CN108333332B - 大比例尺隧道模型试验开挖装置 - Google Patents
大比例尺隧道模型试验开挖装置 Download PDFInfo
- Publication number
- CN108333332B CN108333332B CN201810183008.4A CN201810183008A CN108333332B CN 108333332 B CN108333332 B CN 108333332B CN 201810183008 A CN201810183008 A CN 201810183008A CN 108333332 B CN108333332 B CN 108333332B
- Authority
- CN
- China
- Prior art keywords
- excavation
- wedge
- supporting device
- shaped
- steel blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009412 basement excavation Methods 0.000 claims abstract description 42
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 33
- 239000010959 steel Substances 0.000 claims abstract description 33
- 229910001220 stainless steel Inorganic materials 0.000 claims abstract description 10
- 239000010935 stainless steel Substances 0.000 claims abstract description 10
- 238000000034 method Methods 0.000 claims description 6
- 230000000694 effects Effects 0.000 claims description 5
- 239000000463 material Substances 0.000 claims description 3
- 238000009933 burial Methods 0.000 abstract description 3
- 239000002689 soil Substances 0.000 abstract description 3
- 239000011435 rock Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000009172 bursting Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000009440 infrastructure construction Methods 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N33/00—Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00
- G01N33/24—Earth materials
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Food Science & Technology (AREA)
- Analytical Chemistry (AREA)
- Geology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Medicinal Chemistry (AREA)
- Physics & Mathematics (AREA)
- Remote Sensing (AREA)
- Biochemistry (AREA)
- General Health & Medical Sciences (AREA)
- General Physics & Mathematics (AREA)
- Immunology (AREA)
- Pathology (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明涉及一种大比例尺隧道模型试验开挖装置,属于隧道勘探领域。该装置包括卸载装置和支撑装置;均设置在模型箱内;所述卸载装置由10块楔形不锈钢块组成,自上而下编号为I~X,彼此错缝咬合形成一个环形整体,钢块厚度为10cm,纵向长度与模型箱纵向尺寸保持一致,而且钢块拼成的环形整体外轮廓与开挖孔轮廓紧密贴合;所述支撑装置由两块长条形钢板组成,钢板重叠放置,在重叠处采用螺栓固定。本发明可以很好地模拟实际隧道开挖情况,开挖控制简单,当埋深较大时,模型箱边界对开挖土体的扰动小,对试验结果的准确性影响不大。
Description
技术领域
本发明属于隧道勘探领域,涉及大比例尺隧道模型试验开挖装置。
背景技术
随着我国经济建设的繁荣发展,交通隧道等基础设施建设的需求不断增加。隧道由于修建于地下,因地质作用和人为工程活动可能引起一系列工程地质灾害,如突水突泥、围岩坍塌、地面塌陷等,造成巨大人员伤亡和财产损失。因此采用模型试验研究隧道开挖时围岩变形规律,并据此分析推测现场实际状况是一种重要研究手段。
大比例尺模型试验可以更好地模拟实际隧道开挖情况,但存在着跨径大,开挖难以控制的问题,而且当埋深较大时,若采用手工开挖,模型箱边界对开挖土体的扰动较大,对试验结果的准确性影响较大。
发明内容
有鉴于此,本发明的目的在于提供一种大比例尺隧道模型试验开挖装置。
为达到上述目的,本发明提供如下技术方案:
大比例尺隧道模型试验开挖装置,包括卸载装置和支撑装置;均设置在模型箱内;
所述卸载装置由10块楔形不锈钢块组成,自上而下编号为I~X,彼此错缝咬合形成一个环形整体,钢块厚度为10cm,纵向长度与模型箱纵向尺寸保持一致,而且钢块拼成的环形整体外轮廓与开挖孔轮廓紧密贴合;
所述支撑装置由两块长条形钢板组成,钢板重叠放置,在重叠处采用螺栓固定。
基于所述开挖装置的开挖方法,包括以下步骤:
S1:在进行隧道开挖模型试验时,当填料至开挖孔底部时,将该开挖装置放置与开挖孔处,使开挖装置外轮廓与开孔边缘紧密贴合,各楔形块错缝拼接完好;
S2:将支撑装置放置于中间开孔处,调整支撑装置钢板重叠长度,使其上部抵住I楔形钢块,下部抵住VII楔形钢块,拧紧固定螺栓;
S3:在模型试验开孔外部继续填料并压实,填料直至试验所需高度;
S4:当进行开挖时,将支撑装置的固定螺栓取掉,此时发生卸载效应,取掉支撑钢板;
S5:然后,自上而下,依次按拼接顺序取掉楔形钢块,以完成隧道的开挖过程。
本发明的有益效果在于:本发明可以很好地模拟实际隧道开挖情况,开挖控制简单,当埋深较大时,模型箱边界对开挖土体的扰动小,对试验结果的准确性影响不大。
附图说明
为了使本发明的目的、技术方案和有益效果更加清楚,本发明提供如下附图进行说明:
图1为模型试验开孔;
图2为模型试验开挖装置;
图3为楔形块开挖顺序。
具体实施方式
下面将结合附图,对本发明的优选实施例进行详细的描述。
图1为模型试验开孔;如图2所示,大比例尺隧道模型试验开挖装置,包括卸载装置和支撑装置;卸载装置由10块楔形不锈钢块组成,彼此错缝咬合形成一个环形整体,钢块厚度为10cm,纵向长度与模型箱纵向尺寸保持一致,而且钢块拼成的环形整体外轮廓与开挖孔轮廓紧密贴合;支撑装置由两块长条形钢板组成,钢板重叠放置,在重叠处采用螺栓固定。模拟隧道开挖时,将螺栓拧下,然后取掉钢板进行卸载。而且该装置可以满足不同开挖尺寸的隧道开挖模拟,当断面发生变化时,调整两块钢板重叠处长度,以调整支撑体的整体高度,进而支撑相应的楔形块。
如图3所示,本装置运作具体为:
(1)在进行隧道开挖模型试验时,当填料至开挖孔底部时,将该开挖装置放置与开挖孔处,使开挖装置外轮廓与开孔边缘紧密贴合,各楔形块错缝拼接完好;
(2)将支撑装置放置于中间开孔处,调整支撑装置钢板重叠长度,使其上部抵住Ⅰ楔形钢块,下部抵住Ⅶ楔形钢块,拧紧固定螺栓;
(3)在模型试验开孔外部继续填料并压实,填料直至试验所需高度;
(4)当进行开挖时,将支撑装置的固定螺栓取掉,此时发生卸载效应,取掉支撑钢板;
(5)然后,自上而下,依次按拼接顺序取掉楔形钢块,以完成隧道的开挖过程。
最后说明的是,以上优选实施例仅用以说明本发明的技术方案而非限制,尽管通过上述优选实施例已经对本发明进行了详细的描述,但本领域技术人员应当理解,可以在形式上和细节上对其作出各种各样的改变,而不偏离本发明权利要求书所限定的范围。
Claims (1)
1.基于大比例尺隧道模型试验开挖装置的开挖方法,其特征在于:该方法包括以下步骤:
S1:在进行隧道开挖模型试验时,当填料至开挖孔底部时,将该开挖装置放置与开挖孔处,使开挖装置外轮廓与开孔边缘紧密贴合,各楔形块错缝拼接完好;
S2:将支撑装置放置于中间开孔处,调整支撑装置钢板重叠长度,使其上部抵住I楔形钢块,下部抵住VII楔形钢块,拧紧固定螺栓;
S3:在模型试验开孔外部继续填料并压实,填料直至试验所需高度;
S4:当进行开挖时,将支撑装置的固定螺栓取掉,此时发生卸载效应,取掉支撑钢板;
S5:然后,自上而下,依次按拼接顺序取掉楔形钢块,以完成隧道的开挖过程;
其中,开挖装置包括卸载装置和支撑装置;均设置在模型箱内;
所述卸载装置由10块楔形不锈钢块组成,自上而下编号为I~X,彼此错缝咬合形成一个环形整体,钢块厚度为10cm,纵向长度与模型箱纵向尺寸保持一致,而且钢块拼成的环形整体外轮廓与开挖孔轮廓紧密贴合;
所述支撑装置由两块长条形钢板组成,钢板重叠放置,在重叠处采用螺栓固定。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810183008.4A CN108333332B (zh) | 2018-03-06 | 2018-03-06 | 大比例尺隧道模型试验开挖装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810183008.4A CN108333332B (zh) | 2018-03-06 | 2018-03-06 | 大比例尺隧道模型试验开挖装置 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108333332A CN108333332A (zh) | 2018-07-27 |
CN108333332B true CN108333332B (zh) | 2023-07-07 |
Family
ID=62928819
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810183008.4A Active CN108333332B (zh) | 2018-03-06 | 2018-03-06 | 大比例尺隧道模型试验开挖装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108333332B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112485409B (zh) * | 2021-01-14 | 2024-04-12 | 重庆交通大学 | 用于隧道模拟开挖的试验模型及方法 |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU6962881A (en) * | 1980-04-21 | 1981-10-29 | Voest-Alpine A.G. | Monitoring movement of a cutting tool |
CN103926383A (zh) * | 2014-04-30 | 2014-07-16 | 山东大学 | 隧道突水突泥与注浆处治三维模型试验系统及其试验方法 |
CN204330377U (zh) * | 2015-01-16 | 2015-05-13 | 招商局重庆交通科研设计院有限公司 | 隧道衬砌结构均布加载试验系统 |
BRMU9102546U2 (pt) * | 2011-12-07 | 2015-11-10 | Damião Martins Martos | dosposição introduzida em usina eólica em túnel de vento |
CN105092275A (zh) * | 2015-07-31 | 2015-11-25 | 河南理工大学 | 一种可双向加载的隧道模型试验装置 |
CN105136507A (zh) * | 2015-09-16 | 2015-12-09 | 长安大学 | 一种室内模拟隧道开挖的实验装置及方法 |
CN105971618A (zh) * | 2016-07-01 | 2016-09-28 | 成都理工大学 | 一种模拟隧道开挖的卸载开挖器 |
CN106437781A (zh) * | 2016-10-25 | 2017-02-22 | 中铁第四勘察设计院集团有限公司 | 一种上软下硬地层隧道支护结构及其施工方法 |
CN107328898A (zh) * | 2017-07-18 | 2017-11-07 | 招商局重庆交通科研设计院有限公司 | 穿越断层隧道开挖模拟实验装置 |
CN107702937A (zh) * | 2017-11-23 | 2018-02-16 | 中南大学 | 模拟深部圆形隧洞机械开挖卸荷的试验装置及试验方法 |
-
2018
- 2018-03-06 CN CN201810183008.4A patent/CN108333332B/zh active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU6962881A (en) * | 1980-04-21 | 1981-10-29 | Voest-Alpine A.G. | Monitoring movement of a cutting tool |
BRMU9102546U2 (pt) * | 2011-12-07 | 2015-11-10 | Damião Martins Martos | dosposição introduzida em usina eólica em túnel de vento |
CN103926383A (zh) * | 2014-04-30 | 2014-07-16 | 山东大学 | 隧道突水突泥与注浆处治三维模型试验系统及其试验方法 |
CN204330377U (zh) * | 2015-01-16 | 2015-05-13 | 招商局重庆交通科研设计院有限公司 | 隧道衬砌结构均布加载试验系统 |
CN105092275A (zh) * | 2015-07-31 | 2015-11-25 | 河南理工大学 | 一种可双向加载的隧道模型试验装置 |
CN105136507A (zh) * | 2015-09-16 | 2015-12-09 | 长安大学 | 一种室内模拟隧道开挖的实验装置及方法 |
CN105971618A (zh) * | 2016-07-01 | 2016-09-28 | 成都理工大学 | 一种模拟隧道开挖的卸载开挖器 |
CN106437781A (zh) * | 2016-10-25 | 2017-02-22 | 中铁第四勘察设计院集团有限公司 | 一种上软下硬地层隧道支护结构及其施工方法 |
CN107328898A (zh) * | 2017-07-18 | 2017-11-07 | 招商局重庆交通科研设计院有限公司 | 穿越断层隧道开挖模拟实验装置 |
CN107702937A (zh) * | 2017-11-23 | 2018-02-16 | 中南大学 | 模拟深部圆形隧洞机械开挖卸荷的试验装置及试验方法 |
Non-Patent Citations (10)
Title |
---|
.Peck公式在砂卵石地层盾构隧道施工地表沉降预测中的应用研究;曹鹏等;《五邑大学学报(自然科学版)》;第32卷(第3期);43-48 * |
American Society of Civil Engineers Sixth China-Japan-US Trilateral Symposium on Lifeline Earthquake Engineering - Chengdu, China;Jiang S. P et al;《International Efforts in Lifeline Earthquake Engineering - The Shaking Table Model Test of the Tunnel through Fault》;321–328 * |
Comparative Analysis on Stress State of Submerged Floating Tunnels in Different Anchor Cable Arrangement Modes;Fang L et al;《PROCEEDINGS OF 2ND INTERNATIONAL SYMPOSIUM ON SUBMERGED FLOATING TUNNELS AND UNDERWATER TUNNEL STRUCTURES》;第166卷;279-287 * |
Prediction of backlayering length and critical velocity in metro tunnel fires;Weng MC et al;《TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY》;第47卷;64-72 * |
The shaking table model test of the tunnel through fault;Jiang, S.P et al;《International Efforts in Lifeline Earthquake Engineering. Sixth China-Japan-US Trilateral Symposium on Lifeline Earthquake Engineering. Proceedings.;321-8 * |
偏压隧道洞口段卸荷反压施工效能分析;彭雪峰;《公路交通科技(应用技术版)》;第12卷(第11期);175-177 * |
波浪作用下椭圆形横截面悬浮隧道管段压强特性试验;李勤熙等;《隧道建设》;第38卷(第1期);57-64 * |
环形开挖预留核心土法在杨柳垭隧道洞挖中的应用;杨瑞英等;《四川水力发电》;第38卷(第5期);90-94 * |
砂卵石地层隧道开挖过程中上覆土体应力变化的颗粒流模拟研究;蒋宇卓等;《隧道建设》;第37卷(第S2期);141-146 * |
边坡卸荷与隧道进洞交叉施工条件下高边坡三维稳定性分析;杨承民;《中国优秀硕士学位论文全文数据库 (工程科技Ⅱ辑)》(第3期);C034-37 * |
Also Published As
Publication number | Publication date |
---|---|
CN108333332A (zh) | 2018-07-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108732024B (zh) | 模拟不同地应力条件下底板突水的试验系统及试验方法 | |
CN105204088B (zh) | 构造应力场模拟试验装置及方法 | |
CN103117020B (zh) | 盾构隧道动态掘进诱发地层损失及地表沉陷试验装置 | |
CN108169427B (zh) | 一种平面应力模型的隧道突水物理模拟试验系统及试验方法 | |
CN103837360B (zh) | 一种隧道管棚施工法模拟开挖装置及其实施方法 | |
CN105974056B (zh) | 隧道突水灾害前兆信息监测模型试验系统及试验方法 | |
CN101308126B (zh) | 一种水下开采顶板渗流突水试验方法及装置 | |
CN110195598B (zh) | 一种公路隧道施工一体化控制方法 | |
CN107144470A (zh) | 隧道及地下工程中突水突泥灾害实时监测装置与操作方法 | |
CN202433536U (zh) | 一种隧道穿越地裂缝带的物理模型试验系统 | |
CN110284530B (zh) | 结合基坑与隧道的多功能组合拼装模型试验箱装置及应用 | |
CN105116101A (zh) | 一种矿井灾害预防与控制模拟试验系统及其使用方法 | |
Ochmański et al. | Automated numerical modelling for the control of EPB technology | |
CN110514806B (zh) | 一种相似模拟试验装置及方法 | |
CN110748353A (zh) | 盾构开挖与土体沉降监测模拟试验平台及模拟试验方法 | |
CN211505504U (zh) | 一种模拟隧道穿越富水断层突涌水的试验装置 | |
CN204925064U (zh) | 一种矿井灾害预防与控制模拟试验系统 | |
CN113189302A (zh) | 深埋隧道穿越活动断裂突水突泥动力灾害试验系统及方法 | |
Losacco et al. | Class A prediction of mechanised tunnelling in Rome | |
CN108333332B (zh) | 大比例尺隧道模型试验开挖装置 | |
CN214011233U (zh) | 一种模拟煤层开采顶板含水层运移的相似模拟实验装置 | |
Li et al. | Collapse mechanism and treatments of a deep tunnel in the weathered granite fault zone | |
CN106324222A (zh) | 一种模拟地下隧道施工的模型试验装置及其使用方法 | |
CN110044669B (zh) | 多角度的松散堆积体岸坡模型制作设备及其试验方法 | |
CN214150647U (zh) | 一种条带式采煤沉陷物理模拟实验装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |