encoding device is set on wheel, and encoder is connect with PLC, encoder per revolution, is generated pulse and is once counted, PLC According to encoder data, the movement speed and movable length of steel wire rope are calculated, and then is converted into lifting speed and the stake of drilling rod Deep data;The whitewashing switching valve connects PLC by a controller, and PLC controls the steering opening and closing of switching valve, and then controls up and down The conversion and opening and closing of mouth spray.Inclinator is provided on the pile frame, inclinator connects PLC, and PLC is supervised in real time by inclinator The verticality of pile frame is controlled, and then ensures the verticality of pile.One human-computer interaction interface of PLC connections, can be on human-computer interaction interface Real-time display relevant parameter can input related construction parameter, can carry out the control start and stop in relation to equipment.
Referring to Fig. 3, pulley 81,82 is fixed on holder 86 three pulley structures, and pulley 83 is movable pulley, and steel wire rope 8 pastes 81,82 left side of nearly pulley, and the right side of pulley 83 compresses steel wire rope to pulley 81,82 directions, and encoder is then mounted on pulley On 83, steel wire rope 8 is rotated with movable pulley 83, and then encoder carries out Counts.It is sliding for the ease of replacing and checking encoder Wheel 83 is installed by connecting rod 84 and long bolt 85.84 one end of connecting rod connects the wheel shaft of pulley 83, and other end connecting bracket is long The wheel shaft of the pulley 83 of one end connection obliquely of screw rod 85, the other end is by nut check on holder 86.
Referring to Fig. 5, the intelligence control system of backstage pulp feeding system, including a backstage for slurry PLC (programmable controller), The flowmeter being arranged on stock pump is connect with backstage for slurry PLC, and the motor of stock pump connects backstage for starching PLC by controller;It stirs The motor for mixing tank is variable-frequency motor, and variable-frequency motor connects backstage for starching PLC by frequency converter controller, from the background can be with for slurry PLC Control the rotation and stopping of agitator tank;The poidometer of cement bucket and the poidometer of bucket are also connect with backstage for slurry PLC, are supplied from the background PLC is starched according to the parameter of setting, weighted cement and water are supplied into agitator tank, is then stirred.PLC connections one are man-machine Interactive interface can input related construction parameter with real-time display relevant parameter on human-computer interaction interface, can carry out related The control start and stop of equipment.
Backstage is interconnected for slurry PLC and foreground stake machine PLC and can be with the mutual parameter of real-time display, and according to mutual ginseng Number carries out itself construction adjustment.Backstage is all connected with remote monitoring terminal for slurry PLC and foreground stake machine PLC, and remote monitoring terminal is logical Network connection intelligence Construction control system is crossed, remote monitoring terminal is computer or handheld device.
It is as follows to plant pile driving construction flow:
(1) fluidised form solidified earth is formed
1) slurries are configured:
Slurries parameter is inputted in the pulp feeding system of backstage, carries out River Bank Stability automatically;It configures in slurry processes, from the background for slurry System is weighed stirring automatically according to the slurries total amount of setting, the ratio of mud, and from trend mixing pile construction equipment for slurry.Cement mixing content With the slurries ratio of mud:Cement mixing content is 15%, the ratio of mud 1.0.
2) construction mixing pile:
Construction parameter is inputted in the intellectualizing system of mixing pile construction equipment, using the drilling rod with upper and lower mouth spray, Soil body aliquot replacement in stake holes, stir in situ are formed fluidised form solidified earth by lower brill construction;In drilling process, upper mouth spray spray The slurries gone out by the blade on drilling rod further with soil shear failure;After inputting construction parameter, whole process automated construction;
(2) it is implanted into prefabricated pile:
It is implanted into prefabricated pile body in fluidised form solidified earth, prefabricated pile body is docked by more piece, and it is solid that previous section pile body is inserted into fluidised form Change in soil and reserved banjo fixing butt jointing, later section pile body are lifted by crane and docked with previous section pile body, prefabricated pile is continued into after docking Body forms composite pile until all prefabricated piles are all implanted into;
Cycle construction mixing pile, implantation prefabricated pile successively, form more composite piles.
Implantation construction of prefabricated piles is immediately begun to after mixing pile construction, the construction time of every prefabricated pile is small less than 1.5 When, it plants pile driving construction overall process and carries out measuring for verticality and adjustment.
In prefabricated pile docking operation, previous section prefabricated pile end is clamped using a pile follower equipment, then later section stake with It is docked, and after docking, is unclamped the end clamping of previous section prefabricated pile, will be docked using prefabricated pile gravity or application pressure Prefabricated pile implantation afterwards.The docking connection of prefabricated pile body using mechanical connection or is welded to connect.
The equipment for being implanted into prefabricated pile is pile press machine, referring to Fig. 6, including:Loop wheel machine 101 and workbench 102, loop wheel machine slings stake Pile body is implanted into soil layer by body by workbench 102, and the loop wheel machine 101 is equipped with vibration hammer 103;The workbench upper end It is equipped with and plants stake leading truck 104, plant stake leading truck upper end, which is connected with, plants stake oil cylinder 105, the workbench lower end installation Crossbeam 106 is clasped, clasps to be equipped in crossbeam and clasps oil cylinder and clasp oil cylinder under, above clasp oil cylinder and clasp oil cylinder under and stretch Outlet, which is equipped with, clasps pressing plate.It clasps pressing plate to be clamped for prefabricated pile end, carries out pile extension.
Mixing pile construction is specific as follows:See Fig. 7-9:Ground elevation is ± 0.0, and mixing pile stake bottom absolute altitude is -42.0, below Absolute altitude is drill bit bottom absolute altitude in explanation.
(1) it bores, whitewash under, stirring sinking (rotating forward sinking 42.0m), subsidence velocity 0.8m/min, rotating speed 16rpm, under It is heavy from ± 0.0 to -42.0, the long 42m of mixing pile;
(2) it is promoted, whitewashes, stirs again, sinking again and (being carried in reversion, sink each 4.0m), promoted and subsidence velocity is 1.6m/ Min, rotating speed 32rpm;It is promoted from -42.0 to -38.0, sinks from -38.0 to -42.0;Stir segment length again, with upper and lower mouth spray away from From matching;
(3) it above carries, whitewash, stirring, carrying soil (reversion promotes 11.0m), promotion speed is 1.6m/min, rotating speed 32rpm;It carries Rise from -42.0 to -31.0;
(4) it above carries, whitewash, stirring, carrying soil (rotate forward and promote 31.0m), promotion speed is 1.6m/min, rotating speed 32rpm;It carries It rises from -31.0 to ± 0.0.
Whitewashing mode:Using upper and lower whitewashing mode, 2 whitewashing mouths are set, lower nozzle is set to bottom of drill bit, and top nozzle is set It is placed in away from bottom of drill bit 3.0m among blade, specific mode of whitewashing is subject to construction curve.Whitewashing position and time relationship, are shown in Attached drawing 8.
A, drilling rod stirring is sunk ± 0.0~-6.0 sections, and upper and lower nozzle is not whitewashed;
B, drilling rod stirring sinks down into h1=-6.0, and lower nozzle opens whitewashing, and lasting whitewashing stirring to h3=-42.0 (is sprayed It is -6.0~-42.0 to starch section);
C, drilling rod stirring is promoted to h2=-38.0, and lower nozzle continues to keep whitewashing (section of whitewashing is -42.0~-38.0);
D, drilling rod stirs and sinks down into h3=-42.0 again, does not whitewash, pure stirring (i.e. pure stirring section for -38.0~- 42.0);
E, drilling rod stirring is promoted to stake top, and top nozzle is persistently whitewashed, and stops whitewashing, i.e. top nozzle before reaching stake top Whitewashing section is raising section -42.0~-9.0;
F, drilling rod stirring is promoted to ground elevation ± 0.0, does not whitewash, pure stirring (i.e. pure stirring section is -9.0~± 0.0)
Supplementary explanation:
A, drilling rod is sunk down into -42.0 sections (length 42.0m) by ± 0.0 stirring, and drilling rod rotates forward;
B, drilling rod, which is above carried by -42.0 stirrings to -38.0 (length 4.0m) processes and -38.0 stirring again, sinks down into -42.0 (length Spend 4.0m), rotatings forward is proposed on drilling rod, is stirred sinking again and is inverted;
C, drilling rod is promoted to -31.0 sections of (length 11.0m) processes, drilling rod reversion by -42.0 stirrings;
D, it is promoted to ± 0.0 section (length 31.0m) by -31.0 stirrings, drilling rod rotates forward.The helical blade on drilling rod top takes out The soil body in the hole of stake top portion 6m length
Compared with prior art, it is whitewashed by the way of the combination of upper and lower mouth spray, whitewashing can be made to be obtained with the soil body Adequately stirring, especially upper mouth spray, when drilling rod above carries, slurries are stirred blade and are stirred, consolidation process Soft Soil Plinth makes it have uniform intensity, uniform density, higher bearing capacity and preferable water-stagnating effect, and construction cost is low, entirely certainly Dynamic backstage pulp feeding system so that dust pollution is controlled in work progress, and non-environmental-pollution is environmentally protective.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry For personnel it should be appreciated that the present invention is not limited by examples detailed above, described in examples detailed above and specification is to illustrate the present invention Principle, various changes and improvements may be made to the invention without departing from the spirit and scope of the present invention, these variation and Improvement all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appended claims and its is equal Object defines.

Claims (10)

1. a kind of intelligent plant pile construction method, characterized in that include the following steps:
(1) fluidised form solidified earth is formed
1) slurries are configured:
Slurries parameter is inputted in the pulp feeding system of backstage, carries out River Bank Stability automatically;
2) construction mixing pile:
Construction parameter is inputted in the intellectualizing system of mixing pile construction equipment, using the drilling rod with upper and lower mouth spray, lower brill Soil body aliquot replacement in stake holes, stir in situ are formed fluidised form solidified earth by construction;In drilling process, what upper mouth spray sprayed Slurries by the blade on drilling rod further with soil shear failure;After inputting construction parameter, whole process automated construction;
(2) it is implanted into prefabricated pile:
It is implanted into prefabricated pile body in fluidised form solidified earth, prefabricated pile body is docked by more piece, and previous section pile body is inserted into fluidised form solidified earth In and reserved banjo fixing butt jointing, later section pile body, which lifts by crane, simultaneously dock with previous section pile body, is docked and is continued into prefabricated pile body later, directly It is all implanted into all prefabricated piles, forms composite pile;
Cycle construction mixing pile, implantation prefabricated pile successively, form more composite piles.
2. a kind of intelligent plant pile construction method according to claim 1, characterized in that lower in step 2) to bore construction, tool Body process is as follows:
A) drilling rod stirring is sunk, and is sunk since stake top absolute altitude h1, and lower mouth spray opens whitewashing, lasting whitewashing stirring to stake bottom h3;
B) drilling rod stirring is promoted to h2 from h3, and mouth spray is descended to whitewash in the process;
C) drilling rod stirs again from h2 and sinks down into a bottom h3, does not whitewash in the process, pure stirring;
D) drilling rod stirring is promoted to h2, in the process upper mouth spray whitewashing;
E) drilling rod stirring is promoted to stake top absolute altitude h1, and upper mouth spray continues to whitewash in the process.
3. a kind of intelligent plant pile construction method according to claim 2, characterized in that when stake top absolute altitude is ground mark Gao Shi, h1 0.
4. a kind of intelligent plant pile construction method according to claim 2, characterized in that when stake top absolute altitude is located at ground mark When high following, need to fetching earth within the scope of stake top to ground elevation, corresponding position is provided with helical blade, spiral shell on drilling rod Vane piece takes out the soil body in stake top h1 to 0 range of ground elevation, and does not whitewash within the scope of stake top to ground elevation.
5. a kind of intelligent plant pile construction method according to claim 2, characterized in that e) in step, drilling rod stirring carries When rising to stake top absolute altitude h1,0-3 meters can be shifted to an earlier date and close upper mouth spray whitewashing.
6. a kind of intelligent plant pile construction method according to claim 2, characterized in that
Drilling rod stirs since stake top absolute altitude h1 and sinks down into a bottom h3, and drilling rod rotates forward;
By being carried in the h3 stirrings of stake bottom to h2, drilling rod inverts drilling rod in the process, then stirs sink down into a bottom again, and drilling rod rotates forward;
Drilling rod is promoted to h1 sections by stake bottom h3 stirrings, and drilling rod first inverts, and when needing progress stake top to fetch earth, drilling rod rotates forward.
7. a kind of intelligent plant pile construction method according to claim 1, characterized in that after mixing pile construction immediately Start to be implanted into construction of prefabricated piles, the construction time of every prefabricated pile is less than 1.5 hours, plants pile driving construction overall process and carries out verticality inspection It surveys and adjusts.
8. a kind of intelligent plant pile construction method according to claim 1, characterized in that in step (2), prefabricated pile body Connection using mechanical connection or be welded to connect.
9. a kind of intelligent plant pile construction method according to claim 1, characterized in that in prefabricated pile docking operation, adopt Previous section prefabricated pile end is clamped with a pile follower equipment, then later section stake is interfaced, after docking, unclamps previous section The end of prefabricated pile is clamped, and using prefabricated pile gravity or applies pressure by the prefabricated pile implantation after docking.
10. a kind of intelligent plant pile construction method according to claim 1, characterized in that in configuration slurry processes, backstage Pulp feeding system is weighed stirring automatically according to the slurries total amount of setting, the ratio of mud, and from trend mixing pile construction equipment for slurry.
CN201810133432.8A 2018-02-09 2018-02-09 A kind of intelligent plant pile construction method Pending CN108343062A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810133432.8A CN108343062A (en) 2018-02-09 2018-02-09 A kind of intelligent plant pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810133432.8A CN108343062A (en) 2018-02-09 2018-02-09 A kind of intelligent plant pile construction method

Publications (1)

Publication Number Publication Date
CN108343062A true CN108343062A (en) 2018-07-31

Family

ID=62959370

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810133432.8A Pending CN108343062A (en) 2018-02-09 2018-02-09 A kind of intelligent plant pile construction method

Country Status (1)

Country Link
CN (1) CN108343062A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185029A (en) * 2019-07-02 2019-08-30 上海强劲地基工程股份有限公司 A kind of pile foundation intelligence construction equipment
CN113073629A (en) * 2021-04-20 2021-07-06 上海强劲地基工程股份有限公司 Construction method of solidified soil pile

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204080817U (en) * 2014-04-30 2015-01-07 上海城地建设股份有限公司 A kind of novel dual spindle soil-cement agitation pile device changing whitewashing up and down
CN104674797A (en) * 2013-11-27 2015-06-03 上海城地建设股份有限公司 Construction method for five-shaft cement mixing pile without squeezing soil
CN106638643A (en) * 2016-12-23 2017-05-10 中国建筑第四工程局有限公司 Water-stopping-curtain construction device and method
CN107178311A (en) * 2017-07-17 2017-09-19 上海强劲地基工程股份有限公司 A kind of many principal axis transformations and wheelbase are adjustable and the mixing pile machine of efficient mix

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104674797A (en) * 2013-11-27 2015-06-03 上海城地建设股份有限公司 Construction method for five-shaft cement mixing pile without squeezing soil
CN204080817U (en) * 2014-04-30 2015-01-07 上海城地建设股份有限公司 A kind of novel dual spindle soil-cement agitation pile device changing whitewashing up and down
CN106638643A (en) * 2016-12-23 2017-05-10 中国建筑第四工程局有限公司 Water-stopping-curtain construction device and method
CN107178311A (en) * 2017-07-17 2017-09-19 上海强劲地基工程股份有限公司 A kind of many principal axis transformations and wheelbase are adjustable and the mixing pile machine of efficient mix

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宋阳: "RCP劲性复合桩的应用", 《陕西建筑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185029A (en) * 2019-07-02 2019-08-30 上海强劲地基工程股份有限公司 A kind of pile foundation intelligence construction equipment
CN113073629A (en) * 2021-04-20 2021-07-06 上海强劲地基工程股份有限公司 Construction method of solidified soil pile

Similar Documents

Publication Publication Date Title
CN207891870U (en) A kind of intelligent plant pile driving construction equipment
CN204080817U (en) A kind of novel dual spindle soil-cement agitation pile device changing whitewashing up and down
CN101260669B (en) Drilling, spraying, injection integral enlarging anchor rod construction method
CN109763482A (en) A kind of Dam Foundation Strengthened in Situ weak soil stirs spray mixing drilling tool and construction method
CN101387112B (en) Apparatus capable of automatic balancing surrounding soil pressure during horizontal rotary jet strengthening construction
CN1944809A (en) Three pipe double high pressure rotary jet sprouting reinforced construction method and its equipment
CN104674798A (en) Construction method for non-replacement and up-and-down convertible spouting five-shaft cement mixing pile
CN108086311A (en) A kind of intelligent plant pile driving construction equipment
CN102943468A (en) Multi-axial mixing pile device capable of reducing soil extrusion and application thereof
CN106917404A (en) A kind of prefabricated screw stake
CN107059960A (en) A kind of indoor full automatic simulates the experimental rig of cement mixing method
CN108343062A (en) A kind of intelligent plant pile construction method
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
CN100585090C (en) A kind of injection grouting method and injection slip casting drilling tool
CN110185029A (en) A kind of pile foundation intelligence construction equipment
CN102418337A (en) New grouting method
CN203256735U (en) Multi-shaft mixing pile device capable of reducing soil-squeezing effect
CN104674797A (en) Construction method for five-shaft cement mixing pile without squeezing soil
CN116876486A (en) Free angle soft soil foundation reinforcement construction equipment, construction method and reinforcement pile
CN102235008A (en) Engineering pile deviation preventing structure of soft soil foundation and pretreatment method
CN100374657C (en) Construction method employing threaded stirring shaft to decrease ambient foundation deformation
CN206815410U (en) A kind of experimental rig of indoor full automatic simulation cement mixing method
CN207525751U (en) A kind of hydraulic engineering grouting construction device
CN210507424U (en) Pile foundation intelligent construction equipment
CN206034417U (en) A integrated system is split in high extrusion of deep soft base drilling cream thick liquid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180731